Substation Design Manual PDF
Substation Design Manual PDF
DESIGN MANUAL
                  December 2012
Asset Management Department, TNB Distribution Division
                          Chapter 1: Introduction
1    Introduction
     Background
                                  1
                                  1
                                         Objectives
                                         Scope of this Manual
                                                                     3
                                                                     3
     i
             Chapter 2: Substation Design & Configuration
     Overview                     6      Electrical Clearance        12
2    Design Philosophy
     Substation Categories
                                  7
                                  8
                                         Site Considerations
                                         Operation and Maintenance
                                                                     13
                                                                           SUBSTATION
                                         Considerations              17
     Major Components             10
                                         Safety Considerations       17
                                                                           DESIGN MANUAL
                Chapter 3: PMU, PPU and 33kV SSU Design                    The TNB power distribution
3
     Introduction            18          Mini PPU                    34    network includes medium and low
     Pencawang Masuk Utama               33kV Primary Switching Station
     (PMU)                   18          (33kV SSU)                  50    voltage power lines, substations,
     Pencawang Pembahagian Utama         Testing and                       switching stations and metering
     (PPU)                   26          commissioning               54    system.
                Chapter 4: P/E, 11kV SSU and S/S Design
4    Introduction                 55     Switching Station (S/S)     93
                                                                           Proper design and construction of
                                                                           the substations is aimed to ensure a
     Indoor Distribution Substation      Compact Substation Unit
     (Indoor P/E)                 60     (CSU)                       95    reliable and robust electricity
     11kV Primary Switching              Pole Mounted Substation           distribution network. This is
     Station (11kV SSU)           82     (PAT)                       105   important in order to achieve
5    Outdoor Distribution
     Substation (Outdoor P/E)     85
                                         Pole Mounted Substation
                                         (PAT) with RMU              125
                                                                           optimum system performance,
                                                                           reduce system losses and improve
     Chapter 5: Design for Substations with Special Requirements           customer satisfaction.
     Mobile SSU                   130    Flood Prone Areas           144
6
                                                                           This manual covers the distribution
                      Chapter 6: Primary Equipment
                                                                           substations and related equipment.
     Transformers                 153    Feeder Pillar              257
     Switchgear                   211    Current Transformer (CT) 264
                                                                           The manual is a compilation of
     Neutral Earthing System      239    Potential Transformer (PT) 270    various documents, circulars and
     Medium Voltage Fuse          252                                      requirements pertaining to the
                             Chapter 9: Earthing
     Overview                     330    Earth Connections
     Earth Connections                   Below-Ground                353
     Above-Ground                 334
10                   Chapter 10: Fire Fighting System
     Overview                 363        System Components           372
     Fire System Requirements
     for TNB Substations      364
11   Mobile Equipment
                       Chapter 11: New Technology
                                   375   Cast Resin and Synthetic          December 2012
     Energy Efficient Distribution       Ester                       390
     Transformers                  384   RMU CB                      395   Asset Management Department
                                         Containerised PPU           402   TNB Distribution Division
Substation Design Manual
December 2012
Disclaimer: This Substation Design Manual is a document providing technicians, engineers, and
managers of the Distribution Division of Tenaga Nasional Berhad with an understanding of proper
substation system design. The information in this document has been prepared in good faith and
represents the Asset Management Department’s intentions and opinions at the date of issue.
The Asset Management Department may change any information in this document at any time.
ii   Substation Design Manual
     Acknowledgement
     We would like to express our deepest gratitude to the management of the Distribution Division,
     for giving us the opportunity to develop the TNB Distribution Division’s Substation Design Guide.
     Special thanks to Hj. Ismail Mohd Din (SGM), Hj. Esmet Sidqie bin A.Muttalib, Young Zaidey bin
     Yang Ghazali, Sharizal bin Shamuri, Hannah binti Ahmad Rosli and Mohd Khairul Ikram bin Ghazali
     from Substation Section, Engineering Service Unit, Asset Management Department for their
     valuable contribution and assistance in developing this manual.
     Our appreciation goes to Ideris Shamsudin from Pejabat Pengurus Kawasan Petaling Jaya;
     Tan Siew Hwa from Unit Perancangan dan Pembangunan Sistem; Hj. Muhamad Subian Sukaimy,
     Dr. Abd Rahman bin Khalid and Zaini Zainal from Protection; Mohd Jaffery Raffles and Sek Yean
     Ling from SCADA; Noor Adnan Abdul Aziz, Mohd Fatani bin A Rahman, Ahmad Ridhaudin Abdul
     Razak, Mohd Fauzi bin Mohd Ismail and Ahmad Suhaimi bin Mohamed from Jabatan Perancangan
     & Pembangunan Aset; Mohd Faris Ariffin from Overhead Section, Engineering Service Unit;
     Zahari Dollah and Mohammad Khuzairee bin Ibrahim from Unit Perkhidmatan Pengurusan Aset;
     Mohd Fahami Jaapar and Kamarul Azam Abu Kassim from Unit Perkhidmatan Perjangkaan; and
     finally Mohd Nazri bin Rahmat and Syamsul Fahrizal bin Samsu from Pengurus Kawasan Kulim.
     The project team would also like to express our gratitude to Pairolani bin Safari @ Hj Hashim and
     Govindan Gopal from ILSAS, Bangi. Not forgetting Nurul Azlina Abdul Rahman, Ir. Noradlina
     Abdullah and Mohd Aizam bin Talib from TNB Research Sdn. Bhd. and Muhamad Faiq Mohd Rozi
     from MTM Sdn. Bhd.
     Our appreciation also goes to the Uniten Team, comprising Mohd Zafri Baharuddin, Fareha binti
     Mohd Zainal, Dr. Noor Miza binti Muhamad Razali, Adzly Anuar, Nadhira binti Mat Nashim,
     Shahrul Iznan, Nurul Aishah binti Mohd Rosdi, Redia binti Mohd Redzuwan, Kamalambigai A/P
     Munusamy, Nurulaqilla binti Khamis and Norizzati Shafinaz binti Sabri for their untiring efforts
     and patience towards the successful completion of this manual.
     We welcome any feedback and improvement advice that will be useful for future revisions of this
     manual.
Thank you.
Foreword
VP Distribution Division, Datuk Ir. Baharin Din
From time to time, various technical and engineering circulars and guidelines
have been issued to ensure standard practices on substation design,
construction and installation are practiced among the states and areas.
However, there is a need to compile these guidelines in a form of a practical
handbook to be made more available and accessible for easy reference
throughout the Distribution Division.
Thank you.
iv   Substation Design Manual
     Table of Contents
     Chapter 1:      Introduction ..............................................................................1
       1.1.       Background ...................................................................................1
       1.2.       Objectives .....................................................................................3
       1.3.       Scope of this Manual .....................................................................3
     Chapter 2:      Substation Design & Configuration ...........................................6
       2.1.       Overview .......................................................................................6
       2.2.       Design Philosophy .........................................................................7
       2.3.       Substation Categories ....................................................................8
       2.4.       Major Components ...................................................................... 10
       2.5.       Electrical Clearance ..................................................................... 12
       2.6.       Site Considerations ...................................................................... 13
       2.7.       Operation and Maintenance Considerations ................................ 17
       2.8.       Safety Considerations .................................................................. 17
     Chapter 3:      PMU, PPU and 33 kV SSU Design ............................................18
       3.1.       Introduction ................................................................................ 18
       3.2.       Pencawang Masuk Utama (PMU) ................................................. 18
       3.3.       Pencawang Pembahagian Utama (PPU) ....................................... 26
       3.4.       Mini PPU ..................................................................................... 34
       3.5.       33kV Primary Switching Station (33 kV SSU) ................................. 50
       3.6.       Testing and commissioning .......................................................... 54
     Chapter 4:      P/E, 11 kV SSU and S/S Design ................................................55
       4.1.       Introduction ................................................................................ 55
       4.2.       Indoor Distribution Substation (Indoor P/E) ................................. 60
       4.3.       11 kV Primary Switching Station (11 kV SSU) ................................ 82
       4.4.       Outdoor Distribution Substation (Outdoor P/E) ............................ 85
                                                                            Substation Design Manual             v
Chapter 1: Introduction
1.1.       Background
Electricity distribution is the delivery of electricity from the transmission
network to end users or customers through the distribution network as shown
in Figure 1-1. The TNB power distribution network includes medium and low
voltage power lines and cables, substations, switching stations and metering
system. Typical medium voltage in the network is 11 kV and 33 kV. Some
parts of Perak and Johor distribution network consist of 6.6 kV and 22 kV
systems; however these are being phased out in stages.
GENERATION
                             132kV/275kV
         TRANSMISSION
275kV/132kV 275kV/132kV
                                            PMU                                       PMU
                                      132kV/11kV                                132kV/33kV
                                               PPU            PPU
                                                              33kV/11kV
         DISTRIBUTION
33kV SSU
                                             P/E
                                       11kV/0.4kV
         CUSTOMER
        Chapter 9: Earthing
        The chapter primarily covers the objectives of good earthing design, the earth
        connections above and below ground levels and the earthing components
        used.
7.   For testing and maintenance methods, please refer to the latest editions
     of the following documents:
        2.1.       Overview
        Substation design depends on many factors, either from geographical,
        technical, regulatory, or demographic requirements which determine the type
        of substation to be constructed.
        The design should also allow easy expansion of the station, if required.
        Environmental effects of the substation must be considered, such as drainage,
        noise, water supply and road traffic. Earthing must be calculated to protect
        equipment in case of a short circuit in the distribution system. Ideally, the
        substation site must be reasonably central to the distribution area to be
        served.
                                                                   Introduction   7
(l)   Prolonged equipment life through life cycle and risk assessment
    8   Substation Design Manual
Typical transformer capacities used in PPU are 7.5 MVA, 15 MVA and 30 MVA.
Typical capacity ratings are 1000 kVA, 750 kVA, 500 kVA, 300 kVA and 100
kVA. The design of these substations varies widely according to network
requirement.
         2.4.1.       Transformer
               Transformers step up or step down voltages and transfer power to
                different voltage levels.
               Power transformers work at the MV level and above.
               Distribution transformers function to step down to low voltage
                distribution voltages.
               Local transformers are distribution transformers that provide supply
                locally to the substation only.
         2.4.2.       Switchgear
               Switchgear is a switching device used to control, protect and isolate
                electrical network.
               It may comprise of disconnectors, switches, fuses or circuit breakers.
               Typically, for MV switchgears, they are compartmentalised and metal-
                enclosed.
               Configuration may be of single or double busbar system.
                o A busbar is a strip or bar of copper, brass or aluminium that conducts
                    electricity within a substation.
                o Busbars connect incoming and outgoing circuits.
                                                                     Introduction     11
2.4.4.     Disconnector/Isolator
   Disconnector/isolators function to provide isolation from live parts for the
    purpose of maintenance.
   They can only be operated in off-load condition.
   They are located inside the switchgear.
   Separate isolators are used for pole-mounted installations.
2.6.1.     General                                                                        2
It is becoming increasingly important to perform initial site investigations prior
to the procurement of substation site. The following factors should be
evaluated when selecting a substation site:
2.6.2.     Appearance
Appearance is becoming increasingly important to the public. In some areas,
zoning regulations and suggestions by local authorities often mean screening,
painting, or other measures to improve appearance. The general trend is to
locate substations in a way that they are not strikingly visible to the public.
    14       Substation Design Manual
         A substation set back from a heavily travelled road may be acceptable with
         little or no architectural treatment.
2        Substations strategically located facing main roads can be used to place
                                       1
         company contact information .
         2.6.4.       Effluent
         Effluent is water pollution, such as liquid waste or sewage from industrial
         facilities discharged into surface waters. Upon the failure of a container filled
         with a pollutant, such as oil in a transformer or oil circuit breaker, no harmful
         quantity of such pollutant (oil) may be allowed to enter a navigable waterway.
         For PPU, it is necessary to have a Spill Prevention Control and
         Countermeasures (SPCC) plan of action for disposing of effluent, should spills
         or leaks occur.
         1
           Arahan Naib Presiden (Pembahagian) TNB (Dasar Perkhidmatan dan Amalan
         Kejuruteraan), Bil. A08/2012, Penceriaan Pencawang Pembahagian Utama dan
         Pencawang Elektrik Jenis Bangunan TNB.
         2
           Arahan Naib Presiden (Dasar Perkhidmatan dan Amalan Kejuruteraan), Bil. A02/2010,
         Penggunaan Warna Cat yang Dibenarkan untuk Dinding Luar Semua Bangunan
         Pencawang Baru TNB.
                                                                   Introduction    15
2.6.5.     Weather
As dependence on the use of electricity grows, it is increasingly important that
substations operate more reliably in extremes of weather than in the past.              2
2.6.5.1.   Rain
Malaysia’s climate experiences an average of 250 centimetres of rain per year.
As such, a substation should be designed to be operable under predictable
conditions of rainfall.
Rain can also lead to soil erosion. Areas prone to soil erosion such as steep
slopes are to be avoided.
2.6.5.2.   Lightning
Malaysia has among the highest number of lightning strikes per year in the
world. Typically, for a tropical country, the keraunic level ranges between 100
to 180 Thunderstorm days per year (based upon the Malaysian
Meteorological Office).
Lightning can cause transient conditions which can trip circuit breakers and/or
damage equipment. Lightning surge arresters are the measure normally
employed for pole-mounted substation lightning protection. For substation
buildings, shielding is provided by lightning rods.
2.6.5.3.   Humidity
Being in a tropical climate, the equipment must also operate under high
humidity conditions. Consideration should be given to install differential
thermostat-controlled heating in cabinets such as circuit breaker enclosures
where condensation could be a problem.
2.6.5.4.   Altitude
Equipment that depends on air for its insulating and cooling medium will have
a higher temperature rise and a lower dielectric strength when operated at
higher altitudes. Dielectric strength of air, current ratings of conductors
    16    Substation Design Manual
3        3.1.       Introduction
         This chapter presents general information concerning the design of the
         physical arrangement of PMU, PPU and 33 kV SSU. It describes various types
         of substations, illustrates typical layouts, and presents technical criteria of
         these substations.
         3.2.1.     Overview
         Main Intake Substation / Pencawang Masuk Utama (PMU) is the
         interconnection point between Transmission’s HV network to the
         Distribution’s 33 kV, 22 kV and 11 kV MV network. Distribution Division is
         responsible for the MV primary and related secondary equipment within the
         PMU.
         Figure 3-1 is a PMU line diagram showing the responsibility boundary over the
         assets, operations and maintenance work between Transmission and
         Distribution.
                                                                    PMU, PPU and 33kV SSU Design             19
                                                                            M
                                                                                HV Busbar
                                                                            R
                                                                                   M        Main
                                                           Bus                     R        Reserve
              HV Incomer (CB)
                                                          Coupler                  OG       Outgoing
                                                                                   NER      Neutral earth
                                Y                 Y         NER
                                                                                            resistor
                                Δ                 Δ                                         Asset Boundary
                                                                                            Operation &           3
TNBT                                                                                        Maintenance
                                    Y                 Y
                                                                                            Boundary
                                                                            M
                                                                                  MV Busbar
                                                                            R
                                         Bus
                                        Coupler                O/G Feeder
 O/G Feeder
Figure 3-2: PMU with outdoor Air Insulated Switchgear (AIS) switchyard
    20   Substation Design Manual
AIS PMU consists of a large switchyard with equipments that are controlled
from a nearby substation building. Typical arrangement of the AIS PMU
substation building is shown in Figure 3-5 and switchyard arrangement in
Figure 3-6. An example GIS PMU layout is shown in Figure 3-7.
               AC
                                  Control Room               Relay Room
              Room
                      1.     Fly bus
                      2.     Lightning shield conductor
                      3.     Busbar
                                 Aluminium Tubular
                                 Supported on post insulators
                      4.     Circuit breaker
                                 Open and close operations
                      5.     Power transformer
                      6.     Isolators/disconnects
                                 Isolation duty
                                 Located on both sides of circuit breaker
                                 No current make or break rating
                      7.     Current transformer
                                 Step down current measurement
                                 Protection and control
                      8.     Potential transformer
                                 Step down voltage measurement
                                 Protection and control
                      9.     Surge arrestor
                                 Discharge over-voltage surges to earth
Figure 3-7: Layout of a GIS PMU and typical locations of major components
    24    Substation Design Manual
For civil requirement details, please refer to the “Design Guideline for Built-In        3
GIS Substation” and “Transmission Design Philosophy & Guidelines for
Substations” by the TNB Transmission Division.
    26    Substation Design Manual
         3.3.1.         Overview
         Primary Distribution Substation / Pencawang Pembahagian Utama (PPU) in
         the TNB Distribution network manages primary voltages of 33/11 kV. The PPU
3        is normally to step-down the voltage from 33 kV to 11 kV for distribution to
         pencawang elektrik (P/E) and customers. Figure 3-8 is a sample single-line
         diagram for a basic PPU.
To other PPUs
                                                                                NOP
                                        3L5                 1L5                                 4L5
                                                                                2L5
                                    R
                                                                  1W0                                 Double bus 33kV
                                    M
                                                                        1S0
                                                        1H0                   2H0
                                                    T1                         T2
                                                    30MVA                      30MVA
                                                    33/11kV                    33/11kV
                                                            31                32
                                                                        30                                      Single bus 11kV
13K5 11K5 9K5 7K5 5K5 3K5 1K5 2K5 4K5 6K5 8K5 10K5 12K5 14K5
Local
In Figure 3-8, the breakers are numbered systematically with codes as listed in
Table 3-3.
The PPU would typically contain 33/11 kV transformers, AIS or GIS switchgears
and their control panels, a local transformer for the building supply, auxiliary
battery supply, capacitor banks for power factor correction, and Neutral Earth
Resistance (NER). The NER is connected to the star point of the transformer
to limit the earth fault current.
At present there are two types of PPUs which are the conventional PPU (7.5
MVA, 15 MVA and 30 MVA) and Mini PPU (5 MVA). Mini PPU are installed for
low load areas such as outskirt/rural areas.
The following highlight some typical PPUs found in the distribution network.
    28    Substation Design Manual
           Figure 3-9: One and a Half Storey Primary Distribution Substation (PPU)
                                         – Front view
           Figure 3-10: One and a Half Storey Primary Distribution Substation (PPU)
                                          – Rear view
                                                PMU, PPU and 33kV SSU Design      29
Major components of a typical PPU are listed in Table 3-4. Figure 3-15 and
Figure 3-16 shows the location of these components in a PPU.
                                                                                        3
Generally the lowest floor is the cable cellar and the top floor holds all other
primary and secondary equipment located in the switch room, control room
and battery room. Transformer and NER bays are located outside the building
structure.
Cable cellar
3
         Underground                                                                   Spare bay
         cable trench
                                                                                Distribution
                                                                                transformer
                                                                                    bays
                                                                      NER bay
                   Local transformer bay
                              Capacitor bank bay
                           Figure 3-15: Typical ground floor layout of a PPU
Control room
           33 kV switch
         room with cable
            entry slots
          Roller
       shutter door
Loading bay
         3.4.1.       Overview
         Mini Primary Distribution Substation or Mini PPU is a 33/11 kV 5 MVA PPU
         introduced as an initiative to improve the system performance at suburban
3        and rural areas normally located far from any existing PMU/PPU with load
                                                                                   3
         density less than 5 MVA fed through long distance 11 kV distribution lines .
         The Mini PPU can also contribute in losses reduction in the suburban and rural
         area by means of:
         3
          Surat Pekeliling Pengurus Besar Kanan (Pengurusan Aset) (Perkhidmatan dan Amalan
         Kejuruteraan) Bil. A25/2012 Panduan Perancangan Dan Pemasangan Mini PPU
         33/11kV 5MVA untuk Pertingkatkan Prestasi Sistem Pembahagian
                                                  PMU, PPU and 33kV SSU Design       35
(a) Mini PPU are not suitable for cities or densely populated areas which are
    typically connected by underground cables. These underground cables
    are typically rated at 30 MVA; however the jumper (288A/16.4 MVA) and
    33 kV isolator (400A/22.8 MVA) are rated below 30 MVA, which will
    introduce bottleneck to the network.
                                                                                          3
(b) The pole-top circuit breaker short circuit rating is 12.5 kA; therefore it can
    only be used with systems having short circuit levels not exceeding 90%
    of the rating, which is 11.25 kA.
The single line diagram of the Mini PPU is shown in Figure 3-18. Figure 3-19
and Figure 3-20 provides further illustration of the basic Mini PPU
              4
configuration .
4
    A16/2010 - Panduan Perancangan dan Pemasangan Mini PPU 5MVA 33/11kV
    36   Substation Design Manual
3                                                   3 x 36 kV, 10 kA MOV
                                                    Lighting Arrestor (LA)
                     3-pole switch 36 kV, 400 A
                                                                    3 x 12 kV, 10 kA
                                                                        MOV LA
                      5 MVA 33/11 kV
                        Transformer
                            3 x 12 kV, 10 kA
                                MOV LA
                                                            2
                                                    240 mm 3C XLPE Al
B2 11 kV VCB Indoor
 21                                       1
              2
3 20
4 3
3 3
                                                                             19
                  2
                           5
                                              7                                                                    3
                                              8
                                                              16
                  6
                                                                           5 MVA 33/11 kV    17
                                    18                6000                   Transformer
                                              9
                      11        10
                                                                                                       3420
                                    18
                                                       1740       7                          12 1615
              1600
                                                  R      1000                                     R    13
                                                                      15          14    15
                               13
                                                      2000                     1850
No            Description
 1            Tubular steel pole 15 m or Spun pole 10 m, 5 kN
 2            Lightning arrester 36 kV, 10 kA
 3            Bare aluminium conductor 150 mm sq. (Silmalec) with insulating cover
 4            3-pole switch 36 kV, 400 Amps
 5            Pole top circuit breaker 36 kV, 630 Amps (Auto-recloser)
 6            3-pole switch operating rod
 7            ABC, 33 kV, 3 x 150 mm sq. + 50 mm sq. aluminium
 8            Wooden peg 6” x 6”
 9            PVC pipe 150 mm class B with UV protection
10            Pole top circuit breaker control box
11            Pole top circuit breaker control wire
              3-core XLPE insulated aluminium cable with MDPE outer sheath 11 kV,
12
              240 mm sq.
