21A00064 Bidding Documents
21A00064 Bidding Documents
BIDDING DOCUMENTS
FOR
1
TABLE OF CONTENTS
2
ANNEX II–1.1A
Section I. Invitation to Bid
3
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE I
City of San Fernando, La Union
INVITATION TO BID
For
2. The Department of Public Works and Highways Regional Office I through its Bids and Awards
Committee now invites bids for the hereunder Works:
3. To be eligible to bid for these Contracts, a contractor must meet the following major
requirements: a) Filipino citizen or 75% Filipino-owned with PCAB license for Size Range Medium A, b)
completion of a similar contract costing at least 50% of the ABC, and c) Net Financial Contracting Capacity
(NFCC) at least equal to the ABC. The description of an eligible Bidder is contained in the Bidding Documents,
particularly, in Annex II-1.1 B Section II and III of Bidding Documents.
Contractors/applicants who wish to participate in this bidding are encouraged to enroll in the DPWH Civil
Works Application (CWA) at the DPWH Procurement Service (PrS), 5th Floor, DPWH Bldg., Bonifacio Drive,
Port Area, Manila, while those already enrolled shall keep their records current and updated. The Contractor’s
eligibility to bid on the project will be determined using the DPWH Contractor Profile Eligibility Process (CPEP)
and subject to further post- qualification. Information on registration can be obtained from the PrS during
working weekdays from 7:00 am to 4:00 pm or at the DPWH website www.dpwh.gov.ph.
4. Bidding will be conducted through open competitive bidding procedures using non-discretionary
pass/fail criterion as specified in the 2016 Revised Implementing Rules and Regulations (IRR) of Republic
Act 9184 (RA 9184), otherwise known as the "“Government Procurement Reform Act”. The contract shall
be awarded to the Lowest Calculated Responsive Bidder (LCRB) who was determined as such during post-
qualification.
5. Interested bidders may obtain further information from the Department of Public Works and
Highways Regional Office I and inspect the Bidding Documents at Aguila Rd., Brgy. Sevilla, City of
San Fernando, La Union during weekdays from 8:00 A.M. – 5:00 P.M.
6. A complete set of Bidding Documents may be acquired by interested bidders on October 27, 2020 to
November 18, 2020 from the address below and upon payment of the applicable fee for the Bidding
Documents, pursuant to the latest Guidelines issued by the GPPB, in the amount of Php25,000.00.
4
7. It may also be downloaded free of charge from the website of the Philippine Government Electronic
Procurement System (PhilGEPS), and the website of the Procuring Entity, provided that bidders shall pay
the applicable fee for the Bidding Documents not later than the submission of their bids.
8. The Department of Public Works and Highways Regional Office I will hold a Pre-Bid Conference on
November 03, 2020, 10:00 A.M. at 2nd Floor, Conference Room of DPWH-Regional Office I,
City of San Fernando, La Union, which shall be open to prospective bidders.
9. Bid submission maybe done manually or electronically/online. However, bidders should only select one
mode of submission, either manual or electronic. Similar to manual submission, the guidelines for the
preparation and submission of an electronic bid are contained in the BDS.
10. Bids must be duly received by the BAC Secretariat at the address below for manual submission or at
electronicbids_r1@dpwh.gov.ph for electronic submission on or before November 18, 2020 @
10:00AM. All bids must be accompanied by a bid security in any of the acceptable forms and in the
amount stated in ITB Clause 18.
11. Bid opening shall be on November 18, 2020, 10:00 AM at Conference Room of DPWH-
Regional Office I, City of San Fernando, La Union. Bids will be opened in the presence of the
bidders’ representatives who choose to attend at the address below. Late bids shall not be accepted.
12. The Department of Public Works and Highways Regional Office I reserves the right to reject
any and all bids, declare a failure of bidding, or not award the contract at any time prior to contract award
in accordance with Section 41 of RA 9184 and its IRR, without thereby incurring any liability to the
affected bidder or bidders.
Approved by:
GERRY G. JUCAR
Chief, Construction Division
BAC Chairman
5
ANNEX II-1.1B
Section II. Eligibility Requirements
6
STANDARD FORMAT
ELIGIBILITY REQUIREMENTS
1. Unless otherwise indicated in the Instructions to Bidders (ITB), the prospective bidder
must meet the following Eligibility Requirements (ER) for purposes of determining by the
DPWH the eligibility of the bidder for the contract to be procured:
(a) Registration certificate from the Securities and Exchange Commission (SEC) in
the case of a Partnership or Corporation, or from the Department of Trade and
Industry (DTI) in the case of a Single Proprietorship, or from the Cooperatives
Development Authority in the case of a cooperative.
(b) Mayor’s/Business Permit issued by the city or municipality where the principal
place of business of the prospective bidder is located.
(c) Tax Clearance per Executive Order (EO) No. 298, series of 2005, as finally
reviewed and approved by the Bureau of Internal Revenue (BIR).
(b) Record of the prospective bidder’s completed contracts, both government and
private, including the following information for each contract:
7
v. Contractor’s role (whether sole contractor, sub-contractor, or partner in a joint
venture), specific components or aspects of the work done by it, and its
participation percentage.
vi. Total as-built cost at completion.
(c) Record of the prospective bidder’s on-going contracts, including awarded but not
yet started, both in government and the private sector, indicating the following
information for each contract.
(a) The prospective bidder’s Audited Financial Statement (AFS), stamped “received’’
by the BIR or its duly accredited and authorized institution, for the immediately
preceding calendar year, showing, among other things, the prospective bidder’s
total and current assets and liabilities.
(b) The prospective bidder’s computation for its Net Financial Contracting Capacity
(NFCC).
To facilitate determination of eligibility, the BAC of a Procuring Entity shall use the
contents of the PhilGEPS electronic registry of contractors (IRR Section 23.3).
All bidders shall maintain a current and updated file of the following Class “A”
Eligibility Documents (IRR Section 8.5.2 in relation to Sec. 23.1(a)):
8
For every specific contract to be procured, each bidder shall submit to the BAC, as part of
its bid, its PhilGEPS Certificate of Registration and Membership. This PhilGEPS
Certificate is in lieu of the five Class “A” Eligibility Documents mentioned above since
these are already covered by the said Certificate. The bidder, however, shall submit to the
BAC, as part of its bid for the contract, all other Eligibility Documents which are not
covered by the PhilGEPS Certificate.
For foreign bidders, the foregoing documents may be substituted by the appropriate
equivalent documents in English, if any, issued by the country of the bidder concerned.
These documents shall be accompanied by a Sworn Statement in a form prescribed by the
GPPB stating that the documents submitted are complete and authentic copies of the
original, and all statements and information provided therein are true and correct (IRR
Section 8.5.2).
Valid joint venture agreement (JVA), in case the joint venture is already in existence. In
the absence of a JVA, duly notarized statements from all the potential joint venture (JV)
partners shall be included in the bid, to the effect that they will enter into and abide by the
provisions of the JVA in the instance that the bid is successful. Failure to enter into a JV
shall be a ground for the forfeiture of the Bid Security. Each partner of the JV shall
submit the PhilGEPS Certificate of Registration in accordance with Section 8.5.2 of the
IRR of RA 9184. The submission of technical and financial eligibility documents by any
of the JV partners constitutes compliance. The partner responsible to submit the NFCC
shall likewise submit the statement of all of its ongoing contracts and Audited Financial
Statements.
(2) A partnership duly organized under the laws of the Philippines and of which at least
seventy-five percent (75%) of the interest belongs to citizens of the Philippines.
(3) A corporation duly organized under the laws of the Philippines and of which at least
seventy five (75%) of the outstanding capital stock belongs to citizens of the
Philippines.
(5) Persons/entities forming themselves into a joint venture (JV), i.e., a group of two (2)
or more persons/entities that intend to be jointly and severally responsible or liable
for a particular contract, provided that, in accordance with the President’s Letter of
Instructions No. 630, Filipino ownership or interest in the JV concerned shall be at
least seventy-five (75%); provided, further, that JVs in which Filipino ownership or
interest is less than seventy-five percent (75%) may be eligible where the structures to
be built require the application of techniques and/or technologies which are not
adequately possessed by a person/entity meeting the seventy-five percent (75%)
9
Filipino ownership requirement; and provided, finally, that in the latter case, Filipino
ownership or interest shall not be less than twenty-five percent (25%). For this
purpose, Filipino ownership or interest shall be based on the contributions of each of
the members of the JV as specified in their joint venture agreement (JVA).
For this particular contract to be bid, the prospective bidder must possess a valid
license issued by the PCAB in accordance with the provisions of RA 4566, for the
specific category indicated in the Eligibility Data Sheet (EDS), out of the following
PCAB categories:
For this particular contract to be procured, the Approved Budget for the Contract
(ABC) is indicated in the EDS. The required PCAB license for this project, based on
Table 1 above, is also specified in the EDS.
The prospective bidder must possess the experience of having a Single Largest
Completed Contract (SLCC) “similar” to the contract to be procured, and whose
value, adjusted to current prices using the consumer price indices of the Philippine
Statistics Authority (PSA), is at least fifty percent (50%) of the ABC to be bid. Small
A and Small B contractors without similar experience on the contract to be bid,
however, may be allowed to bid if the cost of such contract is not more than the
Allowable Range of Contract Cost (ARCC) of their respective size range
corresponding to their PCAB license as shown in Table 1 above (IRR Section
23.4.2.4).
As stated in Appendix 2.2 (Guidelines for Major and Similar Categories of Works), a
“Major Category of Works” is the main classification of works in the contract to be
bid, according to type of infrastructure and kind of work performed - e.g. road
construction, bridge rehabilitation, etc. On the other hand, a “Similar Category of
Works” is a kind of works whose classification is considered to be comparable to the
Major Category of Works in the contract to be bid and, therefore, shall be considered
for purposes of evaluation of the bidder’s eligibility for the contract to be bid. A
“Qualifier” is an additional specific requirement on Major or Similar Categories of
Work, to be required from the bidders at the bidding stage, to show that they have the
necessary expertise and experience to execute the contract, such as an extraordinarily
large embankment volume, or soft ground treatment, or long tunnel using tunnel
10
boring machine, or bridge retrofitting using special jacking technology, or very long
sheet piling, multi-level basement, etc.
For the specific project or contract to be bid under these BDs and based on the
Guidelines and Matrix of Categories in Appendix 2.2, the Major Categories of Works
and Similar Categories of Work, as well as any Qualifier, that shall be considered in
determining a bidder’s eligibility for the contract to be bid are indicated in the EDS.
Select either the following item (a) or item (b), whichever is applicable, and delete the
other:
(a) For a contract involving a single category of works (i.e., type of infrastructure and
kind of work) - e.g., road construction, or bridge retrofitting, or flood control
rehabilitation - the following criteria shall be adopted:
ii. To be eligible to bid for the contract, a contractor must have done a Single Largest
Completed Contract (SLCC) for a Major/Similar Category of Works whose total
cost is at least 50% of the Approved Budget of the Contract (ABC) to be bid.
(b) For a contract to be bid involving multiple categories of works – e.g., road
construction plus bridge retrofitting plus flood control rehabilitation – the following
criteria shall be adopted:
i. Each category of works whose cost is at least 30% of the ABC shall be
considered a Major Category of Works. All other categories of works shall
be considered Minor Categories of Works.
ii. To be eligible to bid for the contract, a contractor must comply with the
following work experience requirements:
ii-a As the basic requirement, the contractor must have undertaken a SLCC
similar to the contract to be bid. To be so considered similar, the SLCC
must meet the following requirements:
The SLCC must contain the same Major Categories of Works as the
contract to be bid, and each Major Category of Works in the SLCC
must cost at least 30% of the total cost of the SLCC.
The total cost of the SLCC must be at least 50% of the total ABC to
be bid.
11
In the case of contracts which include special equipment to be supplied and installed
by the supplier/manufacturer, the cost of such equipment shall be excluded from the
ABC to be used in computing the required work experience as stated in the preceding
paragraph.
To support its SLCC, the bidder must submit the corresponding Owner’s Certificate
of Final Acceptance issued by the project owner other than the contractor, or at least a
satisfactory CPES Rating. In case of contracts with the private sector, an equivalent
document shall be submitted.
The prospective bidder must have a Net Financial Contracting Capacity (NFCC) at least
equal to the ABC to be procured.
NFCC = [(Current assets minus current liabilities) (15)] minus the value of all
outstanding or uncompleted portions of the projects under ongoing contracts,
including awarded contracts yet to be started, which portions coincide with the
contact to be bid.
The values of the bidder’s current assets and current liabilities shall be based on the latest
Audited Financial Statements (AFS) submitted to the BIR.
For purposes of computing the foreign bidders' NFCC, the value of the current assets and
current liabilities shall be based on their Audited Financial Statements prepared in
accordance with international financial reporting standards.
The Procuring Entity shall apply the abovementioned Eligibility Requirements (ER) not only
to the main contractor/bidder but also to any sub-contractors for the portions of the main
contract works that are proposed to be sub-contracted to them, except for pakyaw contracts
as defined in Appendix 11 of RA 9184-IRR.
The main contractor/bidder, however, must meet all of the abovementioned Eligibility
Requirements by itself, with or without any sub-contractor. Hence, if any nominated sub-
contractor is declared ineligible, the main contractor, on its own, must still meet the
prescribed Eligibility Requirements.
Notwithstanding the eligibility of a bidder, the Procuring Entity concerned reserves the right
to review the qualifications of the bidder at any stage of the procurement process if the
Procuring Entity has reasonable grounds to believe that a misrepresentation has been made
12
by that bidder, or that there has been a change in the bidder’s capability to undertake the
project from the time it submitted its eligibility requirements. Should such review uncover
any misrepresentation made in the eligibility requirements, statements or documents, or any
changes in the situation of the bidder which will affect the capability of the bidder to
undertake the project so that it fails the eligibility criteria, the Procuring Entity shall consider
the said bidder as ineligible and shall disqualify it from obtaining an award or contract, in
accordance with Rules XXI, XXII, and XXIII of the IRR of RA 9184 (IRR Section 23.6).
2. If, as specified in the EDS, Electronic Bidding is adopted for this procurement pursuant to
GPPB Resolution No. 23-2013, dated 30 July 2013, the following procedure shall be
observed with regard to the registry with the PhilGEPS:
b. Only a Certified Member with the appropriate classification can avail of the PhilGEPS
advance eligibility submission by uploading their electronic documents to the PhilGEPS
document library, which can be accessed for current or future procurements.
13
ANNEX II-1.1C
Section III. Eligibility Data Sheet (EDS)
14
Eligibility Data Sheet
Eligibility
Requirements
1c(1) The ABC for this contract is: Php48,250,000.00
1c(2) (1) The following are the “Major Categories of Works” involved in
the contract to be bid: RCG: Roads: Construction - Gravel
(2) The following are the “Similar Categories of Works” that shall
be considered in the evaluation of the work experience required for the
contract to be bid: RCA,RCP,RRA,RRP,RRG
A. General
1. Scope of Bid
1.1 The Procuring Entity, as defined in the BDS, invites Bids for the construction of
the Works under the proposed Contract, as described in the BDS. The name and
ID of the Contract are stated in the BDS.
1.2 The winning Bidder will be expected to complete the Works by the intended
completion date specified in the SCC Clause 1.17.
a. defines, for purposes of this provision, the terms set forth below as
follows:
3.2 Furthermore, the Procuring Entity will also seek to impose the maximum
penalties for civil and criminal liability available under the applicable law on
individuals and organizations deemed to be involved in corrupt, fraudulent,
collusive or coercive practices.
3.3 The Funding Source and the Procuring Entity reserve the right to inspect and
audit records and accounts of a contractor in the bidding for and performance of a
particular contract, through DPWH official or independent auditors as provided in
GCC Clause 35.
Conflict of Interest
4.1 All Bidders found to have a conflict of interest shall be disqualified to participate
in the procurement at hand, without prejudice to the imposition of appropriate
administrative, civil, and criminal sanctions. A Bidder may be considered to have
a conflict of interest with another Bidder in any of the events described in items a
through d of this ITB Clause 4.1 and a general conflict of interest in any of the
circumstances set out in items e through h of ITB Clause 4.1:
b. A Bidder receives or has received any direct or indirect subsidy from any
other Bidder.
c. A Bidder has the same legal representative as that of another Bidder for
purposes of this Bid.
e. A Bidder submitted more than one Bid in this bidding process. However,
this does not limit the participation of sub-contractors in more than one
Bid.
