0% found this document useful (0 votes)
148 views2 pages

Hazard Identification and Risk Assessment Worksheet.: Zubair New Degassing Station Project Caravan Lifting

1. This hazard identification and risk assessment worksheet identifies potential hazards and harms associated with lifting a caravan using a crane at the Zubair New Degassing Station Project location. 2. Five job steps are identified: equipment mobilization, setting up the crane, loading and unloading the caravan, housekeeping, with associated potential hazards like collision, pinch points, dropped loads, slips and trips. 3. Control measures are provided to reduce risks like using competent operators, maintaining speed limits, having signal persons direct the crane, wearing PPE, restricting work areas, and following procedures. Risk levels are assessed between B and C on the project's risk matrix.

Uploaded by

Naveed Ahmed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
148 views2 pages

Hazard Identification and Risk Assessment Worksheet.: Zubair New Degassing Station Project Caravan Lifting

1. This hazard identification and risk assessment worksheet identifies potential hazards and harms associated with lifting a caravan using a crane at the Zubair New Degassing Station Project location. 2. Five job steps are identified: equipment mobilization, setting up the crane, loading and unloading the caravan, housekeeping, with associated potential hazards like collision, pinch points, dropped loads, slips and trips. 3. Control measures are provided to reduce risks like using competent operators, maintaining speed limits, having signal persons direct the crane, wearing PPE, restricting work areas, and following procedures. Risk levels are assessed between B and C on the project's risk matrix.

Uploaded by

Naveed Ahmed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Hazard Identification and Risk Assessment Worksheet.

Workshop DCBM
Project Stage Zubair New Degassing Station Project Location:

Work Activity Caravan lifting Date: 20/04/2017 to 19/05/2017

Risk Procedure
No Job Steps Potential Hazards Harm Control Measures Severity Likelihood
Level No.

- Should be competent, and having all


documents (Local Driving licence, operator
licence etc).
Equipment Personal, Equipment or - Maintain road speed limit when using
1. Collision / Hit 2 B 2B
Mobilization nearby structure. access roads, 20 Km/h.
- Do not use mobile phones while operating
any equipment.
-with valid third party inspection certificate.

-Equipment should be stationed in proper


distance.
-The ground must be check before start
2 -Setting up crane Hit to personnel or compacted well and levelling.
in working area -Hit/pinch points 2 C 2C
. equipment -Dedicated signalman /flagman should give
standard signal to the operator.
-Area should be barricaded and given signage
for authorised person only.

-Always use basic PPE at all times.


-All equipment & tackles should be Inspection ,
(Third party certification).
-Signal man should give proper signals for
Loading and movement, place to place with right
-Personal injury/equipment
3 unloading of -Pinch point /drop load /hit supervision. 2 C 2C
damage.
caravan -Ensure personal working at safe distance.
-Check wind speed and weather condition to be
proper for lifting work.
-Prepare lifting plan.-Proper ergonomics.
-Working area is restricted and barricaded well.
-Use tag line for lifting.
Personal injury/equipment
Laceration /cuts/bruising damage. -working area is restricted and barricaded well.
Broken limbs/fracture -work must do under complete supervision
Loading and
4 -fall objects -follow the procedure. 2 C 2C
unloading of carvan -crushing -use tag line.
-Struck by -use proper PPE all time on site.
-Work crew is competent and qualified.

Personal injury/equipment -Maintain good housekeeping before and after


-Slip, trip ,injury, damage&
5 House keeping work 2 C 2C
-Environmental issues

Subcontractor
Prepared by: Name ENG Mohammad BAGHER Position Site manager Signature
SECL
Reviewed by:
Department/SI
Name Position Signature

Approved by: SECL HSE Name Position Signature