CLAUSE NO.
TECHNICAL SPECIFICATION FOR INTERNAL ELECTRIFICATION 
 8.01.00                 
8.02.00                   
8.01.01         
8.01.02          
8.01.03     
8.01.04  
Intent of Specification  
This specification is intended to cover Internal Electrification for the building. It is not 
the  intent  to  specify  completely  herein  all  aspects  of  design  and  constructional 
features  of  equipment  and  details  of  the  work  to  be  carried  out,  nevertheless,  the 
equipment and work shall conform in  all  respects to  high, standards of  Engineering, 
design  and  workmanship  and  shall  be  capable  of  performing  in  continuous 
commercial  operation  in  a  manner  acceptable  to  the  owner  who  will  interpret  the 
meaning  of  the  specifications and  drawings  and  shall  have  right  to  reject  or  accept 
any  equipment  or  work  which  in  this  assignment  is  not  complete  to  meet  the 
requirements of  this specification and/or applicable Codes and standards mentioned 
elsewhere in the specifications.    
Scope of Work  
The scope of work under this specification shall include Design, Fabrication, Supply, 
Storage,  Erection,  Testing  and  Commissioning  of  following  items  for  complete 
internal electrification of building:  
(a)        LT Distribution Boards 
(b)        Lighting Panels 
(c)  Lighting/Power  Distribution  System  for  the  building  complete  with  wires, 
conduits,  switch/socket outlet  boxes,switches,sockets, Lighting  fixtures,  fans, 
Receptacles  and accessories etc. 
(d)        LT Power Cables/wires from Main distribution board to Lighting panels 
(e)        Earthing & Lightning Protection System 
(f)         Any other work required for complete electrification  
The  scope  of  work  shall  also  include  all  civil  works  associated  with  erection  of 
Distribution boards,  Lighting panels  and  conduit either  concealed in  walls  or  ceiling, 
switch  boxes,  receptacles,  earthing  &  lightning  protection  system  etc.        Minor  Civil 
Works  like  fixing  of  anchor    bolts  clamps,  cleats  and  breaking  of  walls  /  floor  for 
installing  conduits  /cables/earthing  conductors  etc.  and  sealing  of  walls  /  floors 
afterwards shall also be included in the bidders scope.  
Materials  and  components  not  specifically  stated  in  these  specification  but  are 
necessary for  operation of the systems, mentioned therein shall be  deemed to  have 
been  included  in  the  scope  of  work  of  these  specifications.  Whether  called  for 
specifically  or  not,  all  accessories,  hardware  and  services  required  for  normal 
satisfactory testing, commissioning, operation of equipment/system shall be  deemed 
to  be  included  in  the  contractors  scope  and  cost  of  these  shall  be  included  in  unit 
rates quoted by the Contractor.  
The  Electrical Contractor shall also obtain at his cost all the sanctions from relevant 
authorities such  as  installation checked  and  approved  by  the  Electrical  Inspector  or 
from any other authority if required, on behalf of the owner.  
The  tender  drawings  show  the  lighting  layout  and  electrical  distribution  of 
various  areas  of  the  building  in  general.  However,  the  detailed  electrical  layouts, 
circuit  diagrams,  conduit  layouts  etc.  for  construction  shall  be  prepared  by  the 
contractor  and  submitted  for  owners  site  Engineer  approval  during  detailed 
engineering. It shall   
KUDGI STPP 
STAGE-I (3 X 800 MW)   
Bid Doc. No. : 
CS-9573-000-1  
TECHNICAL 
SPECIFICATIONS 
PART-B   
PART-B 
8. Electrical Works.   
Page 1 of 18   
CLAUSE NO.  
TECHNICAL SPECIFICATION FOR INTERNAL ELECTRIFICATION     
8.01.05    
8.01.06       
8.02.00  
8.02.01    
8.02.02       
8.02.03       
8.02.04    
8.03.00  
8.03.01      
8.03.02       
8.03.03  
be  the  responsibility  of  the  contractor  to  estimate  the  quantities  of  conduits,  wires 
and other equipment/materials etc. correctly as per approved layouts/drawings.  
The  contractor  shall  furnish  all  relevant  drawing,  data,  catalogues,  instructions 
manuals of the equipment supplied by him as per the requirements of the contract.  
The  contractor shall  submit  to  owner  one  marked  up  copy  and  one  original  copy  of 
all  as    built    drawings    after    installation  of    the    lighting    fixtures    and    other 
equipment covered  under  this  package  for  effecting  any  changes  in  the  originals. 
This  work  shall  be  done  immediately  after  completion  of  erection  work  in  a 
particular  area.  Price quoted by the contractor shall be inclusive of furnishing of the 
above drawings.  
General Information  
The  design  and  workmanship  shall  be  in  accordance  with  the  best  Engineering 
practices to ensure satisfactory performance and service life as specified herein.  
Contractor  shall  provide  adequate  and  capable  manpower  and  supervision  for 
electrical  installation  work  covered  under  this  contract.  The  staff  provided  shall  be 
adequate to provide detailed supervision at each stage / site of the work and shall be 
licensed  to  handle  respective  jobs  to  satisfy  the  requirements of  the  electric  supply 
and other connected authorities.  
The Contractor shall have to clean all equipment under erection, as well as the work 
area  and  site  at  regular  intervals  to  the  satisfaction  of  the  owner/Engineer. In  case 
the  cleaning  is  not  to  Owners  satisfaction,  he  will  have  the  right  to  carry  out  the 
cleaning operations and  expenditure incurred by  the  Owner  in  this  regard  will  be  to 
the Contractors account.  
Types and makes of  all  the  bought out  electrical items  shall  be  subject to  NTPCS 
approval.  
Storage Cum Erection Insurance  
All  the  equipment  and  material  being  supplied  by  the  Contractor  shall  be  kept 
completely insured  by  the  Contractor at  his  cost  from  the  time  of  dispatch  from  the 
manufacturers works up to the completion of erection, testing and commissioning at 
site and taking over by the Owner.  
It will be the responsibility of the contractor to lodge, pursue and settle all claims with 
the  insurance  company  in  case  of  any  damage,  loss,  theft,  flood,  earthquake, 
pilferage or fire etc. and the owner shall be kept informed about it. The losses, if any, 
will  have  to  be  borne  by  the  Contractor,  if  the  claims  are  not  lodged  and  pursued 
properly or in time or if the same are not settled by the Insurance Company.  
Site Conditions  
All  equipments  shall  be  designed  for  an  ambient  temperature  of  50  deg.  C.  and 
100%  Relative  Humidity.  It  is  the  responsibility  of  the  contractor  to  survey  the  site 
and  acquaint  himself  to  prevailing  site  conditions  before  quoting.    Failure  on  this 
account shall not relieve the contractor of his responsibility to execute the contract to 
suit the site conditions.   
KUDGI STPP 
STAGE-I (3 X 800 MW)   
Bid Doc. No. : 
CS-9573-000-1  
TECHNICAL 
SPECIFICATIONS 
PART-B   
PART-B 
8. Electrical Works.   
Page 2 of 18   
CLAUSE NO.  
TECHNICAL SPECIFICATION FOR INTERNAL ELECTRIFICATION  
8.04.00  
8.04.01  
8.04.01.01                         
8.04.01.02  
Technical Requirements 
LT Distribution boards 
Codes and Standards 
Distribution  boards  &  components  shall  conform  to  the  requirements  of  the  latest 
revisions including amendments of the following codes and standards:  
IS: 8623  Specification  for  factory  built  assemblies  of  switchgear  and  control 
gear for voltages upto and including 1000V AC/1200V DC. 