4.2 In accordance with Section 47 of the IRR of RA 9184, the Bidder must include in
its Bid a sworn affidavit (part of Form DPWH-INFR-15, as provided in Clause
10.1 of this ITB) that it is not related to the Head of the Procuring Entity (HoPE),
members of the BAC, the Technical Working Group (TWG), and the BAC
Secretariat, the head of the IU, and the project consultants, by consanguinity or
affinity up to the third civil degree. Failure to comply with the aforementioned
provision shall be a ground for the automatic disqualification of the bid in
consonance with Section 30 of this IRR. For this reason, relation to the
aforementioned persons within the third civil degree of consanguinity or affinity
shall automatically disqualify the bidder from participating in the procurement of
contracts of the Procuring Entity, notwithstanding the act of such persons
inhibiting themselves from the procurement process. On the part of the bidder,
this provision shall apply to the following persons:
e. If the Bidder is a joint venture (JV), to each member of the JV for the
applicable items a, b, and c of this Clause.
Eligible Bidders
5.1 Unless otherwise indicated in the BDS, bidders must meet the Eligibility
Requirements in ANNEXII-1.1B of the SBDs.
5.2 The Procuring Entity may also invite foreign bidders when provided for
under any Treaty or International or Executive Agreement as specified in the
BDS.
Bidder’s Responsibilities
6.1 The Bidder is responsible for the following:
c. Having made an estimate of the facilities available and needed for the
contract to be bid, if any.
k. Ensuring that it did not give or pay, directly or indirectly, any commission,
amount, fee, or any form of consideration, pecuniary or otherwise, to any
person or official, personnel or representative of the government in
relation to any procurement project or activity.
Failure to observe any of the above responsibilities shall be at the risk of the
Bidder concerned.
6.2 The Bidder or its duly authorized representative shall submit a sworn statement,
covering items e to k of ITB Clause 6.1 above, in the form prescribed in DPWH-
INFR-15 in ANNEX II-1.1K hereof.
6.3 The Bidder, by the act of submitting its bid, shall be deemed to have inspected the
site, determined the general characteristics of the contract works and the
conditions for this Project and examine all instructions, forms, terms, and project
requirements in the Bidding Documents.
6.4 It shall be the sole responsibility of the prospective bidder to determine and to
satisfy itself by such means as it considers necessary or desirable as to all matters
pertaining to this Project, including: (a) the location and the nature of the contract,
project, or work; (b) climatic conditions; (c) transportation facilities; (c) nature
and condition of the terrain, geological conditions at the site communication
facilities, requirements, location and availability of construction aggregates and
other materials, labor, water, electric power and access roads; and (d) other
factors that may affect the cost, duration and execution or implementation of the
contract, project, or work.
6.5 The Procuring Entity shall not assume any responsibility regarding erroneous
interpretations or conclusions by the prospective or eligible bidder out of the data
furnished by the procuring entity.
6.6 Before submitting their bids, the Bidders are deemed to have become familiar
with all existing laws, decrees, ordinances, acts and regulations of the Philippines
which may affect the contract in any way.
6.7 The Bidder shall bear all costs associated with the preparation and submission of
his bid, and the Procuring Entity will in no case be responsible or liable for those
costs, regardless of the conduct or outcome of the bidding process.
6.8 Bidders should note that the Procuring Entity will only accept bids only from
those that have paid the nonrefundable fee for the Bidding Documents at the
office indicated in the Invitation to Bid.
Sub-Contracts
8.1 Unless otherwise specified in the BDS, sub-contracting of the Works shall be
subject to the provisions of DPWH Department Order (DO) No. 38, series of
2015, as stated in Clauses 8.2 to 8.7.
8.2 All sub-contracts shall be subject to prior approval of the concerned Heads of the
DPWH Procuring Entity within the limits of their delegated authority to approve
the original contracts.
8.3 The contractor may sub-contract portions of the works to such an extent as may
be approved by the Procuring Entity and stated in the BDS, provided that the
main contractor shall directly undertake, using its own resources, not less than
fifty percent (50%) of the contract works in terms of cost.
8.4 Each sub-contractor must comply with the eligibility criteria as specified in the
Eligibility Requirements (ER) for the portion of the contract works to be sub-
contracted to that sub-contractor- e.g., applicable license from the Philippine
Constructors Accreditation Board, satisfactory completion of works similar to the
portion of the contract to be subcontracted and costing at least fifty percent (50%)
of the cost of such portion, and sufficient Net Financial Contracting Capacityto
cover the cost of the work to be sub-contracted, as well as minimum equipment
and manpower for the sub-contracted work set by the Procuring Entity. These
requirements shall not apply to labor pakyaw contracts provided in the IRR
Appendix 11.
8.5 The bidder/main contractor may identify the sub-contractors to whom portions of
the contract works will be sub-contracted at any stage of the bidding process or
during contract implementation, provided that any sub-contracting requires prior
approval of the Procuring Entity. If the bidder opts to disclose the name of the
sub-contractors during the bid submission, the bidder shall include the required
eligibility documents for the sub-contractors as part of the technical component of
its bid. Sub-contractors identified during the bidding may be changed during the
implementation of the contract, subject to compliance with the eligibility
requirements and approval of the Procuring Entity.
8.6 Sub-contracting of any portion of the contract shall not relieve the main contractor
from any liability or obligation that may arise from the contract. The main
contractor shall be responsible for the acts, defaults, and negligence of any
subcontractor, its agents or workmen.
8.7 For any assignment and sub-contracting of the contract or any part thereof made
without prior written approval by the concerned HoPE, the DPWH shall impose
on the erring contractor, after the termination of the contract, the penalty of
suspension for one (1) year for the first offense, and suspension of two (2) years
for the second offense from participating in the public bidding process, pursuant
to the provision of Appendix 3, Section 4.2 of the IRR of RA 9184, in accordance
with Section 69(6) of RA 9184 and without prejudice to the imposition of
additional administrative sanctions as the internal rules of the agency may provide
and/or further criminal prosecution as provided by applicable laws.
9. Pre-Bid Conference
9.1 If so specified in the BDS, a Pre-Bid Conference shall be held at the venue and on
the date indicated therein, to clarify and address the Bidders’ questions on the
technical and financial components of this Project. The Pre-Bid Conference shall
be held at least twelve (12) calendar days before the deadline for the submission
and receipt of Bids. However, attendance of the Bidders shall not be mandatory. If
the Procuring Entity determines that, by reason of the method, nature, or
complexity of the contract to be bid, or when international participation will be
more advantageous to the GOP, a longer period for the preparation of bids is
necessary, the Pre-Bid Conference shall be held at least thirty (30) calendar days
before the deadline for the submission and receipt of bids, as specified in the
BDS.
9.2 Bidders are encouraged to attend the Pre-Bid Conference to ensure that they fully
understand the Procuring Entity’s requirements. Non-attendance of the Bidder
will in no way prejudice its bid; however, the Bidder is expected to know the
changes and/or amendments to the Bidding Documents as recorded in the minutes
of the Pre-Bid Conference and the Supplemental/Bid Bulletin.
9.3 Any statement made at the Pre-Bid Conference shall not modify the terms of the
bidding documents unless such statement is specifically identified in writing as an
amendment thereto and issued as a Supplemental/Bid Bulletin.
9.4 If, as indicated in the BDS, Electronic Bidding is adopted for this procurement
pursuant to GPPB Resolution No. 23-2013, dated 30 July 2013, the Procuring
Entity shall observe following procedure with regard to the PBC:
a. For contracts to be bid where the conduct of PBC is required under Section 22
of RA 9184-IRR (Section 5.5.3 of this Manual Volume II), the same
procedure governing the manual method will also apply.
c. During the conduct of the PBC, Registered Merchants may send requests for
clarification through the PhilGEPS online facility, which shall be read during
the meeting and shall form part of the minutes, unless the Procuring Entity has
previously decided that only those who have purchased the Bidding
Documents shall be allowed to participate in the PBC and raise or submit
written queries or clarifications.
10.1 Bidders should note that the Procuring Entity shall only accept Bids from Bidders
that have purchased the BDs from the office indicated in the IB, or have
downloaded the BDs from the DPWH website subject to the payment of the fee
for the BDs upon submission of their bids.
11.2 The BAC, upon its initiative, may also issue Supplemental/Bid Bulletins to amend
or clarify any provision of the BDs not later than seven (7) calendar days before
the deadline for the receipt of Bids. .
11.3 Any Supplemental/Bid Bulletin issued by the BAC shall be posted on the
websites of the DPWH and the Philippine Government Electronic Procurement
System (PhilGEPS). It shall be the responsibility of all Bidders who secured the
Bidding Documents to inquire and secure Supplemental/Bid Bulletins that may be
issued by the BAC. However, bidders who have submitted bids before the
issuance of the Supplemental/Bid Bulletin must be informed and allowed to
modify or withdraw their bids in accordance with ITB Clause 24.
C. Preparation of Bids
(4) If the bidder is not previously enrolled in the CWR: the bidder’s
Class “A” and Class “B” Documents, excluding the five Class “A”
documents covered by the PhilGEPS Certificate of Registration –
viz., SEC/DTI/CDA Registration, Mayor’s/Business Permit, Tax
Clearance, PCAB License and Registration, and Audited Financial
Statement. These Documents should include, among others, the
following information required in IRR Section 25.2b:
(b) SLCC
(c) NFCC
(3) Bid Security in/with the required form, amount, and validity period
as provided in ITB Clause 18 (Use Form DPWH-INFR-10 or 11
or 12).
14.3 a. Unless indicated in the BDS, all Total Bid Prices that exceed the
Approved Budget for the Contract (ABC) indicated in BDS 1.3 shall be
rejected.
(ii) The Procuring Entity has procedures in place to ensure that the
ABC is based on recent estimates made by the responsible unit of
the Procuring Entity and that the estimates are based on adequate
detailed engineering and reflect the quality, supervision and risk
and inflationary factors, as well as prevailing market prices,
associated with the types of works to be procured.
14.4 The bidder may use, as reference, the checklist of requirements for its Technical
and Financial Proposals, as shown in Form DPWH-INFR-20.
15. Bid Prices
15.1 The Contract shall be for the whole Works, as described in ITB Clause 1.1, based on
the priced BOQ (Use Form DPWH-INFR-17) submitted by the Bidder.
15.2 The Bidder shall fill in its unit and total Bid prices for all items of the Works
described in the BOQ. Bids not addressing or providing all of the required items
in the BOQ, shall be considered non-responsive and, thus, automatically
disqualified. In this regard, where a required item is provided, but no price is
indicated, the same shall be considered as non-responsive, but specifying a "0"
(zero) or a dash (“-”) for the said item would mean that it is being offered for free
to the Government.
15.3 All duties, taxes, and other levies payable by the Contractor under the Contract, or
for any other cause, prior to the deadline for submission of Bids, shall be included
in the Bid prices submitted by the Bidder.
15.4 For the given scope of work in the Contract as awarded, all Bid prices shall be
considered as fixed prices, and therefore not subject to price escalation during
contract implementation, except under extraordinary circumstances as specified in
GCC Clause 47. Price escalation may be allowed in extraordinary circumstances
as may be determined by the National Economic and Development Authority in
accordance with the Civil Code of the Philippines, and upon the recommendation
of the Procuring Entity. Furthermore, in cases where the cost of the awarded
contract is affected by any applicable new laws, ordinances, regulations, or other
acts of the GOP, promulgated after the date of bid opening, a contract price
adjustment shall be made or appropriate relief shall be applied on a no loss-no
gain basis.
16.2 If so allowed in accordance with ITB Clause16.1, the Procuring Entity for purposes
of bid evaluation and comparing the bid prices will convert the amounts in various
currencies in which the bid price is expressed to Philippine Pesos at the exchange
rate as published in the BSP reference rate bulletin on the day of the bid opening.
16.3 Unless otherwise specified in the BDS, payment of the contract price shall be made
in Philippine Pesos.
18.2 A Bid Securing Declaration is an undertaking which states, among others, that the
bidder shall enter into contract with the Procuring Entity and furnish the required
Performance Security within ten (10) calendar days, or less, as indicated in the
BDs, from receipt of the Notice of Award, and commits to pay the corresponding
amount as fine and be suspended for a period of time from being qualified to
participate in any government activity in the event it violates any of the conditions
stated therein as required in the guidelines issued by the Government Procurement
Policy Board (GPPB).
18.3 The Bid Security should be valid for the period specified in the BDS.
18.4 Any Bid not accompanied by a Bid Securing Declaration or an acceptable Bid
Security shall be rejected by the Procuring Entity as non-responsive.
18.5 No Bid Securities shall be returned to Bidders after the opening of Bids and
before contract signing, except to those that failed to comply with any of the
requirements to be submitted in the Technical Proposal and Financial Proposal of
the Bid, as provided in the IRR of R.A. 9184. Without prejudice to the forfeiture
of Bid Securities, Bid Securities shall be returned only after the Bidder with the
Lowest Calculated Responsive Bid has signed the Contract and furnished the
Performance Security, but in no case later than the expiration of the Bid Security
validity period indicated in the BDS.
a. if the Bidder withdraws its Bid after Bid opening during the period of Bid
validity; or
b. if the Bidder does not accept the correction by the Bids and Awards
Committee of arithmetical and computational errors in its Bid prices,
pursuant to ITB Clause 28; or
c. in the case of the winning Bidder, if the Bidder fails, within ten (10) days
from its receipt of the Notice of Award, to:
(k) Latest Income Tax and Business Returns duly stamped and
received by BIR and duly validated with the tax payments
made. Tax Clearance from the BIR to prove full and timely
payment of taxes;
f. if the Bidder allows the use of its name by another contractor, or uses the
name of another contractor, for purposes of public bidding; or
g. if the Bidder refuses to clarify or validate in writing its Bid during post-
qualification within a period of seven (7) calendar days from receipt of the
request for clarification; or
i. if the Bidder commits any other act that tends to defeat the purpose of the
competitive bidding, such as habitually withdrawing from bidding or
submitting letters of non-participation for at least three (3) times within
twelve (12) months, except for valid reasons.
19.2 Each Bidder shall submit only one Bid, either individually or as a partner in a JV.
A Bidder who submits or participates in more than one bid (other than as a
subcontractor if a subcontractor is permitted to participate in more than one bid)
will cause all the proposals with the Bidder’s participation to be disqualified. This
shall be without prejudice to any applicable criminal, civil and administrative
penalties that may be imposed upon the persons and entities concerned.
20. Format and Signing of Bid
20.1 Bidders shall submit their bids through their duly authorized representative using
the appropriate forms provided in Section XI of the SBDs (ANNEX IIA-11) on
or before the deadline specified in the ITB Clause 22 in two (2) separate sealed
bid envelopes, and which shall be submitted simultaneously. The first shall
contain the technical component of the bid as provided in ITB Clause 14.2a, and
the second shall contain the financial component of the bid as provided in ITB
Clause 14.2a.
20.2 Forms as mentioned in ITB Clause 20.1 must be completed without any
alterations to their format, and no substitute form shall be accepted. All blank
spaces shall be filled in with the information requested.
20.3 The Bidder shall submit one original of the Technical Proposal and one original
of the Financial Proposal as described in ITB Clause 20.1 and clearly mark each
as “ORIGINAL - TECHNICAL PROPOSAL” and “ORIGINAL – FINANCIAL
PROPOSAL”. In addition, the Bidder shall submit copies of the Technical
Proposal and the Financial Proposal, and clearly mark them “COPY NO… -
TECHNICAL PROPOSAL” and “COPY NO…. – FINANCIAL PROPOSAL”.
In the event of any discrepancy between the original and the copies, the original
shall prevail.
20.4 The original copy of the Bid as indicated in the BDS shall be typed or written in
indelible ink and shall be signed by the Bidder or a person or persons duly
authorized to bind the Bidder to the contract. Each page of the Bid Form and the
accomplished Bill of Quantities shall be signed by the Bidder or its duly
authorized representative. Failure to do so shall be a ground for the rejection of
the Bid.
20.5 Any interlineations, erasures, alterations or overwriting shall be valid only if they
are signed or initialed by the person signing the Bid.