13            Single wall HDPE corrugated pipe 150 mm
14            Transformer plinth 2700 x 1850 mm (length x width)
15            Angle iron bracket 50 x 50 x 5 mm
16            HV cable box, air type, 33 kV
17            LV cable box, air type 11 kV
18            Angle iron bracket 50 x 50 x 5 mm
19            Bimetal lugs 150 mm sq. (See Detail A)
20            Copper strip 25 x 3 mm with black coating
21            Parallel grooved clamp 150 mm sq.
 Figure 3-19: Mini PPU 5 MVA 33/11kV design configuration
    38   Substation Design Manual
28
22
3 25
                                                                                      22
                                         26                   8
23
22 24
18 22
                                                         27
                                              29
                                                              22
                    No    Description
                     8    Wooden peg 6” x 6”
                    18    Angle iron bracket 50 x 50 x 5 mm
                    22    C-channel iron cross arm min. dimensions 50 x 50 x 100 mm
                          with 5 mm thickness
                    23    Flexible steel strap
                    24    Half stay clip
                    25    Stay insulator (big)
                    26    Stay wire 7/8 swg
                    27    Stay bow and thimble
                    28    Universal band
                    29    Aluminium cleats
                             The fence for the Mini PPU must be installed for the safety
               Fence         purpose and also to indicate the area of the substation. The
                             fence must be 3.05 metres tall.
17000
                                                                                                            for outgoing
                                                                              5000
                                                                                                               cables
5 MVA 33/11 kV
                                                                                                                                  11000
                4000
2000
                                    Transformer                                                      1000
                                                                                         760                                800
                                                                   Battery Charger
                                                                                                                   1200
                                                                                                     Feeder
                                2 000
                                                                                       cables
                                        Pole Top CB
1000 1000
                                                                             4000
                                                               Note
            900 mm trench depth sand filled                    1. A1 configuration VCB shall be used with approved type relays.
            with cement rendered                               2. Battery charger shall be 30 Vdc 10A/40Ah
10100
Local Tx
                                                                                                800
                                                             2000
                                                                          300 kVA
                                                                                                               1200
                                        Cable chute                                  2000
                                        for outgoing
                                           cables
3
                                                             1000
                                                                                                                      Feeder Pillar
                                                                                         1000
                                                                                                                         800 A
                                                                                                                                                       4000
                                                5000
A1
                                                                                                                                                     4000
                                                                                                                          1500
                                                                             VCB
                                                                    A1
                                                                                     17000
                                                                    B2                          Battery
                                                                                                                              3 000
                       19000
                                                                                                Charger
                                                                         760                                                                  Cable chute
                                                                                   900
                                       760                                           760
                                                                          2000
                                                                                                                                              for outgoing
                                                                                                              5000
                                                                                                                                                 cables
                                                                                                                       2000
                                                                                                                                                                      11000
                                                        5 MVA 33/11 kV
                    4000
2000
                                           Transformer                                                                                 1000
                                                4000
                                                                Transformer
                                                                                                                         760                                   800
                                                                                           Battery Charger
                                                                                                                                                     1200 Note
                                                                                                                                       Feeder1000
                                       2 000
                                                                                                                 Cable chute
                                                                                                                 for outgoing                                    approved type relays
                               2 000
                                               Pole Top CB
                                                                                                                    cables                                    2. Battery charger shall
                                                                                                      2 000
                                                         Pole Top
         1000              1000                            CB                                                                                                        900 mm trench d
                                                                                                                                                                     with cement ren
                                                                                                                                          1000
                                                                                                         4000
                                                                                          Note
                900 mm trench depth sand filled                                           1. A1 configuration VCB shall be used with approved type relays.
                with cement rendered                                                      2. Battery charger shall be 30 Vdc 10A/40Ah
Transformation from existing P/E into Mini PPU is encouraged so that new
Mini PPU can be established in a shorter timeframe and procurement for new             3
land can be avoided.
The following criteria should be considered for new Mini PPU located at the
sites of existing P/E distribution substation:
4.   Replace chain link with brick wall of 2.13 meters in height, with extra
     height of 3.05 meter high for walls adjacent to the transformer to provide
     for safety measures and pleasant view to the neighbouring households.
The suggested modified P/E layout for a Mini PPU is shown in Figure 3-23.
    44    Substation Design Manual
14620 – (48’-0’)
Tx
                                                                Existing P/E
          14620 – (48’-0’)
2500
                                                    Plinth
                                                    5 MVA                                                  H-pole with pole-top CB
                                                      Tx
                                                                                                           4Nos, 160mm
                                             1865
CHDPE Pipe
         (a) Spur with 33 kV ABC or bare overhead line directly from 132/33 kV PMU
             source or 33/ 11kV PPU;
         (b) Ring with 33kV ABC between two or more Mini PPU fed by feeders from
             the same or different 132/33 kV PMU or 33/11 kV PPU.
         Table 3-9 shows a summary of Mini PPU connection scenarios and guides on
         planning schemes with accompanying diagrams.
                                                  PMU, PPU and 33kV SSU Design       45
It should be noted that any loop in – loop out (LILO) connection from Mini
PPU to the existing main feeders between PMU to PPU, between PPUs or
between SSUs with fully switched equipment is prohibited. This is to ensure
the stability of the unit protection scheme and the operation of the main
feeders.
    46   Substation Design Manual
                                     33 kV ABC
                                    3 x 150 mm2
Mini PPU
         Figure 3-24: T-off connection from 33 kV bare overhead lines to Mini PPU
                                            PMU, PPU and 33kV SSU Design   47
33 kV Incoming Feeder 1
33 kV Incoming Feeder 2
PPU
                                                          33 kV
                                                          Interconnector
                                                          to another
                                                          PMU/PPU
                              33 kV ABC
                                        2
                             3 x 150 mm
Mini PPU
                                                              PMU
3                                                             132/33 kV
                                            2
                           ABC 3 x 150 mm
                                33 kV
                                                        Mini PPU
A typical connection from a PMU to two Mini PPUs is shown in the single line
diagram of Figure 3-27 below.
                                                Legend:
           PMU 132/33 kV                                  Lightning arrestor
                                                          Pole-top circuit
                                                          breaker                      3
                                                          3-Pole Switch
                                      Connection from
                                        another PMU
                                        or same PMU
                                       (different bus)
                                 2                          2
                ABC 3 x 150 mm         ABC 3 x 150 mm
                     33 kV                  33 kV
                                            2
                           ABC 3 x 150 mm
                                33 kV
         3.5.1.         Overview
         33kV Primary Switching Station / Stesen Suis Utama (33 kV SSU) refers to a
         station that supplies power via circuit breakers to ‘bulk supply customers’ and
3        other distribution circuits at the 33 kV voltage level.
33 kV incomer 33 kV incomer
Bus-tie
33 kV incomer 33 kV incomer
Section A Section B
Bus-tie
                                                                        100% Load
                                                      nd
           33 kV Consumer Service Feeder             2 33 kV Consumer Service Feeder
From the above diagram, the maintenance unit can perform half bus
shutdown for Section A without causing supply disruption to consumers
because the consumers’ load can be transferred to the second service cable.
    52    Substation Design Manual
         Figure 3-30 shows the typical layout of 33 kV SSU and locations of major
         components. Generally the SSU contains a switchgear room, control room,
3        battery room and metering room. Incoming and outgoing cable connections
         would be installed in underground cable trenches or a half-storey cable cellar.
         However, the actual design may vary according to the availability of land and
         suitability to the site.
Switchgear room
Control room
             Store
                                                           Battery
                                                            room
          Metering room
          Figure 3-30: Typical layout of 33kV SSU and locations of major components
                                                      PMU, PPU and 33kV SSU Design     53
         Pre-commissioning tests:
3
             (a)   Current transformer test
             (b)   Instrumentation transformer test
             (c)   Power transformer test
             (d)   Secondary equipment test
             (e)   Instrumentation verification tools test
             (f)   Validation test major component
             (g)   Testing the stability of the protection scheme
             (h)   Switchgears operation test
             (i)   Power transformers operation test
             (j)   Substation battery system test
             (k)   Test indication to the SCADA system
             (l)   Transducer test
             (m)   Grounding system test
             (n)   Heating test
         Commissioning tests:
             (a) Live phasing test
             (b) Phasing voltage test instrumentation
                                                  P/E, 11 kV SSU and S/S Design   55
4.1.        Introduction
This chapter covers general design, illustrates typical layouts, and presents
technical criteria of various types of stations for the MV/LV distribution
network. The types of substations that will be covered in this chapter are:
                                                                                       4
4.2   Indoor Distribution Substation / Pencawang Elektrik (P/E)
4.3   11 kV Primary Switching Station / Stesen Suis Utama 11 kV (11 kV SSU)
4.4   Outdoor Distribution Substation / Pencawang Elektrik (P/E)
4.5   Switching Station / Stesen Suis (S/S)
4.6   Compact Substation Unit (CSU) / Pencawang Elektrik Padat
4.7   Pole Mounted (H-Pole) Substation / Pencawang Atas Tiang (PAT)
4.8   Pole Mounted (H-Pole) Substation (PAT) with RMU
         Figure 4-1 and Figure 4-2 show sample single-line diagrams for distribution
         substations.
                  MV Incoming                                       MV Outgoing
                    feeder                                            feeder
VCB
Transformer
LV customer MV customer
          Figure 4-1: Basic VCB Distribution Substation (P/E) with 1 incoming feeder,
                  1 outgoing feeder, 1 LV transformer feeder, 1 MV customer
                                                   P/E, 11 kV SSU and S/S Design   57
         MV Incoming                                          MV Outgoing
           feeder                                               feeder
                                                                                        4
            Transformer 1                                Transformer 2
LV customer 1 LV customer 2
Incoming Incoming
                            VCB                    VCB
                                                               Busbar
Outgoing
               P/E will have switchgears that are either VCB or RMU. For Indoor P/E
                these switchgears will be installed in a switching room.
Table 4-1 highlights the characteristics and main differences between indoor
distribution substations and 11 kV switching stations.
                                 11 kV SSU (VCB)
    no transformer              1 Transformer                2 Transformers
         4.2.1.     Overview
         The indoor distribution substation or pencawang elektrik (indoor P/E) is a
         substation with all primary equipment installed within a building structure.
         Indoor P/E can be built either standalone or attached to a building. Both can
         be of single or double chamber type, with or without a metering room.
In practice, the real estate developer will construct and provide the substation
building based on the requirements specified by TNB during project planning.
Attached P/E
 Figure 4-5: Indoor – attached, double chamber P/E designed to blend with
                           surrounding structures
Figure 4-6: Indoor – standalone, double chamber P/E designed to blend with
                           surrounding structures
    62       Substation Design Manual
                The sizes below can also cater for SCADA equipment installation.
                Total land area required will need to take into account of land setback
                 requirements.
                Please refer to the latest version of ESAH for updates or changes in layout
                 design.
Major components of a typical indoor P/E are listed in Table 4-4. Figure 4-8
and Figure 4-9 shows the location of these components in indoor P/Es.
Feeder pillar
                                              RCB                              LV feeder
                                                                           underground ducts
                  Manhole                 11 kV feeder
                                        underground ducts
            Figure 4-8: Layout of Standalone Indoor Substation – Double Chamber
Insulating mat
                                                                                          Ventilation
                                                                                             fans
                                                                                         11 kV
                                                                                     feeder cables
                                                                          RCB
                                                                     Feeder pillar
                                         LV feeder
                                     underground cables
          Figure 4-9: Layout of Attached Indoor Substation – Double Chamber with
                                       Metering Room
                                                 P/E, 11 kV SSU and S/S Design   65
Suggested locations for the metering room with respect to the customer are
shown in the following Subchapters (4.2.2.4 and 4.2.2.5).
2000
                                               Metering
                                        550    Cubicle
                                                  1100
                              2000
Entrance
Figure 4-10: Layout for installing metering cubicle in the metering room
         Substations for LV bulk customers must be located at the front area of the
         gated factory with a separate access from the main factory access. This is
         required because of the following objectives:
               TNB personnel can enter the substation easily without getting permission
                from the customer.
               TNB personnel can perform cable and substation upgrading work without
                disturbing roads/facilities inside the customers’ compound.
                                                    P/E, 11 kV SSU and S/S Design    67
(a) Size of the substation must comply with setback and frontage
    requirement of the local authority
(b) Customers’ MSB room are recommended to be place next to the
    substation (Figure 4-11)
(c) If customers’ MSB room cannot be located next to the substation due to
    unavoidable technical issues, customers’ MSB room can be located at the
    factory’s building (Figure 4-12) with these conditions:
      i. The LV service cable cannot have any straight through joints and the
         length of the cable must be less than 250 meters;                                4
     ii. Voltage drop from the substation to the customers’ MSB is less than
         5% as suggested in the LV Planning Guideline;
    iii. If LV service cable is of single core type, it must be laid in a concrete
         trench with earthing copper tape (extended from transformer star-
         point connection) at the bottom for the physical protection of the
         cable and for ease of maintenance. The concrete trench needs to be
         filled with sand and cement rendered.
                                       Factory
                                                                Fence
                                        TNB metering
      Customers’                        room
            MSB
                                P/E
Road
Figure 4-11: Location of P/E with attached MSB room for LV bulk customers
    68       Substation Design Manual
               Customers’ MSB
                                                         Factory
Fence
Road
Figure 4-12: Location of P/E with detached MSB room for LV bulk customers
               If the land area is big, an indoor standalone P/E located at the front area
                of the gated factory is preferred.
               If the land area is small, an attached substation is allowable provided 24
                hour accessibility to the substation is possible.
                                                    P/E, 11 kV SSU and S/S Design   69
         The required land size must consider the size of the substation as shown in
         Table 4-2 and Table 4-3 previously. Additional setback and frontage
         requirement of local authorities must also be considered.
         For standalone substations, the compound area outside the building structure
         should be paved with tarmac or cement of 50 mm (2 inches) thickness with
         150 mm (6 inches) of crusher run underneath.
               Substation gate and fence should ideally be 2.1 metres or 7 feet tall.
               Decorative gate and fence designs are encouraged to harmonize with the
                surrounding.
               Fence for standalone substations can be substituted with concrete kerbs
                (minimum 150 mm in height) or bollards to mark the substation area.
               For attached substations, whenever possible, removable barriers have to
                be installed 3 metres in front of the switchgear room and transformer
                room doors such that the entrance to the substation is not blocked.
4.2.4.1.5. Drainage
4.2.4.2. Structures
4.2.4.2.1. Floor
                                            Nominally 7000 kg
                Transformer
                                         1.4 x transformer weight
                                            Nominally 8000 kg
              Indoor Switchgear
                                       1000 kg x VCB panel number
                 (VCB/RMU)
                                       (8 panels in switching room)
4.2.4.2.2. Walls
   All walls for building structures should be constructed using red clay
    bricks laid with 1:3 cement sand mortar.
   All walls should be 230 mm thick.
   All walls should be reinforced with expanded metal (exmet) at every
    fourth course in order to strengthen the wall structure.
   Partition walls between switching room and transformer room should be
    230 mm thick and 2100 mm tall.
    72       Substation Design Manual
                                                                         Expanded
                                                                         metal layer
                                                             Skirting
                        New chemical DPC
                                                                            DPC membrane
                Ground level
                                                                            in solid floor
                                             Rising damp
4.2.4.2.4. Ventilation
4.2.4.2.5. Doors
4.2.4.2.6. Roofing
         For all standalone substation buildings, the roofing style should match the
         styles of the surrounding building and area.
               RC flat roof designs shall cater for a waterproof slab, cast with waterproof
                concrete, cement screed with waterproofing agent, and provide for
                minimal shrinkage with anti cracking reinforcement.
               A layer of bituminous material must be applied to waterproof the
                concrete slab roof.
               For the attached P/E substation-type, if there are pipes across the top of
                the substation, two layers of water proof concrete roof slabs should be
                built. The first layer (closer to the substation) must contain a bituminous
                layer.
                                                 P/E, 11 kV SSU and S/S Design   75
   All trenches in the substation are to be filled with washed river sand.
   Washed river sand has the following advantages:
    (a) Avoid moisture from entering into the switchgear via the cable entry.
    (b) Better heat dissipation and minimisation of impact due to fire
          hazards.
    (c) Has arc quenching property which can protect neighbouring cables
          from a cable that is at fault.
    (d) From a safety aspect – closed trenches can eliminate the risk of staff
          falling into the trench.                                                    4
   A 50 mm (2 inch) thick cement render (1:2, cement:sand) is required to
    cover the trench. This is to minimize condensation of water from inside
    the trench and to prevent entry of vermin through the trench.
   The spacing from the trench floor to any beam or structure that may
    protrude into the trench should be 600 mm minimum. This is to ensure
    sufficient space to install the cable in the trench.
4.2.4.3. Installations
                                                                           Transformer
                                                                              guard
The feeder pillar must be installed outside the substation building to facilitate
access by fault finders and the LV maintenance team during breakdown or
shutdown.
     Table 4-7: The maximum allowable distance between metering CTs and
                       metering cubicle for LV consumer
                                             Cross Connection         Maximum
                         Secondary Rated
    CT Burden (VA)                             of Conductor            Distance
                            Current (A)                 2
                                                   (mm )            Allowable (m)
         7.5                    5                   2.5                  12.0
         7.5                    5                   4.0                  20.0
              Table 4-8: The maximum allowable distance between metering CTs and
                             metering cubicle for MV and HV consumer
             CT burden      Secondary rated         Cross-sectional area   Maximum allowable
                                                                       2
                (VA)         current (Amps)         of conductor (mm )        distance (m)
                 15                5                        2.5                    30
                 15                5                        4.0                    47
                 30                5                        2.5                    65
                 30                5                        4.0                    100
                 30                1                        2.5                   1,647
                 30                1                        4.0                   2,545
         Where meter burden for current circuit = 0.5 VA/ph
                                                      60mm
                                                                                        4
Copper strip
               Single phase wiring is required to be done with G.I. conduit complete with
                main-switch, ELCB, MCB Distribution Board and separate earthing. The
                source of supply is from the feeder pillar.
               Wiring in conduits for the Earth Fault Indicator (EFI) should be provided
                inside the switchgear room.
               Adequate lighting points should be provided and power socket outlets
                should be installed at convenient locations for the use of hand lamps,
                hand tools, etc.
4              Emergency lighting is also required inside the substation with its own
                battery capable of supplying three hour of backup power to the
                emergency light.
               External lighting should utilise weather proof light fittings and operated
                via a photoelectric control unit (PECU).
4.2.4.4. Finishes
4.2.4.4.1. Colour
4.2.4.4.2. Signboard/Signage
      Head
 protection                                                            No smoking
                               1245
    20                    20                  20           20
              505                 330              330
                                                                   20
                                                                 155
                                                                   20
                                                                 155
                                                                   20
                                                                 210      1005
                                                                   20
210
                                                                   20
                                                                 155
                                                                   20
200 200
150 150
240 240
         4.3.1.     Overview
         Essentially, the 11 kV Primary Switching Station or Stesen Suis Utama (11 kV
         SSU) is a switching station which is installed with 12 kV, 630 A, 30 VDC VCB
         panels, with or without distribution transformers. Additionally, it must also be
         installed with a bus-section panel.
Incoming Incoming
VCB VCB
Outgoing
            Figure 4-22: Example single line diagram for primary switching station
                              (11 kV SSU) without transformer
Incoming Incoming
VCB VCB
Outgoing
            Figure 4-23: Example single line diagram for primary switching station
                                (11 kV SSU) with transformer
                                                  P/E, 11 kV SSU and S/S Design   83
The number of VCB panels that can be erected in an SSU is subjected to the
maximum load duty of the DC charger and battery. Typically one unit of a
30 VDC, 10 A charger with 40 Ah battery can cater for a maximum number of
5 VCB panels. However, the actual allowable number of panels can be
determined by calculating the DC load profile duty cycle using IEEE 1118.
    84    Substation Design Manual
                                                        Underground
                                 Switchgears with       cable trench
                                   bus-section
Ventilation blocks
           Insulating
              mat
RCB
                                    LV feeder
                                underground cables
4.4.1.    Overview
Outdoor substations (Outdoor P/E) are similar in function to their indoor
counterparts. Outdoor P/E are favoured for their cost advantages, and used
mainly for rural electrification and system improvement. They are also used
for industries that have very large land areas such as farms.
incoming outgoing
                        Transformer
                        11/0.433 kV
                   Feeder Pillar
                   1600A/800A
                                                  Ventilation
                                       Roof
                   Barbed wire                  blocks for walls
            Switchgear
                                                                      Transformer
4                                                                        guard
                                                                     Transformer
Feeder pillar
         The typical existing fencing is the chain link fence. However, for new and
         future installations, ventilation blocks are preferred for fencing because they
         partially conceal the outdoor substation from public view as well as contain
         splashes of oil and/or arcing resulting from any possible flashover.
         Additionally the solid structure helps to deter unauthorized entry more
         effectively
         A roof is erected for the switchgear to cover the RMU as a protection from
         direct sunlight and heavy rain as well as providing a comfortable area for
         working personnel.
                                             P/E, 11 kV SSU and S/S Design   87
Transformer
                 Transformer installed capacity   300 kVA, 500 kVA, 750 kVA, 1000 kVA
4
                           Switchgear                 12 kV Ring Main Unit (RMU)
4.4.4.1.2. Plinth
   All plinths should have at least 150 mm above ground level. Plinth may
    need to be taller depending on special site requirements such as flooding.
4.4.4.1.3. Floor
               The substation floor surrounding the plinths must be covered with 150
                mm of stone chips in order to limit the step and touch voltage levels to a
                safe value as the crushed stone layer provides an insulation in series with
                the body.