IS: 13947-I  General requirements for switchgear and control gear for voltages not 
exceeding 1000V. 
IS: 13947-I  Degree of Protection provided by enclosures for low 
Voltage switchgear and control gear.  
IS: 10118   Code of practice for selection,installation and maintenance 
of Switchgear & control gear 
IS: 9224  HRC Cartridge fuses. 
IS: 13947  Air break switches, Air break disconnectors, Air break 
disconnector  and  fuse  combination  units  for  voltages  not  exceeding 
1000 V AC or 1200V DC. 
IS: 6005  Code of practice for phosphating of iron & steel.  
General Description  
(a)  The  panel  shall  be  metal  enclosed,  single  front,  indoor,  floor/wall  mounted 
with  compartmentalized construction type.  The  panel  shall be  designed for  a 
degree of protection of IP 52. The panel height shall not exceed 2100mm. In 
case, horizontal bus bars at the top are provided, panel height up to 2450mm 
is also permitted.  
(b)  The  panel  shall  be  fabricated  using  pressed  and  shaped  cold  rolled  sheet 
steel  of  thickness  not  less  than  2.0mm.   Frames  shall  be  enclosed  by  cold 
rolled sheet steel of  thickness not  less than 1.6mm.   Doors and covers shall 
also be of cold rolled sheet steel of thickness not less than 1.6mm.  Stiffeners 
shall be provided wherever necessary.  
(c)  All cut outs & covers shall be provided with synthetic rubber 
gaskets.  
(d)  The panel shall be divided into distinct vertical sections each comprising of  
i)  A  completely  enclosed  bus  bar  compartment  for  running 
horizontal and vertical bus bars.  
ii)  Completely enclosed switchgear compartment one for each circuit 
for housing  Switchfuse unit etc.  
iii)  A  compartment alley  for  power  and  control cables of  atleast  175 
mm width covering entire height.  
(e)  The front of each compartment shall be provided with the hinged 
single leaf door with locking facilities.   
KUDGI STPP 
STAGE-I (3 X 800 MW)   
Bid Doc. No. : 
CS-9573-000-1  
TECHNICAL 
SPECIFICATIONS 
PART-B   
PART-B 
8. Electrical Works.   
Page 3 of 18   
CLAUSE NO.  
TECHNICAL SPECIFICATION FOR INTERNAL ELECTRIFICATION    
(f)  Provision for installing Energymeters  inside the panel on all 
outgoing feeders for Residential buildings and on incoming 
feeder for other buildings or as specified in BOQ/Drawings.  
(g)  Panel shall be provided with suitable fixing facilities.  
(h)  Isolators  &  switch  fuse  units  shall  be  of  fixed  type,  each  feeder  shall  have 
compartmentalized construction.  
(i)  Cable entry shall be from bottom / top as required  
(j)  The panel shall be provided with three phase buses and a neutral bus bar of 
aluminium  sections  throughout  the  length  of  switchgear  panel  and  shall  be 
adequately  supported  and  braced.   Maximum  temperature  rise  of  bus  bars 
and  bus  bar  connections  while  carrying  rated  current  shall  not  exceed  40 
degree C. over an ambient of 50 degree C.  
(k)  The  minimum  clearance  in  air  between  phases  and    between  phase  and 
earth for the entire run of bus bars, bus bar connections shall be 25mm. Bus 
bar  support  insulators  shall  be  made  of  non  hygroscopic  non  combustible 
track  resistant  &  high  strength  type  sheet  moulded  compound  or  equivalent 
type fibre glass moulded material.  
(l)  All busbars shall be colour coded as per IS: 375.  
(m)  A  galvanized  steel  earth  bus  shall   be  provided  at  the  bottom  of  the  panel 
throughout  the  length.   The  size  of  GI  bus  shall  be  equal  to  half  the  cross 
sectional area of phase bus.  
(n)  The  outgoing  feeders  shall  be  switchfuse  units  or  moulded  case  circuit 
breakers(MCCBs). 
Air  break switches shall be  of  heavy duty,  single throw, group operated AC 
22  category  load  break  fault  make  type  when  associated  with  fuses  and 
suitable for 3 phase 415 V supply complying with IS: 4046.  Switch operating 
handle  shall  be  provided  with  padlocking  facilities  to  lock  them  in  off   
position.   Interlocks  shall  be  provided  such  that,  it  is  possible  to  open  the 
cubicle door only when the switch is in off position. 
MCCBs  shall  conform  to  IS:13947(Part-2)  in  all  respects.  MCCBs  shall  be 
suitable  for  3  phase  415V  or  single  phase  230V  AC.  MCCBs  shall  be  of 
thermomagnetic or static release type.  
(o)  All fuses shall be of HRC cartridge fuse link type and shall be rated for 80 KA 
rms breaking capacity at 415V AC..  
(p)  The neutral link shall be mounted on fuse carriers which shall be mounted on 
fuse bases.  
(q)  Indicating  lamps  shall  be  of  the  panel  mounting,  Cluster  LED  type  and  shall 
have  escutcheon  plates  marked  with  its  function  wherever  necessary.  The 
colour  of  the  translucent  lamp  cover  shall  be  Red  for  ON  and  Green  for 
OFF.   
KUDGI STPP 
STAGE-I (3 X 800 MW)   
Bid Doc. No. : 
CS-9573-000-1  
TECHNICAL 
SPECIFICATIONS 
PART-B   
PART-B 
8. Electrical Works.   
Page 4 of 18   
CLAUSE NO.  
TECHNICAL SPECIFICATION FOR INTERNAL ELECTRIFICATION  
8.04.01.03                   
8.04.01.04                        
8.04.01.05                
8.04.02.00  
8.04.02.01  
Name Plates and Labels  
(a)  Panel   and   all   modules   shall   be   provided   with   prominent,   engraved 
identification  plates.    The  module  identification  plate  shall  clearly  give  the 
feeder number and feeder designation.  
(b)  All  name  plates  shall  be  of  non  rusting  metal  or  3  Ply  lamicoid  with  white 
engraved lettering on black background.  Inscriptions and lettering sizes shall 
be subject to Owners approval.  
(c)  Suitable  stenciled  paint  mark  shall  be  provided  inside  the  panel/module 
identification  of  all  equipment  in  addition  to  the  plastic  sticker  tables,  if 
provided.   These  labels  shall  be  positioned  so  as  to  be  clearly  visible  and 
shall have the device number, as mentioned in module wiring drawings.  
Power Cables/Conduits Termination  
(a)  Cable  termination  compartment  and  arrangement  for  power  cables  shall  be 
suitable  for  1100  V  grade  standard  aluminium  conductor,  armoured,  PVC 
insulated and sheathed. cables.  
(b)  All   necessary   cable   terminating   accessories   such   as   Gland   plates, 
supporting  clamps  and  brackets,  power  cable  lugs,  hardware  etc.  shall  be 
provided  by  the  contractor  and  to  be  included  in  the  quoted  price  of 
Distribution Board.  