21.2 Each copy of the Technical Proposal and Financial Proposal, shall be similarly
sealed duly marked as “COPY NO… - TECHNICAL PROPOSAL” and “COPY
NO… – FINANCIAL PROPOSAL” respectively and the outer envelope as
“COPY NO”.
21.3 These envelopes containing the original and the copies shall then be enclosed in
one single envelope that shall:
a. indicate the name of the Contract to be bid;
e. bear a warning “DO NOT OPEN BEFORE…” the time and date for the
opening of Bids , in accordance with ITB Clause 21.
21.4 If all envelopes are not sealed and marked as required, the Procuring Entity will
assume no responsibility for the misplacement or premature opening of the Bid. If
a Bid is not sealed and marked as required, the bidder or its authorized
representative shall acknowledge the condition of such Bid as submitted;
otherwise the Bid shall be disqualified.
24.2 A Bidder may, through a Letter of Withdrawal, withdraw its Bid after it has been
submitted, for valid and justifiable Reasons; Provided That the Letter of
Withdrawal is received by the Procuring Entity not later than the deadline
prescribed for the receipt of Bids.
24.3 Bids requested to be withdrawn in accordance with ITB Clause 20.2 shall be
returned unopened to the Bidders. A Bidder may also express its intention not to
participate in the bidding through a letter which should reach and be stamped by
the BAC before the deadline for submission and receipt of Bids. A Bidder that
withdraws its Bid shall not be permitted to submit another Bid, directly or
indirectly, for the same contract.
24.4 No Bid may be modified after the deadline for the receipt of Bids. No Bid may be
withdrawn in the interval between the deadline for the receipt of Bids and the
expiration of the period of Bid validity specified by the Bidder in accordance with
ITB Clause 13.1. Withdrawal of a Bid during this interval may result in the
forfeiture of the Bidder’s Bid Security, pursuant to the ITB Clause 14.5, and the
imposition of administrative, civil and criminal sanctions as prescribed by R.A.
9184 and its IRR.
a. On-line Bidders may submit their eligibility requirements to the Procuring Entity
through the e-bidding facility of PhilGEPS.
b. Joint Ventures
(1) In case of joint venture, each partner of the joint venture must: (i) be
registered in the PhilGEPS, (ii) secure Certified Membership Status, and
(iii) electronically send its respective eligibility documents.
(2) The joint venture partners must identify and designate the Primary and
Secondary Partner(s).
(3) Before the PhilGEPS will accept submissions of Technical and Financial
Proposals from the Primary Partner, there must be a confirmation from the
Secondary Partner(s) as to existence of, or agreement to enter into, a joint
venture.
c. With regard to the requirement for a Bid Security as part of the Technical
Proposal under Section 5.6.2a(2) above, the following guidelines shall be
observed:
(1) On-line bidders may submit the Bid Security in cash through the
PhilGEPS electronic payment facility.
(2) In case of other forms of Bid Security, the on-line bidder shall prepare and
submit a scanned copy of the Bid Security together with the electronic bid.
However, the original Bid Security must be submitted to the BAC
concerned before the end of business hours on the day of bid submission, a
failure of which shall automatically render the bid submission as non-
compliant.
(3) If the on-line bidder sends the original Bid security through registered
mail or private courier, the indicated date of receipt by the postal service
or private courier shall be considered as the date of submission to the BAC
concerned, without prejudice to any verifications during post-
qualification.
d. On-line Bidders, or the Primary Partner in the case of Joint Ventures, shall
electronically submit their bids through the Bidder’s On-line Nominee, at any
time before the closing date and time specified in the BDs.
e. The actual time of bid submission of an On-line Bidder shall be the time indicated
on the PhilGEPS Server when the bidder clicks the “Submit” button which shall
be automatically recorded by the PhilGEPS. Upon receipt of a bid, the PhilGEPS
shall automatically generate a bid receipt page that can be printed by the on-line
bidder. This contains the recorded “submission time” which shall be considered as
the Official Submission Time of the bidder.
f. An On-line Bidder may modify its bid at any time before the closing date and
time for the submission and receipt of bids.
g. An On-line Bidder may withdraw its bid before the deadline for the submission
and receipt of bids.
h. The PhilGEPS shall bar all incoming bids after the closing date and time.
26.2 The BAC shall read out and record letters of withdrawal, and return the unopened
envelopes containing the corresponding withdrawn Bid to the Bidders concerned.
If the withdrawing Bidder’s representative is present, the BAC shall return the
original Bid and all copies thereof to that representative during the Bid opening. If
the representative is absent, the BAC shall return the unopened Bid by registered
mail. The Bidder may withdraw its Bid before the deadline for submission and
receipt of Bids, provided that its letter of withdrawal contains a valid justification
requesting such withdrawal, subject to appropriate administrative sanctions.
26.4 The BAC shall then conduct the Preliminary Examination of the Bids. The
purpose of this examination is solely to determine the “presence-or-absence” of
each of the required documents comprising the bid, as stated in Clause 14 above,
using a simple non-discretionary “pass (if present) – or - fail (if absent)” criterion,
with the aid of checklists.
26.5 The BAC shall first open and undertake the Preliminary Examination of the
envelopes containing the Technical Components of the Bids, one at a time, and
reading out and recording the following:
26.6 The BAC of the Procuring Entity shall determine each Bidder’s compliance with
the documents required to be submitted for the Technical Component of the Bid,
as prescribed in ITB Clause 10. For this purpose, the BAC shall check the
submitted documents in the Technical Component envelope against a checklist
(Form DPWH-INFR-31) of required documents to ascertain if the latter are all
present in the Technical Component envelope. If the required document is
present, the Technical Component shall be rated as “passed” for that particular
requirement. On the other hand, if the required document is absent, i.e., missing,
incomplete or patently insufficient, the Technical Component shall be rated as
“failed” for that particular requirement. In case one or more of the required
documents in the Technical Component of a particular Bid is absent - i.e.,
missing, incomplete, or patently insufficient - the BAC shall rate the Technical
Component as “failed” and immediately return to the Bidder concerned its second
envelope (Financial Component) unopened. If all of the required documents in
the Technical Component envelope are present, the Technical Component is
rated as “passed.”
27.1 Unless otherwise indicated in the BDS, after the Preliminary Examination of the
Technical Components of the Bids, the BAC of the Procuring Entity, assisted by
its BAC Secretariat, shall conduct the Eligibility Check of each bidder that passed
the documentary requirements for the Technical Component of the Bids - i.e., the
BAC shall determine if the bidder is eligible to bid for the contract being
procured. This shall be done electronically by computer using the data and
program in the DPWH Civil Works Registry (CWR). The submission of the
Original Receipt (OR) for payment of the BDs for the contract issued by any
DPWH field office is sufficient for the BAC of the Procuring Entity to undertake
the electronic eligibility evaluation of contractors.
27.2 The BAC Secretariat of the Procuring Entity shall enter into the CWR the
Contract Profile (CP) for the contract being procured. The CP will give the basic
contract data, including the ABC, works similar to those of the contract to be bid,
and contract duration.
27.3 In case a bidder is already enrolled in the CWR and submits the Original Receipt
(OR) for payment of the BDs for the contract issued by any DPWH field office,
together with its bid, the BAC Secretariat shall enter into the CWR the PCAB
License Number and/or name of the bidder.
27.4 In case a bidder is not previously enrolled in the CWR and submits its Eligibility
Requirements – i.e., Class “A” and Class “B” Documents - as part of its bid,
together with Original Receipt (OR) for payment of the BDs for the contract
issued by any DPWH field office, the BAC Secretariat shall immediately encode
and enter into the CWR the appropriate data and information – e.g., SLCC,
NFCC, etc. - from the submitted Documents.
27.5 In both cases, the CWR program will then electronically process and match the
prospective bidder’s capability or eligibility data in the CWR – e.g., value of
Single Largest Completed Contract (SLCC) similar to the contract being procured
and actual NFCC - against the eligibility requirements for the contract derived
from the CP – e.g., SLCC similar to the subject contract and costing at least 50%
of ABC, and NFCC at least equal to ABC. The computer program will thus
automatically determine whether or not the prospective bidder meets the
following eligibility requirements:
a. The cost of the bidder’s SLCC is at least 50% of the ABC of the project to be
procured.
The program will also generate the results of the Eligibility Check, including the
Notices of Ineligibility. The reasons for ineligibility will also be automatically
shown in the Notices of Ineligibility.
27.6 During the bids opening session, the BAC will issue the Notices of Ineligibility to
the bidders concerned. If any of the bidders immediately agrees to their
ineligibility as indicated in the Notices, the BAC shall promptly not consider its
bid and thus return its Financial Component envelope to the bidder unopened. If,
on the other hand, any of the bidders indicate its intent to seek a reconsideration
of its declared ineligibility, the BAC shall set aside its sealed Financial
Component envelope which shall be signed on its cover by the bidder and other
competing bidders and members of the BAC. If, after evaluating the bidder’s
request for reconsideration, the BAC finds the bidder to be eligible for the
contract at hand, the BAC shall set the date and time for the opening of its
Financial Component envelope.
27.7 In either case - i.e., the ineligible bidder accepting its ineligibility or expressing it
intent to seek a reconsideration of its ineligibility - the either case - i.e., the
ineligible bidder accepting its ineligibility or expressing it intent to seek a
reconsideration of its ineligibility - the BAC shall then proceed with the opening
and preliminary examination of the Financial Component of the bids of the
bidders that are declared eligible.
28.2 The BAC shall prepare the minutes of the proceedings of the Bid opening that
shall include, as a minimum: (a) the Abstract of Bids as Read including the name
of each Bidder, its Bid prices, Bid Security, and findings of the Preliminary
Examination of Bids; and (b) the attendance sheet.
28.3 The BAC members shall sign the Abstract of Bids as Read and the BAC
Observers may witness the same. The Abstract of Bids as Read and the minutes
of the Bid opening shall be available to the public upon written request and
payment of a specified fee to cover the cost of materials.
a. Upon receipt of manually-filed bids, the Bid Opener, before the Bid Opening, but
immediately after the deadline for submission of bids, shall record and input into
the PhilGEPS E-bidding module the date and time each of the bid was manually
received, including the name of the bidder’s authorized representative.
b. The BAC shall open the bids immediately after the deadline for submission and
receipt of bids, and on the bid opening date.
c. Before the decryption of electronic bids, the Bid Opener must first login to the
PhilGEPS and only then can BAC members input their respective USER IDs and
PASSWORDS, provided however, that PhilGEPS decryption will not take place
unless all the members present and logging in constitute quorum.
d. The Bid Opener shall publicly open the first bid envelopes of bidders who
submitted bids manually to determine each bidder’s compliance with the
documents required to be submitted for eligibility, that is, legal, technical and
financial eligibility documents; and for the technical requirements. For this
purpose, the BAC shall check the submitted documents of each bidder against a
checklist of required documents to ascertain if they are all present, using a non-
discretionary “pass/fail” criterion. If a bidder submits the required document, it
shall be rated “passed” for that particular requirement. In this regard, bids that fail
to include any requirement or are incomplete or patently insufficient shall be
considered as “failed”. Otherwise, the BAC shall rate the bidder “passed” in
relation to the eligibility and technical documents in the first envelope.
e. After all the manually submitted first envelopes of bidders were opened, and the
results and findings were encoded in the PhilGEPS Preliminary Examination
Report facility, the Bid Opener shall thereafter proceed to decrypt the electronic
First Bid Envelopes submitted by the On-line Bidders to determine each bidder’s
compliance with the required eligibility and technical documents following the
steps and procedures outlined in Section 5.6.9d above. Thereafter, the Bid Opener
shall input the findings and results into the PhilGEPS’ Preliminary Examination
Report facility.
g. After all the manually submitted second envelopes of bidders were opened, and
the results and findings were encoded in the PhilGEPS Preliminary Examination
Report facility, the Bid Opener shall thereafter proceed to decrypt the electronic
Second Bid Envelopes of each On-line Bidders whose electronic first bid
envelope was rated “passed” to determine each bidder’s compliance with the
required financial documents following the steps and procedures outlined in
Section 5.6.9f above.
h. In case one or more of the requirements in the second envelope of a particular bid
is missing, incomplete or patently insufficient, and/or if the submitted total bid
price exceeds the ABC, the BAC shall rate the bid concerned as “failed”. The Bid
Opener shall then input the findings and results into the PhilGEPS’ Preliminary
Examination Report facility.
i. Only bids that are determined to contain all the bid requirements for both
components shall be rated “passed” and shall immediately be considered for
evaluation and comparison.
j. The PhilGEPS shall automatically send an electronic mail to all bidders who
failed in the preliminary examination of the first and/or second envelope.
b. In evaluating the Bids to get the Lowest Calculated Bid, the Procuring Entity shall
undertake the following:
c. The detailed evaluation of the Financial Proposals of the Bids, to establish the
correct calculated prices of the Bids.
d. The ranking of the total bid prices as so calculated from the lowest to highest. The
Bid with the lowest price in the ranking shall be identified as the Lowest
Calculated Bid.
e. To determine the Lowest Calculated Bid, the BAC shall use non-discretionary
“pass/fail” criteria, as stated in the IB, which shall include a consideration of the
following:
(1) Completeness of the bid. Unless the ITB specifically allows partial bids,
bids not addressing or providing all of the required items in the BDs,
including the BOQ, shall be considered as non-responsive and, thus,
automatically disqualified. In this regard, where a required item is
provided, but no price is indicated, the same shall be considered as non-
responsive, but specifying a “0” (zero) or a dash (“-”) for the said item
would mean that it is being offered for free to the Government, except
those required by law or regulations to be provided for (IRR Section
32.2.1a); and
(2) Arithmetical corrections. The BAC shall consider computational errors,
omissions and discounts if allowed in the BDs to enable proper
comparison of all eligible bids. It may also consider bid modifications if
expressly allowed in the BDs. Any adjustment shall be calculated in
monetary terms to determine the calculated prices.
In case a bid offers a discount on the total bid price, the percentage of the
discount to the total bid price shall be applied to all pay items for purposes
of evaluating the value of work accomplished during the implementation
stage.
(3) Evaluation on equal footing. The BAC shall evaluate all bids on an equal
footing to ensure fair and competitive bid comparison. For this purpose, all
bidders shall be required to include the cost of all taxes, such as, but not
limited to, value added tax (VAT), income tax, local taxes, and other fiscal
levies and duties which shall be itemized in the Bid Form and reflected in
the detailed estimates. Such bids, including said taxes, shall be the basis for
bid evaluation and comparison.
(5) Total calculated bid prices. The total calculated bid prices are obtained after
making the detailed evaluation and corrections according to the
abovementioned criteria.
f. The Procuring Entity’s evaluation of bids shall only be based on the bid price quoted
in the Financial Bid Form.
(2) total bid prices per pay item and unit prices applied to the quantities per
pay item, or
(3) stated total Bid price and the actual sum of prices of component items, or
(4) unit prices in the detailed estimate and unit bid prices in the Bill of
Quantities,
the latter in each of the above cases shall prevail, and the total Bid amount shall
be corrected accordingly.
h. Based on the detailed evaluation of the bids, those that comply with the
abovementioned requirements shall be ranked in the ascending order of their total
calculated bid prices, as evaluated and corrected for computational errors,
discounts and other modifications, in accordance with the provisions of this ITB
Clause. This will identify the Lowest Calculated Bid. Total calculated bid prices,
as evaluated and corrected for computational errors, discounts and other
modifications, which exceed the ABC shall not be considered, unless otherwise
indicated in BDS 14.3a.
i. The provision in this Clause 32-i is not to be considered in the evaluation of the bids
to determine the technically complying bid or the lowest calculated bid, but shall be
applied by the Procuring Entity during the implementation of the contract,
particularly in making contract payments:
(1) During the evaluation of the bids, the BAC shall take note of any
unbalanced bids on early works and other items for unit-priced contracts.
(2) Unbalanced bids are defined as those where the total bid price for a major
pay item is more than fifty percent (50%) of the corresponding cost of that
pay item in the ABC. A major pay item is defined as that whose cost in the
ABC is 20% or more of the total ABC; if there is no such pay item, then
major pay items are defined as the two pay items in the ABC with the
highest total costs.
(3) Unbalanced bids also include those with a minor pay item whose cost in the
ABC is more than five percent (5%) of the total ABC and where the
corresponding bid price for that pay item is more than one hundred percent
(100%) of the ABC for that item.
