00-Site Instruction

This site instruction from the safety engineer provides details for the replacement of an outdoor substation with a new GIS substation, including descriptions of the work, signatures for receipt and concurrence, and a note that the instruction does not involve changes to the contract terms.

Uploaded by

Syed Munawar Ali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
677 views7 pages

00-Site Instruction

This site instruction from the safety engineer provides details for the replacement of an outdoor substation with a new GIS substation, including descriptions of the work, signatures for receipt and concurrence, and a note that the instruction does not involve changes to the contract terms.

Uploaded by

Syed Munawar Ali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 7

SITE INSTRUCTION

PROJECT TITLE:
CONTRACT NO. :
CONTRACTOR :
INSTRUCTION NO.: DATE : TIME:
TITLE:

DESCRIPTION:

ISSUED BY SAFETY ENGINEER , PD/________

RECEIVED BY SITE ENGR. / SAFETY ENGR. (CONTRACTOR)

CONFIRMED BY PROJECT MANAGER, CONTRACTOR*

CONCURRED BY TRANSMISSION ENGR. SPECIALIST, PD/____

* Note : The contractor confirms that this site instruction does not involve adjustment in the Contract Sum or extension of the Contract Milestones
and not inconsistent with the intent of the Contract Documents.

SEC- SIF/ 101 - Rev. 00


DAILY SITE SAFETY REPORT
Project Title :
Contractor : Contract # :
Date: Timing :

Location : Weather Condition:

STANDARDS NA Yes No COMMENTS


Work Permit Availablity

Daily Attendence Sheet (Contractor+Sub-Con)


Approved Job Safety Analysis /Risk Asssessments /
Method Statements / Hazard Identification Plans for every
activity on site
Work Site General

Toolbox Talk Topic :


First Aid kit / First Aider / Emergency Telephone
Numbers at site
Valid SEC IDs
Safety Orientation for all employees
(contractor+SubCon) has been conducted
Drinking Water Facility

Site log book

Work area clean and tidy


Housekeeping

Waste containers provided and are being used

Regular disposal of waste

Passage/Walkways/ access roads unobstructed

Signage / Marking for walkways/passages

Fire Extinguishers available with every vehicle


Fire prevention

Fire Extinguishers inspected and in working


condition
Hot work permit implementation

Designated "Smoking Area"

Adequate wiring, well insulated


Electrical Installations
(Temp/Permanent)

Wiring without joints and damages

Valid Extension cords with proper plugs

Proper barrication

Wiring properly terminated with suitable outlets

Double insulated hand tools shall be used


Hand Tools

Properly kept and well maintained

Any damaged hand tool found at site.

Pre Task tool inspection done

Page 01/03 SEC- DSR/ 59/1 - Rev. 01


STANDARDS NA Yes No COMMENTS
Double insulated and three pin plug fitted
Portable Electrical tools/

Mechanical Safegaurds in use


equipments

Correct Tool for correct job

Any damaged hand tool found at site.

Required PPEs being worn

Proper storage and well maintained

In good condition

Fitted with anti-slip footing

Step ladders fully opened and locked while using

Site made ladders properly constructed with


suitable material
Scaffolding frame work Firm Footing
Ladders / Scaffoldings

(Foundation)
Sole and base plate as per standard

Standards supported and secured

Scaffold level and plum

All nuts bolts tightened

Necessary Railing and toe board fitted

Warning signs displayed

Inspection tag available

Necessary Safety Harness is being used

Area around scaffolding barricaded


Use of Safety Shoes, Halmats, Gloves, Belts &
Harnesses
PPEs use

Use of Masks, Goggles , full face sheild if necessary

In good condition and Well maintained

Adequate use of PPE


Loading / Unloading

Is area barricated

Warning Signal given while loading/unloading

Sling in good condition, without damage

Specify the machinary :


Heavy Equipments/ Machinary used

Operator fully trained (Attach Certificate)

Competent Rigger present at site

Good Physical and medical condition of operator

Ground suitable to use for that machine ?

Alarms, hooters in working condition


Page 02/03 SEC- DSR/ 59/2 - Rev. 01
STANDARDS NA Yes No COMMENTS
Pre job inspection for hydraulic system done
Pre job inspection for electrical (Operation
Control and Selector Swiches) system done
Angle Indicator, Pressure Guage, Boom Stop,
LRI in working condition
Outriggers , Jack Cylinders condition
Tyre pressure, Deisel Level, Battary Level,
Engine Oil, Radiator Water inspected
Any Oil leakage

Boom Hoist and Load Hoist wire in good condition

Wintch Motor, Cluch, Brakes in working condition

Wire Rope, Hook block condition

Goal Posts, Hazard Signs, Traffic Signs installed

Any incident happened on site

Nature of Incident Minor Moderate Major

Brief description of Incident


Incident / Near Miss

Time

Immediate Corrective Action taken :

No. of injured persons First Aid at site / Hospitalized

Machinary Damaged
No. of Hours work
Machinary Repared at site / Replaced with other
stopped
Accident Reported to SEC Safety Engineer

Accident Report submitted to SEC

Comments :

By :

Signature of Site Safety Supervisor (Contractor) :__________________________________

Signature of Site Engineer (Contractor) :__________________________________

Attachments:
*Attendence Sheet
*Certificates of HE Operator
* 2-3 Site Pictures

Page 03/03 SEC- DSR/ 59/3 - Rev. 01


SITE INSTRUCTION
REPLACEMENT OF EXISTING OUTDOOR UTHMANIYAH P/P 115KV
Project Title:
WITH NEW GIS SUBSTATION
LARSEN AND TOUBRO
Contractor: SAUDI ARABIA LLC
Contract No.: 4400012370

Instruction No. : 1 Date & Day : 3/7/2020 / Friday


Title: SAFETY VIOLATION

Violation Description :
Attention Project Manager Mr. Ivan.
This is to inform you that concrete pouring was unable to complete
before 12:00 Pm due to poor supply of concrete from HACO
supplier.as you are aware that Saudi Arabia's Ministry of Human
Resources and Social Development announced that there is a ban to
work under the sun — from 12 p.m. to 3 p.m. — for three months
starting from 15th june to 15th september stipulates that it is not
permissible to make an employee work in the open under direct
sunlight.

The ministry decision aims to


preserve the safety and health of workers and employees in the private
sector and is in line with its commitment to provide them a healthy
and safe work environment and spare them from any risks and harm as
part of the safety and occupational health considerations.

Issued By : Site Engineer/ PD/ E -PD/H SYED MUNAWAR ALI

Received By: Site Engineer/ Safety Engineer. (Contractor)

Confirmed By: Project Manager (Contractor)*

Concurred By: Transmission Engr./Specialist , PD/ ______

* Note : The contractor confirms that this site instruction doest not involve adjustment in the Contract Sum or
extension of the contract milestones and NOR inconsistent with the intent of the Contract Documents.
SEC/SIF/101- Rev 0.0