               Optionally, a layer of tarmac is allowable as long as it matches the
                required insulation level of the stone chips.
               Both stone chips and tarmac have similar function to the insulating mat in
                the indoor P/E.
4              The additional benefit of using stone chips or tarmac is to reduce
                grass/vegetation growth.
4.4.4.2. Structures
4.4.4.2.1. Roof
4.4.4.2.2. Fence/Wall
4.4.4.2.3. Drainage
   Water drainage shall be provided at the corners of the walls at floor level
    to enable water to flow from within substation to the outside drainage.
4.4.4.2.4. Doors
                                                o
    The door shall be erected preferably at 90 angle from the RMU location
    to enable quick exit in emergency situation during switching.
   Double leaf composite doors are to be used with the dimensions 1300
    mm(W) x 1800 mm(H) each door.
                                                                                         4
4.4.4.2.5.     Signboard/Signage
4.4.4.3. Installations
The feeder pillar is installed in a recessed part of the outdoor substation wall
as in Figure 4-27.
4
                                                   P/E, 11 kV SSU and S/S Design   93
         Figure 4-33 shows the location of a switching station in a single line diagram.
         When required, switches A and C can be turned on to provide feedback supply
         in the event of network failure.
S/S
NOP NOP
A B C
4.6.1.     Overview
The Compact Substation Unit (CSU or Compact Sub) is a substation with type
tested equipment comprising of a distribution transformer, medium voltage
switchgear, low voltage feeder pillar, connections and associated equipment,
all in a compact enclosed unit.
A CSU is shown in Figure 4-34 and a basic line diagram is shown in Figure 4-35.
                                                                                        4
Advantages of the CSU include:
 Require only a small site (7000 mm x 4000 mm);
 Physically small and therefore unobtrusive, and can be erected quickly;
 Available in 500 kVA and 1000 kVA capacities;
 Can be installed in a shorter time compared to a conventional substation.
As such, the compact substation can only be considered as a last resort after
all options have been exhausted on a case by case basis. It is considered as a
special feature design in which special features cost is charged to the
customer as per Clause 8.0 of Statement of Connection Charges 1994/1995.
MV incoming MV outgoing
                                Transformer
                                11/0.433 kV
                    Feeder Pillar
                   800 A or 1600 A
         Prior approval must be obtained from the respective Regional Chief Engineer
         (Ketua Jurutera Operasi Wilayah).
         CSU with sizes bigger than 500 kVA for domestic development requires prior
         approval from the respective Regional Chief Engineer (Ketua Jurutera Operasi
         Wilayah).
                                                   P/E, 11 kV SSU and S/S Design   99
                                                                    2000
   Doors
                                    2500
                         Figure 4-36: Top view of a CSU
    100   Substation Design Manual
                RMU                                                            MV
                                                                           transformer
                                                                               tail
                                         Incoming
                                     disconnector unit
                  Outgoing fuse-switch
                     disconnectors
RMU Compartment
                    630A 11 kV 3-phase 50 Hz
HRC fuse
11 kV in                                                   11 kV out
                                                                                        4
Transformer Compartment
                                     11 kV/433 V
                                     Transformer
                                     1000 kVA
A x3
                       3 x CT                  PF          kWh    (0-1600 A)
                       1600/5 A
                                       F
                                                    10 x 400 A
                                                    Outgoing Fuse-switch
                                                    Disconnector
      The criteria mentioned here is applicable to both the 500 kVA and 1000 kVA
      CSU.
    4.6.4.2.                Plinth
    Minimum size of the CSU plinth is 4600 x 2200 mm. The CSU sits in the middle
    of the plinth and it must be able to support the weight of the CSU which is
    approximately calculated as 1.4 x 5000 kg = 7000 kg.
    The specification of the plinth shall be as in Figure 4-40 and Figure 4-41
    below. Proper plinth design is important to ease cable laying and termination
    to the CSU.
                                                                                       earth strip embedded in concrete plinth
                                                                                 with earthing rod in earthing chamber 200x200mm                                                                                                      Opening
                                                          Earth strip embedded in concrete plinth with
                                                         earthing rod
                                                                          earth strip embedded4600
                                                                    with in  earthing
                                                                         earthing
                                                                                                  in concrete plinth
                                                                                                chamber
                                                                                   rod in earthing                 200 x 200 mm
                                                                                                   chamber 200x200mm                                                                                                    Opening
                                                                                                                                                                                                                                                    4
               100                1000                                          400                            1230                          770                                   1000                 100
                                                 900         100                                                4600                                            100                  900
                      100                  1000                          150      400                          1230                    770               150              1000                100
        300
                                                       900         100                                                                                    100               900
                                                                                 150
                                                                           150                                                                     150
               300                                                                                                                                 460                                                            700
A
                                                                                     150
        400                                                                                                                                  460                                                       700
                                                                                                                                                                                                                                                A
                                                                                                 Trench
    A          400                                                                              Opening                                                                                                                           A
                               Removable                                                        LVTrench
                                                                                                    cable                                                                         Removable
                                Concrete                                                         Opening
                                                                                                                    Trench
        400                                                                                    Termination                                                                         Concrete                       400
                                 Slab
                                     Removable                                                   LV cable          Opening                                               Removable
                                         Concrete                                                                  Trench                                                          Slab
               400                                                                              Termination       11kV cable                                              Concrete                     400
                                          Slab                                       1600                         Opening            980
                                                                                                                 Termination                                               Slab                                            2200
                                                                                                                 11kV cable
                                                                                        1600                                   980
                                                                                                                 Termination                                                                                   2200
        400
                                                                                                                                                                                                                  400
               400
                                                                                                                                                                                                       400
        400
               400                                                                                                                                 460                                                            700
                                                                                                                                             460                                                       700
                                                                                  150150
        300    300
                                                                               150150
        Foundation/RC structure to
        structural engineer’s details
                                                                                                       Compact Sub
                                           900                                                         Compact Sub                                                         900
                                   900                                                                                                                                              900
                100                                                                                                                                                                                 100mm
                                                                                                                                                                                                    thick
         100                                                                                                                                                                                        concrete   100mm
                                                                       Angle
                                           800                         Iron
                                                                                                     Cement                                                                800                      slab       thick
                300                                                 Angle
                                                                       50mm x 50mm                  Ready-Mix                                                                                                  concrete
                                  800                                                                                                                                               800                        slab
                                                                    Iron                             Grade 25
         300                                                        50mm x 50mm                                                                                                                                  1000
                                2 layers                                                                                                      Trench diisi
                                                        Trench diisi
                                4 nos                                                                                                         dengan pasir                  2 layer
                                                        dengan pasir                            Foundation/RC                                                                                        150mm                     1000
                                150mmp                                                                                                                                      2 nos 150mmp
               600      2 layerscable chute                                                                                                         Trench diisi                                     thick trench
                                                    Trench diisi                                 structure to                                                               cable chute
                        4 nos                                                                                                                       dengan pasir                                     base on
                                                    dengan pasir                                                                                                                     2 layer
                        150mmp                                                                    structural                                                                                         50mm thick 150mm
        600                                                                                                                                                                          2 nos 150mmp    screed
                        cable chute                                                                                                                                                                               thick trench
               150                                                                             engineer’s details                                                                    cable chute                 base on
                                                                                                                                                                                                                 50mm thick
                                                                                                                                                                                                                 screed
        150
                      100 50             800                 50 100               400                     1230                        770                100 50             800            50 100
      The area around substation plinth can be filled with crusher run and a thin
      layer of premix to ease maintenance work in a future and prevent unwanted
      vegetation growth.
4.7.1.     Overview
Pole-mounted substations or Pencawang Atas Tiang (PAT), also known as
H-pole substations, contain substation components and equipment that are
safely and securely mounted on pre-stressed spun concrete poles. Pole-
mounted substation designs can be used for both 33 kV and 11 kV systems to
be stepped down to LV.
It is the most economical substation because it does not require any high             4
voltage switchgear and utilises only a small piece of land. These substations
can also be erected in a very short amount of time due to its simple design
and construction requirements.
PATs are suitable for rural areas where the load density is low. At the same
time, a larger number of these small capacity substations may be required to
satisfy customer demand. Pole-mounted substations can be considered for
the following conditions:
The disadvantages of PAT are that they are not encouraged as a permanent
solution and not more than 3 such substations may be erected in series.
    106    Substation Design Manual
      As can be seen in the single line diagram in Figure 4-43, the PAT is connected
      to 11 kV or 33 kV MV feeders, preferably isolated by 3-pole switches,
      protected by external drop-out fuses, feeding to a transformer which steps
      down voltage to be distributed via an LV feeder pillar. Optionally, LV may be
      distributed through a fuse-switch disconnector (black-box) as shown in
      Figure 4-44.
                        MV incoming                     MV outgoing
4
                                                              Lightning
                                  EDO Fuse                     arrester
                                                 Distribution
                                                 transformer
                                Feeder Pillar
                                                Link switch
                                                    Fuse-switch
                                                    disconnector
MV incoming MV outgoing
                                              Lightning
                           EDO fuse            arrester
                                      Distribution
                                      transformer
                                           Fuse-switch
                                           disconnector
    (3a)                                                (2)
Isolator link                                     Covered jumper
                                                    conductors
                                                             (4)                 4
                                                     Lightning arrester
    (1)
Underground
                                                           (5)
 MV cable
                                                         EDO fuse
                                                             (6)
                                                         Insulating
                                                           covers
                                                           (7)
                                                      Distribution
                                                      transformer
Feeder pillar
LV feeders
Pin Isolator
                                                   Lightning
                                                   arrestor
                                                   Jumper
                                                   Conductor
                                                    EDO Fuse
                                                                            4
                                                    Isolator Link
                                                    with animal
                                                    guard
                                                   Anti climbing
                                                   device
                                                   EFI
      Channel iron dimensions and distance between the poles depend on the
      system voltage level as per Table 4-14. Equipment for 33 kV are larger and
      thus longer channel irons are required.
      The number of channel irons required to support the transformer on the pole
      differs for each type of pole-mounted substation as follows:
                                                               Wooden
                                                               cross arms
Figure 4-51: Wooden cross arms shall not be used to replace channel irons
There are 5 types of insulating covers to be used on PATs listed here and
shown in Figure 4-52:
    1.     Animal guard
    2.     Conductor cover
    3.     Lightning arrester cover
    4.     Drop out fuse cover
    5.     Transformer bushing cover
    116    Substation Design Manual
          (2) Conductor
          cover
                                                       (3) Lightning                   6
                                                       arrester cover
      Guidelines provided here are also applicable to all other substations with pole
      structures.
4.7.4.1. Structures
      Usually, 4 numbers of stay wires are used to support the 2-pole structure. For
                                                                                   2
      33 kV PAT where the primary incoming cable uses bare conductor 150 mm ,
      Silmalec, the pole structure is to be supported by 4 numbers of stay wires (45
      tonne, SWG 7/8).
                                                                    Legend:
                                                                        Pole
                                                                        Transformer
                                                                        Stay wire
                                       Main Road
                                Figure 4-53: Stay wire (top view)
                                                  P/E, 11 kV SSU and S/S Design     119
For area that has limited space for stay wires, a concrete base (concrete grade
25) is used to support the structure. The dimension of the base depends on
the system voltage level as shown in the following table.
Concrete base
Concrete footing
4.7.4.2. Installations
                                                                    SF6 load
                                                                    break switch
Buried underground cables are preferably used for feeder cables instead of
overhead cables to connect to the first pole. This practice is to prevent
animals like squirrels and monkeys from reaching the pole-mounted
substation via any overhead line.
                                                                                            4
All underground cables entering and leaving the PAT should be encased in
150 mm G.I. pipe or PVC class B pipe (3 m long, with 2.7 m above ground and
0.3 m underground) and attached to the pole for cable protection. All cable
terminations must be of a type/brand pre-approved by TNB for use in the
distribution system.
For 11 kV connections the incoming and outgoing feeders use XLPE, 3-core,
         2
150 mm , aluminium underground cables. Sometimes, the incoming cables
consist of 11 kV ABC.
For LV system, typical connection from the secondary side of the transformer
to the fuse switch disconnector or feeder pillar is shown below:
      To achieve buried connection to the first pole of the low voltage overhead
      system for prevention of animal encroachment, the outgoing cable from the
      fuse switch disconnector that connects to the first pole is typically LV XLPE, 4-
                    2
      core, 185 mm , Aluminium underground cable.
      The single core cables must be laid in trefoil and must not be laid singularly
      (alone) in a G.I. pipe. This is to avoid induced and circulation currents in the
      G.I. pipe.
      Due to the height of the transformer on the PAT, the stressing effect of the
      weight of the connected cables to the LV transformer bushings, especially
      when LV underground cables are used, can be damaging to the bushings.
      Hence, proper and sufficient cable clamping must be provided to support the
      weight of the LV transformer tail.
Jumper conductors connect the incoming cable to the lightning arrester, down
to the EDO fuse and then to the HV bushing of the transformer. The
conductors used are typically:
    
                                               2
           For 33 kV PAT – ABC, 33 kV 3x150 mm , Aluminium
    
                                              2
           For 11 kV PAT – ABC, 11 kV 3x150 mm , Aluminium
However, the use of a feeder pillar is also allowable to provide more outgoing
LV feeders for better load distribution. Using several fuse-switch
disconnectors to achieve this has the disadvantage of being prone to lose
contact issue as several LV cables will be connected to a transformer bushing.
          Anti-climbing device
4
Substation signage
4.8.1.    Overview
Pole mounted substations (PAT) with insulating cover and ring main units
(RMU) is a combination of insulated pole-mounted with outdoor substation
for the 11 kV system.
The advantages of the PAT and RMU are ease of operation, suitable to limited
land area and cheaper construction costs compared to outdoor P/E.
                                                                                     4
However, it is important to ensure that permission to use the appropriate
land area is obtained from the local authorities.
11 kV incoming 11 kV outgoing
                          Distribution
                          transformer
                  Fuse-switch
                  disconnector
Figure 4-57: Single line diagram for PAT with RMU connected to fuse-switch
                                disconnector
    126     Substation Design Manual
11 kV incoming 11 kV outgoing
                                  Transformer
                                  11/0.433 kV
                             Feeder Pillar
                             1600A/800A
          Figure 4-58: Single line diagram for PAT with RMU connected to feeder pillar
                                             P/E, 11 kV SSU and S/S Design   127
                                                                                   4
                                                           Transformer
                                                           bushing covers
Transformer
RMU
Feeder pillar
The Mobile SSU was introduced to perform the main functions as below:
The Mobile SSU enables TNB to fulfil its commitment for high network
reliability which in turn would enhance TNB’s service level.
3 2 1 1 2 3 4 5 6 7 8
Mobile SSU
                      On-Site Transformer
        Figure 5-2: Mobile SSU connected to an on-site transformer
    132   Substation Design Manual
      5.1.2.      Layout
      All equipment for the Mobile SSU is contained inside a standard intermodal
      ISO container sized compartment, which is pulled on a trailer. Figure 5-3
      below shows the dimension of the container.
                                                      Landing Gear
                 Prime mover
5
2590 (8.5ft)
                   3940 (12.9ft)
                  General height
1350 (4.4ft)
Figure 5-4 below shows the locations of major components inside the Mobile
SSU. A Mobile SSU typically consists of:
The following figures show some of the equipment inside the Mobile SSU.
(a) (b)
(c)
           Figure 5-9: Cable entry point into the GIS switchgears underneath the
                                       2                     2                    2
          Mobile SSU, (a) 3C x 240 mm , (b) 3 x 1C x 500 mm , (c) 3 x 1C x 630 mm
                               Design for Substations with Special Requirements   137
The Mobile SSU requires an external LV power source to provide supply to all
LV instruments including battery charger and air conditioning.
       1 for 33 kV switchgears
       1 for 11 kV switchgears
       1 for CRP
       1 for other equipment such as battery charger and LVAC
    138   Substation Design Manual
      PPUs typically have 10 to 14 feeders. The Mobile SSU is designed to supply for
      half-bus loads which is 7 feeders.
   Installation altitude
    High‐voltage switchgear can be installed up to an altitude of 1000 meters.
    At higher installation altitudes, the reduced voltage endurance must be
    taken into account.
                                                                                        5
   Air pollution
    The ambient air must be free of dust, smoke, corrosive or combustible
    gases, steam and salts.
           Pengurus Besar
           Jabatan Perkhidmatan Logistik
           Bahagian Perkhidmatan Korporat
           Tenaga Nasional Berhad
           129 Jalan Bangsar
           50732 Kuala Lumpur
The container is suitable for prime mover class 4 x 2 for loads less than 35
tonnes. The prime mover should also have fifth wheel coupler.
      5.1.4.3.     Equipment
      The special tools/ test plug supplied with the Mobile SSU are:
      Two sets of landing gear supports are provided at the front and back side of
      the container. The container will stand on these landing gears while in
      operation.
      During parking, the mobile SSU will be supported by the landing gears and
      tyres. If wedges are to be used, the wedges suitable for 41 ft trailer are
      recommended.
                                    Design for Substations with Special Requirements   141
The mobile container requires its own comprehensive first party vehicle
insurance, separate from the prime mover insurance.
The container requires a separate road tax from the prime mover. For road
tax renewal, the container should undergo road worthiness inspection
annually at PUSPAKOM.
Prior to towing the container the followings inspection and actions should be
taken:
5.1.4.4.9. Security
      For the purpose of prevention of theft and unauthorized entry, pad locking
      options are provided at each door.
5.1.5.2.     Equipment
The electrical installation shall be tested at each re‐location prior to start‐up,
or at intervals not exceeding 6 months, whichever comes first. The result of all
tests shall be recorded and retained.
It is essential that the common earth grid is tested in order to ensure that the
impedance to earth is not greater than the value required as calculated using
IEEE Std 80 as in Subchapter 9.3.
The cable insulation resistance tests shall be carried out between phases and
earth, between phases, and between phases and neutral.
    144    Substation Design Manual
      5.2.1.       Overview
      Generally, new substation sites should not be placed in flood prone areas.
      Meanwhile for existing substations in flood prone areas, mitigation steps need
      to be taken to prevent damage of substation equipment.
      The following flood mitigation techniques are summarized from Pekeliling PBK
      (Pengurusan Aset) Bil. A22/2012 – Kaedah Mitigasi Pencawang 11kV dan 22kV
      di Kawasan yang Dilanda Banjir.
      5.2.2.       Methodology
      The standard methodology for electrical installations flood mitigation is
      outlined below:
      1.    Maximum Flood Level – Get historical and expected worst flood level
            information from Jabatan Pengairan dan Saliran / Drainage and Irrigation
            Department (DID). This information will be used to construct the
            substation floor to a higher level than the worst flood level.
      2.    Mitigation Technique – Select the appropriate mitigation initiatives. In
            general, the most suitable mitigation method shall comply to the
            following:
            (a) Safety issues when operating the equipment shall not be
                 compromised.
            (b) The minimum clearance between tools/workers and the live parts
                 should be met.
                                  Design for Substations with Special Requirements   145
Initiatives for new and existing substations to reduce the effect of flooding
upon the distribution network are explained as follows:
(a) Protection of individual equipment – raise plinth level for the equipment              5
    or the floor of the substation.
(b) Protection of buildings – build a flood wall at the substation door
    (indoor), block water entry through cable trench or install submersible
    pump to pump out water from the substation.
(c) Convert to pole mounted substation.
(d) If the above mitigation options cannot be implemented, relocate the
    substation.
Selection of mitigation techniques are based on the height of flood level and
type of substation involved. The mitigation techniques for the following types
of substations are further discussed in this chapter:
 Raise feeder pillar plinth level to one foot above the flood level.
      This configuration will ensure that the MV feeder can still supply to other
      unaffected areas.
          Raise RMU plinth level to one foot above the flood level; or
          Replace the RMU with load break switch (LBS).
          If the water level does not reach the transformer, replace the RMU with
           load break switch.
          If the water level reaches the transformer, PAT must be relocated.
                                    Design for Substations with Special Requirements   147
     Raise the RMU, transformer and feeder pillar plinths to one foot above
      the flood level; or
     Raise the substation floor to one foot above the flood level.
     Raise the substation floor to one foot above the flood level.
     If raising the floor is not possible, change the substation to pole-mounted
      substation (PAT).
     If both are not practical, the substation has to be relocated.
    Figure 5-15: RMU, transformer and feeder pillar plinths are raised higher
                              than the flood level
           Figure 5-18: Raised substation floor for flood level of more than 3 feet
                                    Design for Substations with Special Requirements   149
   Raise the RMU, transformer and feeder pillar plinths to one foot above
    the flood level; or
   Raise substation floor to one foot above the flood level; or
   Construct a water barrier / flood wall at the substation door and install a
    submersible water pump. Water entry through cable trenches should be
    blocked to minimise the amount of water entering the substation.
Figure 5-20: Water barrier / flood wall constructed at the substation door
           Figure 5-21: Higher flood walls may require staircase access to be built
                                    Design for Substations with Special Requirements   151
 Raise compact substation plinth to one foot above the flood level.
   Raise compact substation plinth one foot above the flood level.
   If this is not practical, change to PAT or relocate the substation.
Figure 5-22: Raised compact substation plinth one foot above the flood level
    152   Substation Design Manual
6.1. Transformer
6.1.1.       Overview
In “IEC Standard 60076 – Part 1: Power Transformers”, a transformer is
defined as a static piece of apparatus with two or more windings which, by
electromagnetic induction transforms a system of alternating voltage and
current in one winding into another system of alternating voltage and current
in one or more other windings, usually of different values and at the same
frequency for the purpose of transmitting electrical power.