(4) For unbalanced bids, during the implementation of the contract works, the
payment for these major and minor pay items shall be made initially at the
unit prices in the ABC, and the remainder - i.e., contract unit price minus
ABC unit price for the major pay item - shall be paid when the work under
the major pay item is completed.
b. The PhilGEPS shall automatically rank the bidders in ascending order based on
their total calculated bid prices to identify the LCB as evaluated and corrected for
computational errors, and other bid modifications. Total calculated bid prices, as
evaluated and corrected for computational errors, and other bid modifications,
which exceed the ABC shall be disqualified. After all bids have been received,
opened, examined, evaluated, and ranked, the system shall thereafter generate the
Abstract of Bids in the form of PhilGEPS Evaluation Summary Report.
c. The BAC shall manually prepare a Resolution whether approving or denying the
Abstract of Bids generated by the system. However, after the BAC Resolution
approving the Abstract of Bids is uploaded in the PhilGEPS, an electronic
message shall be automatically sent to all bidders who participated informing
them that the Abstract of Bids is available for downloading.
b. Within five (5) calendar days from receipt by the Bidder of the notice from the
BAC that it submitted the LCB, the Bidder shall submit the following post-
qualification documentary requirements (IRR Section 34.2):
(2) Other appropriate licenses and permits required by law and stated in the BDS.
Failure of the Bidder declared as LCB to duly submit the requirements under this
Clause or a finding against the veracity of such, shall be ground for forfeiture of
the bid security and disqualification of the Bidder for award.
d. If the BAC determines that the Bidder with the LCB passes all the criteria for
Post-Qualification, it shall declare the said bid as the Lowest Calculated
Responsive Bid, (LCRB) and recommend to the HoPE the award of contract to
the said Bidder at its submitted price or its calculated bid price, whichever is
lower.
e. If the BAC determines that the Bidder with the LCB fails the criteria for Post-
Qualification, it shall proceed to the next LCB to make a similar determination of
that Bidder’s capabilities. If the second Bidder, however, fails the Post-
Qualification, the procedure for Post-Qualification shall be repeated for the
Bidder with the next LCB, and so on until the LCRB is determined for contract
award.
35. Post-Qualification under Electronic Bidding
If, as indicated in the BDS, Electronic Bidding is adopted for this procurement pursuant
to GPPB Resolution No. 23-2013, dated 30 July 2013, the Procuring Entity shall observe
the following procedure with regard to the post-qualification:
a. Within one (1) day after the approval of the Abstract of Bids, the bidder with the
Lowest Calculated Bid (LCB) should be notified through electronic mail that the
bidder shall undergo post-qualification and submit the post-qualification
requirements within five (5) calendar days as provided for under Section 34.2 of
RA 9184-IRR.
b. If the BAC determines that the bidder with the LCB passes all the criteria for
post-qualification, it shall declare the said bid as the Lowest Calculated
Responsive Bid (LCRB), and recommend to the HoPE the award of contract to
the said bidder at its submitted bid price or its calculated bid price, whichever is
lower or, in the case of quality-based evaluation procedure, submitted bid price or
its negotiated price, whichever is lower.
c. If, however, the BAC determines that the bidder with the LCB fails the criteria for
post-qualification, it shall immediately notify the said bidder electronically in
writing of its post-disqualification and the grounds for it.
d. Immediately after the BAC has electronically notified the first bidder of its post-
disqualification, and notwithstanding any pending request for reconsideration
thereof, the BAC shall initiate and complete the same post-qualification process
on the bidder with the second LCB. If the second bidder passes the post-
qualification, and provided that the request for reconsideration of the first bidder
has been denied, the second bidder shall be post-qualified as the bidder with the
LCRB.
e. If the second bidder, however, fails the post-qualification, the procedure for post-
qualification shall be repeated for the bidder with the next LCB, and so on until
the LCRB, as the case may be, is determined for award, subject to Section 37 of
the IRR.
f. The post-qualification process shall be completed in not more than twelve (12)
calendar days from the determination of the LCB. In exceptional cases, the post-
qualification period may be extended by the HoPE, but in no case shall the
aggregate period exceed forty five (45) calendar days.
g. The BAC or its Bid Opener shall record and encode the post-qualification results
of manually submitted documents in the PhilGEPS. For electronic documents
submitted online, the BAC or its Bid Opener shall decrypt the documents and the
results recorded automatically.
h. After recording the post-qualification summary and uploading the BAC resolution
declaring the bidder with the LCRB in the PhilGEPS, an electronic message shall
be automatically sent to all bidders who participated informing them that the
Notice of LCRB is available for downloading.
36.2 The Procuring Entity reserves the right to reject any and all bids, declare a failure
of bidding, or not award the contract in the following situations, without incurring
any liability to the affected bidders:
c. For any justifiable and reasonable ground where the award of the contract
will not redound to the benefit of the Government as follows:
(3) if the funds for the contract have been cancelled, withheld or reduced
through no fault of the Procuring Entity.
36.3 In addition, the Procuring Entity may likewise declare a failure of bidding,
without incurring any liability to the affected bidders, when:
d. the bidder with the LCRB refuses, without justifiable cause to accept the
award of contract, and no award is made.
F. Award of Contract
37. Award Criterion
The Procuring Entity shall award the contract to the winning Bidder whose Bid has been
determined, after the evaluation of bids and Post-Qualification, as the LCRB, at its submitted bid
price or its calculated bid price, whichever is lower (IRR Section 34.4).
38.2 The NOA shall state the proposed contract price – i.e., whichever is lower of the
submitted bid price or calculated bid price - together with the documentary
requirements to be submitted by the Bidder to perfect the contract.
38.3 Notwithstanding the issuance of the NOA, award of contract shall be subject to
the following conditions:
(1) Notice of Award (NOA) with the bidder’s signed “conforme” (Use
Form DPWH-INFR-41)
(3) For a joint venture (JV), Contractor’s PCAB Special JV License and
JV Agreement.
(11) Latest Income Tax and Business Returns duly stamped and received
by BIR and duly validated with the tax payments made. Tax
Clearance from the BIR to prove full and timely payment of taxes.
(12) For a local contractor, Certification under oath stating that the
Contractor is free and clean of all tax liabilities.
(13) For a foreign bidder, valid PCAB License and Registration for the
type and cost of the contract to be bid, when the Treaty or
International or Executive Agreement expressly allows submission
of the PCAB License and Registration for the type and cost of the
contract to be bid as a pre-condition to the NOA.
(14) Integrity Pledge in accordance with Department Order No. 86, series
of 2013.
39.2 Failure of the winning Bidder to comply with the requirements of ITBClause34
shall constitute sufficient grounds for cancellation of the award and forfeiture of
its Bid Security. In this event, the Procuring Entity shall initiate and complete the
post-qualification of the second Lowest Calculated Bid. The procedure shall be
repeated until the Lowest Calculated and Responsive Bid is identified and
selected for contract award. However, if no Bidder passed post-qualification, the
BAC shall declare the bidding a failure and conduct a re-bidding with re-
advertisement.
(2) Contractor’s Bid in the Form of Bid, including its Technical and
Financial Proposals, as calculated by the Procuring Entity and
conformed by the Contractor through the NOA
(3) Bidding Documents (other than b(4) to b(7) below) with Bulletins
(4) Specifications
(5) Drawings
(9) Integrity Pledge under Department Order No. 86, series of 2013
c. Other Documents
c. The documents in ITB Clauses 40.1a and b(2) to b(7) shall be provided by the
Procuring Entity, while the documents in Clauses 40.1b(1), b(8), and c(1) to c(6)
shall be submitted by the winning bidder to the Procuring Entity within ten (10)
calendar days from the date of its receipt of the Notice of Award.
41.2 If further approval of the contract is required, the approving authority is given a
maximum of twenty (20) calendar days from receipt thereof to approve or
disapprove it.
41.3 Upon approval of the Contract, the Procuring Entity shall notify the other Bidders
that their bids were unsuccessful.
The scope of the Works under this Contract are 1. Earthworks (Clearing,
Excavation, & Embankment); 2. Construction of Cross Drainages (RCPC); 3.
Construction of Slope and Bank Protection Structures (Stone Masonry); 4.
Spreading and Compaction of Aggregate Sub-Base Course; 5. Construction of
Concrete Catch Basins
The name of the Project is Construction of Missing Links/ New Roads - Piddig-
Carasi-Calanasan Road, Ilocos Norte.
NOTE: The contractor shall undertake not less than 50% of the contracted works with
its own resources. Subcontracting is allowed subject to the DPWH evaluation and
approval.
8.3 If subcontracting is allowed specify the portions of Works and the maximum percentage
allowed to be subcontracted, otherwise state “Not applicable.”
9.1 The Procuring Entity will hold a Pre-Bid Conference for this Project on November 03,
2020 at 10:00 o’clock am at Conference Room, 2nd Floor, DPWH-Regional Office I,
City of San Fernando, La Union.
9.4 Electronic Bidding in accordance with GPPB Resolution No. 23-2013 will not be
adopted in this procurement.
11.1 The Procuring Entity’s address is:
GERRY G. JUCAR
Chief, Construction DivisionBAC Chairman
Department of Public Works and Highways
Aguila Road, City of San Fernando, La Union
Telefax. No. (072) 607-1298
14.1 No further Instruction
14.2a(2)(a)i No further Instruction
14.2 a(3)(b) The minimum work experience requirements for the key personnel are the
following:
55
Key Personnel Similar Experience Similar and Related
(Same Position) Experience
1 - Project Manager 5 5
1 - Project Engineer 5 3
1 - Materials Engineer DPWH Accredited Materials Engineer I
1 -Foreman 5 2
The key personnel should meet the following number of years’ work experience.
1. The experience means total years of civil works experience (of any
nature in construction and engineering consultancy services)
14.2 a(3)(c) The minimum major equipment requirements are the following:
Required No Minimum
Construction Equipment
of Units. Capacity/Unit
Payloader 2 1.50 cu.m.
Dump Truck 4 12 cu.yd.
Backhoe 1 0.80 cu.m.
Motorized Road Grader 1
Vibratory Roller 1 10 mt.
Water Truck / Pump 1 16000 L
Bar Cutter 1
Bar Bender 1
Cargo Truck 1 10T, 270Hp
One Bagger Mixer 2
Concrete Vibrator 1
Bulldozer 1
56
exceeding this amount shall not be accepted.”
14.3 b “No further instructions.”
17.1 Bids shall be valid until March 18, 2021 or not later than one hundred
twenty (120) days from the date set for bids opening.
18.1 The bid security shall be limited to a Bid Securing Declaration or one of the
following forms in accordance with the following amounts:
18.3 The Bid Security shall be valid until one hundred twenty (120) days from the
date set for bids opening.
19.1 No further instruction
20.4 The Bidder shall submit One (1) original and two (2) copies of the first
(Technical) and second (Financial) components of its bid.
21.3 d The specific identification of this bidding process is 21A00064 and Contract
Name: Construction of Missing Links/ New Roads - Piddig-Carasi-
Calanasan Road, Ilocos Norte.
22 Bid submission maybe done manually or electronically/online. However,
bidders should only select one mode of submission, either manual or
electronic.
The address for receipt of Bids submitted manually is Conference Room, 2nd
Floor, DPWH-Regional Office I, City of San Fernando, La Union.
The deadline for receipt of Bids is on November 18, 2020 at 10:00 o/clock
A.M..
For example, the filename of the attached PDF containing the Official
Receipt of the Contractor with PCAB ID No. 12345, who intends to
participate in the bidding of Contract ID No. 20Z00123 shall be
57
“12345_20Z00123_OfficialReceipt.pdf”. Further, the e-mail subject
would be “Official Receipt for 20Z00123”.
b. Has no attachment;
58
option to submit bid electronically. However, If a bidder
chooses to submit an electronic bid, the same bidder can
no longer submit a bid manually for the same contract,
and vice versa.
In case the total file size of the main archive file folder is
more than the allowable size of an attachment per e-mail of
the prospective bidder’s e-mail service provider (e.g. Gmail,
Yahoo Mail, Outlook), they shall need to split its electronic
bid into two or more PASSWORD PROTECTED
COMPRESSED ARCHIVE MAIN FILE FOLDERS.
59
In case of multiple compressed archive main file folders, it
shall be submitted in multiple e-mails, each with Subject in
the format “Bid Submission [Insert Number of main
archive folder]/[Insert total number of main archive
folders]” (e.g. “Bid Submission 1/2 for 20Z00123”and “Bid
Submission 2/2 for 20Z00123”.
Bids may only be withdrawn prior the deadline for bid submission. In
case of withdrawal of an electronic bid, the bidder shall send an e-
mail with the subject “Bid Withdrawal for <Contract ID>” and the
letter of bid withdrawal in pdf format with filename “<PCAB
ID>_<CONTRACT ID>_BidWithdrawal.pdf” shall be attached. This
e-mail should be sent to [Insert dedicated e-mail address] before the
deadline for bid submission.
60
7. Opening of the electronic bid
Only during the actual opening of bids shall the bidder disclose the
passwords for his electronic bid. This can be done by the bidder’s
authorized representative verbally in person, through phone call,
online platforms (e.g. videoconferencing, webcasting), or through
writing. In all cases, the bidders will have only three (3) attempts or
fifteen (15) minutes, whichever comes first, to provide the correct
password. Otherwise, the bidder shall be disqualified except in
unforeseen justifiable circumstances. The bidder may also be
subjected to the three-strike policy (D.O. 17, Series of 2015) as
warranted by the circumstances.
61
acknowledges such condition. The BAC shall assume no
responsibility for the misplacement of the contents of the contents of
the improperly sealed or marked bid, or improperly compressed or
password-protected folder, or for its premature opening.
25 Electronic Bidding in accordance with GPPB Resolution No. 23-2013 will not be
adopted for the Receipt of Bids in this procurement.
27.1 The place of opening of Bids is Conference Room, 2nd Floor, DPWH-
Regional Office I, City of San Fernando, La Union.
The date and time of opening of Bids is on November 18, 2020 at 10:00
o/clock A.M.
29 Electronic Bidding in accordance with GPPB Resolution No. 23-2013 will not be
adopted for Bids Opening and Preliminary Examination in this procurement.
34 b(2) List additional contract documents relevant to the Project that may be
required by existing laws and/or the Procuring Entity, such as
construction schedule and S-curve, manpower schedule, construction
methods, equipment utilization schedule construction safety and
health program approved by the Department of Labor and
Employment, and Precedence Diagram Method (PDM).
35 Electronic Bidding in accordance with GPPB Resolution No. 23-2013 will not
be adopted for Post-Qualification in this procurement.
62
ANNEX II-1.1F
Section VI. General Conditions of Contract
63
GENERAL CONDITIONS OF CONTRACT
TABLE OF CONTENTS
1. Definitions …………………………………………………………………………… 64
2. Interpretation ………………………………………………………………………… 66
3. Governing Language and Law ……………………………………………………… 67
4. Communications …………………………………………………………………….. 68
5. Procuring Entity’s Obligation to Deliver the Site, Materials, Equipment, and Plans .. 68
6. Contractor’s Obligations …………………………………………………………… 68
7. Performance Security ……………………………………………………………….. 69
8. Sub-Contracting…………………………………………………………………….. 70
9. Liquidated Damages ………………………………………………………………… 71
10. Site Investigation Reports …………………………………………………………… 72
11. Licenses and Permits ………………………………………………………………… 72
12. Contractor’s Risk and Warranty Security …………………………………………… 72
13. Liability of the Contractor …………………………………………………………… 74
14. Procuring Entity’s Risk…………………………………..…………………………… 74
15. Insurance …………………………………………………………………………….... 74
16. Termination for Default of Contractor …………………………................................... 76
17. Termination for Default of Procuring Entity ………………………………………… 78
18. Termination for Convenience ………………………………………………………… 78
19. Procedure for Termination of Contracts ……….……………………………………. 79
20. Force Majeure and Release from Performance …………………................................ 81
21. Payment on Termination …………..………………………………………………… 82
22. Resolution of Disputes ………………………………………………………………. 82
23. Suspension of Loan, Credit, Grant, or Appropriation ……………………………….. 83
24. Procuring Entity’s Representative’s Decisions ……………………………………… 83
25. Approval of Drawings and Temporary Works by Procuring Entity’s Representative.. 83
26. Acceleration Ordered by Procuring Entity’s Representative ………………………. 83
27. Extension of Intended Completion Date ……………………………………………. 84
28. Contractor’s Right to Claim …………………………………………………........... 84
29. Dayworks ………………………………………………………............................... 84
30. Early Warning ……………………………………………………………………… 84
31. Program of Work …………………………………………………………………… 85
32. Management Conferences ………………………………………………………….. 85
33. Bill of Quantities ……………………………………………………………………. 86
34. Instructions, Inspections and Audits ……………………………………………….. 86
35. Identification of Defects …………………………………………………………….. 86
36. Cost of Repairs ……………………………………………………………………… 87
37. Correction of Defects …………………………………………….............................. 87
38. Uncorrected Defects ………………………………………………………………… 87
39. Advance Payment …………………………………………………………………… 87
40. Monthly Statements or Progress Billings …………………………………………… 88
41. Monthly Certificates and Progress Payments ………………………………………. 88
42. Retention …………………………………………………………………………….. 89
43. Variation Orders ………………………………………………….............................. 90
44. Punch List…………………………………………………………………………….. 92
45. Suspension of Work …………………………………………………………………. 92
46. Extension of Contract Time …………………………………………………………. 94
47. Price Adjustment …………………………………………………………………….. 95
48. Certificates of Completion and Acceptance …………………………………………. 95
49. Taking Over …………………………………………………………………………. 96
50. “As-Built” Drawings and Operating and Maintenance Manuals ……………………. 97
GENERAL CONDITIONS OF CONTRACT
1. Definitions
1.1 Arbiter is the person appointed jointly by the Procuring Entity and the Contractor
to resolve disputes in the first instance.