(c)  The  gland  plates  shall  be  removable  type  and  shall  cover  the  entire  cable 
alley.  Bidder  shall  ensure  that  sufficient  space  is  provided  for  all  cable 
glands.  For  all  single  core  cables,  gland  plates  shall  be  of  non  magnetic 
material.  
(d)   Suitable arrangement and space shall be provided for connection 
of outgoing feeders in conduits, if required.  
Painting  
All  sheet  steelwork  shall  be  pretreated,  in  tanks,  in  accordance  with  IS:6005.   The 
phosphate  coating  shall  be  Class-C  as   specified  in   IS:6005.  The  phosphated 
surfaces  shall  be  rinsed  and  passivated  prior  to  application  of  stoved  lead  oxide 
primer  coating.  After  primer  application,  Electrostatic  powder  painting  shall  be 
applied.  Finishing  paint  shade  shall  be  RAL  9002  unless  otherwise  required  by  the 
owner.The paint thickness shall not be less than 50 microns.  Finished parts shall be 
coated  by  pealable  compound  by  spraying  method  to  protect  the  finished  surfaces 
from scratches, grease dirt and oily spots during testing, transportation, handing and 
erection. All  hardware shall  be  Nickle/Cadmium plated.   The  pad  locking plate  shall 
also be suitably painted to avoid rusting.  
Lighting Panels  
Lighting panels shall be metal enclosed,single front, indoor, recess/surface mounting 
type. constructed out  of  1.2  mm  thick  CRCA  sheet  steel.   The   main  door  shall  be 
hinged  and  the  panel  shall  be  gasketted  with  degree  of  protection  of  IP-42.  The 
panel  shall  be  provided  with  terminal  blocks  for  incoming  and  outgoing  circuits, 
earthing   terminals,   M.S.   mounting   brackets   suitable   for   surface   mounting   on   
KUDGI STPP 
STAGE-I (3 X 800 MW)   
Bid Doc. No. : 
CS-9573-000-1  
TECHNICAL 
SPECIFICATIONS 
PART-B   
PART-B 
8. Electrical Works.   
Page 5 of 18   
CLAUSE NO.  
TECHNICAL SPECIFICATION FOR INTERNAL ELECTRIFICATION         
8.04.02.02     
8.04.02.03                
8.04.02.04      
8.04.02.05         
8.04.02.06         
8.04.02.07    
8.04.02.08  
wall/column/structure(as  applicable),  latching  arrangement  for  door,circuit  directory 
plate &  circuit diagram fitted on the inside of  the  door etc.   Removable gland plates 
shall  be  provided  for  entry  of  cables/conduits.  The  quoted  price  of  Lighting  panel 
shall  include  cable  glands  and  lugs  of  suitable  sizes  for  all  incoming  &  outgoing 
feeders.  
Wiring  inside  the  panel  shall  be  carried  out  with  1100  V  grade.  PVC  insulated 
stranded  copper  wires  of  adequate  size.    On  both  ends  of  each  wire  engraved 
identification ferrules shall be provided.  
The  Lighting  panels  shall  be  of  three  phase  or  single  phase  type  with  incoming 
Isolator/ELCB  and  outgoing  MCBs  as  per  requirement.  All  MCBs/  ELCBs/ 
Isolators/Switches etc.  shall  be  mounted  inside  the  panel  with  the  front  cover.  Only 
the  operating  knobs  of  Isolators/ELCBs/MCBs   etc.,  shall  project  out  of  the  front 
cover, through neatly machine made opening,  for safe operation against  accidental 
contact. The front  cover with  Isolators/ELCBs/MCBs shall  be  covered by  the  hinged 
main  door.  The  busbars  shall  be  made  of  solid  electrolytic  copper  of  appropriate 
cross-section  with   plug-in  or  bolted  type  Isolators/ELCBs/  MCBs.  Neutral  busbars 
shall  be  provided for  adequate  no.  of  terminals as  required.  An  earth  bar  of  similar 
size  as  the  neutral  bar  shall  also  be  provided. Phase  barriers shall  be  fitted  and  all 
live  parts  shall  be  adequately covered  by  the  front  cover.  Adequate  clearance  shall 
be provided between phases and between phase & earth.  
Equipment  mounted  inside  the  panel  shall  be  provided  with  individual  labels  with 
equipment  designation/rating.   Main  door  of  the  panel  shall  be  provided  with  label 
engraved  with  designation of  the  panel  as  furnished  by  the  employer.   Labels  shall 
be made of 3 ply lamicoid/engraved PVC having white letters on black background.  
Adequate space shall be provided for terminating incoming & outgoing cables/wires. 
Terminal bocks shall be of 750 V grade, clip-on stud type for cables and  screw type 
moulded  in  melamine  for  wires,  suitable  for  terminating  multicore  stranded 
aluminium/copper  conductor  cables/wires          of  the  required  sizes  for 
incoming/outgoing feeders. All  terminals shall  be  shrouded, numbered and  provided 
with identification strip for the feeders.  
MCBs  shall  be  current  limiting  type  with  magnetic  and  thermal  release  suitable  for 
manual closing and automatic tripping under fault condition.  MCBs shall have short 
circuit  interrupting capacity  of  9  KA  rms.   MCB  knob  shall  be  marked  with  ON/OFF 
indication.  A trip free release shall be provided to ensure tripping on fault even if the 
knob  is  held  in  ON  position.   MCB  terminal  shall  be  shrouded  to  avoid  accidental 
contact.  
The  exterior    side    of    panel,    shall    be    powder    coated    with    smoke    grey, 
shade RAL9002 and the interior side of the panels shall be white.  
ELCBs shall be  Electro-mechanical,  self  immuned type having inbuilt filter to  avoid 
nuisance tripping.   
KUDGI STPP 
STAGE-I (3 X 800 MW)   
Bid Doc. No. : 
CS-9573-000-1  
TECHNICAL 
SPECIFICATIONS 
PART-B   
PART-B 
8. Electrical Works.   
Page 6 of 18   
CLAUSE NO.  
TECHNICAL SPECIFICATION FOR INTERNAL ELECTRIFICATION  
8.04.03.00  
8.04.03.01     
8.04.03.02         
8.04.03.03      
8.04.04.00  
8.04.04.01     
8.04.04.02     
8.04.05.00  
Cable glands & lugs  
The  cost  of  cable  glands  and  lugs  shall  be  included  in  the  quoted  price  of  the 
respective  Distribution  Board/Lighting  Panel  for  which  these  are  to  be  provided  for 
termination of cables/wires.  
Cable   glands   shall   be   of   compression   type,   made   of   tin   plated   heavy   duty 
brass    castings     &     machine     finished.     Glands     shall     be      of      robust 
construction  capable    of    clamping    cable    &    cable    armour,    firmly    without 
injury  to    the    cable.    All    washers    &    hardware    shall    be    made    of    brass 
tinned.   Rubber    components    used    in    the     glands    shall    be    made    of 
neoprene/ synthetic rubber of tested quality.  
Cable  lugs  shall  be  aluminium alloy  solderless crimping  type  conforming to  IS:8309 
suitable  for  aluminium  conductors.  Crimping  of  terminals  shall  be  done  by  using 
corrosion  inhabitory  compound.  Cable  lugs  for  copper  cables  shall  be  made  of 
tinned copper and shall be provided with insulating sleeve.  
Cables & Wires  
LT   Power   cables   shall   be   of   1.1KV   grade,   multicore,   stranded   aluminium 
Conductor  ,PVC  insulated,  PVC  innersheathed,  unarmoured,  PVC  outersheathed 
conforming to IS:1554(Part-1).  