Laminated Core
primary secondary
                                        (9)
                                                       (8)
                        (10)
                     (11)                                         (7)
             (12)
(6)
(1)
                                                                                         6
                                                       (5)
                                              (4)
                     (2)               (3)
(8)
                                            (9)                                   (7)
                                  (10)
                        (11)
                                                                                (6)
(1)
(2)
                           (3)
                                                                    (5)
                                                      (4)
6
                1.         HV winding                       7.    Top clamping
                2.         LV winding                       8.    Neutral bar
                3.         Core (limb)                      9.    LV bar (red phase)
                4.         Insulation (press board)         10.   LV bar (yellow phase)
                5.         Bottom clamping                  11.   LV bar (blue phase)
                6.         LV connection bar
                                                   (13)                       (12)
                                                                                     (11)
                                              (14)
                                       (16) (15)
                                      (17)                                                      (10)
                               (18)
                        (19)
                    (20)
                                                                                                     (9)
                 (21)
(8)
                                                                                       (7)
6
                                                                             (6)
           (1)
                                 (9)
                  (10)
(8)
(1)
                                                                  (7)
          (2)
(3) (6)
(4) (5)
HV Winding LV Winding
                             HV Winding              LV Winding
6
           Figure 6-7: Phasor diagrams and clock number notation showing phase
          displacement of +30⁰ for 3-phase transformers with connection symbols
                                     Dyn11 and YNd11
                                                        Primary Equipment   163
HV Winding LV Winding
                 HV Winding                LV Winding
                                                                                  6
 Figure 6-8: Phasor diagrams and clock number notation showing phase
displacement of -30⁰ for 3-phase transformers with connection symbols
                            Dyn1 and YNd1
    164   Substation Design Manual
      The load loss, also known as winding loss, copper loss or short circuit loss of a
      transformer is generated by the flow of load current which varies as the
      square of the load current. Load loss can be divided into three categories:
      
                           2
           Resistive loss (I R) within the winding conductors and leads. This type of
6          loss dominates load loss.
          Eddy current loss in the winding conductors
          Stray loss due to leakage flux that intercepts the tanks and structural
           steelwork which give rise to the eddy current flow
      Other losses are due to effect known as magnetostriction where magnetic flux
      in the core, causes it to physically expand and contract slightly with each cycle
      of the magnetic field, produces the humming sound commonly associated
      with transformers. This can cause losses due to frictional heating. In addition
      to magnetostriction, mechanical loss due to fluctuating forces between the
      primary and secondary windings as the result of the alternating magnetic
      field. These incite vibrations within nearby metalwork, adding to the humming
      noise and consuming a small amount of power.
      The guaranteed no-load loss and load loss in kW of distribution and power
      transformers are as shown in the tables that follow.
                                                              Primary Equipment       165
                                                  Output
                              %Efficiency =
                                              Output + Losses
Where,
      Example of energy efficiencies at 0.9 lagging power factor for TNB distribution
      transformers of various sizes calculated using the above formula are as
6     plotted in the graph of Figure 6-9.
      The graph shows that distribution transformers are most efficient between
      0.4 to 0.5 per unit loading. It also shows that bigger capacity transformers by
      design, for example 1000 kVA, are more efficient as compared to the lower
      capacity, for example 100 kVA.
      As such, the design and construction of all types of substations should strictly
      follow the requirement underlined by the latest revision of ESAH in order to
      ensure the noise generated by a transformer is contained within the
      substation so that the noise radiated outwards from the substation will not
      exceed the specified limits above.
                                                            Primary Equipment    169
      6.1.4.12. Overloading
      The normal design life expectancy of a transformer is based on continuous
      duty under design ambient temperature and normal service or rated
      operating conditions. However, the application of a load in excess of
      nameplate rating and an ambient temperature higher than design ambient
      temperature involves a degree of risk and accelerated ageing that reduces the
      expected design life of the transformer.
      Although the maximum loading capability of the transformer can be safely set
      to 100% under normal condition of its capacity for a design ambient
      temperature of 40:C, it is technically possible to overload the transformer
      under the following conditions:
               33/11,
                             +5% to -5%      2.5%      33000       34650        31350
              33/0.433
Category 2, 22/11, 11/22,
                             +5% to -5%      2.5%      22000       23100        20900
   3&4        22/0.433
              11/0.433
                             +5% to -5%      2.5%      33000       11550        10450
              0.415/11
    172   Substation Design Manual
              *Step-up transformer
                                                            Primary Equipment   173
33/0.433 kV
                                   22/0.433 kV
                                                     100, 300, 500, 750, 1000
     Distribution Transformer                                 kVA
                                   11/0.433 kV
      (Category 4)
                                  6.6/0.433 kV
    *Step-up transformer
    174   Substation Design Manual
      6.1.5.1.    Core
      The purpose of transformer core is to provide a low reluctance path for the
      magnetic flux linking primary and secondary windings. The core is made up of
      stacks of thin laminated magnetic sheet. Each lamination is insulated by a thin
      non-conducting layer of insulation that increases resistivity of the material to
      minimize the eddy current loss. The use of high permeability grain oriented
      silicon steel is preferred due to its improved grain orientation to reduce
      hysteresis loss.
𝜙1 𝜙2 𝜙3
      6.1.5.2.    Winding
      A winding is made up of conductors, coiled concentrically around the
      magnetic circuit limbs to produce the desired number of turns in which will
      determine the voltage of the winding. The conductor is usually made of
      copper which is electrically insulated from each other with paper and in some
      cases with enamel and paper to ensure that the current travels throughout
      every turn.
      The number of turn and the current in the winding primarily determine the
      choice of winding type. The maximum current density in any winding is
                                                2
      designed usually not higher than 3 A/mm to reduce the dynamic effect
      during short circuit.
Enamel coating
Conductor
For layer type winding, the turns are arranged axially along the winding. The
consecutive turns are wound close to each other without any intermediate
space. The winding may be made as a single or multilayer winding.
    178   Substation Design Manual
      Foil windings are made of wide copper sheet, from some tenths of millimeter
      up a few millimeters thick. It is usually used for windings with a small number
      of turns but relatively high currents. The main technical advantage is that axial
      mechanical forces acting on the windings in the transformer during short
      circuit currents become insignificant.
The disc winding concept is used for windings with a large number of turns
and relatively small currents. It is built up of a number of discs connected in
series. The major difference between a helical and a disc winding is the
number of turns per disc. In helical windings there is never more than one
turn per disc while disc windings have more than one turn per disc.
(a)
                      (b)                                (c)
                            Figure 6-20: Disc winding
    180   Substation Design Manual
      The helical winding is suitable for high currents where the current is shared
      between several parallel strands. The quantity of conducting material that can
      be fitted inside a given volume is high compared to other types of winding.
      Moreover it is mechanically robust and easy to manufacture, particularly
      when continuously transposed cable is used.
(a)
                            (b)                                  (c)
                                  Figure 6-21: Helical winding
                                                              Primary Equipment        181
Mineral hydrocarbon oil has been the major liquid electrical insulation due to
its high dielectric strength to withstand the electric stresses imposed in                   6
service. It also has sufficiently low viscosity to circulate and transfer heat, thus
it has been used as cooling medium in power transformers.
The combination of oil and cellulose material is one of the most satisfactory
insulant yet known and the electrical and thermal strength of this
combination is much higher than that of the individual materials used
separately. For example in terms of temperature rise, cellulose material alone
is of Class Y insulation with thermal withstand capability of up to 90:C.
However, with the impregnation of oil, the cellulose material has become
Class A type insulation with the maximum thermal withstand capability of up
to 105:C.
    182   Substation Design Manual
In ONAN type cooling system, heat is transferred from the windings, core and
structural metal parts to the oil. The heated oil circulates in the transformer
tank by the principle of natural convection and it is cooled by the natural air.
Cooling fins and radiators provide the means of increasing the area for heat
dissipation.
In ONAF type cooling system, fans mounted on the radiators, are used to
force an air blast on the radiators to increase the heat dissipation rate. The
fans are automatically switched on when the temperature of the oil and
windings increases above the permissible value. This happens during heavy
load condition and during higher ambient temperatures. Forced cooling can
increase the kVA rating of an oil immersed transformer by 15% to 30%.
                               (a)                                   (b)
                   Figure 6-29: Off circuit tap changer basic connection type
                                (a) Linear and (b) Single Bridging
                                                           Primary Equipment       189
The function of an OLTC is to switch from one winding tap to another without
interrupting the load current. OLTC can be installed inside the transformer (in-
tank) or in an externally mounted compartment which is welded or bolted to
the transformer tank. Figure 6-30 illustrates both of the OLTC installation
types.
  Figure 6-30: Type of OLTC installation showing in-tank (left) and external
                            compartment (right)
There are two different designs of OLTC which are the diverter switch type
and the selector switch type OLTC. Figure 6-31 (a) shows diverter switch type
which has a tap selector and a diverter switch in a separate compartment; and
(b) the selector switch type also known as arcing type selector which
combines both functions of tap selector and diverter switch in one oil-filled
compartment.
The oil filled compartment is a free breathing tank connected via a pipe to a
conservator with the addition of a dehydrating breather to remove moisture
from the air that is in contact with the oil as shown in Figure 6-32. On the
other hand, there are two switching principles that have been used for the
load transfer operation during tapping transition i.e. by means of high speed
resistor or reactor.
    190   Substation Design Manual
                                                                  Change-over
                                                                  selector
                                      Diverter
                                      switch
                                                                     Selector/Arching
                                                                     switch
                                                                     Transition
                                                                     resistors
                                      Tap
                                      selector
(a) (b)
          Figure 6-31: Two Different Types of OLTC (a) Diverter Switch Type OLTC,
                               (b) Selector Switch Type OLTC
6
                                                 Change-over
                                                                                       6
                                                   selector
                      Transition
                       resistors
Vacuum switch
      There are three different kinds of connecting schemes to which the OLTC can
      be connected to the tapping winding (Figure 6-35) which are:
           (a) linear,
           (b) plus/minus; and
           (c) coarse/fine.
                                                                                       6
 Figure 6-35: Typical arrangements of tapping winding for OLTC connection
On the other hand, for larger tapping ranges, tapping winding in plus/minus or
coarse/fine arrangements can be used. In plus/minus arrangement, the
tapping winding is connected to the main winding via a change-over selector
that functions as plus minus switch. This switch provides an ability to add or
subtract the voltage of the tapping windings to or from the voltage of the
main winding allowing the tapping range to be doubled and at the same time
reduce the number of the tapping windings.
   Rupture Disk
The rupture disk is a pressure-relief device without signaling contact located
in the OLTC cover. Faults with large energy release can lead to strong pressure
waves with high pressure peaks, which can damage the on-load tap changer
oil compartment. An overpressure of more than 5 bar will rupture the disk
and enables the pressure to relieve immediately.
           Table 6-11: Maximum dimension and weight for new power transformer
                                Complete Installation
                                                                       Transport Arrangement
            33/11 kV               Arrangement
          Transformer                              Total                                    Total
                             L x W x H (mm)                         L x W x H (mm)
                                                 Weight (kg)                              Weight (kg)
            1.5 MVA         2380x1400x2460            5500         2380x1400x2460            5500
             5 MVA          3500x3300x3400            15000        3400x1480x2540           12000
            7.5 MVA         5890x3140x3120            20000        3640x3020x3120           16550
            15 MVA          6160x3730x3380            32300        3940x3730x3380           28750
            30 MVA          7390x3900x4120            46800        4390x3900x3190           41900
             30 MVA
                            7260x4950x4710            54350        4760x4950x3370           49300
          (33/22-11 kV)
                                                                Primary Equipment      197
Distribution and power transformers are equipped with outdoor type oil-air
bushings made of solid porcelain on HV and LV sides for both phase and
neutral terminals. All conducting parts of the bushing are designed for rated
current of the transformers and capable to withstand overcurrent during
earth fault and cyclic overloading.
For distribution and power transformers, crimping type terminal lugs are
provided where they are bolted onto the HV and LV bushing terminals. For
new LV bushing design, bushing flag is provided on the LV and neutral                        6
terminals for the cable lug connection.
              Table 6-13: Minimum size for crimping type terminal lugs for Power
                                        Transformers
                         HV Terminals             LV Terminals
          Tx Rating                                                         Neutral
                            33 kV                     11 kV
                      3 x tinned copper lug   9 x tinned copper lug   1 x tinned copper lug
          30 MVA                  2                       2                       2
                      for 400 mm Cu cable     for 400 mm Cu cable     for 400 mm Cu cable
            Partially insulated cable box – cable cores only are fully shrouded for the
             appropriate highest system.
            Fully insulated cable box – All live metal parts and cable cores are fully
             shrouded for the appropriate highest system voltage.
                                                               Primary Equipment    199
The minimum air clearance for open bushing terminals and bushing terminals
in cable box is tabulated in Table 6-14 below.
415 V 77 58 - -
Gas actuated relay is also known as Buchholz relay after its inventor. The gas
actuated relay is fitted in the connection pipe between the main tank and the
conservator. The relay has two functions:
  To collect free gas bubbles on their way up to the conservator from the
     transformer tank.
  To detect abnormal oil flow to the conservator in the event of a serious
     fault such as arcing within the transformer.
    200   Substation Design Manual
      At all times, the gas actuated relay should be filled with oil. When gas is
      generated in the transformer due to incipient fault, the gas will displace the
      oil in the relay and float will sink down. The protection is therefore arranged
      in such a way that when a minor amount of a gas is collected in the gas
      actuated relay an alarm signal is actuated. If an additional amount of gas is
      collected tripping contact may be actuated.
                                                           Primary Equipment       201
When a serious fault such as arcing occurs in the transformer, the gas
evolution will push a burst of oil up towards the conservator causes the lower
element to be deflected, actuating the contacts of the tripping circuit, thus
disconnecting the transformer from the supply.
                                                                                         6
Figure 6-40: Winding temperature indicators for power transformer (left) &
                      distribution transformer (right)
                                         Dedicated CT
                                         Calibration
                                         Calibration circuit
                                                         circuit
                                                    Temperature sensing bulb
                                                    Capillary tube
                                                    Dial gauge & switches
      The temperature of the winding depends on the transformer load and the
      temperature of the cooling medium. These two parameters are measured and
6     made to interact in the temperature indicator. The winding temperature is
      therefore measured by adding the temperature difference of the winding to
      top oil temperature.
      Fans are preferably activated as soon as the temperature hits the set value,
      but it is not switched off again until the oil has truly cooled. There should be a
      10 degree temperature difference in fan auto start and stop to avoid hunting.
      The recommended temperature settings are:
  Figure 6-42: Magnetic oil level gauge for (left) the conservator tank; and
      (right) top cover of hermetically sealed distribution transformers
The dehydrating breather contains silica gel crystals. During expansion and
contraction of transformer oil due to change in temperature, the air passes
over the crystals which absorb any moisture in the air. Thus, allowing only dry
air goes inside the tank and reducing the amount of moisture absorbed in the
oil and winding insulation that can speed up degradation process. Due to
moisture absorption, the silica gel changes colour from blue to pink in the
course of time. On the other hand, new type of silica gel is cobalt chloride free
and is non-carcinogenic. It changes colour from orange when dry to green or
colourless when contains moisture.
The amount or mass of silica gel used is calculated based on among others the
mass of oil used, the maintenance interval and the average thermal cycle of
the transformer. Silica gel can be dried and restored to the original colour by
heating, though, proper health and safety cautions should be taken. The
dehydrating breathers are also provided with an oil trap, preventing
continuous contact between the moist air and the silica gel, thus allowing a
                                                                                          6
longer life and lower maintenance of the silica gel.
<10%
                                         35%
                                         50%
60%
                                         90%
         (a)                  (b)                             (c)
6.1.5.8.7. Valves
      Figure 6-48 and Table 6-16 below shows typical schematic drawing for valves
      arrangement and their functions respectively for power transformers.
Valve Legend
   Table 6-16: Description of typical valves and types used for power
                               transformer
 Item                       Description                         Size
   1.    Oil sampling/complete drain valve               50 mm gate type
   2.    Filter valve (top)                              50 mm gate type
   3.    Shut off valve for HV disconnecting chamber     25 mm gate type
   4.    Buchholz relay shut off valve                   80 mm gate type
   5.    Radiator shut off valve                         80 mm plate type
   6.    OLTC conservator drain valve                    25 mm socket type
   7.    Return valve for OLTC                           25 mm gate type
   8.    Oil drain valve for HV disconnecting chamber    25 mm socket type
   9.    Oil surge relay shut off valve                  25 mm gate type
  10.    Main conservator drain valve                    25 mm socket type
  11.    Suction valve for OLTC                          25 mm gate type
    208   Substation Design Manual
n a b c a b c
                 A          B            C        N        A        B       C
6
              Figure 6-49: Typical terminal markings for step-down (left) and
                                step-up (right) transformers
6.2. Switchgear
6.2.1.     Overview
In “IEC 62271-1 Part 1: High-voltage Switchgear and Controlgear – Common
Specifications”, switchgear is defined as a general term covering switching
devices and their combination with associated control, measuring, protective
and regulating equipment, also assemblies of such devices and equipment
with associated interconnection, accessories, enclosures and supporting
structures.
      6.2.1.1.     Enclosure/Panel
      Installations are designed so that their insulation capacity, degree of
      protection, current carrying capacity, switching capacity and mechanical
      functions conform to TNB requirements. These designs are tested against the
      IEC standards to verify that the design could withstand and perform within
      their designated rating.
                Atmospheric air
                Fluid form e.g. SF6 gas, oil
                                      (3)                     (4)
                (1)        (2)
                                                                              (5)               6
 (12)
                                                                               (6)
                                                                             (7)
                                                                                    (8)
      6.2.2.1.     Enclosure/Panel
      Metal-enclosed switchgear panels normally consist of:
           To house the withdrawable circuit breaker and the facility to test the
            circuit breaker in isolated position.
           A set of metal shutters is provided to cover each 3-phase group of
            stationary isolating contacts. Each set is capable of being individually
            operated and padlocked closed. The shutters shall open and close
            automatically by a positive movement. When padlocked the shutters
            shall prevent access to the fixed isolating contacts.
Metal shutter
Earthing switch
Space heater
Reserve busbar
    spout
Cable spout
  Main busbar
    spout
      The busbars shall be adequately supported against short circuit forces and
      provision shall be made to allow for thermal expansion of the conductors due
      to normal and pulse load currents and short circuit current. The busbars shall
      be contained in a separate compartment within the general casing of the
      switchboard.
6
The cable compartment is designed to cater for the connection of the power
cables and the switchgear. This is to provide lasting and dependable
connection of cable conductors and the switchgear. The methods of
connection employed could be of the bolted or the plug in method.
In the case of air insulated switchgear panels, cable compartment would cater
for a 3-phase air insulated cable box suitable for dry type non thermal
termination system. The cable box shall be suitable for terminating the
maximum size of the following types of cables:
                                          2
    1.   33 kV, XLPE, single core, 630 mm , Aluminium
                                         2
    2.   11 kV, XLPE, single core, 500 mm , Aluminium, with M16 bolts
                                         2
    3.   11 kV, XLPE, three core, 240 mm , Aluminium, with M12 bolts
6.2.2.1.4. LV Compartment
          Figure 6-59: Control gear and protective device inside the control relay panel
                                                              Primary Equipment       219
Circuit breakers used complies with the requirements of IEC 62271-100 and
meets the technical specification of TNB Distribution. All circuit breakers
having the same rating shall be identical in arrangement and shall be
interchangeable.
The circuit breaker type is differentiated by its arc extinction medium for                 6
example vacuum, SF6 gas and dielectric oil. The type of circuit breakers that
has been used in TNB Distribution system is as follows:
Bulk and minimum oil circuit breaker utilize transformer insulating oil for arc
extinction. In bulk oil circuit breakers, the contacts are separated inside a steel
tank filled with dielectric oil while in minimum oil circuit breaker, the three
phase contacts are mounted in separate insulated housing filled with
dielectric oil.
Bulk and minimum oil circuit breaker has been phased out due to
environmental and operational issues.
    220   Substation Design Manual
      In vacuum circuit breakers, the fixed and moving contacts are housed
      permanently inside a sealed vacuumed ceramic bottle. The arc is quenched as
      the contacts are separated in vacuum. In the MV switchgear range, vacuum is
      the most predominant insulating medium for circuit breaking.
Gas circuit breaker employs Sulphur Hexafluoride (SF6) gas for its arc
quenching medium. The three phase breaking contacts are individually
housed in gas filled insulated chambers at pressures of above 1 bar. The
pressure and gas flow for arc quenching is obtained by piston action.
       Stationary
       arc contact                        Stationary
                                           contact
Nozzle
    Moving
                                           Moving
  arc contact
                                           contact
                                         Piston rod
      Cylinder
                                           Piston
                                                                                       6
             Opening                            Opening
      TNB Distribution Division requires that the earth switch be provided to earth
      the outgoing circuit. Circuit earthing shall be carried out by means of three
      phase quick-acting fault-making earthing switches which forms an integral
      part of the switch panel. The design utilised for earth switches is normally of
      the manual charged spring operation.
      6.2.2.5.    Indicators
      Capacitive voltage indicator is provided for every feeder to give indication if
      the every phase of the feeder is live or not. Mounted on the front fascia, the
      indicator typically uses neon bulbs that light up or blink when the circuit is
      energised.
                                                            Primary Equipment      223
6.2.2.7.     Interlocks
All switchgears shall be provided with a comprehensive system of strong
mechanical interlocking device as well as electrical and software interlocks to
prevent any dangerous or undesirable operations.
