PROJECT MANAGEMENT
REPORT
OFFICE SHIFTING PROJECT
                Prepared by: Manoj Kumar Das
                               0191MBA025
                                       Project Charter.
Project Overview
 Project Name              Lincoln Engineering Pvt. Ltd office shifting
 Sponsor                   Lincoln Engineering Pvt. Ltd
 Project Manager           Manoj Kumar Das
 Project Description       Lincoln Engineering Pvt. Ltd plans to shift its office from Sector II,
                           Saltlake to Sector V, Saltlake in order to improve and expand the
                           overall infrastructure and to better serve its clients, partners and
                           associates.
 Project Start Date                               Project End Date
 Prepared By               Manoj Kumar Das Role                           Project Manager
                                                                          (Operations)
 Prepared Date
Project Scope and objectives
                     Scopes                                         Objectives
       Shifting of office with minor                   To end up in the right office space
        modifications to a currently vacant &            best suited to the business.
        operational building.                           To avoid business disruption by
       Real-time office relocation of current           making advanced planning of
        employees, IT infrastructure and                 company’s IT relocation and ensuring
        systems.                                         the right cabling infrastructure is in
                                                         place in the new office before shifting.
                                                        To move on time which can cost up
                                                         for the business
                                                        To move within budget
                                                        To look out for workforce team and
                                                         concerns throughout the relocation
                                                         process
                                                        Staff to be happy & settle quickly
Project Budget
                Breakdown                                                   Amount
 Project Budget(Estimated)                                                 ₹ 1000000
 Moving Budget                                                              ₹844000
Project Deliverables
 The project deliverables are to find and hire
      a painting contractor
      a carpet installation service
      a specialists that will set up all of the technology and cabling infrastructure in the new office
      a moving company
      purchase additional chairs and furniture for all 50 cubicles, office and conference room
      set dates for the moves
      configure a communication plan for the employees of the departments
 all within scope, budget, and timeframe
Project Assumption
        All permits for the building are approved
        New office space renovation will be complete by moving date
        New office furnishings will arrive by date
        Employees will pack up their personal belongings prior to the move
        There will be a loading dock for the movers to safely transfer all office supplies
        Good weather conditions on moving day
Project Constraints
        scheduling and timing issues
        reliability of contractors
        costs associated with moving
        having sufficient moving supplies and accommodations
Project Work Breakdown Structure (WBS)
Initiating the shifting of office
As with any major project, proper planning and organization are key to success for shifting the
office. Once the decision to relocate is made, the first task is to create an Office Shifting Project
Plan. This is one of the most important steps taken in an office move.
By creating a framework of every step in the process of move, it is ensured that the necessary
tasks are completed in the required time period. When following the office shifting project plan,
inactivity of work and loss of productivity should be kept minimum as the move needs to be
successfully completed on time and on budget.
How to Create an Office Shifting Project Plan
      Determining of who will be the primary person in charge of the move who will serve as
       the in-office shifting coordinator and will have the authority to represent the company,
       and be capable of making quick decisions when it is needed.
      Making a project planning team. The in-office shifting coordinator will be serving as
       leader of the team, and together the team will create the office shifting plan.
      Determining certain important dates, such as current lease termination, preferred shifting
       date, new lease signing, new office build-out start and finish, and final date for
       completion of the shifting.
      Estimating the budget of the whole project. After that it is needed to be reviewed time to
       time throughout the shifting process to ensure the whole process stays within the budget.
      Develop a project plan customized for your office shifting. Mention down every
       important tasks that is needed to done to complete the shifting process. Also it had to be
       mentioned in the plan that who will be responsible for which task and when it is needed
       to be completed.
Team formation for project
Sponsor: Idrish Ali
Provides overall direction for the project
Responsibilities include:
    Approval of the project charter and related plans
    Makes all decisions on intense problems
Project Manager: Manoj Kumar Das
Leads in the planning and development of the project; manages the project to scope.
Responsibilities include:
     Develop the project plan
     Identify project deliverables
     identify risks and develop risk management plan
     Direct the project resources (team members)
     Scope control and change management
     Oversee quality assurance of the project management process
     Maintain all documentation including the project plan
     Report and forecast project status
     Resolve conflicts within the project or between cross-functional teams
     Ensure that the project’s product meets the business objectives
Team Members:
Works toward the deliverables of the project.
Names:                    Harshit Gupta
                          Shubham Gokhale
                          Ashish Sati
                          Swapnil Jha
Responsibilities include:
    Understand the work to be completed
    Complete research, data gathering, analysis, and documentation as outlined in the
      project plan
    Inform the project manager of issues, scope changes, and risk and quality concerns
    Pro-actively communicate status.
Cost/Budget control
                                    Project Budget
                        Expenses                       Cost
Leasing fees expenses
                        Architect                    ₹ 81000
         Communication and network consultant        ₹ 38000
                    Security deposit                 ₹ 420000
                    Electrical cabling               ₹ 40000
Moving expenses
                    Moving vendors                   ₹ 25000
                Computer relocation vendor           ₹ 32000
New equipment/Furnishing expenses
                     Phone systems                    ₹ 43000
                   Office equipments                   ₹ 6000
                        Projector                     ₹ 32000
                       Computers                      ₹ 65000
                       Furnishing                     ₹ 62000
Total shifting expense                                ₹ 844000
Risk management matrix
 Sr. no                  Risk description                                Strategy
   1      Office is partially ready for access on 1st    Make and stick to the decided plan
          September                                      for ending up on 1st September and
                                                         be sure that it doesn’t gets delayed
                                                         for access
   2      Moving vendor takes much more time to          Having a clear talk with the moving
          move the packing than expected                 vendor face to face and strictly
                                                         follow the schedule for each moving
                                                         activities
   3      Painting and flooring work takes longer time   Having a face to face talk before and
          than as decided                                make the contractor aware of the
                                                         schedules for finishing at the
                                                         decided time
   4      Employees aren’t ready/packed to move their    Inform the employees earlier. Make
          belongings on declared dates                   a plan when each employee is
                                                         moving and remind each employee
                                                         with their moving date
   5      Packing boxes for each employees are found     Ask each employees how many
          lesser than required                           boxes do they need to move
   6      Employees not able to work on ongoing          Divide the department by
          projects because of disturbance while          employees, those who work together
          moving                                         and move them on same time
   7      Weather conditions are not good to move.       Having an extended date for moving
                                                         if uncompleted
Quality control
Quality standards have been followed and the services have met the requirements as they were
specified earlier for completion of the project. It was made sure that every essentials is done
according to project planning in the best manner possible. Quality planning in present project
was very important. If it wouldn’t have been kept as per as the standards, then it would have
affected the costs, scheduling and timescale of project.
      Quality inspection has been executed under which the documentation related to the
       project, the resource and budgeting information, the task list and task responsibilities
       have been reviewed in order to determine the project progress.
      The code compliance has been checked. The codes associated with health and safety
       regulations and other aspects of project such as construction, design and electrical
       arrangements in the new office are checked under quality review. The occupancy
       certificates are checked as well.
      Quality assessment have been done to see whether quality compliance has been
       maintained in the project or not.
      The above steps are followed within the whole project activities which have been resulted
       in achieving Total Quality Management.