PVC  wires    shall    be    of    1.1    KV    grade,    PVC    insulated,    single    core, 
stranded,   copper   /   aluminium   conductor   conforming   to   IS:694.   The   wires 
shall be colour coded for R.Y.B. phases and neutral.   
Receptacles  
Receptacles shall be fabricated out of MS sheet of 2mm thick and hot dip galvanised 
or of die-cast aluminium alloy of thickness not less than 2.5 mm.  The boxes shall be 
provided  with   two   nos.   earthing  terminals,  and   gasket  to   achieve  degree  of 
protection,  terminal  block  for   loop-in  loop-out,  of   wire/cable  of   specified  size, 
mounting  brackets  suitable  for  surface  mounting  on  wall/column/structure,  conduit 
entry/gland plate etc. Thedegree of protection for 63A, 415V,TPN receptacle shall be 
IP-55.  The  On/OFF  switches shall  be  rotary  type,  heavy  duty,  double  break,  AC  23 
category, suitable for AC supply.  
Plug  &  socket  shall  be  of  shrouded  die-cast  aluminium.   Socket  shall  be  provided 
with  lid  safety  cover.  Robust  mechanical  interlock  shall  be  provided  for  receptacles 
type RA such that the switch can be put ON only when the plug is fully engaged and 
plug can be withdrawn only when the  switch is in Off position. Wiring inside the box 
shall  be  carried  out  with  1100  V  grade  PVC  insulated  stranded  aluminium/copper 
wire of adequate size. The terminal block shall be of 750 V grade, clip  on/ stud type, 
moulded  in  Melamine,  suitable  for  terminating  cables  of  suitable  sizes.  All  the 
terminals shall  be  shrouded. The  rating of  receptacles shall be  63A,415V,TPN,5-pin 
or 20A,240V,SPN,3-pin as per BOQ.   
KUDGI STPP 
STAGE-I (3 X 800 MW)   
Bid Doc. No. : 
CS-9573-000-1  
TECHNICAL 
SPECIFICATIONS 
PART-B   
PART-B 
8. Electrical Works.   
Page 7 of 18   
CLAUSE NO.  
TECHNICAL SPECIFICATION FOR INTERNAL ELECTRIFICATION  
8.04.06.00  
8.04.06.01                   
8.04.06.02            
8.04.07.00  
8.04.07.01  
8.04.07.02  
8.04.07.03    
8.04.07.04                    
8.04.07.05  
Switches & Socket outlets  
Lighting Switches/ Boxes  
(a)  The  switch  boxes  shall  be  of  bent  steel  construction,  fabricated  of  1.6  mm 
thick  M.S.Sheets.  The  boxes  shall  be  hot-dip  galvanized.  The  switch  boxes 
shall be provided with earth terminal.  
(b)        The switch boxes shall be flush mounted in walls.  
(c)        The switch boxes shall have conduit knock-out on all four sides.  
(d)  Switches shall be of decorative modular type having quick-make, quick-break 
mechanism, provided with position marking.The switches shall be suitable for 
single  phase,  240V,  50  Hz,  supply  and  shall  be  suitable  for  terminating  two 
wires of 1.5 sq.mm. in each bore.  
Socket outlets/ Boxes  
(a)  Socket  outlet  box  shall  consist  of  modular  socket  outlet  with  associated 
switch.  The  socket  outlet  and  switch  shall  be  flush  mounted on  a  box  which 
shall be suitable for recessed mounting into walls.  
(b)        The  socket  outlet  boxes  shall  be  fabricated  from  1.6mm  thick  M.S.Sheets. 
The boxes shall be hot dip galvanized. The boxes shall have conduit knock- 
outs on all sides. The socket outlet box shall have one earth terminal.  
Conduits & Accessories  
PVC conduits shall fully conform to IS:9537(part-3) 1983.  
The conduit shall be of approved make suitable for medium duty.  
The   conduits   shall   be   straight   and   to   be   supplied   in   standard   length.The 
manufacturers name shall be stamped on each length.  
All  accessories  /  fittings  required  for  making  the  conduits  installation  complete, 
including  but  not  limited  to  couplers,  bends,  ordinary  and  inspection  tees  and 
elbows,  reducers,  enlargers,  male  and  female  bushings,  G.I.  wires  for  cable/  wire 
pulling, terminal boxes, &  pull out  boxes  complete with  glands, gaskets and  covers, 
plugs,  saddles,  clips,  spacing  plates,  nuts,  bolts   and   screws,  other  clamping 
materials and all necessary supporting steel work shall be supplied by the contractor 
alongwith  the  conduits. The  requirements of  these  shall  be  estimated  based  on  the 
conduit  layout  drawings  prepared  by  the  Contractor  and  approved  by  the  Owner. 
The price of the accessories / fittings shall be included in the erection price of items 
quoted.   Conduit accessories shall be of   PVC. Conduits shall be joined together by 
a  vinyle  type  cement/solvent.  Minimum  size  of  the  conduit  shall  be  20mm.For 
termination  of  PVC  conduits  into  switch/outlet/junction  boxes,PVC  female  adopters 
shall  be  used.  Conduits  shall  be  bent  using  springs  of  suitable  size.  Long  radius 
bends  shall  be  provided.  Heating  shall  not  be  used  to  bend  the  conduits.  Size  of 
conduit shall depend upon number & sizes of wires to be drawn.  
The  terminal  boxes/pulL  boxes  shall  be  of  circular/rectangular  shape  made  of 
PVC.The boxes shall be complete with conduit knock outs/adaptors etc.Cover plates   
KUDGI STPP 
STAGE-I (3 X 800 MW)   
Bid Doc. No. : 
CS-9573-000-1  
TECHNICAL 
SPECIFICATIONS 
PART-B   
PART-B 
8. Electrical Works.   
Page 8 of 18   
CLAUSE NO.  
TECHNICAL SPECIFICATION FOR INTERNAL ELECTRIFICATION       
8.05.00  
8.05.01.00  
8.05.01.01          
8.05.01.02                   
8.05.01.03       
8.05.01.04     
8.05.01.05      
8.05.01.06      
8.05.01.07  
shall  be  made  of  3mm  thick   white  phenolic  laminated   sheet  of  approved  make. 
Flush cover plates shall be secured to the box with counter sunk brass screws & cup 
washers.  
Equipment Erection  
General  
The  erection  work  shall  include  receipt  at  site,  unloading,  handling,  storing, 
unpacking,  and  installation  of  all  electrical  equipments  alongwith  supply  of  all 
mounting  accessories  such  as  fixing  brackets,  clamps,  anchors,  wedges,  nuts  and 
bolts,  concrete  inserts  etc.  consumables  and  other  incidental  materials  required  to 
complete  the  installation,  testing  and  commissioning  of  the  Electrical  system  for 
successful  operation  and  to  the  satisfaction  of  Owner.  The  contractor  shall  provide 
all supervision, labour tools and rigging materials.  
The  entire  work  shall  be  carried  out  in  accordance  with  Construction 
drawings(prepared  by  Contractor  and  approved  by  Owner),specified  installation 
instructions,  manufacturers  recommendations  and/or  as  directed  by  the  Owner. 