1.2 As-Built Drawings refer to the engineering plans for the structure as actually
constructed and completed under this Contract, considering all variations and
modifications as approved and executed.
1.3 Bill of Quantities refers to a list of the specific pay items of the Works under this
Contract, particularly their identification numbers, descriptions, units of
measurement, and quantities, together with their corresponding unit and total bid
prices.
1.5 Contract is the legal agreement between the Procuring Entity and the Contractor
to execute, complete, and maintain the Works. It consists of the documents listed
in GCC Clause 2.2.
1.6 Contract Price is the price stated in the Notice of Award and thereafter to be paid
by the Procuring Entity to the Contractor for the execution of the Works in
accordance with this Contract.
1.7 Contract Time is the allowable period or duration within which the Contract
Works must be completed, i.e., from the Start Date to the Intended Completion
Date as specified in the SCC.
1.8 Contractor is the juridical entity whose bid has been accepted by the Procuring
Entity and to whom this Contract to execute the Work was awarded, entered into,
and approved.
1.9 Contractor’s Bid is the signed offer or proposal submitted by the Contractor to
the Procuring Entity in response to the Bidding Documents.
1.12 Defect is any part of the Works not constructed in accordance with this Contract.
1.16 Defects Liability Period is the one-year period after the issuance of the
Certificate of Completion during which the Contractor assumes the responsibility
to undertake the repair of any defect in or damage to the Works at his own
expense as a condition for the issuance of the Certificate of Acceptance.
1.17 Drawings are graphical presentations of the Works. They include all engineering
plans, supplementary details, shop drawings, calculations, and other information
provided or approved for the execution of this Contract.
1.18 Equipment refers to all machines, tools, facilities, supplies, appliances, and
related items required for the execution and completion of the Works provided by
the Contractor and which shall not form or are not intended to form part of the
Permanent Works.
1.19 Intended Completion Date refers to the date specified in the SCC when the
Contractor is expected to have completed the Works. The Intended Completion
Date may be revised only by the Procuring Entity’s Representative by issuing an
extension of Contract Time or an acceleration order.
1.20 Materials are all supplies, including consumables, used by the Contractor for
incorporation in the Works.
1.21 Notice to Proceed is a written notice issued by the Procuring the Procuring
Entity’s Representative to the Contractor requiring the latter to begin the Works
not later than the date specified in this Notice.
1.21 Permanent Works refer to all permanent structures and all other project features
and facilities required to be constructed and completed in accordance with this
Contract which shall be delivered to the Procuring Entity and which shall remain
at the Site after the removal of all Temporary Works.
1.23 Plant refers to the machinery, apparatus, and the like intended to form an integral
part of the Permanent Works.
1.24 Procuring Entity is the party that engages the Contractor to carry out the Works
stated in the SCC.
1.25 Procuring Entity’s Representative refers to the HoPE or his duly authorized
representative, identified in the SCC, who shall be responsible for supervising the
execution of the Works and administering this Contract.
1.26 Site is the right-of-way or place provided by the Procuring Entity where the
Works shall be executed and any other place or places which may be designated
in the SCC, or notified to the Contractor by the Procuring Entity’s Representative,
as forming part of the Site.
1.27 Site Investigation Reports are factual and interpretative reports about the surface
and subsurface conditions at the Site, which are provided by the Procuring Entity
in the Bidding Documents.
1.30 Start Date, as specified in the SCC, is the date when the Contractor is obliged to
commence execution of the Works. It is the same as the effectivity date of the
Contract as stated in the Notice to Proceed. It does not necessarily coincide with
any of the Site Possession Dates.
1.31 Sub-Contractor is any person or organization to whom a part of the Works has
been subcontracted by the Contractor for execution, as allowed by the Procuring
Entity, but not any assignee of such person.
1.32 Temporary Works are works designed, constructed, installed, and removed by
the Contractor that are needed for the construction or installation of the Permanent
Works.
1.33 Work(s) refer to the Permanent Works and Temporary Works to be executed by
the Contractor in accordance with this Contract, including (i) the furnishing of all
labor, materials, equipment and others incidental, necessary or convenient to the
complete execution of the Works; (ii) the passing of any tests before acceptance
by the Procuring Entity’s Representative; (iii) and the carrying out of all duties
and obligations of the Contractor imposed by this Contract as described in the
SCC.
2. Interpretation
2.1 In interpreting the Conditions of Contract, singular also means plural, male also
means female or neuter, and the other way around. Headings have no
significance. Words have their normal meaning under the language of this
Contract unless specifically defined. The Procuring Entity’s Representative will
provide instructions clarifying queries about the Conditions of Contract.
2.2 If sectional completion is specified in the SCC, references in the Conditions of
Contract to the Works, the Completion Date, and the Intended Completion Date
apply to any Section of the Works (other than references to the Completion Date
and Intended Completion Date for the whole of the Works).
2.3 The documents forming this Contract shall be interpreted in the following order of
priority:
a. Contract Agreement
(2) Contractor’s Bid in the Form of Bid, including its Technical and
Financial Proposals, as calculated by the Procuring Entity and
conformed to by the Contractor through the NOA
(3) Bidding Documents (other than b(4) to b(7) below) and Bulletins
(4) Specifications
(5) Drawings
c. Other Documents
3.2 This Contract shall be interpreted in accordance with the laws of the Republic of
the Philippines.
4. Communications
Communications between parties that are referred to in these Conditions of Contract shall
be effective only when in writing. A notice shall be effective only when it is received by
the concerned party.
5.2 If possession of a portion is not given by the date stated in SCC Clause 5.1, the
Procuring Entity will be deemed to have delayed the start of the relevant
activities. The resulting adjustments in contract time to address such delay shall
be in accordance with GCC Clause 46.
5.3 The Contractor shall bear all costs and charges for special or temporary right-of-
way required by it in connection with access to the Site. The Contractor shall also
provide at its own cost any additional facilities outside the Site required by it for
purposes of the Works.
5.4 The Contractor shall allow the Procuring Entity’s Representative and any person
authorized by the Procuring Entity’s Representative access to the Site and to any
place where work in connection with this Contract is being carried out or is
intended to be carried out.
5.5 The Procuring entity shall be responsible for obtaining the appropriate
Environmental Compliance Certificate (ECC) for the Project.
6. Contractor’s Obligations
6.1 The Contractor shall carry out the Works properly and in accordance with this
Contract. The Contractor shall provide all supervision, labor, Materials, Plant and
Equipment, which may be required. All Materials and Plant on Site shall be
deemed to be the property of the Procuring Entity.
6.2 The Contractor shall commence execution of the Works on the Start Date and
shall carry out the Works in accordance with the approved PERT/CPM network
diagram submitted by the Contractor, as updated with the approval of the
Procuring Entity’s Representative, and shall complete the Works by the Intended
Completion Date.
6.3 The Contractor shall be responsible for the safety of all activities on the Site.
6.4 The Contractor shall carry out all instructions of the Procuring Entity’s
Representative that comply with the applicable laws where the Site is located.
6.5 The Contractor shall employ the key personnel, named in the Schedule of Key
Personnel in the SCC, to carry out the supervision of the Works. The Procuring
Entity will approve any proposed replacement of key personnel only if their
relevant qualifications and abilities are equal to or better than those of the
personnel listed in the Schedule.
6.6 If the Procuring Entity’s Representative asks the Contractor to remove a member
of the Contractor’s staff or work force, for justifiable cause, the Contractor shall
ensure that the person leaves the Site within seven (7) days and has no further
connection with the Work in this Contract.
6.7 During Contract implementation, the Contractor and its subcontractors shall abide
at all times by all labor laws, including child labor related enactments, and other
relevant rules.
6.8 The Contractor shall submit to the Procuring Entity for consent the name and
particulars of the person authorized to receive instructions on behalf of the
Contractor.
6.9 The Contractor shall cooperate and share the Site with other contractors, public
authorities, utilities, and the Procuring Entity during the dates given in the
schedule of other contractors particularly when they shall require access to the
Site. The Contractor shall also provide facilities and services for them during this
period. The Procuring Entity may modify the schedule of other contractors, and
shall notify the Contractor of any such modification thereto.
7. Performance Security
7.1 The Contractor shall submit its Performance Security to the Procuring Entity not
later than the date specified in the Notice of Award and shall be issued in any of
the following forms and corresponding amounts in ITB Clause 34.
7.2 The Performance Security posted in favor of the Procuring Entity shall be
forfeited in the event it is established that the Contractor is in default in any of its
obligations under the Contract.
7.3 The Performance Security shall remain valid until issuance by the Procuring
Entity of the Certificate of Final Acceptance.
7.4 The Performance Security may be released by the Procuring Entity and returned
to the Contractor after the issuance of the Certificate of Final Acceptance, subject
to the following conditions, provided that the Performance Security is replaced by
a Warranty Security against structural defects and/or failure as provided in GCC
Clause 12:
a. There are no pending claims against the Contractor or the surety company
filed by the Procuring Entity;
b. The Contractor has no pending claims for labor and materials filed against
it; and
7.5 The Contractor shall post an additional Performance Security following the
amount and form specified in ITB Clause 34 to cover any cumulative increase of
more than ten percent (10%) over the original value of the contract as a result of
amendments to order or change orders, extra work orders and supplemental
agreements, as the case may be. The Contractor shall cause the extension of the
validity of the performance security to cover approved contract time extensions.
7.6 In case of a reduction in the contract value or for partially completed Works under
the contract which are usable and accepted by the Procuring Entity the use of
which, in the judgment of the implementing agency or the Procuring Entity, will
not affect the structural integrity of the entire project, the Procuring Entity shall
allow a proportional reduction in the original performance security, provided that
any such reduction is more than ten percent (10%) and that the aggregate of such
reductions is not more than fifty percent (50%) of the original Performance
Security.
7.7 Unless otherwise indicated in the SCC, the Contractor, by entering into the
Contract with the Procuring Entity, acknowledges the right of the Procuring
Entity to institute action pursuant to Act 3688 against any sub-contractors be they
an individual, firm, partnership, corporation, or association supplying the
Contractor with labor, materials and/or equipment for the performance of this
Contract.
8. Sub-Contracting
8.1 Unless otherwise provided in the SCC, sub-contracting of the Works shall be
subject to the provisions of DPWH Department Order (DO) No. 38, series of
2015 as provided below.
8.2 All sub-contracts shall be subject to prior approval of the appropriate official of
the Procuring Entity within the limits of his delegated authority.
8.3 The Contractor may sub-contract portions of the works to such an extent as may
be approved by the Procuring Entity and stated in the SCC, provided that the
Contractor shall directly undertake, using its own resources, not less than fifty
percent (50%) of the contract works in terms of cost.
8.4. Each sub-contractor must comply with the eligibility criteria as specified in the
Eligibility Requirements (ER) for the portion of the contract works to be sub-
contracted to that sub-contractor- e.g., applicable license from the Philippine
Constructors Accreditation Board, satisfactory completion of works similar to
the portion of the contract to be subcontracted and costing at least fifty percent
(50%) of the cost of such portion, and sufficient Net Financial Contracting
Capacity, as well as minimum equipment and manpower. This requirement does
not apply to labor pakyaw contracts.
8.5 The bidder/main contractor may identify the sub-contractors to whom portions of
the contract works will be sub-contracted at any stage of the bidding process or
during contract implementation, provided that any sub-contracting requires prior
approval of the Procuring Entity. Sub-contractors identified during the bidding
may be changed during the implementation of the contract, subject to compliance
with the eligibility requirements and the approval of the Procuring Entity.
8.6 Sub-contracting of any portion of the contract shall not relieve the main
contractor from any liability or obligation that may arise from the contract. The
main contractor shall be responsible for the acts, defaults, and negligence of any
subcontractor, its agents or workmen.
8.7 For any assignment and sub-contracting of the contract or any part thereof
without prior written approval by the concerned Head of the DPWH Procuring
Entity, the DPWH shall impose on the erring contractor, after the termination of
the contract, the penalty of suspension for one (1) year for the first offense, and
suspension of two (2) years for the second offense from participating in the
public bidding process, pursuant to the provision of Appendix 11 Section 4.2 of
the IRR of RA 9184, in accordance with Section 69(6) of RA 9184 and without
prejudice to the imposition of additional administrative sanctions as the internal
rules of the agency may provide and/or further criminal prosecution as provided
by applicable laws.
9. Liquidated Damages
9.1 The Contractor shall pay liquidated damages to the Procuring Entity for each day
that the Completion Date is later than the Intended Completion Date. The
applicable liquidated damages is at least one-tenth (1/10) of a percent of the cost
of the unperformed portion for every day of delay. The total amount of liquidated
damages shall not exceed ten percent (10%) of the amount of the contract. The
Procuring Entity may deduct liquidated damages from payments due to the
Contractor. Payment of liquidated damages shall not affect the Contractor. Once
the cumulative amount of liquidated damages reaches ten percent (10%) of the
amount of this Contract, the Procuring Entity shall rescind this Contract, without
prejudice to other courses of action and remedies open to it.
9.2 If the Intended Completion Date is extended after liquidated damages have been
paid, the Engineer of the Procuring Entity shall correct any overpayment of
liquidated damages by the Contractor by adjusting the next payment certificate.
12.2 The defects liability period for infrastructure projects shall be one year from
contract completion up to final acceptance by the Procuring Entity. During this
period, the Contractor shall start the repair works, at his own expense, of any
damage to the Works on account of the use of materials of inferior quality, and
shall complete the repair works within ninety (90) days from the time the HoPE
has issued an order to undertake repair. In case of failure or refusal to comply
with this mandate, the Procuring Entity shall undertake such repair works and
shall be entitled to full reimbursement of expenses incurred therein upon demand.
12.3 Unless otherwise indicated in the SCC, in case the Contractor fails to comply
with the preceding paragraph, the Procuring Entity shall forfeit its performance
security, subject its properties to attachment or garnishment proceedings, and
perpetually disqualify it from participating in any public bidding. All payables of
the GOP in his favor shall be offset to recover the costs.