                      B2-50 = 50/5 CT
                                                B2-200= 200/5 CT
                      B2 -75= 75/5 CT
  Metering CT                                   B2-300= 300/5 CT
                     B2-100= 100/5 CT
                                                B2-400 = 400/5 CT
                     B2-150 = 150/5 CT
                                                                            Not
                                                                          Required
    Voltage
                                    11/0.11 kV(sq.rt 3)
  Transformer
 Ammeter/Volt       Ammeter to be in built in Relay but voltmeter
   meter                            is required                                                 6
   Relay Test        Automatic current shorting and isolating trip
 Terminal Block                 circuit to be provided
  Trip Circuit                                                         To provide push
                           To utilize relay in built functions
  Supervision                                                              buttons
Where,
A1 – Circuit Breaker with Overcurrent & Earth Fault Protection Relay
A4, A5, A6 – Circuit Breaker with OCEF, inclusive of Class X 600/300/5 CT’s with relays
for unit protection with specific relays
B2 (1) – Circuit Breaker with OCEF Protection Relay and VT &CT for metering (wound)
B2 (2) – Circuit Breaker with OCEF Protection Relay and VT & CT for metering (ring)
C1 – Bus Section
    226        Substation Design Manual
(11)
(1)
(2)
                                                                                       (10)
      (3)
(4)
      (5)
6
      (6)                                                                           (9)
                                                                             (8)
                                                               (7)
       13
        8
       10
12
13 1
       10                                                           3
            9
        8                                                           4
                                                                    6
        7
                                                                    2
                                                                                     6
      6.2.3.1.    Enclosure/Panel
      The gas-insulated and metal-enclosed switchgear has been designed to
      optimize availability and operator safety. The advantages of having gas-
      insulated switchgear are as follows:
                                                                          Vacuum
                                                                        Interrupter
                                                                        Contact fingers
                                                                         (fixed type)
6
                       Figure 6-70: Typical Fixed Type CB used in GIS
      6.2.3.5.    Indicators
      Another important indicator is the SF 6 gas level gauge, also called manometer.
      The manometer gives indication whether sufficient level of SF 6 is present
      inside the tank especially prior to operation of the switches.
                                                            Primary Equipment     231
6.2.3.7.     Interlocks
The interlocks are to ensure safety to operators and correct sequence of
operation of all circuit breakers, load break switches, isolators, earthing
switches.
      To operate the switches inside the tank, operating mechanisms are mounted
      externally on the tank and actuated manually using operating handles.
      In TNB, the RMU is the switching equipment used extensively in the 11 kV and
      22 kV systems as it suits the system configuration and protection practice.
6
      Additionally, the RMU offers the following advantages:
      (a)   Economical
      (b)   Ease of maintenance
      (c)   Space saving
      (d)   Suitable for indoor and outdoor use
SF6 tank
     Operating
     mechanism
For the insulation, RMU can either use mineral oil or Sulphur Hexafluoride
(SF6) gas. The insulation is responsible to clear the arc during operation. Other
than that, the insulation will also assist in cooling the bus-bar and the switch
blade inside the tank. In TNB, the RMU installed in the system is currently of
SF6 gas insulated.
    234    Substation Design Manual
                              (a)                               (b)
          Figure 6-72: (a) Example of an outdoor RMU with front enclosure to achieve
          IP54 requirement (b) When the enclosure is opened, the front fascia can be
6                       accessed for operation and to observe indications.
The typical ratings for the RMU are given in the following table.
Additionally, the RMU is internal arc tested to minimum 20 kA, 1 second for                 6
the tank with accessibility Type A. Internal arc test is a type test used to verify
that the RMU is able to withstand the overpressure within the RMU due to
fault or flashover and hence to contain the arc internally without endangering
the authorised operators present near the RMU. Pressure relief valves are
installed on the tank usually at the bottom and are designed to rupture first
when there is overpressure inside the tank to release the arc away from the
authorised operators.
Tank
                                     Pressure
                                   relief device
      A load break switch (LBS), as used in an RMU, can be used to make and break
      a circuit under normal load current. However, it can only make but cannot
      break the circuit during short circuit or fault conditions.
      Due to this characteristic, the operating handle supplied with the RMU to
      activate the operating mechanism of the LBS must have features to prevent
      inadvertent breaking on fault to occur within 3 seconds after unintentional
      closing on fault during operation. This requirement can be achieved for
      example by the use of anti-reflex handle. The LBS is gang-operated to ensure
      the 3 phases are operated simultaneously.
Figure 6-77: Example of anti-reflex handle for LBS (Siemens 8DJ 20)
    238       Substation Design Manual
      6.2.4.3.        Switch-Fuse
      The main function of this switch-fuse is to control the T-off circuit, which is
      connected to the distribution transformer. Switch-fuse is essentially an LBS
      connected in series with a fuse. Other than the closing and opening
      operations, this switch is able to trip and isolate the supply automatically
      during overload and fault conditions. In order to trip and isolate, a medium
      voltage fuse is used to trigger the tripping mechanism. Alternatively, the
      switch-fuse can also be replaced by a circuit breaker to control the
      transformer T-off feeder. The tripping of this circuit breaker is controlled by a
      time-lag fuse. The correct ratings of high voltage fuse and time-lag fuse must
      be ensured for proper protection is achieved.
      6.2.4.4.        Interlocks
      The RMU is equipped with mechanical interlocking facilities to ensure safety
      to operators by principally preventing the following operations:
      6.2.4.5.        Indicators
      Capacitive voltage indicator is provided for every feeder to give indication if
      the every phase of the feeder is live or not. Mounted on the front fascia, the
      indicator typically uses neon bulbs that light up or blink when the circuit is
      energised. It is possible to conduct low voltage live phasing of the ring feeders
      at the capacitive voltage indicator.
      Another important indicator is the SF6 gas level gauge also called manometer.
      The manometer gives indication whether sufficient level of SF 6 is present
      inside the tank especially prior to operation of the switches.
6.3.1.     Overview
TNB distribution practices an “effective system earthing” policy where the
source of supply at PMU and PPU must be earthed at the star point on the
secondary side of the transformer. This type of earthing system is known as
Neutral Earthing System where neutral is earthed by means of solid or
resistive earthing. Resistive earthing is achieved by the use of Neutral Earthing
Resistor (NER). The main purpose of the NER is to limit the single phase to
earth fault to a transformer rated full load current, thus protecting
installations, such as cables and transformers from damages due to extreme
heat generated by the fault current.
NEI
NER
       Table 6-22 summarizes the normal rating of voltage, current and the size of
       NER and NEI used.
          Table 6-22: Standard ratings of voltage, current and the size of NER and NEI
                Power Transformer                                    NER                       NEI
                                                                                     NEI
                         Secondary Secondary                    Voltage Current               Voltage Current
     Voltage Capacity                             Resistance                       Busbar
                           voltage       current                 rating rating                Rating Rating
    ratio (kV) (MVA)                                 (Ohm)                           size
                          rating (V) rating (A)                    (V)      (A)          2      (V)      (A)
                                                                                    (mm )
    33/22-11      30          22           787        16*          22      1600    10x100       36      1600
    33/22-11      30          11          1575         4*          22      1600    10x100       36      1600
      33/22       30          22           787         16          22      800     10x100       36      1600
      33/11       30          11          1575          4          11      1600    10x100       12      1600
      11/33       15          33           262         24          33      800     10x100       36      1600
      33/11       15          11           787          8          11      800     10x100       12      1600
      22/11      12.5         11           656         16          11      800     10x100       12      1600
      22/6.6     12.5         6.6         1093          4          11      1600    10x100       12      1600
        *Note: NER dual rating specific for connection of star point transformer dual ratio 33/22-11 kV
                                                           Primary Equipment       241
 Figure 6-80: Dry metallic type NER showing the metallic resistor elements
                                   (grid)
    242   Substation Design Manual
6.3.2.1.1. Voltage
      NER is often described by the system or line voltage of the supply, e.g. 11 kV
      NER. The maximum voltage that NER actually experiences in service is the line
      to neutral or phase voltage. The available voltage ratings of the NER in TNB
      distribution network is as shown in Table 6-22.
                                                               MVA
                                        Ifull   load   =
                                                             3 × Vline
      System impedances are ignored. This implicitly specifies the ohmic resistance
      value of the NER as follow.
6                                                           Vphase
                                               NER =
                                                           Ifull load
      By Ohms Law, the ohmic resistance value of the NER can also be calculated
      by:
                                                            V 2 line
                                                NER =
                                                            MVA
                                                        30
                                Ifull   load    =                = 1574 A
                                                       3 × 11
                                                        112
                                          NER =             =4Ω
                                                        30
      Table 6-22 provides a comprehensive list of the current ratings and ohmic
      resistance values according to the transformer capacity.
                                                           Primary Equipment      243
6.3.2.1.3. Time
6.3.2.1.7. Termination
NER has three main terminals or connection points. The first terminal
connects one end of the resistor to the neutral of the transformer. The second
terminal connects the remaining end of the resistor to earth. The third
terminal provides enclosure earth bonding.
      The NER in TNB distribution network is typically designed to have the degree
      of ingress protection for the enclosure of at least IP23 in accordance with IEC
      60529. The materials used within a NER typically include resistive alloys,
      stainless steels, ceramics, galvanised steel and copper. All of these materials
      are durable in harsh environments. Hence the need for stringent
      environmental protection is low.
      Higher IP ratings of the NER in excess of IP54 can significantly restrict the
      escape of heat from the resistor. High IP requirement thus can significantly
      increase size and weight of the NER to cater for effective heat dissipation. This
      will result in higher cost.
6
      NER is hot during and after operation. The IP rating does not infer that it is
      safe to touch the NER.
6.3.2.1.9. Enclosure
      The enclosure is made of stainless mild steel or galvanised steel for free
      maintenance.
The Isolators are typically single pole double air break, centre rotating post
type with minimum 50 degree blade opening and is of wall mounted type.
Neutral busbars is made of tinned copper. The isolator blade is made of
copper where its tip is coated with silver for good electrical contact.
The neutral earth switch is normally provided with vertical drive rod and
mechanism box. The adjustable drive rod is made of galvanised steel pipe with
length and diameter suitable for easy operation. Adjustable rod clamp is also
provided to allow for on-site adjustment of the vertical drive rod.
6.3.2.2.1. Ratings
The ratings of the NEI namely, voltage, impulse withstand voltage continuous
current and time are designed to be at least equal to the ratings of the NER.
The minimum short circuit current rating of the NEI is shown in Figure 6-22
below.
However, most of the NEI used in the system is often rated at 25 kA, 3 secs.
    246        Substation Design Manual
                                                       NEI busbar
                                50˚ blade opening
          Disconnectors
                                                                           Vertical drive rod
           Non-thermal
           termination
                                                                             Adjustable
                                                                             drive clamp
                                                                               Mechanical
                                                                             switch assembly
6.3.2.2.3. Clearance
      The air gap between terminals of the same pole with the isolator open is
      designed to be of a length to withstand a minimum impulse voltage wave of at
      least 115 percent of the specified impulse insulation rating to earth. The
      typical distance of the gap between the terminals of the same pole for NEI
      rated at 33 kV is 500 mm.
Sample calculation to determine REF and SBEF CT ratios for 30 MVA 33/22 kV
transformers neutral earthing system is as follows.
                                                  NER 
                                                              22,0002     16
                                                             30,000,000
CTSBEF = 800/5A
                                                                    33
          30 MVA           800/5 A    900/1 A
                                                   CTREF  600        / 1  900 / 1A
         33/22 kV                                                   22
                            3
                                      3
                           SBEF       REF
                                                   22 kV
 IFL = 787.3A ≈ 800A
                                        NER        800 A
                                                   16 Ω
                                                                                              6
Sample calculation to determine REF and SBEF CT ratios for 30 MVA 33/11 kV
transformers neutral earthing system is as follows.
                                                 NER 
                                                             11,0002     4
                                                           30,000,000
  IFL = 524.9A ≈ 600A                            INER = IEF = IFL ≈ 1600A
CTSBEF = 1600/5A
                                                                  33
           30 MVA          1600/5 A   1800/1 A   CTREF  600        / 1  1800 / 1A
          33/11 kV                                                11
                             3
SBEF REF
                                                    11 kV
IFL = 1574.6A ≈ 1600A
                                         NER        1600 A
                                                    4Ω
    248     Substation Design Manual
CT 1
CT 2
iii.       Neutral Switch Auxiliary Contacts enclosed in stainless steel cubicle for
           each isolator connecting to Transformers 1 and 2, NER and direct earth
           connection and is rated for 110 VDC with eight numbers (8 Nos.) of
           Normally Open and eight numbers (8 Nos.) Normally Close contacts.
        Figure 6-83: Neutral Switch Auxiliary Contacts cubicle for indication of the
                              isolator’s open-close operation
                                                                                               6
       6.3.3.     Safety
       During single line fault to ground, fault current will flow through NER, copper
       conductor connecting NER to NEI, copper busbar on the NEI and back to the
       transformer star point via the neutral cable as depicted by Figure 6-84.
Red Phase
Star Point
Blue Phase
If Fault
          Figure 6-84: Fault current flowing If due to phase short circuit to earth
    250   Substation Design Manual
      The fault current flowing through the NER will instantaneously produce a
      voltage across it approximately equal to the value of the phase voltage or
      VL/√3. For example, the voltage across the NER connected on the star point of
      a 33/11 kV transformer during single line to ground fault is approximately
      6.35 kV. This proves that NER and NEI including all neutral earthing
      conductors are High Voltage equipment as defined in TNB Safety Rules since
      during single line to ground fault the equipment will experience phase-to-
      earth voltage of more than 600 V. As such, NER, NEI and all neutral earthing
      conductors shall be treated strictly in accordance with TNB Safety Rules.
      In the event where NER is isolated and transformer star point is connected
      directly via solid earthing, fault current will flow directly to earth. This will
      produce a voltage approaching the earth potential or 0 V. However, the value
      of the fault current will rise as no NER is connected to limit the fault current.
      Hence, when working with NER, NEI and all neutral earthing conductors, the
      procedures stipulated in Subchapter 6.3.4 shall be strictly observed.
6
      6.3.4.      Procedures When Working with NER, NEI and Neutral
                  Earthing Conductors
      6.3.4.1.    General Procedures:
      (a) The NER Bay shall be locked at all time to prevent anyone from entering
          the area without the permission from TNB authorized personnel.
      (b) All TNB personnel or contractors must wear safety shoes provided or
          approved by TNB when entering the high voltage zone including the NER
          Bay.
      (c) All TNB personnel must wear the personal protective equipment (PPE)
          when operating the high voltage equipment during shutdown and
          normalization of supply.
      (d) Only TNB approved wooden ladder shall be used when working in the
          high voltage zone including the NER Bay.
                                                           Primary Equipment      251
      6.3.4.5.    Prohibitions
      (a) Any work performed on the NER, NEI and neutral earthing conductors
          that are directly connected to NER, NEI Busbar and star point of any
          energised transformer is totally PROHIBITED. This is to avoid danger to
          the personnel resulting from the high voltage produced in the event of
          single line to earth fault.
      (b) Bypassing the NER by means of connecting the solid earthing to the
          neutral earthing system at any time is totally PROHIBITED. This is to
          protect the respective apparatus such as cables and transformers from
          damage due to infinitely high fault current due to the absence of the NER.
      (c) Concealing the neutral earthing conductors underneath the surface of the
          substation wall is PROHIBITED. The fault current will leak through the
          wall surface under wet condition and can cause electrical shock to
          personnel touching the wet wall. Additionally, heat caused by the fault
          current will cause surface crack and degradation of the wall.
6
      MV fuses used in RMU in TNB system are of high rupture capacity (HRC) and
      back-up current limiting type. A HRC fuse is a fuse that is filled with silica sand
      surrounding the fuse link. It is used on applications where the fault current
      needs to be suppressed fast and with no flash over. On a fault current a
      tremendous amount of heat is created within the fuse. That heat melts the
      silica sand into glass, and glass being an insulator, suppresses the arc over and
      breaks the circuit instantaneously.
                                                                     Primary Equipment      253
MV fuses used in RMU in TNB system are also fitted a striker mechanism. This
would provide the user with a visual indication that the fuse link has operated.
Striker mechanisms are driven by explosive charges or compressed springs
and both are triggered by a thin fuse in parallel with the elements that when a
current flows through it, the elements would melt. The current would then
heats up the wire and detonates the explosive charge or melt the wire and
releases the spring, pushing the striker pin out of the fuse link’s end cap. A
suitable mechanism is used to prevent from the pin being pushed back into
the fuse body.
                                                                                                  6
                                       Granular Quartz
                   Fuse elements                              Striker coil   Expelled striker
                      Figure 6-85: Front view of MV fuse
                                      Silver ceramic
                                      point contact
                      Star core
                                                   Striker coil
                                                           Granular
                                                            Quartz
                   Fuse elements
                                           Porcelain barrel
      Another type of fuse used for transformer protection in RMU utilising circuit
      breaker is the time lag fuse. This type of fuse, also known as anti-surge, or
      slow-blow is designed to allow a current which is above the rated value of the
      fuse to flow for a short period of time without the fuse blowing. This situation
      normally arises in magnetising inrush current of transformers which can draw
      larger than normal currents for up to several seconds when first energised.
                                       442 mm
                                                                   22 kV
11 kV
292 mm
2.    Oil insulated with in-air fuse            Based on IEC 60282-1 Type III
      compartment                               with type D tags
      Example: HFU Tamco, HFU
      Cutler-Hammer
                                                                                          6
                                         Side view
Top view
          (a) Shall provide 3-phase protection against short-circuit current that occurs
              in the HV or LV side of the transformer
          (b) Able to withstand transformer inrush magnetising current which is
              typically 12 x full load current transformers for 100 ms
          (c) Able to withstand the usual periodic overcurrent up to 150% of
              transformer full load current
          (d) Giving discriminatory grading with low voltage (LV) fuses for the highest
              rating used in the LV system which is 250 A. This is to ensure that the LV
              fuses operate properly when there is fault in the LV system.
The design and technology of the DIN-type feeder pillar has been used by TNB
for feeder pillar rated at 400 Amps (also known as mini feeder pillar) since
1999. Based on the experience of using DIN-type feeder pillar 400 Amps, TNB
has started to migrate to DIN-type feeder pillar for rating 1600 A since 2010,
and since 2012 for 800 A rating.
Figure 6-88: DIN-type feeder pillar rated at 400 Amps (or mini feeder pillar)
    258   Substation Design Manual
Copper contacts
Copper contacts
             (2)                                                               (4)
      Disconnector unit                                                   Fuse-switch
         (Incoming)                                                       disconnector
                                                                           (Outgoing)
      1.    Instrument panel
             Instrument panel is only available in FP 1600 A and 800 A. It is front-
                 mounted and is equipped with ammeter with maximum demand
                 indicator and 13 A, 3 pin switched socket outlet.
             Additionally, the instrument panel is fitted with 60 A cartridge type fuse
                 wired to the blue phase busbar and one neutral link wired to the
                 neutral busbar to facilitate the connection of auxiliary single phase
                 loads such as substation lighting, portable tools, etc.
                                                          Primary Equipment    261
3.   Cable termination
      Cable cores of the incoming and outgoing cables for Red, Yellow and
         Blue phases are terminated via bolted connection in the termination
         area provided at the bottom of the respective incoming disconnector
         and outgoing fuse-switch disconnector units (for FP 1600 A and 800
         A).
                 For FP 400 A, the incoming cables are directly terminated via bolted
                  connection onto the busbars. The outgoing cables are connected to
                  the termination area provided at the bottom of the outgoing fuse rail
                  units via core clamps.
                 All neutral cores are terminated directly via bolted connection onto
                  the neutral busbar.
          Figure 6-95: LV DIN fuse blade contact type of size NH2 used in the outgoing
                                              unit
                                                             Primary Equipment   263
5.   Busbar
      The phase busbar system is designed to carry the rated continuous
         current
      Made of tinned copper with the following minimum copper
         equivalent dimension:
             o 80 mm x 10 mm (for FP 1600 A)
             o 38 mm x 10 mm (for FP 800 A)
             o 6 mm x 40 mm (for FP 400 A)
      The neutral busbar has similar material and dimension to the phase
         busbar. The neutral busbar is connected to the earth bar through
         braided copper wire.
Camlock
Handle
Padlocking facility
Camlock
   Current transformer is normally of the dry type design using epoxy resin
    as insulation and tested to IEC 60044-1.
   The CT shall be capable of carrying rated primary current for one minute
    with the secondary winding open. Where open circuit secondary voltage
    would exceed 3.5 kV, suitable protection shall be provided at the
    secondary terminals to limit the voltage.
   The CT is installed on the circuit side of the circuit breaker except on
    busbar sectionalising and coupling equipment as may be required.
Protection CTs
Metering CTs
   Ratio         :            Is 5A
                               *where Is is the primary ratio of the metering CT
   Class         :            0.2
   Burden        :            7.5 VA
   Unit          :            3 Nos. (One for each feeder)
   Standards     :            IEC 60044-1 (1996)
Specifications of metering CTs for consumers taking 6.6 kV, 11 kV, 22 kV and
33 kV (indoor breaker) are:
   Ratio         :            Is 5A
                                                                                           6
                               *where Is is the primary ratio of the metering CT
   Class         :            0.2
   Burden        :            15 VA
   Unit          :            3 Nos. (One for each feeder)
   Standards     :            IEC 60044-1 (1996)
                                               50/5, 75/5,
                MV CT ratio                100/5, 150/5, 200/5,
                                              300/5, 400/5
cos 𝜃 = 0.85
           Where:-
              P       = Apparent power
              Vp-p    = Line voltage system
                I     = Line current ampere
                cos θ = Power factor
           For example:
                                              500 𝑘𝑊
                                 I=
                                      3 × 0.415 𝑘𝑉 × 0.85
                                       I = 818.36 𝐴
Figure 6-100: Armoured cable is used to connect the CT and PT to the meters
                                                                                      6
                Table 6-29: Armoured Cable Configuration
            Cable No.               Cable configuration
               1         S1 terminal red phase current transformer
               2         S2 terminal red phase current transformer
               3        S1 terminal yellow phase current transformer
               4        S2 terminal yellow phase current transformer
               5         S1 terminal blue phase current transformer
               6         S2 terminal blue phase current transformer
               7                     Red phase voltage
               8                   Yellow phase voltage
               9                    Blue phase voltage
               10                         Neutral
             11&12                       Earthing
    270   Substation Design Manual
           (a) Measurement/metering
           (b) Automatic Voltage Regulation (AVR)
           (c) Protection for directional OCEF relay
          The PT is normally of the cast resin filled type and it is complies with
           IEC 60044-2 with a class of 0.5.