Manufacturers  drawings  and  instructions  shall  be  correctly  followed  in  handling, 
setting,,  testing  and  commissioning of  all  equipment  and  care  shall  be  exercised  in 
handling  to  avoid  distortion  to  structures  marring  of  finished  surface  damaging  of 
delicate instruments or other electrical parts.  
The  equipment shall  be  installed in  a  neat  work-man like  manner so  that  it  is  level- 
plumb,  square  and  properly  aligned  and  oriented.  Adjustments  shall  be  made  as 
necessary   to   the   stationary   structures   for   plump   and   level,   for   the   sake   of 
appearance  or  to  avoid  twisting  of  frames,  bending  of  hinged  members  etc. 
Tolerances shall be as established in manufacturers drawings or as stipulated by the 
Owner.  
The erection work shall conform to the latest applicable Indian Standards, codes and 
practices. Electricity Rules, Fire  Insurance Regulations and  safety regulations of  the 
locality where the equipment will be installed.  All apparatus, wiring and connections 
shall be designed so as to minimize risk of fire or any damage which will be caused 
in the event of fire.  
The  contractor shall  work  in  co-ordination with  civil  and  mechanical contractors and 
where holes or openings in walls and floors, cut-outs in false ceiling are required the 
contractor shall inform the owner and other concerned contractors well in advance.  
The  contractor  shall  be  responsible  for  any  loss  or  damage  to  Lighting  fixtures, 
lamps,  Distribution  boards,  lighting  panels  etc.  during  installation.  All  damages  & 
thefts shall be made good by the Contractor till the installation is handed over to the 
owner.  
The  contractor shall  note  that for  any  change  in  the  location  of  Distribution Boards, 
panels, lighting fixtures, switches,socket outlets etc. no extra charges will be paid, in 
case  the  modifications are  informed to  the  Contractor before  commencement of  the 
work on that particular equipment or circuit.  
Except  as  specifically  approved  by  the  Engineer-in-Charge  installation  of  exposed 
conduit, mounting of lighting fixtures etc. shall be taken up only after other services   
KUDGI STPP 
STAGE-I (3 X 800 MW)   
Bid Doc. No. : 
CS-9573-000-1  
TECHNICAL 
SPECIFICATIONS 
PART-B   
PART-B 
8. Electrical Works.   
Page 9 of 18   
CLAUSE NO.  
TECHNICAL SPECIFICATION FOR INTERNAL ELECTRIFICATION     
8.05.01.08    
8.05.02.00  
8.05.02.01     
8.05.02.02     
8.05.02.03      
8.05.02.04       
8.05.03.00  
8.05.03.01     
8.05.03.02    
8.05.03.03     
8.05.04.00  
8.05.04.01     
8.05.04.02  
8.05.04.03  
such  as  piping,  air  ducting,  cable  tray/bus  duct  hangers,  structural  bracing  etc.  in  a 
particular area, have been installed.  
After  installation  of  lighting  fixtures/socket outlets,  panel  number  and  circuit  number 
shall be painted on them at a suitable place in non-residential buildings.  
Lighting Fixtures, Fans and Accessories  
The  type  of  fixture mounting will  generally be  indicated on  the  layout drawing.   The 
exact  mounting  will  however  be  decided  at  site  depending  upon  the  actual 
space/other facilities available at site.  
Wooden plugs in  walls and ceilings for fixing of lighting fixtures and accessories are 
not  acceptable.  A  suitable  fool-proof  method  (preferably  using  nylon  rawl  plug)  for 
fixing these shall be offered and this shall be subject to the Owners approval.  
Flood lights shall be mounted   on steel base facing the tentative direction shown on 
drawings.  Fixing  holes  shall  be  provided  with  slot  to  turn  the  fixtures  by  about  5 
degree  on  both  sides.    Bolts  shall  be  tightened  with  spring  washers.    Terminal 
connection to the flood lights shall be made through flexible conduits.  
In  the  rooms,  where  false  ceilings  are  provided,  the  lighting  fixtures  shall  be 
supported separately from roof slab and not from false ceiling.   The erection rate of 
lighting  fixtures  shall  include  the  supply  of  all  steel  brackets,  supporting,  anchoring 
material and hardware, also steel brackets/hangers for  bridging the  gap above false 
ceiling etc. required for installation of lighting fixtures.  
Distribution Boards & Lighting Panels  
Distribution  Boards  including  Meter  Boards,  shall  be  mounted  on  wall/floor  and 
Lighting  Panels  shall  be  mounted  on  the  walls/columns/steel  structures  at  the 
locations indicated in the drawings.  
Lighting  Panels  shall  be  installed  by  fastening  to  studs  of  not  less  than  12mm  dia 
which will be suitably grouted/welded to the wall/column by the Contractor.  
The  erection  rate  of  Dist.Boards/Lighting panels  shall  include  the  supply  of  all  steel 
brackets, supporting, anchoring material and hardware and  required accessories for 
the erection of the panel.  
Lighting Switches/ Boxes & Socket outlets/ Boxes  
The  locations  of  switch/socket  outlet  boxes  shall  be  tentatively  shown  on  the 
drawings. The exact location shall be finalized by the Contractor in consultation with 
the Engineer-in-Charge.  
All switches/socket outlets shall be flush mounted in the wall.  
Unless  otherwise  noted  on  the  drawings,  the  height  of  the  following 
fixtures/accessories, from finished floor level, shall be as follows:   
(a)        Lighting panels                                        -  1500mm   
KUDGI STPP 
STAGE-I (3 X 800 MW)   
Bid Doc. No. : 
CS-9573-000-1  
TECHNICAL 
SPECIFICATIONS 
PART-B   
PART-B 
8. Electrical Works.   
Page 10 of 18   
CLAUSE NO.  
TECHNICAL SPECIFICATION FOR INTERNAL ELECTRIFICATION                   
8.05.05.00  
8.05.05.01              
8.05.05.02  
8.05.05.03    
8.05.05.04     
8.05.05.05    
8.05.05.06       
8.05.05.07    
8.05.05.08  
8.05.05.09  
(b)        Lighting Switch Boxes                              -  1200mm  
(c)        Light Fixtures, wall bracket/exhaust fans -  2300mm  
(d)        Socket outlet Boxes                                 - 300mm (in general)  
-  1500mm (for Geyser) 
(e)  Ceiling Fans  -  2500mm 
(f)         Telephone Tag block/outlet boxes        -    300mm  
/tap-off/outlet boxes   
Conduits and Accessories 
Size of conduit shall be selected as per the table given below: 
Size of Wire  Conduit Size / Max. Number of Wires 
20 mm  25 mm  32 mm 
1.5 sq.mm.  5  10  14 
2.5 sq.mm.  5  8  12 
4.0 sq.mm.  3  6  10 
6.0 sq.mm.  2  5  8 
10  sq.mm.  -  3  5 
16  sq.mm.  -  -  3 
Embedded  conduit  shall  be  securely  fixed  in  position  to  avoid  any  movements. 
Spacing of embedded conduits shall permit flow of concrete between them and in no 
case shall be less than 40mm.  
For  direct  embedding  in  soil,  GI/PVC  pipe  shall  be  used.   Concrete  pier  or  anchor 
shall  be  provided,  where  necessary,  to  support  the  GI  pipe  rigidly  and  to  hold  it  in 
place.  
For  long conduit runs, junction/pull boxes shall be  provided at  suitable intervals (not 
exceeding 10 m) to facilitate wiring.  