12.4 After final acceptance of the Works by the Procuring Entity, the following shall
be held responsible for “Structural Defects”, i.e., major faults/flaws/deficiencies
in one or more key structural elements of the project which may lead to structural
failure of the completed elements or structure, or “Structural Failures,” i.e., where
one or more key structural elements in an infrastructure facility fails or collapses,
thereby rendering the facility or part thereof incapable of withstanding the design
loads, and/or endangering the safety of the users or the general public:
12.6 The Contractor shall be required to put up a warranty security in the form of cash,
bank guarantee, letter of credit, GSIS or surety bond callable on demand, in
accordance with the following schedule:
12.7 The warranty security shall be stated in Philippine Pesos and shall remain
effective for one year from the date of issuance of the Certificate of Final
Acceptance by the Procuring Entity, and returned only after the lapse of said one
year period.
a. The risk of personal injury, death, or loss of or damage to property (excluding the
Works, Plant, Materials, and Equipment) which are due to:
(1) any type of use or occupation of the Site authorized by the Procuring
Entity after the official acceptance of the works; or
(2) negligence, breach of statutory duty, or interference with any legal right
by the Procuring Entity or by any person employed by or contracted to
him except the Contractor.
b. The risk of damage to the Works, Plant, Materials, and Equipment to the extent
that it is due to a fault of the Procuring Entity or in the Procuring Entity’s design,
or due to war or radioactive contamination directly affecting the Philippines.
15. Insurance
15.1 The Contractor shall, under his name and at his own expense, obtain and
maintain, for the duration of this Contract, the following insurance coverage:
15.2 The CARI shall cover the value of the completed portions of the Works. It shall
not, however, cover any damage to the Works whose value is not more than ten
percent (10%) of the Total Contract Cost, as this is to be absorbed by the
Contractor. The CARI shall, therefore, start with nil at the beginning of Contract
execution. It shall then be increased over time as the Works progresses so that at
any time it covers the value of the portions of the Works actually completed.
15.3 The Contractor shall provide evidence to the Procuring Entity’s Representative
that the insurance required under this Contract has been effected and shall, within
a reasonable time, provide a copy of the insurance policy to the Procuring Entity’s
Representative.
15.4 The Contractor shall notify the insurer of changes in the nature, extent, or
program for the execution of the Works and ensure the adequacy of the insurance
at all times in accordance with the terms of this Contract and shall produce to the
Procuring Entity’s Representative the insurance policy in force including the
receipts for payment of the current premiums.
15.5 If the Contractor fails to obtain and keep in force the insurance which it is
required to obtain under the terms of this Contract, the Procuring Entity may
obtain and keep in force any such insurance and pay such premiums as may be
necessary for the purpose. From time to time, the Procuring Entity may deduct
the amount it shall pay for said premiums including twenty five percent (25%)
therein from any monies due, or which may become due, to the Contractor,
without prejudice to the Procuring Entity exercising its right to impose other
sanctions against the Contractor pursuant to the provisions of this Contract.
15.6 In the event the Contractor fails to observe the above safeguards, the Procuring
Entity may, at the Contractor’s expense, take whatever measure is deemed
necessary for its protection and that of the Contractor’s personnel and third
parties, and/or order the interruption of dangerous Works. In addition, the
Procuring Entity may refuse to make the payments under GCC Clause 41 until
the Contractor complies with this Clause.
15.7 The Contractor shall immediately replace the insurance policy obtained as
required in this Contract, without need of the Procuring Entity’s demand, with a
new policy issued by a new insurance company acceptable to the Procuring Entity
for any of the following grounds:
b. Reasonable grounds exist that the insurer may not be able, fully and
promptly, to fulfill its obligation under the insurance policy.
a. Due to the Contractor’s fault and while the Works are on-going, it has
incurred a negative slippage of fifteen percent (15%) or more in
accordance with Presidential Decree 1870; or
b. Due to the Contractor’s fault and after the Contract time has expired, it has
incurred a negative slippage of ten percent (10%) or more in the
completion of the Works; or
c. The Contractor:
(1) abandons the Contract Works, refuses or fails to comply with a valid
instruction of the Procuring Entity or fails to proceed expeditiously
and without delay despite a written notice by the Procuring Entity;
(3) does not actually have on the Site the minimum essential equipment
listed in the Bid necessary to prosecute the Works in accordance with
the approved PERT/CPM network diagram and equipment utilization
schedule as required under the Contract;
(4) does not execute the Works in accordance with this Contract or
persistently or flagrantly neglects to carry out its obligations under this
Contract;
(1) The Contractor stops work for twenty eight (28) days when no
stoppage of work is shown on the current Program of Work and the
stoppage has not been authorized by the Procuring Entity’s
Representative.
(5) The Contractor has delayed the completion of the Works by the
number of days for which the maximum amount of liquidated
damages can be paid, as defined in the GCC Clause 9.
(6) In case it is determined prima facie by the Procuring Entity that the
Contractor has engaged, before or during the implementation of the
contract, in unlawful deeds and behaviors relative to contract
acquisition and implementation, such as, but not limited to, the
following:
16.2 When persons from the Procuring Entity gives notice of a fundamental breach to
the Procuring Entity’s Representative in order to terminate the existing contract
for a cause other than those listed under GCC Clause 16.1-e, the Procuring
Entity’s Representative shall decide whether the breach is fundamental or not.
16.3 If this Contract is terminated, the Contractor shall stop work immediately, make
the Site safe and secure, and leave the Site as soon as reasonably possible.
16.4 All materials on the Site, Plant, Equipment, and Works shall be deemed to be the
property of the Procuring Entity if this Contract is terminated because of the
Contractor’s default.
a. If the works are completely stopped for a continuous period of at least sixty
(60) calendar days through no fault of the Contractor, due to any of the
following reasons:
17.2 When persons from the Contractor gives notice of a fundamental breach to the
Procuring Entity’s Representative in order to terminate the existing contract for a
cause other than those listed under GCC Clause 17.1-b, the Procuring Entity’s
Representative shall decide whether the breach is fundamental or not.
18. Termination for Convenience
The Procuring Entity may terminate this Contract, in whole or in part, at any time for its
convenience. The HoPE may terminate this Contract for the convenience of the
Procuring Entity if he has determined the existence of conditions that make Project
Implementation economically, financially or technically impractical and/or unnecessary,
such as, but not limited to, fortuitous event(s) or changes in law and National
Government policies.
(1) that this Contract is being terminated for any of the grounds
aforementioned, and a statement of the acts that constitute the
ground(s).
c. Show Cause. Within a period of seven (7) calendar days from receipt of
the Notice of Termination, the Contractor shall submit to the HoPE a
verified position paper showing cause as to why the Contract should not
be terminated. If the Contractor fails to do so, the HoPE shall issue a
written Notice of Decision confirming the Notice of Termination of the
Contract.
19.2 Pursuant to Section 69(f) of RA 9184 and without prejudice to the imposition of
additional administrative sanctions as the internal rules of the agency may provide
and/or further criminal prosecution as provided by applicable laws, the Procuring
Entity shall impose on contractors after the termination of the contract the penalty
of suspension for one (1) year for the first offense, suspension for two (2) years
for the second offense from participating in the public bidding process, for
violations committed during the contract implementation stage, which include but
not limited to the following:
b. Failure by the contractor to fully and faithfully comply with its contractual
obligations without valid cause, or failure by the contractor to comply
with any written lawful instruction of the Procuring Entity or its
representative(s) pursuant to the implementation of the contract. For the
procurement of infrastructure projects or consultancy contracts, lawful
instructions include but are not limited to the following:
iii. Stockpiling in proper places of all materials and removal from the
project site of waste and excess materials, including broken
pavement and excavated debris in accordance with approved plans
and specifications and contract provisions;
(1) Negative slippage of 15% and above within the critical path of the
project due entirely to the fault or negligence of the contractor; and
20.3 If the event continues for a period of eighty four (84) days, either party may give
the other a Notice of Termination, which shall take effect twenty eight (28) days
after the receipt of the Notice.
20.4 After termination, the Contractor shall be entitled to payment of the unpaid
balance of the value of the Works executed and of the materials and Plant
reasonably delivered to the Site, adjusted by the following:
a. Any sum to which the Contractor is entitled under GCC Clause 28.
20.5 The net balance due shall be paid or repaid within a reasonable time period from
the date of the Notice of Termination.
21.2 If the Contract is terminated for the Procuring Entity’s convenience or because of
a fundamental breach of Contract by the Procuring Entity, the Procuring Entity’s
Representative shall issue a certificate for the value of the work done, materials
ordered, the reasonable cost of removal of Contractor’s equipment, and the
Contractor’s costs of protecting and securing the Works, less advance payments
received up to the date of the certificate.
21.3 The net balance due shall be paid or repaid within twenty eight (28) days from the
notice of termination.
21.4 If the Contractor has terminated the Contract under GCC Clause 17 or 18, the
Procuring Entity shall promptly return the Performance Security to the
Contractor.
22.2 If the Contractor believes that a decision taken by the Procuring Entity’s
Representative was either outside the authority given to the Procuring Entity’s
Representative by this Contract or that the decision was wrongly taken, the
decision shall be referred to the Arbiter indicated in the SCC within fourteen (14)
days of the notification of the Procuring Entity’s Representative’s decision.
22.3 Any and all disputes arising from the implementation of this Contract covered by
the RA 9184 and its IRR shall be submitted to arbitration in the Philippines
according to the provisions of RA 876, otherwise known as the “Arbitration Law”
and RA 9285, otherwise known as the “Alternative Dispute Resolution Act of
2004. However, disputes that are within the competence of the Construction
Industry Arbitration Commission to resolve shall be referred thereto. The process
of arbitration shall be incorporated as a provision in this Contract that will be
executed pursuant to the provisions of RA 9184 and its IRR. By mutual
agreement, however, the parties may agree in writing to resort to other alternative
modes of dispute resolution.
b. If the Contractor has not received sums due it for work already done within forty
five (45) days from the time the Contractor’s claim for payment has been certified
by the Procuring Entity’s Representative, the Contractor may immediately issue a
suspension of work notice in accordance with GCC Clause 44.
24.2 The Procuring Entity’s Representative may delegate any of his duties and
responsibilities to other people, except to the Arbiter, after notifying the
Contractor, and may cancel any delegation after notifying the Contractor.
25.2 The Contractor shall be responsible for the design of Temporary Works.
25.3 The Procuring Entity’s Representative’s approval shall not alter the Contractor’s
responsibility for the design of the Temporary Works.
25.4 The Contractor shall obtain approval by third parties of the design of the
Temporary Works, when required by the Procuring Entity.
26.2 If the Contractor’s Financial Proposals for an acceleration are accepted by the
Procuring Entity, they are incorporated in the Contract Price and treated as a
Variation.
27.2 The Procuring Entity’s Representative shall decide whether and by how much to
extend the Intended Completion Date within twenty one (21) days of the
Contractor asking the Procuring Entity’s Representative for a decision thereto
after fully submitting all supporting information. If the Contractor has failed to
give an early warning of a delay or has failed to cooperate in dealing with a delay,
the delay by this failure shall not be considered in assessing the new Intended
Completion Date.
29. Dayworks
29.1 Subject to GCC Clause 44 on Variation Orders, and if applicable as indicated in
the SCC, the Dayworks rates in the Contractor’s Bid shall be used for small
additional amounts of work only when the Procuring Entity’s Representative has
given written instructions in advance for additional work to be paid for in that
way.
29.2 All work to be paid for as Dayworks shall be recorded by the Contractor on forms
approved by the Procuring Entity’s Representative. Each completed form shall be
verified and signed by the Procuring Entity’s Representative within two days of
the work being done.
29.3 The Contractor shall be paid for Dayworks subject to obtaining signed Dayworks
forms.
30.2 The Contractor shall cooperate with the Procuring Entity’s Representative in
making and considering proposals for how the effect of such an event or
circumstance can be avoided or reduced by anyone involved in the Work and in
carrying out any resulting instruction of the Procuring Entity’s Representative.
31.2 An update of the Program of Work shall the show the actual progress achieved on
each activity and the effect of the progress achieved on the timing of the
remaining work, including any changes to the sequence of the activities.
31.3 The Contractor shall submit to the Procuring Entity’s Representative for approval
an updated Program of Work at intervals no longer than the period stated in the
SCC. If the Contractor does not submit an updated Program of Work within this
period, the Procuring Entity’s Representative may withhold the amount stated in
the SCC from the next payment certificate and continue to withhold this amount
until the next payment after the date on which the overdue Program of Work has
been submitted.
31.4 The Procuring Entity’s Representative’s approval of the Program of Work shall
not alter the Contractor’s obligations. The Contractor may revise the Program of
Work and submit it to the Procuring Entity’s Representative again at any time. A
revised Program of Work shall show the effect of any approved Variations.
31.5 When the Program of Work is updated, the Contractor shall provide the Procuring
Entity’s Representative with an updated cash flow forecast. The cash flow
forecast shall include different currencies, as defined in the Contract, converted as
necessary using the Contract exchange rates.
31.6 All Variations shall be included in updated Program of Work produced by the
Contractor.
32.2 The Procuring Entity’s Representative shall prepare the minutes of Management
Conferences and provide copies of the minutes to those attending the Conference.
The responsibility of the parties for actions to be taken shall be decided by the
Procuring Entity’s Representative either at the Management Conference or after
the Management Conference and stated in writing to all who attended the
Conference.
33.2 The BOQ is used to calculate the Contract Price. The Contractor shall be paid for
the actual quantity of each pay item, certified by the Procuring Entity’s
Representative as accomplished, at the unit price in the Bill of Quantities for that
item.
33.3 If the final quantity of any pay item accomplished differs from the original
quantity in the BOQ for that item and is not more than twenty five percent (25%)
of that original quantity, provided the aggregate changes for all work items do not
exceed ten percent (10%) of the Contract Price, the Procuring Entity’s
Representative shall make the necessary adjustments to allow for the changes,
subject to applicable laws, rules, and regulations.
33.4 If requested by the Procuring Entity’s Representative, the Contractor shall provide
the Procuring Entity’s Representative a detailed cost breakdown of any unit price
or rate in the BOQ.
34.2 If the Procuring Entity’s Representative instructs the Contractor to carry out a test
not specified in the Specifications to check whether any work has a defect and the
test shows that it does, the Contractor shall pay for the test and any samples. If
there is no defect, the test shall be a Compensation Event.
34.3 The Contractor shall permit the Funding Source named in the SCC to inspect the
accounts and records of the Contractor relating to its performance and to have
them audited by auditors approved by the Funding Source, if so required by the
Funding Source.
37.2 Every time notice of a Defect is given, the Contractor shall correct the notified
defect within the length of time specified in the Procuring Entity’s
Representative’s notice.
37.3 The Contractor shall correct the Defects which it notices itself before the end of
the Defects Liability Period.
37.4 The Procuring Entity’s Representative shall certify that all Defects have been
corrected. If the Procuring Entity’s Representative considers that correction of a
Defect is not essential, he can request the Contractor to submit a quotation for the
corresponding reduction in the Contract Price. If the Procuring Entity’s
Representative accepts the quotation, the corresponding change shall be covered
by a Variation Order.
a. The first installment shall require the written request of the Contractor and
submission of the instrument prescribed in GCC Clause 39.2.
39.2 The Advance Payment shall be made only upon the submission by the Contractor
to and acceptance by the Procuring Entity of an irrevocable standby letter of
credit of equivalent value from a commercial bank, a bank guarantee or a surety
bond callable upon demand, issued by a surety or insurance company duly
licensed by the Insurance Commission and confirmed by the Procuring Entity.
39.3 The Advance Payment shall be repaid by the Contractor by deducting, from
periodic progress payments to be made to the Contractor, a percentage equal to
the percentage of the total Contract Price used for the Advance Payment.
39.4 The Contractor may reduce its standby letter of credit or guarantee instrument by
the amounts refunded by the Monthly Certificates in the advance payment.
a. the cumulative value of the Works it executed to date, based on the items
in the Bill of Quantities; and
40.2 Except as otherwise stipulated in the SCC, materials and equipment delivered on
the site but not completely put in place shall not be included for payment.
41. Monthly Certificates and Progress Payments
41.1 The Procuring Entity’s Representative shall check the Contractor’s monthly SWA
and certify the amount to be paid to the Contractor.
41.2 The Procuring Entity’s Representative shall check the Contractor’s monthly
statement and certify the amount to be paid to the Contractor.
b. comprise the value of the quantities of the items in the Bill of Quantities
completed; and
41.4 The Procuring Entity’s Representative may exclude any item certified in a
previous certificate or reduce the proportion of any item previously certified in
any certificate in the light of later information.
41.5 The Procuring Entity’s Representative shall deduct the following from the
certified gross amounts to be paid, resulting in the net amount payable to the
Contractor as Progress Payment:
b. Portion of the advance payment to be recouped for the month under the
present certificate.
f. Value of any work item presently certified but already paid for under an
earlier certification.