          The rated output of the PT is normally specified at 50 VA per phase but
           alternatively adequacy can be determined by calculation of the burden.
          The normal ratio of PT is normally to the rating of 33 kV, 22 kV, and
           11kV/110V (3 single phase star-connected and neutral earthed).
          The PT should be able to be isolated from the circuit during testing by
6          means of isolatable links or withdrawable mechanism.
Potential Transformer
     Ratio       :
                              Vs   3
                            110 3
                      *Where Vs is the supply voltage given to the consumer
     Class       : 0.5
     Burden      : 50 VA minimum.
                      Sharing between protections and metering PT can be
                      allowed provided that separate fusing is provided and the
                      burden of the shared load does not exceed 10 VA. If the
                      burden of the shared load is more than 10 VA, then 100 VA
                      PT should be used.
      Each PT is equipped with PT fuse normally rated at 3.15 A. This fuse will
      isolate the PT from the system in the event of fault at the PT i.e. internal
      winding, secondary bushing. Therefore, the system will not trip or de-
      energize.
      However, the fuse will not blow if the fault is at the secondary circuit because
6
      the fault current equivalent at the primary side is too small to blow the fuse.
      Normal practice is to place fuse or MCB at the secondary side to protect the
      circuit, but they are prone to tampering and nuisance tripping causing
      incorrect energy consumption recorded by the meter.
      For the future, TNB will replace these fuses with copper links to avoid PT fuse
      blow issue and solely depends on OCEF protection to trip if there is any fault
      caused by the PT.
                                                          Secondary Equipment   273
7.1.         Overview
Secondary equipment is needed to ensure reliable operation of the primary
equipment. They cover the functions of protection, monitoring, control,
automation and communication.
3. Circuit Breaker
4. DC System
Protection System
                                                                 Circuit Breaker
             CT
                               Protection                 Trip                CB
                               Equipment                  Coil             Mechanism
                                 / Relay
            PT
                                                                    CT – Current Transformer
                                                                    PT – Potential Transformer
                                             DC System              CB – Circuit Breaker
1. Electromechanical relay
2. Electronics/static relay
Upper poles
Metal disk
                                       Moving
                                       contact
                                                                  Damping contact
                                Fixed
                                contact
                                                      Direction of torque produced
                                                      on disk
        Current
                                                 Restraining force of spring;
                                    Spring       normally holds disk at rest                 7
                                                 against mechanical stop
                  Lower pole   Shaft
    Pickup point adjusted by
    selecting current tap
Although this type of relay has been in operation for many years, there are
several limitations such as:
      One of the advantages of the IED relay is that size is significantly reduced
      compared to the electromechanical type. Examples of IED relays used in TNB
      Distribution Division are shown in Figure 7-5.
7.2.1.5.   DC System
Protection system requires uninterrupted and independent power source.
Typically, DC supply is preferred over AC supply due to its reliability and
immunity to disturbance and surges.
                                                                     Solkor
                                                                      RF/Current
                                                                      Differential
                                                                     OC/EF
                33 kV
                                                                            33 kV Outgoing
          1HO                                                 2HO
                            Tx Differential
                                                                               Tx Differential
                            Tx Guard
                                                                               Tx Guard
                            OC/EF
                                                              Tx2              OC/EF
          Tx1
NER
                           OC/EF                                            OC/EF
                           REF                                              REF
           31                             Bus Section          32
                                                  SBEF Tx1
                             11 kV Outgoing
7                                                 SBEF Tx2
             OC/EF
             Translay
   OCEF
   Auto reclose
   Other alternatives subject to the network configuration.
   Transformer Differential
                                                                                      7
   OCEF
   Transformer mechanical protection – refer to Subchapter 6.1.5.8
    o Gas activated relay (Buchholz)
    o Winding and oil temperature
    o Pressure Relief Device (PRD)
   Other alternatives subject to the network configuration.
7.2.2.1.5. Busbar
      Current input to the scheme is taken from the LV incomer. The scheme is such
      that outgoing feeder breaker will trip for downstream fault in the switchgear
      and the scheme will trip LV incomers for busbar fault. In case of a transformer
      breaker failure or delays to open, an intertrip to HV transformer feeder will
      take place.
7                         Master
                          VAMP 220 (Master)                                    Master
                                                                              VAMP 220 (Master)
Ib>
                                                   T2              T2
                                                                                          VX010
                                              VX010                                       (Slave)
                                              (Slave)
CB1 T1 CB2 T1
CB3
X1 X2
Sensors
   OCEF
   Other alternatives subject to the network configuration.
      7.3.        Control
      Control hierarchy is designed in TNB equipment to ensure safety to personnel
      in the field by restricting the permission to control the equipment. It
      comprises:
      This priority determines how the internal wiring will be designed. Descriptions
      of the controls are as follows:
           1.   Local Control
                Personnel are required to do switching at the equipment or
                switchgear. This facility is to facilitate maintenance, inspection and
                emergency operation.
           2.   Remote Control
                In this mode, personnel are required to do switching activities from
                the control room.
           3.   Supervisory Control
                Switching activities are done from Regional Control Centre (RCC),
                where principal items of substation are controlled and monitored via
                SCADA system. The SCADA is covered in Chapter 8.
                                                         Secondary Equipment      285
The colour coding for the mimic as practiced in TNB are as follows:
Metering
                                                                    Windows
                                                                    Alarm Fascia
                                                                    Protection
                                                                    Relay
      In the mimic diagram, each circuit breaker is uniquely numbered for ease of
      identification. These numbers are always referred to during operation. The
      standard numbers are as explained in Subchapter 3.3.1.
                                                          Secondary Equipment   287
7.3.1.1.     Interlock
Mechanical and electrical interlocks are included on mechanisms and in the
control circuits of apparatus installed in substations as a measure of
protection against an incorrect sequence of manoeuvres by operating
personnel.
If the station is equipped with Remote Control Box (RCB) the three levels of
control hierarchy can be achieved.
                                                                                      7
The Remote Control Box (RCB) can be incorporated into existing 11 kV circuit
breaker / RMU to provide control and indication of the circuit breaker / LBS
(RMU). The control panel incorporates:
(a) Two different coloured lamps to show the status of the circuit
    breaker/LBS (RMU):
      i. Green lamp      : “OFF” condition of circuit breaker/LBS (RMU)
     ii. Red lamp        : “ON” condition of circuit breaker/LBS (RMU)
(b) Feeder signal
(c) Station alarm
(d) Switches
      i. Supervisory remote switches
     ii. Open/close switch
    iii. Earth switch
    288   Substation Design Manual
      The RCB is SCADA ready for future interconnection with RTU. The signal must
      include:
      Each RCB box can control up to 4 feeders. Where space is a constraint, RCB can
      be mounted outside the substation’s wall as shown in the Figure 7-10.
                                                        Secondary Equipment       289
RCB
Battery charger
                                       DC distribution
                                           board                  Battery bank
7.4.1.1.1. Charger
          Figure 7-12: Dual battery charger panel and DC distribution board (110 V)
                                                          Secondary Equipment       291
Battery banks and battery chargers must be well maintained to ensure that
the protection system functions properly.
7.4.2.     AC System
AC System is required to supply all substation AC auxiliaries such as:
7.5. Heater
              1.   Breaker compartment
              2.   Cable compartment
              3.   CT compartment
      All the heaters are installed in parallel. The power capacity and the number of
      heaters are dependent on the type/model of the switchgear. The typical
      ratings for the heaters are given in Table 7-2.
7                                       ON/OFF
                                        Switch        Thermostat
                         Fuse
          L
                                                                                         Heater 3
                                                                   Heater 1
Heater 2
                            Link
          N
       1.   Breaker compartment
       2.   Cable compartment
Both heaters are installed in parallel. The power capacity and the number of
heaters are dependent on the type/model of the switchgear. The typical
ratings for the heaters are given in Table 7-3.
                                     ON/OFF
                                     Switch      Thermostat
                    Fuse
   L
                                                                                           7
                                                               Heater 1
Heater 2
                        Link
   N
      7.6.2.      AC Wiring
          AC wiring is the nerve for all the AC station auxiliaries.
7     
                                   2
           Black coloured 2.5 mm wiring 1000 V grade is used for AC circuitries.
          AC wiring should be segregated from DC wiring for fear that induced AC
           will be present in the DC system.
          Special attention should be given to CT wiring as it is required to be
           colour coded as per the phase that it carries namely RYB and the size of
                                            2
           the conductor shall be 4.0 mm . All circuitries are to be numbered for its
           usage as per BS 158.
                                                           Secondary Equipment   297
7.7.       Metering
The purpose of metering in the substation is as follows:
    1.   MV metering                                                                   7
         (a) For customer taking bulk supply 6.6 kV, 11 kV, 22 kV, 33 kV,
             66 kV, 132 kV, 275 kV.
         (b) For PMU between transmission and distribution
         (c) For PPU between primary distribution medium voltage (33 kV &
             275 kV) and secondary medium voltage (22 kV and 11 kV)
         (d) For P/E between neighbouring area or ‘Kawasan’
    2.   LV metering
         (a) For customer taking bulk supply more than 100 A
         (b) for recording substation use or free units
For metering installations up to 33 kV, CTs and VTs shall be provided and
installed by TNB at TNB's outgoing switchgear. A floor mounted metering
cubicle shall be provided by the consumer in the specified metering room for
the installation of TNB meters.
    298   Substation Design Manual
      For LV metering and supply scheme with substation, the meter panel/cubicle
      is installed inside TNB substation perimeters (refer ESAH).
Metering Panel
                                     Voltage
                                    Isolators
Potential Transformer
110 V (Line)
                                                   11 kV (Line)
                                       Test
                                       Terminal    PT Fuse (PT)
                                       Block
The main and check meters are located at the front panel of the metering
compartment as shown in Figure 7-21. Main meter is on the left side and
check meter is on the right side.
   Feeder                                                              Feeder
  main meter                                                         check meter
    Figure 7-21: Typical MV metering panel with main and check meter
    300   Substation Design Manual
                                                                           Voltage
                                                                           isolators
                                                                           Test Terminal
                                                                           Block (TTB)
Figure 7-25: TTB and voltage isolators inside MTB (internal view)
      7.8.        Communications
      Two types of communication cables exist in TNB, i.e. fibre optics and pilot
7     cables. They are both used for Supervisory Control and Data Acquisition
      (SCADA), communication and protection system. Currently, TNB only use fibre
      optics for new installation.
  Table 7-5: Typical no. of pilot cable pairs used in the distribution system
                                    No. of pair used
    Voltage                                                 No. of pair used for SCADA
                   No. of pairs         for unit
     (kV)                                                             to RCC
                                      protection
                                                            1-2 pairs per
                     12 pairs
                                                            communication loop
         11                                1 pair
                                                            8 pairs for telecontrol &
                     37 pairs
                                                            telecoms
                                                            17 pairs for telecontrol
         33          37 pairs              1 pair
                                                            10 pairs for telecoms
Table 7-6 below shows the diameter resistance and elongation of conductor
in completed cable.
Table 7-7 shows the maximum mutual capacitance and capacitance unbalance
with the conductor size.
Table 7-8 shows the core identification for the pilot cable.
                  1.    Slotted
                  2.    Loose tube
Fibre optic cables provide better performance compared to pilot cables. The
reasons behind the use of optical fibre cable as against pilot cables are:
Table 7-9 and Table 7-10 show the underground fibre optic cable
specifications and underground fibre optic characteristics.
5
 Refers to the fibre optic cable that fulfils the needed criteria to support applications
up to capacity of STM-16, and permits the transmission of extended wavelength
between the range of 1360nm to 1530nm.
    306   Substation Design Manual
                                               125 ± 1 µm
           Cladding diameter
The fibre core groups for the slotted type cable need to be easily identified by
slot Identification markings.
                                                                                           7
7.8.2.3.   Fibre Optics Boundary of Responsibility
TNB Distribution Division has developed fibre optic infrastructure in power
system to replace the pilot cable as a telecommunication medium. In order to
ensure efficient management of the fibre optic infrastructure, TNB
Distribution Division has agreed to hand over the fibre optic infrastructure to
ICT Division (Fibre Optic Distribution Management Charter between ICT
                                                  6
Division and Distribution Division, June 2012) . The ICT – Distribution
Operational Boundary is shown in Figure 7-27.
6
 Fibre Optic Distribution Management Charter between ICT Division and Distribution
Division, June 2012
    308    Substation Design Manual
                        RTU
                   Communication Box
                              RTU Multi-core/
                              Control Cable
                       RTU/SCS                     Equipment 1            Equipment 2
          Legend
                      Distribution
                      ICT
                                                                         CT Ring
EFI Controller box
LED Indicator
(c) Endau
Incoming Outgoing
CT
The EFI current sensor is in the form of a CT ring for the detection unit is an
encapsulated split – core design suitable for embracing the sheath of:
                                                        2
    3 core cables of conductor section of up to 300 mm
    (maximum diameter – 90 mm)
                                                             2
    3 single core cables of conductor section of up to 500 mm
    (maximum diameter – 300 mm)
The fault passage indicator is required to detect earth fault currents down to a
value of at least 40 A.
The detection relay provides for multiple, discrete user settable earth fault
current pick up values with a minimum range of 40 A to 240 A. It provides for
user settable operation delay time with a minimum range 50 ms to 150 ms.
The indicator may be a separate unit in itself or form an integral part of the
whole device.
CT Ring
7
                    EFI Controller Box
                                                                                                                                  Switchgear    body
                                                                                                                                   BADAN PERKAKASUIS
DISEMAK
DILUKIS
                     TAJUK
                                                                                                                                                                      Gasket
                                                                                                                                                                         GASKET
                                                                                                   Screw
                                                                                                    SKRU
                                                                                                                                                                                    EFI
                                     WILAYAH PAHANG
CABLE BOX-4
                                                                 Socket   200A
                                                       TENAGA NASIONAL BERHAD
SOCKET 200A
                                                                  P/EBUSBAR
                                                                        earth
                                                                            BUMIbar
                                                                                  P/E
                                                                Socket   200A
                                                                      SOCKET 200A
                                                                                                                                                                                                  GAMBAR 4
                                                                                                               Socket    200A
                                                                                                                SOKET 200A                              Cable Gland
                                                                                                                                                        CABLE GLAND
                                                                                                              Through     the
                                                                                                               DI DALAM CT EFI
                                                                                                                  CT ring                              Sheath
                                                                                                                                                       SHEATH
TN/
      NO. FAIL
                                                                                                                                                                 CTCT ring
                                                                                                                                                                      EFI
                                                                                                                                                                                                             7
                                     DAERAH TEMERLOH
                                                                                                                                                                               Conductor    from
                                                                                                                                                                                  PENGALIR DARI CT KE EFI
                                                                                                                                                                                  CT to EFI
                                                                                                                                                            BUAH PLUMB BAWAH
                                                                                                                                                        PILC  Cable
                                                                                                                                                                 CABLE Armouring
      PERKARA
AMOURING PILC
MOHAN MANON
                                                                                                                        Switchgear    Body
                                                                                                                            BADAN PERKAKASUIS
DILUKIS
               TAJUK
                                                                                                                                                                                Gasket
                                                                                                                                                                                 GASKET
                                                                                              Screw
                                                                                             SKRU
                               WILAYAH PAHANG
CABLE BOX-8
                                                                                                                                           Location
                                                                                                                                            LOKASI A A
                                                 TENAGA NASIONAL BERHAD
                                                                             Socket    200A
                                                                              SOKET 200A
                                                                                                                                                        Raychem
                                                                                                                                                           RAYCHEM
                                                                                                                                                                                             GAMBAR 8
                                                                                                                                            Location
                                                                                                                                            LOKASI B B
                                                                                 wire
                               DAERAH TEMERLOH
                                                                                                                                                         XLPE    cable
                                                                                                                                                         KABEL PILC ATAU XLPE
                                                                                                                                          Location
                                                                                                                                           LOKASI C C
PERKARA
MOHAN MANON
                                                                          Where:
                                                                                       IEF = Prospective Earth Fault Current of feeder (minimum case)
                                                                                       ITrip = EFI current trip level setting
                                                                                       ITCap = Downstream capacitive current
                                                                          ITCap can be determined by multiplying the charging current (IC) of the various
                                                                          size of cables with the total length of the cables involved downstream from
                                                                          the location of the EFI.
                                                        Secondary Equipment       315
Table 7-12 shows the values of charging current (A/km) of various sizes of
XLPE and PILC cables as given by manufacturer.
 Table 7-12: Charging current per unit length of 11 kV XLPE and PILC cables
                       (Ic – Data from manufacturer)
                  XLPE                                   PILC
                             Charging                               Charging
          2                                       2
 Size (mm )     Rating (A)   Current     Size (mm )   Rating (A)    Current
                              (A/km)                                 (A/km)
    150            280       0.7587         25            80          0.82
                                      PPU 1                       PPU 2
                                           CB 18                           CB 1
                                                                                  Multiple
                           st
                                                                                   P/Es
                           1 Leg
                                          Main                            Backup
                                          CB 16675                        CB 16678
                                          (PT new installation)           (PT new installation)
7
           CB 16676                    CB 16677         P/E
           (PT-existing)
                    Consumer
                                       (b) Single line diagram
PPU 1 PPU 2
                   st                                             st
               1 Leg                                             1 Leg
               Main                                              Main
               CB 14976            Bus section                   CB 18622
               (PT-new installation) open                        (PT-new installation)
                                  Consumer substation
                               (b) Single line diagram
RTU
SIP
(5)
(6) (7)
(8)
                  (9)               (10)
        Description
 1      Thermostat
 2      Miniature circuit breaker – AC power supply
 3      Cubicle illumination lamp
 4      Door switch
 5      Heater ON/OFF switch
 6      Terminal block
 7      Terminal block
 8      Terminal block (AC bus wiring)
 9      Heater
10      Earth bar
Figure 7-38: Supervisory Interface Panel (SIP)
    320   Substation Design Manual
      8.1.        Overview
      Supervisory Control and Data Acquisition (SCADA) is a concept used to
      describe a system that enables control and monitoring of devices or
      equipment remotely. In TNB Distribution Division, SCADA systems are used to
      assist the operation and management of transmission and distribution of
      electricity. The advantages of using SCADA system are optimization of plant
      processes, and provide operations that are more efficient, reliable and safer.
           1.   Master System
           2.   Communication System
           3.   Remote Terminal Units (RTUs)
        Data
                         Communication
                           Communications              RTU
                             system
                              System
RTU
                                                       RTU
Master System       Communication System
                                             Remote Terminal Units
    (RCC)
           Figure 8-1: Overview of SCADA system
                                                                  Front end
                                                   Data
Servers/Back end
                                                                       Human
                                                                      Machine
                                                                      Interface
                                         Printer
                Operator’s workstation             Operator’s workstation
           1.     Front-end Subsystem
           2.     Server/Back-end Subsystem
           3.     Human Machine Interface (HMI) Subsystem
                                                                 SCADA System        323
          The first DMS function covers activities and tasks such as Distribution
           Operation Analysis, Safety Documents, Operational Document
           Management and Operational Planning.
          The second DMS function is the Forced Outage Management Functions,
           which include Fault Location, Isolation, and Service Restoration function,
           estimation of customer interruption, and Network Normalization
           Management.
             i.   Fibre optic
            ii.   Pilot cable
           iii.   Leased lines
           iv.    GPRS
            v.    Radio
           vi.    Microwave
      The network topology consists of:
             i. Point-to-point
8           ii. Multi-drop
           iii. Loop configuration
      While the communication schemes are:
             i. Polling
            ii. Unsolicited reporting
             i.   IEC 60870-5-101
            ii.   DNP 3.0
           iii.   Extended WISP+
           iv.    Harris H6000
                                                                SCADA System     325
The Extended WISP+ and Harris H6000 are required for legacy systems to
support existing RTUs. Whereas the IEC 60870-5-101 protocol is mainly used
to communicate with the newer RTUs installed in TNB’s network.
Master System
                                             Supervisory           Remote
          Control and Relay Panel
                                           Interface Panel      Terminal Unit
SIP RTU
Figure 8-5: Connection of Control Panels, Relay Panels, SIP and RTU
The RTU input/output interface cards comprise of three (3) main items as
described below:
                                                                  RTU Cabinet
            Cabinet                                                Indicators
             Lamp
                                                             Power Distribution and
                                                             Interport Link Module
            HX RTC
            Module
                                                                 RTU Input/Output
                                                                      Module
8            Grounding
                Bar
Chapter 9: Earthing
      9.1.         Overview
      Earthing may be described as a system of electrical connections to the general
      mass of earth.
      An earthing system consists of two elements, the earth conductors and the
      earth electrodes.
      The substation earthing system shall meet two main purposes which are:
9     1.    To provide means to carry electric currents into the earth under normal
            and fault conditions without exceeding operating and equipment limits or
            adversely affecting continuity of service.
      2.    To assure that a person in the vicinity of earthed installations is not
            exposed to the danger of critical electric shock.
                                                                      Earthing    331
To meet the design objectives and requirements, the design for earthing of all
equipment and the provision of earthing systems and connections shall be in
accordance with the recommendations in the following standards:
As can be seen in the example shown in Figure 9-2, the voltage drops V1, V2,
and V3 etc (known as surface potential) vary according to earth resistance and
the earth current at particular instant of flow.
/ lightning
    Figure 9-1: Fault current path to earth and its induced potential gradient
    332   Substation Design Manual
                                                             Surface of
                                                             earth
                                                             Top view of
                                                             energised
                                                             electrode
                                                    V1
                                     V4
V3 V2
9
                                                                       Earthing      333
Earthing systems shall have an overall voltage rise, touch voltage and step
voltage that are uniformly distributed and within the allowed tolerances.
      The following are the approved types of earthing conductors and connection
      methods, followed by above-ground earthing layout for different substations.