Conduits  shall  be  securely  terminated  at        LPs  /junction  boxes  of  lighting 
fixtures/fans/call bells by proper fastening with a lock nut on inside and outside.  The 
number  of  conduits  terminating  at  LPs  shall  not  exceed  the  permissible  number 
considering the  glanding  area  of  lighting  panel.  Conduit  terminations shall  be  made 
water and vermin proof.  
Conduits  shall  be  cleanly  cut.   Cut  ends  shall  be  reamed  and  all  burrs  and  sharp 
edges removed.  
After installation the conduits shall be cleaned before pulling in the wire.  
Conduits  and  fittings  shall  be  properly  protected  during  construction  period  against 
mechanical  injury.  Conduit  ends  shall  be  plugged  or  capped  to  prevent  entry  of 
foreign materials.   
KUDGI STPP 
STAGE-I (3 X 800 MW)   
Bid Doc. No. : 
CS-9573-000-1  
TECHNICAL 
SPECIFICATIONS 
PART-B   
PART-B 
8. Electrical Works.   
Page 11 of 18   
CLAUSE NO.  
TECHNICAL SPECIFICATION FOR INTERNAL ELECTRIFICATION   
8.05.05.10    
8.05.06.00  
8.05.06.01      
8.05.06.02    
8.05.06.03     
8.05.06.04    
8.05.06.05  
8.05.06.06      
8.05.06.07    
8.05.06.08                
8.05.06.09    
8.05.06.10   
Lighting  fixtures  shall  not  be  suspended  directly  from  the  junction  box  in  the  main 
conduit run.  
Cabling/Wiring  
The  cables/wires  from  Distribution  boards  to  Lighting  panels  shall  be  laid  on  cable 
trays/clamped on  wall/in  GI/PVC  conduits  of  required  size,  as  per  BOQ.   The  wires 
from  lighting  panels  to  switch/socket  outlet  boxes  and  switch  boxes  to  lighting 
fixtures/Fan boxes/call bells shall run in conduits.  
All  wires  in  a  conduit  shall  be  drawn  simultaneously.  No  subsequent  drawing  is 
permissible.  
Wires  shall  not  be  pulled  through  more  than  two  equivalent  90  degree  bends  in  a 
single conduit run.  Wherever required, suitable conduit pull boxes shall be provided. 
All types of wiring concealed or unconcealed shall be accessible of easy inspection.  
Power  Sockets  and  lighting  circuits  shall  be  fed  from  different  circuits.The  switch 
controlling these circuits shall be on the live side (phase wire) of the circuit.  
Separate conduits shall be used for light, power, telephone & T.V. circuits.  
Wiring  shall  be  spliced  only  at  terminal  blocks.  Maximum  of  two  wires  shall  be 
connected  at  each  terminal.  Terminal  blocks  shall  be  of  650V  grade  screw  type 
moulded  in  melamine suitable  for  loop-in  loop-out  of  upto  4  sqmm  stranded  copper 
wires and tap off of 1.5 sqmm copper wire.  
In vertical run of wires in conduit, the wires shall be suitably supported by means of 
hard rubber plugs at each pull/terminal box.  
1100V  grade,  PVC  insulated  wires  of  different  size  shall  be  used  for  following 
purposes:  
(a)Light   Fixture   /   fan   (ceiling,   wall  2.5  mm2  stranded  Cu 
bracket,exhaust)/call bell / 5 A socket  Conductor 
(Point wiring from switches onwards) 
(b)  Circuit  wiring  for  light  points   4     mm2  Stranded  Cu 
(from lighting panel to switch box)  Conductor 
(c) Single power socket (15A)   4  mm2  stranded  Cu 
conductor 
(d)  Two power sockets (15A)   6  mm2  stranded  Cu. 
conductor  
All lighting wires of more than 6 sq.mm. size shall be crimped using suitable type of 
solderless, crimping, tinned fork type copper lugs.  
There  shall  be  maximum  of  two  power  points  on  each  circuit.  Wiring  for  first  point 
shall be carried out with 2x6sqmm copper wire while for the second point, it shall be 
carried  out  with  2x4  sqmm  copper  wires.  Wiring  for  first  point  include  wiring  from 
lighting panel to  first   point and  the  wiring for  second point shall  include wiring from 
first point to second  point.   
KUDGI STPP 
STAGE-I (3 X 800 MW)   
Bid Doc. No. : 
CS-9573-000-1  
TECHNICAL 
SPECIFICATIONS 
PART-B   
PART-B 
8. Electrical Works.   
Page 12 of 18   
CLAUSE NO.  
TECHNICAL SPECIFICATION FOR INTERNAL ELECTRIFICATION  
8.05.06.11     
8.05.06.12         
8.05.06.13     
8.05.06.14    
8.05.06.15     
8.05.06.16            
8.05.06.17     
8.05.06.18  
8.05.07.00  
8.05.07.01     
8.05.07.02    
8.05.07.03    
8.05.07.04  
Point wiring shall include the cost of conduits, wires, earth wire, switch/socket outlet 
boxes,  switches,  cover  plates,  terminal  boxes  alongwith  connectors,  pull  boxes  all 
hardware & accessories etc. as required to complete the installation.  
Point wiring shall include the following:  
(a)  Wiring from lighting panel to switch board/socket outlet. 
(b)  Switchboard & switches, socket outlets with cover plates 
(c)  Wiring from switch board to light/fan/socket/bell including earth wire etc. 
(d)  All necessary  PVC conduits,fittings with accessories.  
Separate  switch  boxes/socket  outlet  boxes  shall  be  provided  for  different  circuits. 
Power  &  lighting  circuits,  should  not  be  mixed  up  in  the  same  switch  box/socket 
outlet box.  
Each circuit shall have independent neutral wire complete upto outlet box and switch 
box.  
Earthing of the third pin shall be  included in  the  point wiring of  socket outlets. Earth 
pin  shall  be  connected  to  socket  outlet  box  earth  terminal  by  flexible  copper 
braid/wire.  
In  case  of  more  than  one  light  point  controlled by  the  same  switch,  the  wiring  upto 
the terminal block or any other approved terminations of the first light point including 
the switch shall be considered as a primary point, loop wiring from light to light shall 
be considered as secondary point and  the distinguishing rate shall be quoted. 
The maximum no. of Points controlled by one switch of 5 Amps. are as follows:  
(a)        2x36 Watts F.L.Fixtures                      3 Nos. 
(b)        1x36 Watts F.L. Fixture                      6 Nos. 
(c)        18 Watts CFL Fixtures                        5 Nos.  
Lights,  fans,  5  Amps.  socket  outlet  and  bell  push  etc.  may  be  wired  on  a  common 
circuit. Such sub-circuits shall not have more than a total of 8 points of lights, fans & 
sockets outlets. The load of each circuit shall be restricted to 800 Watts.  
There shall not be more than two power socket outlets on each circuit.  
Cabling Work  
The cost of laying of cable shall include all clamping, fixing, crimping, drilling, cutting, 
fixing  glands,  connecting to  terminal  blocks,  grounding  etc.  as  required  to  complete 
the job.  
Size  of  glands  &  lugs  shall  be  as  per  the  size  of  the  cables/wires,  selected  during 
detailed engineering.  
All  cable  entry  points  shall  be  sealed  and  made  vermin  &  dust  proof.  Unused 
openings shall be effectively closed.  