41.6 The Procuring Entity shall pay the Contractor the said net amounts certified by
the Procuring Entity’s Representative within twenty eight (28) days from the date
each certificate was issued. No payment of interest for delayed payments and
adjustments shall be made by the Procuring Entity.
41.7 The first progress payment may be paid by the Procuring Entity to the Contractor
provided that at least twenty percent (20%) of the work has been accomplished as
certified by the Procuring Entity’s Representative.
41.8 Items of the Works for which a price of “0” (zero) has been entered will not be
paid for by the Procuring Entity and shall be deemed covered by other rates and
prices in the Contract.
41.9 The Procuring Entity shall pay the Contractor a cumulative gross amount not
exceeding ninety percent (90%) of the total Contract price, since the remainder
shall serve as the ten percent (10%) retention money, as provided in GCC Clause
42.
42. Retention
42.1 The Procuring Entity shall retain from each progress payment ten percent (10%)
of such payment, referred to as the “retention money.” Such retention money
shall be based on the total amount due to the Contractor prior to any deduction
and shall be retained from every Progress Payment until fifty percent (50%) of the
value of the Works, as determined by the Procuring Entity, is completed. If, after
fifty percent (50%) completion, the Works are satisfactorily done and on
schedule, no additional retention shall be made; otherwise, the ten percent (10%)
retention shall again be imposed using the rate specified therefor.
42.2 The total retention money shall be due for release upon final acceptance of the
Works. The Contractor may, however, request the substitution of the retention
money for each progress billing with an irrevocable standby letter of credit from a
commercial bank, bank guarantee and/or surety bond callable on demand, of
amounts equivalent to the retention money substituted for and in a form
acceptable to the Procuring Entity. The Procuring Entity shall allow such
substitution provided that the Contract is on schedule and is satisfactorily
undertaken. The said irrevocable standby letter of credit, bank guarantee and/or
surety bond, to be posted in favor of the Procuring Entity, shall be valid for a
duration to be determined by the Procuring Entity and shall answer for the
purpose for which the retention is intended, i.e., to cover uncorrected discovered
Defects and third party liabilities.
42.3 On completion of the whole Works, the Contractor may substitute retention
money with an “on demand” Bank guarantee in a form acceptable to the
Procuring Entity.
43.2 A deductive VO may be allowed only if it would not significantly impair the
functionality of the original design, i.e., it must not reduce the size of the facility
by more than ten percent (10%) of the original scope (e.g., shortening of road
length) or must not make the facility unsafe (e.g., removal of guard rails) or
structurally unstable (e.g., removal of a column) or unusable (e.g., removal of a
bridge abutment).
43.3 A VO in the form of a Change Order may be issued by the Procuring Entity to
cover any increase or decrease in quantities of original Work items in the
Contract.
43.4 A VO in the form an Extra Work Order may be issued by the Procuring Entity to
cover the introduction of new work necessary for the completion, improvement or
protection of the project which were not included as items of work in the original
Contract, such as where there are subsurface or latent physical conditions at the
Site differing materially from those indicated in the Contract, or where there are
duly unknown physical conditions at the Site of an unusual nature differing
materially from those ordinarily encountered and generally recognized as inherent
in the Works or character provided for in the Contract.
43.5 Any cumulative positive VO beyond ten percent (10%) shall be the subject of
another contract to be bid out if the works are separable from the original
Contract.
43.6 In claiming for any VO, the Contractor shall, within seven (7) calendar days after
such work has been commenced or after the circumstances leading to such
condition(s) leading to the extra cost, and within twenty-eight (28) calendar days
deliver a written communication giving full and detailed particulars of any extra
cost in order that it may be investigated at that time. Failure to provide either of
such notices in the time stipulated shall constitute a waiver by the contractor for
any claim. The Contractor shall not “accumulate” claims for VOs before
submitting them to the Procuring Entity for investigation and processing.
b. In the absence of unit prices for the same items rates in this Contract, at
prices or rates obtained from those of similar or related items in this
Contract.
c. Failing the above, at appropriate new unit prices or rates equal to or lower
than current market rates and to be agreed upon by both parties and
approved by the HoPE.
a. Force majeure or any fortuitous event that has taken place, which inflicts
extensive damage and/or makes it difficult to proceed with the work, such
as a devastating earthquake or flood.
b. Failure on the part of the Contractor to correct bad conditions which are
unsafe for workers or for the general public.
c. Failure of the contractor to carry out valid orders given by the Procuring
Entity or to perform any provisions of the contract.
The Contractor shall immediately comply with such order to suspend the Works
wholly or partly.
45.2 The Contractor or its duly authorized representative shall have the right to
suspend work operation on any or all projects/activities along the critical path of
activities after fifteen (15) calendar days from date of receipt of written notice
from the Contractor to the district engineer/regional director/consultant or
equivalent official, as the case may be, on any of the following grounds:
45.3 The contractor shall immediately demobilize its equipment and manpower upon
its receipt of the Work Suspension Order and to remobilize the same upon the
lifting by the Procuring Entity the Work Suspension Order through a Work
Resumption Order.
45.4 The issuance of a Work Suspension Order shall not be an automatic contract time
extension. A corresponding time extension, complete with the documentary
requirements in accordance with DO No. 52, series of 2012,has to be approved by
the authorized DPWH official in lieu of suspension, subject to evaluation to
consider pre-determined unworkable days, bond extension, quit claim for
damages, and their effect on the approved PERT/CPM schedule in order to reflect
the official revised contract time and expiry date as a result of such suspension. If
the suspension is due to any fault of the contractor, no contract time extension
shall be granted.
46.2 Should the amount of additional work under an approved Variation Order or other
special circumstances of any kind whatsoever occur such as to fairly entitle the
Contractor to an extension of Contract Time, the Procuring Entity shall determine
the amount of such extension; provided that the Procuring Entity is not bound to
take into account any claim for an extension of time unless the Contractor has,
prior to the expiration of the Contract time and within thirty (30) calendar days
after such work has been commenced or after the circumstances leading to such
claim have arisen, delivered to the Procuring Entity notices in order that it could
have investigated them at that time. Failure to provide such notice shall constitute
a waiver by the Contractor of any claim. Upon receipt of full and detailed
particulars, the Procuring Entity shall examine the facts and extent of the delay
and shall extend the Contract time to complete the contract work when, in the
Procuring Entity’s opinion, the findings of facts justify an extension.
46.3 No extension of contract time shall be granted the Contractor due to (a) ordinary
unfavorable weather conditions and (b) inexcusable failure or negligence of
Contractor to provide the required equipment, supplies or materials.
46.4 Extension of contract time may be granted only when the affected activities fall
within the critical path of the PERT/CPM network.
46.5 No extension of contract time shall be granted when the reason given to support
the request for extension was already considered in the determination of the
original contract time during the conduct of detailed engineering and in the
preparation of the contract documents as agreed upon by the parties before
contract perfection.
46.6 Extension of contract time may be granted for any of the following grounds:
c. Shortage of construction materials, general labor strikes, and peace and order
problems that disrupt construction operations through no fault of the
Contractor, provided that they are publicly felt and certified by appropriate
government agencies such as Department of Trade and Industry (DTI),
Department of Labor and Employment (DOLE), Department of Interior and
Local Government (DILG), and Department of National Defense (DND),
among others.
46.7 The written consent of bondsmen must be attached to any request of the
Contractor for extension of Contract Time and submitted to the Procuring Entity
for consideration, and the validity of the Performance Security shall be
correspondingly extended.
47. Price Adjustment
Except for extraordinary circumstances as determined by the National Economic and
Development Authority (NEDA) and approved by the GPPB, no price adjustment shall
be allowed unless otherwise indicated in the SCC. Nevertheless, in cases where the cost
of the awarded contract is affected by any applicable new laws, ordinances, regulations,
or other acts of the GOP, promulgated after the date of bid opening, a contract price
adjustment shall be made or appropriate relief shall be applied on a no loss-no gain basis.
a. Upon receipt of notice from the contractor that the project is completed,
the HOPE shall instruct its Inspectorate Team to conduct an inspection of
the project and to submit its Completion Inspection Report within fifteen
(15) days, indicating any construction defects/deficiencies detected and
the corresponding measures that must be taken by the contractor to correct
them. If no defects/deficiencies are detected, the report is considered as
the Final Completion Inspection Report.
b. Based on the Inspection Report, the HOPE shall issue to the Contractor a
Notice of Defects/Deficiencies and Required Corrective Repair Works,
with the instructions for the Contractor to commence the repair works
within seven (7) days and to complete the works within thirty (30) days.
c. Upon receipt of advice from the Contractor that the defects and
deficiencies indicated in the said Notice have been corrected, the HOPE
shall instruct the Inspectorate Team to conduct an inspection of the project
and to submit its Completion Inspection Report within seven (7) days. If
the report shows that the defects/deficiencies have been satisfactorily
corrected, the report is considered as the Final Completion Inspection
Report. Otherwise, the process is repeated until the noted
defects/deficiencies have been satisfactorily corrected.
d. Upon the receipt of the Final Completion Inspection Report from the
Inspectorate Team, the HopE shall issue the Certificate of Completion of
the project, certifying that the Project has been satisfactorily completed as
of the date indicated in the Final Inspection Report.
48.2 The Certificate of Acceptance shall be issued by the HoPE at the end of the one-
year Defects Liability period, after all defects/deficiencies, if any, shall have been
repaired by the Contractor to the satisfaction of the same Inspectorate Team of the
Procuring Entity mentioned above and upon submission of the Warranty
Certificate by the Contractor in accordance with the provisions of GCC Clause
12.The issuance of a Certificate of Acceptance shall be subject to the provisions
of DPWH DO 99, series of 2015.
a. Upon receipt of notice from the Contractor that the project is ready for
inspection after the one-year Defects Liability Period from the issuance of
the Certificate of Completion, the HoPE shall instruct its Inspectorate
Team to conduct an inspection of the project and to submit its Inspection
Report within fifteen (15) calendar days, indicating any construction
defects/deficiencies detected and the corresponding measures that must be
taken by the Contractor to correct them. If no defects/deficiencies are
detected, the report is considered as the Final Acceptance Inspection
Report.
b. Based on the Inspection Report, the HoPE shall issue to the Contractor a
Notice of Defects/Deficiencies and Required Corrective Repair Works,
with the instructions for the Contractor to commence the repair works
within seven (7) calendar days and to complete the works within ninety
(90) days.
d. Upon the receipt of the Final Acceptance Report, the Head of the I0 shall
issue the Certificate of Acceptance.
50.2 If the Contractor does not supply the said Drawings by the date stated in the SCC,
or if they do not receive the approval of the Procuring Entity’s Representative, the
Procuring Entity’s Representative shall withhold the amount stated in the SCC
from payments due to the Contractor.
ANNEX II-1.1G
Section VII. Special Conditions of Contract
100
SPECIAL CONDITIONS OF CONTRACT
GCC Clause
1.19 The Intended Completion Date is July 10, 2021.
1.24 The Procuring Entity is DPWH-Regional Office I, City of San Fernando,
La Union.
1.25 The Procuring Entity’s Representative is GERRY G. JUCAR, BAC
Chairman, DPWH-Regional Office I, City of San Fernando, La Union.
1.26 The Site is located at Piddig-Carasi, Ilocos Norte and is defined in
Drawings No. _______
1.30 The Start Date is December 16, 2020.
1.33 The Works consist of 1. Earthworks (Clearing, Excavation, & Embankment);
2. Construction of Cross Drainages (RCPC); 3. Construction of Slope and Bank
Protection Structures (Stone Masonry); 4. Spreading and Compaction of
Aggregate Sub-Base Course; 5. Construction of Concrete Catch Basins
2.2 No applicable
5.1 The Procuring Entity shall give possession of the Site to the Contractor upon
issuance of the Notice to Proceed (NTP).
6.5 The Contractor shall employ the following Key Personnel:
8.3 The Contractor shall undertake not less than 50% of the contracted works
with its own resources.
10. The Site Investigation Reports are: if applicable
101
29.1 No dayworks are applicable to the contract.
31.1 The Contractor shall submit the Program of Work to the Procuring
Entity’s Representative within ten (10) da y s of delivery of the Le t te r of
Acceptance.
31.3 The period between Program of Work updates is Thirty (30) days.
39.1 The amount and schedule of the advance payment is 15% of the Contract Price
to be recouped by deducting fifteen percent (15%) from the periodic progress
billing.
40.2 Materials and equipment delivered on the site but not completely put in place
shall be included for payment.
50.1 The date by which operating and maintenance manuals are required is
not applicable.
The date by which “as built” drawings are required is thirty (30) cal. days
from completion of the project.
50.2 The amount to be withheld for failing to supply the As-Built Drawings by the
date required is 10% of the final Contract Price.
102
ANNEX II-1.1H
Section VIII. Specifications
1. DPWH Standards
The DPWH Standard Specifications for Public Works and Highways (“Blue Book”)
shall be the main basis for the standards and codes to be met by the goods and materials
to be furnished and work performed or tested for the Contract. In particular, Volume II
of the Blue Book shall be used if the Contract pertains to Highways, Bridges and
Airports. Volume III of the Blue Book shall be used if the Contract pertains to Buildings,
Flood Control and Drainage, or Water Supply. The Blue Book incorporates standards of
the American Association of State Highway and Transportation Officials (AASHTO),
American Society for Testing and Materials (ASTM), and American Concrete Institute
(ACI), among others, pertaining to construction.
The Procuring Entity shall use the Standard Pay Items in the Project and Contract
Management Application (PCMA) in drawing up the Specifications.
2. Modifications of Standards
2.1 Modifications of and additions to standards and codes as stated in the DPWH
Standard Specifications for Public Works and Highways, if any, shall be included
in the enclosed Supplemental Specifications, which is part of these Bidding
Documents.
2.2 Entries in the Supplemental Specifications are numbered to coincide with the
numbering of items in the DPWH Standard Specifications for Public Works and
Highways.
103
Section VIII-A. Particular Specifications
A.1.1(8): Provision of Field Office for the Engineer (Rental Basis)
The Contractor shall provide or rent a field office and living quarters with an area = 63.00 sq.m. for
the exclusive use of the DPWH Engineer and his staff with the provision of toilet and bath, potable
water, sewerage and electricity connected to a local power supply.
A.1.1 (16): Operation and Maintenance of Field Office for the Engineer
The Office shall be provided with minimum requirements of furniture, equipment, etc. specified
below:
Description Unit Quantity
Bond Paper, 80 gsm (8.27" x 11.69" , 8.5" x 13" , A3) ls 1
Within one month of his arrival on site the Contractor shall submit a Health and Safety Plan with operational
details of his proposals to the engineer for his approval.
1. Due precautions shall be taken by the Contractor, at his own cost, to ensure the safety and protection
against accidents of all staff and labour engaged on the works, local residents in the vicinity of the works,
and the public travelling through the works.
2. The contractor shall have on his staff on site a designated full-time officer qualified to promote and
maintain safe working practices. This officer shall have authority to issue instructions and shall take
protective measures to prevent accidents, including but not limited to the establishment of safe working
practices and the training of staff and labour in their implementation.
3. The contractor shall be responsible for all costs including medical treatment, transport,
accommodation, etc. incurred by any member of the public or his labour forces whether on direct contract or
sub-contract as a result of injuries or illness arising from the execution of the works.
1. The contractor shall at his own expense provide protective clothing and safety equipment to all staff and
labor engaged on the Works to the satisfaction of the Engineer. Such clothing and equipment shall
include, at a minimum, high visibility vests for workers directing traffic, protective footwear for
workmen undertaking concrete mixing work, protective footwear and gloves for any workmen
performing bituminous paving works, protective footwear, hard hats, safety dust masks and otherwise as
appropriate to the job in hand and to the Engineer’s satisfaction.
2. If the Contractor fails to provide such clothing and equipment the employer shall be entitled to provide
the same and recover the cost from the Contractor.
104
D. Medical and First-Aid Facilities
The contractor shall provide and maintain throughout the duration of the Contract, a medical examining
room and sick bay together with all necessary supplies and equipment to be sited in the Contractor’s main
camp. The rooms shall be used exclusively for medical purposes and shall be of good quality construction
with electric lighting and otherwise suitable for their purpose. The sick bay shall have at least two beds, and
shall be provided with adjacent washing and sanitation facilities.