      2.    Bonding conductor:
             These ensure that exposed metallic parts such as metal enclosures of
               equipment and other items of conductive material are bonded
               together and remain at approximately the same potential during
               electrical fault conditions.
             E.g. copper strip.
9
      The criteria for selecting the material and sizing of earth conductors are:
Where,
    Ko is the 1 𝛼0 or 1 𝛼𝑟 − 𝑇𝑟 in C
                                   o
    TCAP is the thermal capacity per unit volume from Table 1, pg 42 IEEE
                    3 o
    Std.80, in J/(cm · C)
                                        𝐼       𝑡
                                   𝑆=
                                            𝑘
Where,
         I is the average fault current, in Amperes (rms)
         t is the fault current duration, in seconds
    336   Substation Design Manual
                                                    𝑇2 + 𝛽
                                     𝑘 = 𝐾 𝑙𝑜𝑔𝑒
                                                    𝑇1 + 𝛽
      Where,
                                                o
                T1 is the initial temperature, in C
                                                 o
                T2 is the final temperature, in C
And values of K and β for typical conductor materials are shown in Table 9-1.
      Based on the criteria and calculations for selecting earth conductors, the types
      of earth conductors used in TNB are copper strips and tin-plated copper braid.
9
                                                                    Earthing   337
                                                   Switchgear body
                                                                                   Gasket
                          Screw
             Lug socket
                                                                     Heat shrink
                  Back to PMU
                   (star point)
                                               Earth
                                               fault
           Braided copper wire                 flow
                                                                     PILC or
                                                                     XLPE cable
9.2.2.1.   Brazing
   Connection is made by heating a piece of Silver Copper Phosphorus
    (SilFos) in between two copper plates.
   This method gives a solid electrical and mechanical connection.
              Silver SilFos
                                                                                        9
Copper plate
                                                                                  Brass bolt
                                             Brass nut
                                                                                  Lock nut
Jam nut
The earthing for lightning arrestors must have dedicated earth electrodes. The
                                                                                       9
lightning earthing electrodes and system earthing electrodes must be bonded
together.
    342   Substation Design Manual
                                                                                   2
      All metal parts shall be bonded together using copper strip of 300 mm Cu
      equivalent and connected at some points to the earth electrodes. All
      connections of earth conductors shall be brazed. The design of the earth
      electrodes (i.e. earthing layout below-ground) shall refer to Subchapter 9.3 in
      accordance to IEEE Std. 80.
      Common earthing layout of a typical one and a half storey PPU is shown in
      Figure 9-11 and Figure 9-12 for each floor.
                                                                               50 x 6 mm
                                                                               copper tape
                                                                               to be
                                                                               concealed
                                                                               on the floor
         50 x 6 mm                                                             50 x 6 mm
     copper tape to                                                            copper tape to
          be buried                                                            be buried
9     under ground                                                             under ground
            Figure 9-11: Earth connection of PPU (Ground floor and cable cellar)
                                                     Earthing   343
EF-2
EF-3
TC Test clamp
                                                                        50 mm x 4 mm
                                                                        copper tape
                               50 mm x 4 mm copper tape                 4 mm DIA. HEX NUT
                                                      450
                                                                   Ground Level
                                                                                          9
    346   Substation Design Manual
                                                                           Earthing
                                                                            point
                                                                               Feeder
                                                                                pillar
9
                                     Entrance                           Earth chamber
Earthing point
Transformer
Switchgear
                                                                     Feeder
                                                                      pillar
                                                                                       9
    348   Substation Design Manual
                           LV
                                      Transformer         RMU
                         Feeder
                          Pillar
Doors
Earth chamber
9
                                                                   Earthing     349
Earthing point
Earth chamber
Lightning arrester
LV neutral
                     Copper braid
                     from cable                              Transformer
                     termination                             body
Copper strip
Earth chamber
9 Earth rod
LV neutral
                                                           Transformer
               Copper braid                                body
                 from cable
                termination
Copper strip
Earth chamber
 Figure 9-21: Earth Connection of Pole Mounted Substation (PAT) with RMU
                                (front view)
    352    Substation Design Manual
                                      Copper braid
                                       from cable
                                      termination
              Add more earth                             Add more earth rods as
            rods as and when                             and when required to
                  required to                            improve earth
               improve earth                             resistance
                    resistance
Copper strip
                                            RMU
                                                                 Feeder pillar
Earth Chamber
          Figure 9-22: Earth Connection of Pole Mounted Substation (PAT) with RMU
                                          (top view)
9
                                                                    Earthing     353
    1.   Earth rods
    2.   Earth plates
    3.   Horizontal conductors
Earth rods must have rigid cores for easy driving-in. The earth electrode used
in TNB is copper-clad steel. Copper-clad steel is used as it has high tensile
strength, copper plating for better conductivity. They are able to reach into
deeper, low resistivity soil with limited excavation and backfilling.
Additionally, they are easy and cheap to install.
Earth rods are protected inside earth chambers as shown in Figure 9-24. The
earth chamber is specified as:
Driving head
Coupler
Earth rod
Coupler
Earth rod
                                                                                      9
    Figure 9-25: Cadweld mould (left) and completed connection (right)
The connection to each earth rod inside the earth chamber is considered as an
above-ground connection. Hence, bolted connections are allowed between
earth conductor and earth rod inside the earth chamber.
    356   Substation Design Manual
      Case study calculations of the Bukit Gambir Containerised PPU can be found in
      Appendix B. The executive summary and case study results are as follows.
      The design of the earthing system for the newly proposed Bukit Gambir CPPU
      has been carried out. Preliminary calculations have been performed using the
      IEEE Std.80 routines and the final design has been checked using the
      specialized earthing software package which is Current Distribution,
      Electromagnetic Fields, Grounding and Soil Structure Analysis (CDEGS). The
      main parameters and findings are shown in Table 9-3.
The earth resistance value of the earthing must be less than 3 ohms.
                                                     Legend:
                                                     1 – Electrode resistance
                                                     2 – Contact resistance
                                                     3 – Earth resistance
                                                     I – Current
I I 9
                                               V
                                                                    Current
                                      E                    P        electrode            C
                                                                    Potential                 Current
                                                                    electrode                 electrode
                                                x
                 Electrode
                                                                d
                being tested
      The FOP involves measurement of voltage and current by using potential and
      current probes driven into the earth. RE is calculated from the measured
      voltage and current (R = V/I) as a function of distance between the potential
      probe and the earth electrode under test, x. This is achieved by moving the
      potential probe at a certain distance from current probe which remains fixed.
9
                                          62% of D                          38% of D
                                                                                                       Auxiliary
                     Resistance
                                                                                                       current
                                          Resistance of auxiliary
                                          current electrode                                            electrode
According to IEEE Std. 81, the apparent RE value is the resistance at the 61.8%
of the distance between the earth electrode under test and the current probe,
D. This 61.8% rule is credible provided the following are met:
According to IEEE Std. 81, the spacing between the current electrode and the
electrode/earth system being tested, D, shall be minimum 6 to 10 times the
diagonal size of the earthing system of the substation, d (Figure 9-29).
                                                  Diagonal distance
        Substation
          earthing
           system
This may require the use of extended leads for the current and potential
probes as the standard lead’s length provided with earth resistance test
equipment is typically 100 m only. The spacing is required to obtain more
accurate RE as adequate separation will ensure the return current and voltage
measuring points are effectively outside the influence of the earth system to
be tested. If separation is not adequate and effective resistance areas                  9
overlap, the test result in Figure 9-30 is obtained leading to inaccurate RE.
Another source of measurement error in FOP is when the return current and
voltage measuring points are within metallic objects inherent of the site such
as buried pipes. In this case, the test equipment will read RE value that is not
the true apparent value. Therefore, the measurement area must keep away
from metallic objects and must minimize their interferences.
    360   Substation Design Manual
                                              Auxiliary   Auxiliary
                           Ground
                                              potential    current
                          electrode
                                              electrode   electrode
                          under test
                                                                        Overlapping effective
                                                                        resistance areas
                            Resistance
    Figure 9-31: Soil treatment around earth rod to lower soil resistivity
    362   Substation Design Manual
                                                                80
                          Percent resistance of one electrode
60
50
                                                                40
                                                                     0    5     10     15    20        25 30
                                                                                     Electrode spacing, m 0
           Figure 9-32: Effect of inter-electrode spacing on combined resistance
9
                                                           Fire Fighting System   363
10.1.      Overview
In case of fire occurring in a substation, a properly designed fire fighting
system is important to mitigate and contain the fire. This chapter aims to
introduce the basic concepts and requirements for TNB Distribution
Substations. Table 10-1 shows requirements for substation fire protection.
       (a) Performance Based Design must be used based on the design fire
           scenario for substation fires applied for each particular enclosure, i.e.,
           control room, switchgear room and indoors transformer room.
       (b) For halogenated agent, the maximum HF by products shall be LESS than
           500 ppm. Engineering correlation may be used to estimate the maximum
           allowable fire size.
       (e) Pressure relieving vents, located near the finished ceiling, may be
           necessary to regulate rapid pressure changes during discharge. Comply
           with the manufacturer’s recommended procedures relative to enclosure
           venting.
       Table 10-2 and Table 10-3 highlight the extinguishing system performance
       parameters and minimum standard requirements for detection system.
10
                                                         Fire Fighting System   365
10          ENGR-5202-PSI
                                 ENGR-5206-PSI       ENGR-5207-PSI        INSTALLATION
            ENGR-5203-PSI
                                                         Fire Fighting System   367
A summary of contents from the PSI requirements that are required for
system design approval are as follows.
    1.   Design Brief
    2.   Site Survey Report
    3.   Performance Based Design Analysis
    4.   Hydraulic Flow Calculation
    5.   Battery Load Calculation
    6.   Design Drawing (Shop Drawing)
             Plan Layout Drawing
             Fire Alarm And Detection Systems Layout
             Schematic Diagram - Fire Extinguishing System
             Schematic Diagram – Releasing Agent Control Panel
             Fire Suppression Piping Layout
             Fire Suppression Isometric Diagram
           Cylinder Arrangement and Demarcation Lines
    7.   Manufacturer Type Endorsement Certificate for Design Analysis
               
           220 – 240 VAC
                                                                                           Solenoid Actuator
                              POWER LINE
                               LIGHTNING
                               ARRESTOR                                      SIGNAL LINE
                                                                             LIGHTNING
                                                                              ARRESTOR
           The use of Power Line and Signal Line Lightning Surge Arrestor have the
           following benefits:
                1.         Damaging the control panel system components
10              2.         Maintain the expected backup batteries life and avoiding the
                           premature damage.
                3.         Minimizing the accidental (voluntary) discharge due to lightning
                           strike
                                                                       Fire Fighting System       369
(b) In the case of control panel power loss during fire event, the
    extinguishing agent shall be capable to be discharged manually
    (redundancy system).
                                                                                     ELECTRIC
                                                                                     SOLENOID
 MANUAL INITIATING DEVICES                                                           DISCHARGE
                                                                                     ACTUATOR
CYLINDER VALVE
AC POWER
BACKUP BATTERIES
The discharge system actuation of extinguishing agent shall have two actuation
systems, i.e., electrically and manually. Electrical actuation can be triggered
automatically by system detectors or manually by manual release station
through control panel. The manual mechanical actuation will be the last
survival of the system to enable to discharge the extinguishing agent in the
case of electrical power loss during fire event.
                                                                                                        10
     370   Substation Design Manual
            (c) The guaranteed of the goods shall be for an initial period of 1 year,
                subject to an annual revision done by the panel contractor and
                annually renewed once every revision is done, with maximum
                guarantee of 5 years.
10
                                                           Fire Fighting System    371
Within the guarantee period in force, the manufacturer shall warrant the
following conditions:
    (a) The extinguishing agent discharge shall be clean, non corrosive and
        will not damage to the machinery and equipment, non toxic and will
        not harm to human. Under technical advice from manufacturer,
        panel contractor (installer) shall be responsible for cleaning, repair
        work or replace or pay the damages claimed by TNB on TNB’s assets
        which are directly damaged by the voluntary discharge of
        extinguishing agent.
    (c) Within the warranty period, the systems shall not have false
        discharge due to the system manufacturing and/or design defect.
        Panel contractor (installer) shall be responsible for rectification work
        on the system supplied and gas refill due to the false discharge.
A list of presently approved products with SGP can be found in the Circular
Surat Pekeliling Pengurus Besar Kanan (Pengurusan Aset) Bil. A14/2012
Menggunapakai Khidmat Syarikat Panel dan Produk Sistem Pemadam
                                                                                         10
Kebakaran untuk Bahagian Pembahagian.
     372   Substation Design Manual
10
                7
                                              6
   TO PIPE                5
DISTRIBUTION                                                                3
AND NOZZLE(S)                                                  4
2 2 2 1
   1.   Master cylinder
   2.   Slave cylinder
   3.   Solenoid actuator
   4.   Opening valve connection hose
   5.   Discharge hoses
   6.   Manifold
   7.   Restrictor (pressure reducer only for systems using inert gasses)
                                                                                            10
     374   Substation Design Manual
       Other components of the fire detection system are Secondary Power Backup
       Batteries, Automatic Initiating Devices (Fires Detectors), Manual Initiating
       Devices (Manual Release and Abort Stations), Alarm Bell, Sounder
       (Horn/Siren) and Strobe (Beacon), Evacuate Sign, Agent Discharge Sign, LED
       Beacon.
            PENGESAN
           KEBAKARAN
                                                                                                         ALARM
            AUTOMATIC                                                                                     BELL
            INITIATING                                          RELEASING AGENT CONTROL PANEL
               DEVICE
             (ZONE-01)                                                                                     LED
                                                                                                         BEACON
                                                                                                          HORN
                                                                                                         STROBE
             AUTOMATIC                                                                                   EVACUATION
             INITIATING                                                                                    SIGNAL
                DEVICE
              (ZONE-02)
                                                                          PANEL KAWALAN
                                                                                                             EVACUATE
                                                                                     MANUAL INITIATING
                          AC POWER                        12VDC BACKUP BATTERY                             SOLENOID ACTUATOR
                                                                                         DEVICES
BEKALAN ELEKTRIK
10
                                                               New Technology       375
For the reasons mentioned above, many utilities in the world have utilized
mobile transformer simply for its main advantage of fast and rapid
deployment capability. In short, mobile transformer can be used to ensure
supply availability and reliability for the following purposes and conditions:
        Planned maintenance
        Forced outage for transformer repair
        Supply restoration due to transformer failure
        Temporary supply before completion of PPU                                        11
     376   Substation Design Manual
11.1.1.2. Design
       In addition, the mobile power transformer will be fully equipped with a Prime
11     Mover suitable for the application.
                                                              New Technology     377
Similar to the power transformer, the auxiliary transformer will also be using
synthetic ester bio-degradable oil. All other technical parameters are similar
to the specification of a normal distribution transformer.
The NER ratings will follow the basic parameters as listed in Table 6-22
Chapter (NER).
                                                                                       11
     378   Substation Design Manual
RTCC
       However, the above practice to step up supply using a normally step down
       transformer is strictly prohibited by TNB with the issue of the Vice President
       Directive No. A14-2008. This is because under normal load flow and normal
       voltage regulation condition, use of step down transformer as step up will
       work and supply can be fed without any problem. However, problem usually
       occurs during line-to-earth fault condition in the 11 kV (delta) side. This is
11
       because step down transformer with Dyn11 vector group has no star point on
                                                            New Technology       379
the 11 kV side and therefore the system protection could not detect the earth
fault current to trip the protection device. Under this condition, the faulty
phase will normally approach zero volts but the voltage of the un-faulty
phases will rise by   3 times their phase voltage and give rise to safety
hazards.
   i.    The vector groups for the step-up transformer shall either be YNd11
         or YNd1 or YNyn0. For standardization purposes, the use of YNyn0
         vector group is not recommended for new project.
   ii.   Voltage ratio shall be 0.415/11 kV.
  iii.   Installation of the step-up transformer shall be at substation on a
         spur feeder.
  iv.    The selected substation shall be installed with added RMU T-off
         Transformer Circuit or a VCB.
  v.     The RMU T-off Transformer Circuit shall be fitted with appropriate
         fuses whilst the VCB shall be fitted with appropriate relays.
  vi.    LV distribution board or feeder pillar may be installed when
         necessary.
 vii.    The capacity of the step-up transformer shall be equal or more than
         the capacity of the mobile generator. For example 625 kVA
         transformer for 500 kW generator.
viii.    The step-up transformer shall be tested and proven healthy for use.
The substation selected for the permanent installation may be at the upper
stream, middle or downstream of the spur feeder depending on the rating
and size of 11 kV cables, logistic and installation suitability, operation and
customer requirement as illustrated in the diagram below:
                                                                                       11
     380    Substation Design Manual
                                  Step up transformer
                                      0.415/11 kV        Distribution Board
                                    YNd1 or YNd11       (DB) or Feeder Pillar      Mobile
                                                                                generator set
                                                                                      To LV
                                                                                    customer
                          Step down transformer
                                                          Distribution Board
                               11/0.415 kV               (DB) or Feeder Pillar
                                 Dyn11
                                                              To the other
                                                               substation
                                                              To the other
                                                               substation
PE 11/0.415 kV
       For the proposed mobile step-up transformer unit, RMU T-off Transformer
       Circuit or VCB shall be permanently installed at the selected substation and
       will not be part of the mobile step-up transformer unit.
11
                                                              New Technology       381
The proposed concepts for the design of the mobile step-up transformer are:
11.1.2.3.3. Application
It should be noted that the substation or feeder fed by the mobile generator
through the step-up transformer shall be operated in islanded operation and
isolated from other system or other source of supply.
                                                                                         11
     382   Substation Design Manual
       11.1.2.4. Rationale for the Use of Mobile Step-Up Transformer and the
                 Advantages over Permanent Installation
       The rationales and advantages for the use of mobile step-up transformer are
       as follow:
11
                                                            New Technology       383
The capacity of the transformer of CSU is 1000 kVA and further details are the
same as in Chapter 4.6.
                                                                                       11
     384   Substation Design Manual
       11.2.1. Overview
       Transformers operate 24 hours a day, seven days a week during which time
       they undergo constant losses of 1 to 2% of the electricity that passes through
       them. Energy efficient transformers can help to minimize these losses. In
       Malaysia, more than 80% of electricity generation is by fossil fuel that
       contributed to the CO2 emission. In financial year 2010/11, a total of 0.54
       metric tons of CO2 emission was estimated per MWh of electricity produced
       by TNB. Thus, by reducing transformer losses, CO 2 emission can directly be
       reduced to minimize the global green house effect.
                                         33kV OH & UG
                      Distribution        cables 0.29%
                                                         22kV OH & UG
                      Transformer
                                                          cables 0.10%
                         1.21%
                                                                    11kV OH & UG
                                                                     cables 1.61%
                  Power
               Transformer
                  0.41%
                                                              6.6kV OH & UG
                                                               cables 0.06%
                                LV OH & UG
                               cables 1.67%
           Figure 11-5: Technical losses by components in TNB distribution system
11
                                                              New Technology       385
       transformers. Typically, core loss can be 70–80% less than with traditional
       crystalline materials.
             Figure 11-7: Flat wound core and coil assembly of amorphous core
                                        transformer
11
                                                               New Technology       387
When fully assembled, the joined sections of the laminated cores form three
identical columns or limbs which are almost perfectly round in shape with
cross sectional filling factor reaching 99%, avoiding magnetic flux distortion at
joined sections. All the above factors contribute to the reduction of no-load
loss by 15 ~ 20% and noise level improvement by 5 ~ 10 dB for the same
silicon steel grade. In addition, for the same cross sectional area of the limb,
the average length of the winding can be reduced by 2 ~ 3% as compared to
the conventional stack core due to the more circular cross sectional area of
the limb as shown in Figure 11-10.
                                                                                          11
     388   Substation Design Manual
           Figure 11-10: Cross sectional area of a tri-dimensional core limb (left) and
                              conventional stack core limb (right)
11
                                                                   New Technology       389
                                                                                              11
     390     Substation Design Manual
       11.3.1. Overview
       TNB has been using oil filled transformers in its system. However there are
       issues such as fire (flammability) environmental concerns (low
       biodegradability), leakage and maintenance associated with these
       transformers. These concerns are magnified for those transformers located in
       the densely populated areas, public areas, shopping centres, especially when
       the substations are attached to the building. Hence, the use of cast resin
       transformers and synthetic ester bio-degradable oil immersed transformers
       have been approved for use in indoor and outdoor (including pole mounted
       and mobile) distribution substations respectively for less flammable and more
11     environmental friendly insulation materials.
                                                             New Technology       391
The metal parts of a cast resin transformer account for around 90% of its total
weight. The insulation materials amount to only about 10%. Of this, less than
half can be considered flammable because typically about two-thirds of the
resin compound is silicon dioxide filler (quartz powder) and much of the
insulation material of the LV winding is glass based. Hence not more than 5-
6% of the total weight of the transformer comprises of flammable substances.
In addition, the resin used has typical self ignition temperature of 450 ⁰C at
which the material will start to ignite. Some main features of cast resin
transformer are as follow:
   Uses epoxy resin reinforced with glass fibre which prevents cracking of
    epoxy compound even under overload conditions.
   Epoxy resin has excellent electrical properties, low shrinkage, good
    adhesion to many metals and resistance to moisture, thermal and
    mechanical shock.
   By molding process.
                                                                                        11
     392    Substation Design Manual
11
                                                                  New Technology     393
  Temperature Rise
                                    100 K                            60 K
       Limit
 Typical Dimension
                              1590 x 900 x 1750
    (L x W x H)                                                1700 x 950 x 1525
                             (without enclosure)
        mm
                                                             The replacement of a
                        The replacement of a winding
       Repair                                             winding can only be done in
                             can be done on site
                                                                  the factory
                                                                                           11
     394   Substation Design Manual
       The dielectric strength of synthetic ester oil is less affected by moisture than
       mineral oil. Under normal transformer loading, synthetic ester oil can retain
       higher moister content as compared to mineral oil and therefore allow more
       migration of moisture from paper insulation into the oil. This “drying”
       property can contribute to preserve cellulose life. Furthermore, synthetic
       ester is highly stable towards oxidation and the by-products as the result of
       aging of synthetic ester oils are less aggressive than mineral oil and hence less
       harmful to paper insulation. This property of synthetic ester oils makes it
       suitable for use in a free breathing transformer.