Each cable shall be tagged with the cable no. as per cable schedule. The tags shall 
be  of  rectangular  shape  &  attached  to  the  cable  by  not  less  than  two  turns  of  20 
SWG  G.I.  wire.    Cable  tags  shall  be  provided  at  each  end  of  the  cable  before 
entering  the  equipment  enclosure,  on  both  sides  of  wall  or  floor  crossing  and  at   
KUDGI STPP 
STAGE-I (3 X 800 MW)   
Bid Doc. No. : 
CS-9573-000-1  
TECHNICAL 
SPECIFICATIONS 
PART-B   
PART-B 
8. Electrical Works.   
Page 13 of 18   
CLAUSE NO.  
TECHNICAL SPECIFICATION FOR INTERNAL ELECTRIFICATION     
8.05.07.05     
8.05.08.00  
8.05.08.01     
8.05.08.02              
8.05.08.03           
8.05.08.04     
8.05.08.05      
8.05.08.06     
8.05.08.07  
8.05.08.08  
every  30  M  of  cable  runs.  Cost  of  the  tags  shall  be  included  in  the  erection  of  the 
cables.  
Cutting  of  slabs/beams/columns  and  exposing  reinforcement  are  strictly  prohibited. 
Contractor  shall  use  dash  fasteners  of  adequate  strength  for  supports  from  RCC 
structure.  
Earthing System  
Earthing  system  shall  be  in  accordance  with  IS:3043  and  Indian  Electricity  Rules, 
Codes of  practice and regulations existing in  the location where the system is being 
installed.  
Pipe  Earth  electrode for  earthing station  shall  compriseof medium class GI  pipe  of 
40  mm.  nominal  dia  and  2.5  mtr.  Long.  Bottom  half  of  the  pipe  shall  have  holes 
drilled at  intervals of  7.5  cms. on  its  surface.   Removable caps shall  be  provided at 
the  top  of  its  pipe  to  facilitate  pouring  of  water.  Suitable  clamps  shall  be  provided 
with the electrodes for connecting earth conductors.  The top of the earth electrodes 
shall be about 100 mm below ground level. While connection to the earth conductor 
shall be made at 150 mm below ground level.  The top portion of the electrodes shall 
be  enclosed in  300x300x300 mm  M  15  concrete housing and  provide with  concrete 
top  cover  and  mark.      Provision  shall  be  kept  at  each  earth  station  for  testing 
resistance.  Earth station shall be complete with alternate layers of charcoal and salt.  
Plate  Earthing  shall  comprise  of  GI  plate  electrode  of  size  600mmx600mmx6.3mm 
thickness. The electrode shall be buried in ground with its faces vertical and not less 
than  3  meters  below  ground  level.  20mm  dia.  Medium  class  GI  pipe  shall  be 
provided and attached to the electrode. A funnel with mesh shall be provided on top 
of this pipe for watering earth electrode. The watering funnel attachment shall be be 
enclosed in 300x300x300 mm M 15 concrete housing and provide with concrete top 
cover and mark. Provision shall  be  kept  at  each  earth  station for  testing resistance. 
Earth station shall be complete with alternate layers of charcoal and salt.  
GI strip of 25x6mm shall be used as earth conductor directly buried in ground & shall 
be  provided with  one  coat  of  bituminized paint, one  layer  of  half  lapped bituminised 
tape and a final coat of bituminised paint to prevent corrosion.  
Galvanized  M.S.Saddles  shall  be  used  for  clamping  earth  conductor  on  cable 
trays/structures/walls/ceiling etc.   The saddles shall be  clamped to  M.S. flat  spacers 
with  tapped holes  and  supporting the  earth  conductors.   Flats shall  be  supported at 
interval not exceeding 1000 mm and stranded wires at an interval of 500 mm.  
As  far  as  possible  all  earth  terminations  and  connections  shall  be  visible  for 
inspection.  Each  earthing  system  shall  be  so  designed  that  testing  of  individual 
electrode is easily possible. 
Connection of earthing leads to earth electrodes shall be made by means of bolting. 
The  earth  conductors  shall  be  free  from  pitting,  laminations,  rust,  scale  and  other 
electrical/mechanical  defects.  The  material  of  the  earthing  conductors  shall  be 
galvanized steel/copper as specified.   
KUDGI STPP 
STAGE-I (3 X 800 MW)   
Bid Doc. No. : 
CS-9573-000-1  
TECHNICAL 
SPECIFICATIONS 
PART-B   
PART-B 
8. Electrical Works.   
Page 14 of 18   
CLAUSE NO.  
TECHNICAL SPECIFICATION FOR INTERNAL ELECTRIFICATION  
8.05.08.09               
8.05.08.10    
8.05.08.11  (             
8.05.08.12                
8.05.08.13      
8.05.08.14  
8.05.08.15  
Metallic frame of all electrical equipment shall be:  
(a)        Earthed by two separate and distinct connections to earthing system 
(b)  Metallic sheaths, screens and armour of all multicore cables shall be earthed 
at both equipment and panel/DB. 
(c)  Lighting  fixtures,  fans,  socket  outlets,  conduits,  JBs,  switch  boxes,  socket 
outlet  boxes  shall  be  earthed  with  18  SWG  bare  copper  wire.  Single  phase 
Power socket outlets shall be earthed with 14 SWG bare copper wire. Three 
phase Receptacles shall be earthed with 8 SWG bare copper wire. 
(d)  Distribution boards shall be earthed with 50x6mm GS.flat. 
(e)  Lighting panels shall be earthed with 8SWG GI wire.  
Neutral  connections  shall  not  be  used  for  the  equipment  earthing.      Metallic 
conduits/pipes shall not be used as earth continuity.  
a)  Connections between earth  leads  and  equipment shall  be  normally of  bolted 
type.  Contact  surface  shall  be  thoroughly  cleaned  before  connections. 
Equipment  bolted  connections,  after  being  tested  and  checked,  shall  be 
painted with anti-corrosive paint/compound.  
(b)  Resistance  of   the   joints   shall   not   be   more   than   the   resistance  of   the 
equivalent length of conductor.  
(c)  All  welded  connections  shall  be  made  by  electric  arc  welding    with  low 
hydrogen content electrodes.  
(a)  Earthing  conductors  buried  in  ground  shall  be  laid  minimum  600  mm  below 
grade  level  unless  otherwise  indicated  in  the  drawing.   Back  filling  material, 
placed  over  buried  conductors,  shall  be  free  from  stones  and  harmful 
mixture. Back filling shall be placed in the layer of 150mm.  
(b)  Earthing  conductors  embedded  in  the  concrete  floor  of  the  building  shall 
have approximately 50mm concrete cover.  
(c)  A  minimum  earth  coverage  of  300mm  shall  be  provided  between  earth 
conductor  and  the  bottom  of  trench/foundation/underground  pipes  at 
crossings.    Earthing  conductors  crossing  the  road  can  be  installed  in  the 
hume pipes.  
Normally  an  earth  electrode  shall  not  be  situated  less  than  2  m  from  any  building. 
The  location of  earth electrode shall be such where the  soil  has reasonable chance 
of  remaining moist,  as  far  as  possible.  Entrances,  pavements, roadways  and  metal 
fence are definitely avoided, for locating the earth electrode.  
Minimum spacing between electrodes shall be 6000mm.  