The contractor shall employ part time Safety Practitioner and first aider on site who shall be engaged solely
for medical duties.
The contractor shall at his own expense provided first aid equipment at all camps and work sites to the
satisfaction of the Engineer, and shall ensure that at all camps and works shall at all times have a person
qualified in first-aid with access to appropriate first-aid equipment.
The location of the medical room and other medical and first-aid facilities shall be made known to all
employees by posting suitable notices at prominent locations around the site and by verbal instruction upon
recruitment.
The Contractor shall provide on the Site and at his expense an adequate supply of potable drinking water for
all staff and labor engaged on the works, together with sanitary facilities (portable toilets or latrines), to the
satisfaction of the Engineer. The Contractor shall thoroughly disinfect and fill all latrine pits, sumps and
trenches when no longer required.
Health and Safety will be measured and paid in accordance with the current DPWH Department Order,
series 2005: Re “Guidelines for the Implementation of DOLE D.O. No. 13, series of 1998, Governing
Occupational Safety and health in the Construction Industry”.
105
ANNEX II-1.1I
Section IX. Drawings
BILL OF QUANTITIES
Part No. _____________ Part Description: _____________________________
PART C EARTHWORKS
In words: Pesos In figures:
Php__________
1700(1) Clearing and Grubbing sq.m. 2,925.00
In figures:
Php____________
In words: Pesos In figures:
Php__________
Structure Excavation,
1702(1)a cu.m. 750.00
common soil
In figures:
Php____________
In words: Pesos In figures:
Php__________
1704(1)b Embankment from borrow cu.m. 7,667.69
In figures:
Php____________
TOTAL OF PART C Php________
PART D SUBBASE AND BASE COURSES
In words: Pesos In figures:
Php__________
200(1) Aggregate Subbase Course cu.m. 5,845.82
In figures:
Php____________
TOTAL OF PART D Php________
Submitted by:
_____________________________
Name and signature of Bidder’s Representative Date: __________________
____________________________
Position
____________________________
Name of Bidder
Department of Public Works and Highways
Contract ID:
Contract Name:
Location of the Contract:
---------------------------------------------------------------------------------
1. Part No. – Enter the “Part No.” for each section of the BOQ where unit prices are entered.
2. Part Description – Enter the “Part Description” corresponding to the “Part No.”
3. Total Amount – Enter the “Total Amount” in Pesos for all pages having the same “Part
Description”
PART C EARTHWORKS
Total of Amount
DPWH-INFR-20: Bidder’s Checklist of Requirements for Its Bid, Including Technical and
Financial Proposals Requirement for Bidders
Duly initialed Contractor’s List of Key Personnel for the Contract (Form DPWH-INFR-14)
Duly signed Bid Prices in the Bill of Quantities (Forms DPWH-INFR-17 and 18)
-------------------------------------------------------------------------------------------------------------------
DPWH-INFR-20-2016 Page 1 of 1
Department of Public Works and Highways
Contract ID:
Contract Name:
Location of the Contract:
---------------------------------------------------------------------------------
REPUBLIC OF THE PHILIPPINES )
CITY OF _______________________ ) S.S.
x-------------------------------------------------------x
BID-SECURING DECLARATION
1. I/We understand that, according to your conditions, bids must be supported by a Bid
Security, which may be in the form of a Bid-Securing Declaration.
2. I/We accept that: (a) I/we will be automatically disqualified from bidding for any
contract with any procuring entity for a period of two (2) years upon receipt of your
Blacklisting Order; and, (b) I/we will pay the applicable fine provided under Section 6 of
the Guidelines on the Use of Bid Securing Declaration, within fifteen (15) days from
receipt of the written demand by the Procuring Entity for the commission of acts
resulting to the enforcement of the bid securing declaration under Sections 23.1(b),
34.2, 40.1 and 69.1, except 69.1(f), of the IRR of RA 9184; without prejudice to other
legal action the government may undertake.
3. I/We understand that this Bid-Securing Declaration shall cease to be valid on the
following circumstances:
(a) Upon expiration of the bid validity period, or any extension thereof pursuant to your
request;
(b) I am/we are declared ineligible or post-disqualified upon receipt of your notice to
such effect, and (i) I/we failed to timely file a request for reconsideration or (ii) I/we
filed a waiver to avail of said right;
(c) I am/we are declared as the bidder with the Lowest Calculated and Responsive Bid,
and I/we have furnished the performance security and signed the Contract.
IN WITNESS WHEREOF, I/We have hereunto set my/our hand/s this ____ day of [month] [year]
at [place of execution].
---------------------------------------------------------------------------------------------------------
DPWH-INFR-12-2016 Page 1 of 2
Department of Public Works and Highways
Contract ID:
Contract Name:
Location of the Contract:
---------------------------------------------------------------------------------
SUBSCRIBED AND SWORN to before me this __ day of [month] [year] at [place of execution],
Philippines. Affiant/s is/are personally known to me and was/were identified by me through
competent evidence of identity as defined in the 2004 Rules on Notarial Practice (A.M. No. 02-
8-13-SC). Affiant/s exhibited to me his/her [insert type of government identification card used],
with his/her photograph and signature appearing thereon, with no. ______ .
Witness my hand and seal this ___ day of [month] [year].
---------------------------------------------------------------------------------------------------------
DPWH-INFR-12-2016 Page 2 of 2
Department of Public Works and Highways
Contract ID:
Contract Name:
Location of the Contract:
---------------------------------------------------------------------------------
Date of Issuance
WHEREAS, Name of Bidder , hereinafter called the “Bidder,” has undertaken to submit to you a bid for the
above stated Contract, and whereas you have stipulated in the Instructions to Bidders for the said Contract that the
Bidder shall furnish you with an irrevocable standby Letter of Credit for a sum specified therein as Bid Security for
the faithful compliance of the obligations of the Bidder:
1) if the Bidder withdraws the Bid during the period of bid validity specified in the Form of
Bid; or
2) if the Bidder does not accept the correction of arithmetical errors of its bid price in
accordance with the Instructions to Bidder; or
3) if the Bidder having been notified of the acceptance of the Bid and award of contract to it
by the Entity during the period of bid validity:
a) fails or refuses to submit the requirements for and to execute the Form of Contract in accordance with
the Instructions to Bidders; or
b) fails or refuses to furnish the Performance Security in accordance with the Instructions to Bidders;
we undertake to pay to the Entity up to the above amount upon receipt of its first written demand,
without the Entity having to substantiate its demand, provided that in its demand the Entity will note
that the amount claimed by it is due to the occurrence of any one or combination of the three (3)
conditions stated above.
------------------------------------------------------------------------------------------------------------------------------------
DPWH-INFR-11-2016 Page 1 of 2
Department of Public Works and Highways
Contract ID:
Contract Name:
Location of the Contract:
---------------------------------------------------------------------------------
THEREFORE, we hereby affirm that we are guarantors and responsible to you, on behalf of the Bidder, up to the
total amount of amount of guarantee and we undertake to pay you, upon first written demand declaring the
Bidder to be in default under the Instructions to Bidders and without cavil or argument, any sum or sums within the
limits of _amount of guarantee as aforesaid, without you needing to prove or show grounds or reasons for
your demand for the sum specified therein.
This irrevocable guarantee is valid until one hundred twenty (120) calendar days after the date of opening of bids for
the said Contract on date__.
This certification is being issued in favor of the said Bidder in connection with your requirements of the bidding for
the said Contract. We are aware that any false statements issued by us make us liable to perjury.
Concurred by:
------------------------------------------------------------------------------------------------------------------------------------
DPWH-INFR-11-2016 Page 2 of 2
Department of Public Works and Highways
Contract ID:
Contract Name:
Location of the Contract:
---------------------------------------------------------------------------------
WHEREAS, ___Name of Bidder__, hereinafter called “the Bidder,” has submitted its bid dated
_________ for the ___Contract ID and Name__, hereinafter called “the Bid.”
KNOW ALL MEN by these presents that We, __Name of Bank__ of __Name of Country__, having
our registered office at ________________________, hereinafter called “the Bank,” are bound unto
__Name of Procuring Entity__, hereinafter called “the Entity,” in the sum of ________amount in
words and figures________ for which payment well and truly to be made to the said Entity the Bank
binds itself, its successors and assigns by these presents.
SEALED with the Common Seal of the said Bank this _____ day of _________ 20___.
1) if the Bidder withdraws the Bid during the period of bid validity specified in the Form of
Bid; or
2. if the Bidder does not accept the correction of arithmetical errors of its bid price in
accordance with the Instructions to Bidder; or
3. if the Bidder having been notified of the acceptance of the Bid and award of contract to it
by the Entity during the period of bid validity:
a) fails or refuses to submit the requirements for and to execute the Form of Contract in
accordance with the Instructions to Bidders, if required; or
b) fails or refuses to furnish the Performance Security in accordance with the
Instructions to Bidders;
we undertake to pay to the Entity up to the above amount upon receipt of its first written demand,
without the Entity having to substantiate its demand, provided that in its demand the Entity will note
that the amount claimed by it is due to the occurrence of any one or combination of the three (3)
conditions stated above.
The Guarantee will remain in force up to a period of _______________ days after the opening of
bids as stated in the Instructions to Bidders or as it may be extended by the Entity, notice of which
extension(s) to the Bank is hereby waived. Any demand in respect of this Guarantee should reach
the Bank within the said period.
Submit a copy of the Organizational Chart that the Contractor intends to use to execute the
Contract if awarded to it. Indicate in the chart the names of the Project Manager, Project
Engineer, Structural Engineer, Materials and Quality Control Engineer, Foremen, and other
Key Personnel, as required in the Instructions to Bidders (Bid Data Sheet). Include Sub-
Contractors, if any.
Attach the required Proposed Organizational Chart for the Contract as stated above.
----------------------------------------------------------------------------------------------------------------------------
----DPWH-INFR-13-2016 Page 1 of 1
Department of Public Works and Highways
Contract ID:
Contract Name:
Location of the Contract:
---------------------------------------------------------------------------------
LIST OF CONTRACTOR’S KEY PERSONNEL TO BE ASSIGNED TO THE CONTRACT, WITH THEIR
QUALIFICATION DATA
Date of Issuance
Dear Sir/Madame:
Supplementing our Organizational Chart for the abovestated Contract, we submit, and certify as true and correct, the
following information:
1. We have engaged the services of the following key personnel to perform the duties of the positions
indicated in the abovestated Contract if it is awarded to us:
2. We submit the enclosed Curriculum Vitae and Affidavits of Commitment to Work on the Contract of these
key personnel.
3. We ensure that the abovementioned personnel shall employ their best care, skill, and ability in performing
the duties of their respective positions in accordance with the provisions of the Contract, including the
Conditions of Contract, Specifications, and Drawings, and that they shall be personally present in the
jobsite during the period of their assignment in the Contract.
4. In the event that we choose to replace any of the abovementioned key personnel, we shall submit to you in
writing at least fourteen (14) days before making the replacement, for your approval, the name and biodata
of the proposed replacement whose qualifications shall be equal to or better than that of the person to be
replaced.
5. We understand that any violation of the abovestated conditions shall be a sufficient ground for us to be
disqualified from this Contract and future biddings of the DPWH.
------------------------------------------------------------------------------------------------------------
DPWH-INFR-14-2016
Department of Public Works and Highways
Contract ID:
Contract Name:
Location of the Contract:
----------------------------------------------------------------------------------
LIST OF CONTRACTOR’S MAJOR CONSTRUCTION AND LABORATORY EQUIPMENT UNITS TO BE ASSIGNED TO THE CONTRACT,
SUPPORTED BY CERTIFICATIONS OF AVAILABILITY
Minimum major construction equipment requirement as prescribed in the Bid Data Sheet: Minimum major laboratory equipment requirements as prescribed in Bid Data Sheet:
________________________________ ________________________________
______________________ _______________________________
______________________ ________________________________
Contract ID:
Contract Name:
Location of the Contract:
----------------------------------------------------------------------------------
OMNIBUS SWORN STATEMENT
AS REQUIRED BY RA 9184-IRR SECTION 25.2b)iv)
AFFIDAVIT
I, [Name of Affiant], of legal age, [Civil Status], [Nationality], and residing at [Address of Affiant], after
having been duly sworn in accordance with law, do hereby depose and state that:
1. Select one, delete the other:
If a sole proprietorship: I am the sole proprietor or authorized representative of [Name of
Bidder] with office address at [address of Bidder];
If a partnership, corporation, cooperative, or joint venture: I am the duly authorized and
designated representative of [Name of Bidder] with office address at [address of Bidder];
2. Select one, delete the other:
Contract ID:
Contract Name:
Location of the Contract:
----------------------------------------------------------------------------------
DPWH-INFR-16-2016 Page 1 of 3
6. Select one, delete the rest:
If a sole proprietorship: The owner or sole proprietor is not related to the Head of the
Procuring Entity, members of the Bids and Awards Committee (BAC), the Technical Working
Group, and the BAC Secretariat, the head of the Project Management Office/Implementing
Unit, and the project consultants by consanguinity or affinity up to the third civil degree;
If a corporation or joint venture: None of the officers, directors, and controlling stockholders
of [Name of Bidder] is related to the Head of the Procuring Entity, members of the Bids and
Awards Committee (BAC), the Technical Working Group, and the BAC Secretariat, the head of
the Project Management Office/Implementing Unit, and the project consultants by
consanguinity or affinity up to the third civil degree;
8. [Name of Bidder] is aware of and has undertaken the following responsibilities as a Bidder:
b) Acknowledge all conditions, local or otherwise, affecting the implementation of the Contract;
c) Make an estimate of the facilities available and needed for the contract to be bid, if any; and
d) Inquire or secure Supplemental/Bid Bulletin(s) issued for the [Name of the Project]; and
9. [Name of Bidder] did not give or pay directly or indirectly, any commission, amount, fee, or any
form of consideration, pecuniary or otherwise, to any person or official, personnel or
representative of the government in relation to any procurement project or activity.
IN WITNESS WHEREOF, I have hereunto set my hand this __ day of ___, 20__ at ____________,
Philippines.
______________________________________
[Bidder’s Representative/Authorized Signatory]
---------------------------------------------------------------------------------------------------------
Department of Public Works and Highways
Contract ID:
Contract Name:
Location of the Contract:
----------------------------------------------------------------------------------
DPWH-INFR-16-2016 Page 2 of 3
SUBSCRIBED AND SWORN to before me this __ day of [month] [year] at [place of execution],
Philippines. Affiant/s is personally known to me and was identified by me through competent
evidence of identity as defined in the 2004 Rules on Notarial Practice (A.M. No. 02-8-13-SC). Affiant
exhibited to me his/her [insert type of government identification card used], with his/her photograph
and signature appearing thereon, with no. ______.
---------------------------------------------------------------------------------------------------------
DPWH-INFR-16-2016 Page 3 of 3
Department of Public Works and Highways
Contract ID:
Contract Name:
Location of the Contract:
----------------------------------------------------------------------------------
BID FORM
Date:
Contract ID:
Contract Name:
Location of the Contract:
----------------------------------------------------------------------------------
h. our Bid shall be valid for a period of _______________________ days after the date fixed
for the opening of bids in accordance with the Bidding Documents, and it shall remain
binding upon us and may be accepted by you at any time before the expiration of that period;
i. if our Bid is accepted and we receive from you a Notice of Award, we commit, within ten
(10) calendar days after our receipt of the said Notice, (1) to submit to you the required
Performance Security and other documents prescribed in the Bidding Documents, and (2) to
sign the Contract Agreement;
j. we understand that, if the contract is awarded to us, this Bid, together with your written
acceptance thereof through your Notice of Award, shall constitute a binding contract
between us, until a formal Contract Agreement is prepared and executed;
k. we understand that you are not bound to accept the Lowest Calculated Bid or any other Bid
that you may receive; and
l. we acknowledge that failure to sign each page of this Form of Bid and the accomplished Bill
of Quantities shall be a ground for the rejection of our Bid.
Name: ______________________________
In the capacity of:
Signed:
Duly authorized to sign the Bid for and on behalf of:
Date:
---------------------------------------------------------------------------------------------------------
DPWH-INFR-09-2016 Page 2 of 2
Department of Public Works and Highways
Contract ID:
Contract Name:
Location of the Contract:
----------------------------------------------------------------------------------
Submitted by:
----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
DPWH-INFR-19-2016 Page 1 of 1