       However, the synthetic ester oil has slightly higher viscosity as compared to
       the mineral oil. This is a disadvantage for efficient cooling and during
       impregnation process. In addition, the dielectric strength of synthetic ester
       impregnated paper against rms and impulse breakdown voltage is relatively
       lower compared to the mineral oil. However, these disadvantages can be
       remedied through improved design clearance and modification on the cooling
       fins as well as through longer impregnation under vacuum during
       manufacturing. DGA can be still used as a condition assessment tool for
       synthetic ester oil, but the diagnosis criteria and interpretation need to be
       adjusted.
11
                                                                  New Technology     395
Table 11-5: Technical Comparison between Synthetic Ester with Other Fluids
Fluids/ Criteria Mineral Oil Silicone Oil Synthetic Ester Natural Ester
        BDV (kV)
                             55             50              70               70
      Typical Value
    Viscosity (Typical
                            9.24            40              28               33
         Value)
                                          Needs
        Design,                                           Needs
                                       modification                       Prone to
     Manufacturing            -                        modification
                                        on cooling                        Ageing.
    and Operational                                   on cooling fins
                                           fins
      Safety & Fire
                             O              K3              K3               K2
      Classification
                          Non-Bio        Non-Bio      Biodegradable     Biodegradable
    Environmental &
                          Effect to      Effect to     No Effect To      No Effect To
         Health
                           Health         Health          Health            Health
11.4. RMU CB
11.4.1. Overview
The ring main unit with circuit breaker (RMU CB) is RMU with circuit breaker
function installed at the outgoing feeders. This tripping of the circuit breaker
is controlled by self powered relay. As in a conventional RMU, the incoming
feeder still uses load break switch (LBS) and the transformer T-off feeder still
uses switch-fuse combination with MV DIN fuse.
Features:
                                                                                           11
     396   Substation Design Manual
RMU CB
Currently, some RMUs used in TNB have circuit breaker function but only for
the transformer T-off feeders. Its tripping function is controlled using time lag
fuse. This kind of circuit breaker is usually of the rotating arc type which has
very limited number of switching operation at rated short circuit breaking
current i.e. 20 kA. Additionally, the integral earth switch in series with this
circuit breaker has rated short time withstand current of 2.1 kA, 1 second.
Therefore, by design this kind circuit breaker cannot be used for outgoing
feeders whereby circuit breaker with more superior performance such as
vacuum circuit breaker is required.
                                                                                          11
     398   Substation Design Manual
The relay is buffered by a battery for feeding the liquid crystal display as well
as for memorising fault values and reset of the trip relay. Failure of the
battery has no effect on the protective functions of the relay. The battery has
a typical service life of more than 10 years.
The front portion of the relay is protected by a transparent cover and meets
IP54 requirement and hence is suitable for outdoor application.
                                  SSU
                     PMU
11
                                                               New Technology   401
Selepas RMU-CB
PMU
SSU
       11.5.1. Overview
       The containerised PPU uses GIS-type for both 33 kV and 11 kV switchgears.
       The advantages of this containerised PPU include:
                                               8
The CPPU shall have the following features:
7
  Design, fabricate, supply, install and commission containerised primary distribution
substation (CPPU) at PPU Jalan Bukit Gambir, for TNB Distribution Pulau Pinang                 11
(Volume i)-Part 1: Instruction To Tenderers (ITT)
     404   Substation Design Manual
       8
         Design, fabricate, supply, install and commission containerised primary distribution
11     substation (CPPU) at PPU Jalan Bukit Gambir, for TNB Distribution Pulau pinang
       (Volume i)-Part 2c: Technical Specifications (CPPU)
                                                              New Technology   405
                                                                                     11
406   Substation Design Manual
Appendix
                                   𝑅 = 𝜌×𝑙 𝐴                                              (1)
                                                                                      o
  Where, 𝜌 = resistivity of the conductor material (given typically at +20 C)
         𝑙 = length of the conductor
         𝐴 = cross-sectional area
                                                                     o
        Table A-2: Resistance per one meter cable length (+75 C) for copper
                                          2               2                2
                 Material        2.5 mm            4 mm             6 mm
                 Copper       0.00865 Ω/m      0.00541 Ω/m        0.00360 Ω/m
  Using the MV wiring connection in Figure 7-20, the worst case scenario is with
                                         o
  resistance per cable length at +75 C, maximum secondary current 5 Amps
  flowing in the circuit, CT burden is given as 15 VA, while main and check meter
  burdens are 1 VA each. The conductor is laid from CT (S1 pin) to the main
  meter, then through the check meter, and back to CT (S2 pin). Thus the total
  conductor length is 2 x L, where L is the distance from the meter to the CT.
                                                                                2
  With this information, the maximum allowable distance, L, for a 2.5 mm
  copper cable can be calculated as follows:
       Cable burden = 𝑆 = 𝐼 2 𝑅
       Total CT burden − meter burden = 𝐼 2 × 𝜌 × 𝑙 𝐴
        15VA − 2 × 1VA = (5 Amps)2 × 0.0216 μΩ ∙ m × 1m/2.5mm2 × 2𝐿
       13 = 0.432 × 𝐿
       𝐿 = 13/0.432
       𝐿 = 30.09 m
                                                                   Appendix      407
B.1       Introduction
The Bukit Gambir Containerised Primary Distribution Substation (CPPU) has
been proposed to be constructed next to the existing P/E Bukit Gambir 2.
A consultant has been engaged to design the earthing system for the
substation. This earthing design report is concerned with the following work:
Calculations carried out are earth resistance, touch and step profiles for the
whole substation and the surface potential profile of the surrounding area of
the substation.
408   Substation Design Manual
  The traverses were chosen based on the best available land area in order to
  maximize the spacing and minimize the likely interference from buried
  metallic objects. Both traverses R1 and R2 were conducted using Wenner
  spacing of up to 13.5 metres.
                                 R1
                                                                  R2
The Wenner 4-point Method is by far the most used test method to measure
the resistivity of soil. Other methods do exist, such as the General and
Schlumberger methods, however they are infrequently used for earthing
design applications and vary only slightly in how the probes are spaced when
compared to the Wenner Method.
A four-terminal earth tester is required, equipped with four short test rods
and connecting leads. The test leads should be checked for continuity and
condition prior to use.
Before carrying out any testing, checks should be made from cable records or
by using above-ground detection equipment, for the location of any buried
cables, earth conductors or metal pipe work. These would adversely affect the
accuracy of the readings taken, particularly if they are parallel to the
measurement traverse. Clearly this will not be an issue at most rural locations.
Figure B-2 shows the general measurement arrangement. The four earth rods
should be driven into the ground in a straight line, at distance “a” metres
apart and driven to a depth of “d” metres.
410   Substation Design Manual
                                       Array Centre
                                             X
                          3a                      a
                          a2                      2
                     a                   a                      a
                                                                       Soil Surface
      d
Probe
C1 P1 P2 C2
EARTH TESTER
  The four earth rods should be connected to the tester, with the outer rods
  connected to the C-1 and C-2 terminals, and the inner rods to the P-1 and P-2
  terminals.
If the surface soil is very dry, the high contact resistance with the rod will
restrict the flow of test current. To overcome this it is recommended that a
short steel rod, having a smaller radius than the test rod, is driven into the soil
to a depth of 150 mm and removed. A weak solution of saline water is poured
into the hole and the test rod driven in. If this does not provide a satisfactory
reading, the rod may be driven in a little deeper.
Software programs are available for carrying out detailed calculations, based
upon data from the above readings, to provide a “best-fit”, representative soil
model for the area, consisting of a number of vertical and horizontal layers
having different resistivity values.
B.2.3    Results
The result of the measurements taken and their corresponding apparent
resistivities are shown in Table B-3.
Legend
RESAP<Bukit Gambir>
 Figure B-4: Plot of the soil resistivity measurements data and the derived
                              electrical soil model
      Table B-4: Derived electrical soil model and its uniform equivalent
                  Layer           Resistivity (Ω·m)      Thickness (m)
                   Top                  130.6                       13.4
                  Bottom                146.0                         ∞
            Uniform equivalent          132.8                         ∞
  B.3.2      Results
  The minimum allowable conductor cross-sectional area is calculated to be
             2
  203.31 mm . In the present work, the dimension of the earth electrode to be
                                                      2
  used in 50 mm x 6 mm (cross-sectional area of 300 mm )
B.4.2     Results
Surface layer resistivity derating factor,
                           ρ
                  0.09 1 −
                           ρ𝑠
      𝐶𝑠 ∶= 1 −
                2 ∙ 𝑠 + 0.09
                                                    (Eq 27 pg 23 IEEE Std.80)
      𝐶𝑠 = 0.78
Tolerable touch voltage for human with 50 kg body weight in V (no footwear),
                                       0.116
      𝐸𝑡𝑜𝑢𝑐 50 ∶= 1000 + 1.5𝐶𝑠 ∙ ρ𝑠
                                             𝑡𝑠
                                                    (Eq 32 pg 27 IEEE Std.80)
      𝐸𝑡𝑜𝑢𝑐 50 = 739.45 V
Tolerable step voltage for human with 50 kg body weight in V (no footwear),
                                    0.116
      𝐸𝑠𝑡𝑒𝑝 50 ∶= 1000 + 6𝐶𝑠 ∙ ρ𝑠
                                       𝑡𝑠
                                                     (Eq 29 pg27 IEEE Std.80)
      𝐸𝑠𝑡𝑒𝑝 50 = 2466.0 V
The main parameters of the design are shown on Table B-5 below.
B.6.2    Results
Resistance of grid conductors,
             ρ     2𝐿𝑐    𝑘1 ∙ 𝐿𝑐
    𝑅1 ∶=       In    ′
                        +         − 𝑘2
            𝜋𝐿𝑐     𝑎        𝐴
                                                       (Eq 54 pg 66 IEEE Std.80)
    𝑅1 = 2.739 Ω
                ρ              4𝐿𝑟         2𝑘1 ∙ 𝐿𝑟            2
    𝑅2 ∶=                 In         −1+              𝑛𝑅 − 1
            2𝜋. 𝑛𝑅 . 𝐿𝑟         𝑏              𝐴
                                                       (Eq 55 pg 66 IEEE Std.80)
    𝑅2 = 2.689 Ω
Mutual resistance between the group of grid conductors and group of earth
rods,
             ρ     2𝐿𝑐   𝑘1 ∙ 𝐿𝑐
    𝑅𝑚 ∶=       In     +         − 𝑘2 + 1
            𝜋𝐿𝑐    𝐿𝑟       𝐴
                                                       (Eq 56 pg 66 IEEE Std.80)
    𝑅𝑚 = 2.325 Ω
                       2
              𝑅1 𝑅2 − 𝑅𝑚
    𝑅𝑔 ∶=
            𝑅1 + 𝑅2 − 2𝑅𝑚
                                                       (Eq 53 pg 66 IEEE Std.80)
    𝑅𝑔 = 2.519 Ω
418   Substation Design Manual
  B.7.1     Results
  Corrective weighting factor that adjust the effect of inner conductors on the
  corner mesh:
                     1
        𝐾′𝑖𝑖 ∶=           2
                    2∙𝑛   𝑛
𝐾𝑖𝑖 = 1
  Note: For grids with earth rods along the perimeter, or for grids with earth
  rods in the grid corners, as well as both along the perimeter and throughout
  the grid area, Kii = 1
                                                                      Appendix      419
    𝐾𝑖 ∶= 0.644 + 0.148 ∙ 𝑛
                                                        (Eq 89 pg 94 IEEE Std.80)
    𝐾𝑖 = 1.088
Corrective weighing factor that emphasises the effects of the grid depth:
                  
    𝐾 ∶= 1 +
                  𝑜
    𝑜 = 1 m (grid reference depth)
                                                        (Eq 83 pg 93 IEEE Std.80)
    𝐾 = 1.14
             1        𝐷2      𝐷 + 2     2
                                                     𝐾𝑖𝑖           8
    𝐾𝑚 ∶=      · In         +                −      +     + In
            2𝜋      16 ∙ 𝐷    8𝑑 ∙ 𝐷            4𝑑   𝐾       𝜋 2𝑛 − 1
                                                       (Eq 81 pg 93 IEEE Std.80)
    𝐾𝑚 = 0.54
            ρ ∙ 𝐾𝑚 ∙ 𝐾𝑖 ∙ 𝐼𝐺
    𝐸𝑚 ∶=
                  𝐿𝑀
                                                        (Eq 80 pg 91 IEEE Std.80)
    𝐸𝑚 = 415.0 V
The mesh voltage is calculated to be lower than the allowable touch voltage
limit calculated in Section B.4.2, which is 739.45 V.
420   Substation Design Manual
  B.8.2     Results
  The effective buried length of conductors:
        𝐿𝑠 ∶= 0.75 · 𝐿𝑐 + 0.85 · 𝐿𝑅
                                                          (Eq 93 pg 94 IEEE Std.80)
                1 1    1   1
        𝐾𝑠 ∶=        +   +   1 − 0.5𝑛−2
                𝜋 2· 𝐷+ 𝐷
                                                          (Eq 94 pg 94 IEEE Std.80)
        𝐾𝑠 = 0.608
        𝐾𝑖 ∶= 0.644 + 0.148 · 𝑛
                                                          (Eq 89 pg 94 IEEE Std.80)
        𝐾𝑖 = 1.088
                                                                       Appendix     421
Step voltage between a point above the outer corner of the grid and a point 1
metre diagonally outside the grid:
              ρ · 𝐾𝑠 · 𝐾𝑖 · 𝐼𝐺
      𝐸𝑠 ∶=
                    𝐿𝑠
                                                        (Eq 92 pg 94 IEEE Std.80)
      𝐸𝑠 = 597.67 V
The step voltage is calculated to be lower than the allowable limit, 2466 V, as
calculated in Section B.4.2.
  Figure B-6 shows that the touch potentials in the areas where the equipment
  will be placed do not exceed the allowable limit.
                                                                  Appendix      423
For the purpose of calculating touch potentials for different EPR magnitudes,
the touch potential plot with respect to the percentage of EPR is produced
and is shown in Figure B-7.
     Figure B-7: Touch potential plot for CPPU Bukit Gambir (% of EPR)
424   Substation Design Manual
Figure B-8: Step potential plot for CPPU Bukit Gambir (% of EPR)
  As shown in Figure B-8, the maximum step potential that can be experienced
  in and around the substation is 16.61% of the substation’s EPR. Assuming a
  net single-phase-to-earth fault current of 1600 A and an EPR of 4020.16 V, the
  maximum step voltage which can be experienced in and around the
  substation is therefore 667.75 V, which is smaller than the calculated
  allowable limit of 2466 V (Section B.4.2). The substation is therefore safe
  against step potential hazards.
LEGEND
100
LEVEL 3 (60,000)
                             50
          Y AXIS (METERS)
                              0
                                                                                       LEVEL 2 (25,000)
-50
                                                                                       LEVEL 1 (15,000)
                            -100
                                   -50       0            50             100
                                            X AXIS (METERS)
                                    Potential Profile (% reference PR)
   Figure B-9: Surface potential profile for CPPU Bukit Gambir (% of EPR)
Figure B-9 shows that surface potentials of up to 15% of the EPR can be
experienced up to a distance of 50 m from the edge of the substation earth
grid, as shown by contour Level 1. For an EPR of 4020.16 V, the surface
potential at this distance is 603.0 V.
  B.10.2     Recommendations
  1.    Install the earthing system as shown in Figure B-10.
  2.    Cover the whole substation area with insulating material, e.g. crushed
        rock.
  4.    The substation has a large prospective EPR which exceeds the ITU limit of
        430 V. Precautions will need to be taken against services coming in and
        going out of the substation, e.g. water rains, LV supplies and
        telecommunication lines.
Notes:
    1.   Conductor for earth Grid is 50 mm x 6 mm copper tape, to be buried at
         300 mm below surface level.
    2.   Base of structures and equipment to be connected to earth grid using
         50 mm x 6 mm copper tapes.
    3.   Connection between copper tapes is by brazing.
    4.   Earth rod diameter is 16 mm, 3 x 1.8 m long.
    5.   Connection between electrodes and rods to be carried out in earth pits.
    6.   Substation area to be covered with crushed rock, 150 mm thick.
    7.   Minimum 2 m separation required between fence and any earthed
         equipment.
IP 3 5
                        Code Letters
         First Characteristic numeral
      Second Characteristic numeral
  Example – IP35
  With the IP rating IP35:
  An "X" can use for one of the digits if there is only one class of protection, i.e.
  IPX1 which addresses protection against vertically falling drops of water e.g.
  condensation.
                                                                       Appendix       429
                        Full penetration of 50 mm
                        diameter of sphere not
1                       allowed. Contact with
                                                               Back of hand
                        hazardous parts not permitted
                        Full penetration of 12.5 mm
                        diameter of sphere not
2                       allowed. The jointed test finger           Finger
                        shall have adequate clearance
                        from hazardous parts
                                      The access probe
                                      of 2.5 mm
3                                     diameter shall
                                                                    Tool
                                      not penetrate
                                     Protected against
      8                              continuous submersion at a      Continuous immersion
                                     specified depth.
                                                                 Appendix   431
List of Abbreviations
  ABC     Aerial bundled cables
  AC      Alternating Current
  AHJ     Authority Having Jurisdiction
  AIS     Air Insulated Switchgear
  Al      Aluminium
  ALF     Accuracy Limit Factor
  ASME    American Society of Mechanical Engineers
  ASTM    American Society for Testing and Materials
  ATS     Automatic Transfer Switch
  AVR     Automatic Voltage Regulator
  AWG     American Wire Gauge
  BS      British Standards
  CB      Circuit Breaker
  CDG     Circular Disk Gear
  CPPU    Containerised Primary Distribution Substation
  CRP     Control & Relay Panels
  CSU     Compact Substation Units
  CT      Current Transformer
  CTC     Continuous Transposed Cable
  Cu      Cuprum
  DC      Direct Current
  DID     Drainage and Irrigation Department
  DIN     German Institute for Standardization /Deutches Institut fur
          Normung
  DITCM   Design-Installation-Testing-Commissioning-Maintenance
  DMS     Distribution Management Systems
  DNP     Distributed Network Protocol
  DOE     Department Of Environment
  DPC     Damp-Proof Course
  EDO     Expulsion Drop-Out
  EFI     Earth Fault Indicator
432   Substation Design Manual
LV      Low Voltage
LVAC    Low Voltage AC
M&E     Management and Engineering
MCB     Miniature Circuit Breaker
MDPE    Medium Density Polyethylene
MDU     Motor Drive Unit
MSB     Main Switch Board
MTB     Meter Test Box
MV      Medium Voltage
NER     Neutral Earth Resistance
NOAEL   No Observable Adverse Effect Level
NTL     Non-Transferable Load
OCEF    Over Current Earth Fault
OCTC    Off-Circuit Tap Changer
ODP     Ozone depletion potential
OLG     Oil Level Gauge
OLTC    On-Load Tap Changer
PAT     Pencawang Atas Tiang / Pole Mounted Substation
PBPK    Physiologically-based Pharmacokinetic
PE      Pencawang Elektrik / Distribution Substation
PECU    Photoelectric Control Unit
PF      Power Factor
PMU     Pencawang Masuk Utama / Main Intake Substation
PN6     Pressure Nominal 6 – max pressure 6 bar
PPU     Pencawang Pembahagian Utama / Primary Distribution
        Substation
PRD     Pressure Relief Device
PSI     Process System Improvement
PT      Potential Transformer
PVC     Polyvinyl Chloride
RC      Reinforced Concrete
RCB     Remote Control Box
RCC     Regional Control Centre
REF     Restricted Earth Fault
RHS     Right Hand Side
434   Substation Design Manual
Glossary
Annunciators               An indicator showing remotely whether each of several
                           items is in the required position or state or not, e.g. door
                           signal with automatic doors or lamp indicating any of
                           several abnormal conditions
Bio-degradable             Biodegradation or biotic degradation or biotic
                           decomposition is the chemical dissolution of materials
                           by bacteria or other biological means
Busbar                     Low-impedance conductor to which several electric
                           circuits can be connected at separate points
Bushing                    Device that enables one or several conductors to pass
                           through a partition such as a wall or a tank, and insulate
                           the conductors from it.
Carcinogenic               Any substance, radionuclide, or radiation that is an agent
                           directly involved in causing cancer
Clearance                  Shortest distance in air between two conductive parts
Creepage distance          Shortest distance along the surface of a solid insulating
                           material between two conductive parts
Discrepancy Switch         A switched indicator, with an acknowledgement facility,
                           which shows any discrepancy between the actual and
                           indicated state of the equipment being monitored
Double Busbar Substation   A substation in which the lines and transformers are
                           connected via two busbars by means of selectors
Earth Resistance           The resistance existing between the electrically
                           accessible part of a buried electrode and another point
                           of the earth, which is far away
Heat Shrink                Mechanically expanded extruded plastic tube ordinarily
                           made of nylon or polyolefin, which shrinks when heated
                           in an effort to return to the relaxed diameter it originally
                           had when extruded
Incoming Feeder            In a substation a feeder bay which is normally used to
                           receive power from the system
Interlock                  A device used to help prevent a machine from harming
                           its operator or damaging itself by stopping the machine
                           when tripped
Internal Arc               The result of a rapid release of energy due to an arcing
                           fault between phases, neutral or a ground
Magnetostriction           Reversible deformation of a body due to magnetization
                           arising from an applied magnetic field
436   Substation Design Manual