Complete  building  earthing  system  shall  be  fully  tested  in  accordance  with  the 
relevant clauses of applicable standards.  
On  completion  of  installation,  continuity  of  earth  conductors  and  efficiency  of  all 
bonds  &  joints  shall  be  checked.    Earth  resistivity  at  earth  terminations  shall  be 
measured  in  presence  of  Owners  representatives.    All  equipment  required  for 
testing shall be furnished by contractor.   
KUDGI STPP 
STAGE-I (3 X 800 MW)   
Bid Doc. No. : 
CS-9573-000-1  
TECHNICAL 
SPECIFICATIONS 
PART-B   
PART-B 
8. Electrical Works.   
Page 15 of 18   
CLAUSE NO.  
TECHNICAL SPECIFICATION FOR INTERNAL ELECTRIFICATION   
8.05.09.00  
8.05.09.01         
8.05.09.02    
8.05.09.03     
8.05.10.00  
8.05.10.01    
8.05.10.02      
8.05.10.03    
8.05.10.04  
8.05.10.05    
8.05.10.06     
8.06.00  
8.06.01.00  
8.06.01.01  
8.06.01.02     
8.06.02.00  
8.06.01.01   
Lightning Protection System  
The Lightning protection of the building shall be provided as per  IS:2309.   G.I.Strips 
of  25x6mm  shall  be  fixed  for  both  horizontal  and  vertical  conductors.   Galvanized 
M.S.Saddles shall be used for fixing the strips on parapet walls/on vertical runs.   All 
down conductors shall be  provided with  Test joints. The min. size GI  strips used for 
directly  burried  in  ground  shall  be  25x6mm.   The  code  of  practice  shall  be  as  per 
IS:2309.  
Down conductor shall be cleated on outer side of building wall, at 750mm interval or 
welded to outside building column at 1000mm interval.  
All  metallic  structures,  within  the  vicinity  of  2  mtr.  of  any  conductor  of  lightning 
protection system, shall be bonded to the conductor of lightning protection system.    
Foundations & Civil Works  
Equipment  foundations,  panel  foundation  and  other  materials  as  per  relevant 
drawings and specifications clauses shall be provided by the Contractor.  
Any  cutting  of  masonry/concrete  work,  which  is  necessary  shall  be  done  by  the 
Contractor at his own cost and shall be made good to match the original work.   The 
contractor  shall  obtain  approval  of  the  Engineer  before  proceeding with  any  cutting 
of masonry/concrete work.  
The  contractor  shall  perform  all  excavation  and  backfilling  as  required  for  ground 
connections and casting foundations.  
Excavation shall be performed upto the required depth.  
The  contractor  shall  make  use  of  his  own  arrangement  for  pumping  out  any  water 
that may be accumulated in the excavation.  
All  excavation  shall  be  backfilled  to  the  original  level  with  good  consolidation  and 
surplus soil shall be disposed off as per the instruction of site engineer.    
Testing of Equipment & Installation  
Testing of Equipment  
All equipment to be supplied shall be of type tested quality.  
All  acceptance  and  routine  tests  as  per  the  specification,  QA  tables  and  relevant 
standards shall be carried out. Charges for these shall be deemed to be  included in 
the equipment price.  
Testing of Installation  
Inspection & testing of the installation shall be carried out as per   Part-1, Section 10 
of the National Electrical Code 1985.   
KUDGI STPP 
STAGE-I (3 X 800 MW)   
Bid Doc. No. : 
CS-9573-000-1  
TECHNICAL 
SPECIFICATIONS 
PART-B   
PART-B 
8. Electrical Works.   
Page 16 of 18   
CLAUSE NO.  
TECHNICAL SPECIFICATION FOR INTERNAL ELECTRIFICATION  
8.06.03.00       
8.07.00  
The  contractor  shall  be  responsible  for  providing  the  necessary  instruments  and 
subsidiary earth for carrying out the tests.  The earth continuity test shall comply with 
the relevant IS Standards.  In case, the results of above tests do not comply with the 
limits  laid  down,  the  contractor  shall  rectify  the  faults  until  the  required   results  are 
obtained.  
Field Quality Assurance Programme (FQAP)  
Bidder  shall  furnish  a  FQAP  for  all  equipment and  accessories used  for  the  Quality 
Assurance.  The  Field  Quality  Assurance  Programme  of  the  bidder  shall  generally 
cover the following:  
(a)  Organisational  structure  for   the  management  and  implementation  of   the 
proposed FQAP.  
(b)        Documentation Control System.  
(c)        Qualification data for Bidders key personnel.  
(d)  The  procedure  for  purchase  of  material,  parts,  components  and  selection  of 
sub   contractors   service   including   vendor   analysis   source   inspection, 
incoming raw-material inspection, verification of material purchased etc.  
(e)  System   for    shop   manufacturing   controls   including   process   controls, 
fabrication and assembly controls.  
(f)         Control of non-conforming items and system for corrective actions.  
(g)  Inspection and test procedure both for manufacture and field activities. 
(h)  Control of calibration and testing of measuring and testing equipments. 
(i)  System for indication and appraisal of inspection status. 
(j)         System for quality audit.  
(k)  System for authority release of manufactured product to the owner. 
(l)  System for handling, storage and delivery. 
(m)       System for maintenance of records.  
(n)  Quality  plan  detailing  out  the  specific  quality  control  procedure  adopted  for 
controlling  the  quality  characteristic  relevant  to  each  item  or  equipment 
furnished.  
(o)  System   for   controlling  site   activities   i.e.   receipt,   storage,   pre-   erection, 
erection and commissioning.   
KUDGI STPP 
STAGE-I (3 X 800 MW)   
Bid Doc. No. : 
CS-9573-000-1  
TECHNICAL 
SPECIFICATIONS 
PART-B   
PART-B 
8. Electrical Works.   
Page 17 of 18   
CLAUSE NO.  
TECHNICAL SPECIFICATION FOR INTERNAL ELECTRIFICATION            
1.00.00    
2.00.00       
2.01.00   
ANNEXURE    
TECHNICAL INFORMATION AND DATA TO BE SUBMITTED WITH THE 
PROPOSAL    
Bidder shall give the details of his previous experience for the similar jobs done by 
him till this date.  
Drawings and Literature:  
The   following   information   and   drawings   of   the   proposed   equipment   shall   be 
submitted  in  four  (4)  copies  by  the  bidder  along  with  his  proposal  as  separate 
appendices to the proposal.  
Complete  technical  literature  supported  by  catalogues,  as  applicable,  indicating  the 
makes,  constructional features,  type  of  material,  and  any  other  relevant  information 
and Type Test Certificates for  
(a)        Socket outlets & boxes  
(b)        Switches & switch boxes  
(c)        Conduits & conduit accessories  
(d)        Electric cables & wires  
(e)        Terminals, glands & lugs  
(f)         Distribution Boards/Lighting panels alongwith following components  
(i)  Switches / switch fuse units/MCCBs 
(ii)  ELCBs,Miniature Circuit Breakers 
(iii)  Meter boxes  
(g)        Earthing/Lightning protection materials   
KUDGI STPP 
STAGE-I (3 X 800 MW)   
Bid Doc. No. : 
CS-9573-000-1  
TECHNICAL 
SPECIFICATIONS 
PART-B   
PART-B 
8. Electrical Works.   
Page 18 of 18