Defects in construction projects
– current issues: Part 1
Donald G Gavin
Akerman Senterfitt LLP,    Design and construction defects – and the resulting efforts to allocate
Vienna, US                 responsibility, correct, remedy and deal with the cost and additional time
                           of such remediation – are frequently a problem in construction whatever
                           the set of contractual agreements used. New allocations of risk are
                           primarily influenced by amended contract language and defences utilised
                           to shield parties from liability, while various insurance products may offer
                           partial solutions. Limitations on individual parties’ liability are sometimes
                           provided for by contract. Legislatures seek to provide specific relief for
                           certain groups, so that assumptions once valid as to responsibility, burden
                           of proof and remedies available need to be re-thought and verified
                           depending on what contractual documents have been utilised and the
                           applicable law in the jurisdiction. The concluding Part 2 of this article will
                           be published in the next edition of Construction Law International.
                          The boundary between snags and                  or compliance within whatever contractual
                          defects                                         period is provided for before allowing the
                          A tension can exist on a constr uction          contractor to proceed with the remaining
                          project where the employer’s inspectors         work. The FIDIC Conditions of Contract for
                          or owner’s agents identify work as either       Works of Civil Engineering Construction
                          improperly installed or not meeting plans       (4th ed 1987, as amended in 1988 and 1992)
                          and specifications and require its correction   provides for the contractor’s obligation to
Construction Law International Volume 5 Issue 4 December 2010	                                                    13
feature article
‘remedy any defects’ in Clauses 8.1, 13.1,            The contractor could seek to exercise this right
37.4 and 48.1. While the contractor believes          in order to create a record with the owner of
that the work is properly installed and in the        the contractor’s efforts to repair expeditiously.
worst case it is an item to be added to the             Under the FIDIC Conditions of Contract,
punch list and to be addressed after beneficial       the contractor can give notice commencing
occupancy or completed during the warranty            the issuance of the Taking-Over Certificate
period or just prior to the issuance of the           and the entitlement to receive such a
‘Taking-Over Certificate’. The employer may           certificate within 21 days of completion, thus
choose to delay acceptance of the work based          putting pressure on the employer/owner to
on the existence of the defect. Sometimes the         take over the works.
cause of this conflict can be attributed to the         The FIDIC Conditions of Contract for
suspicion that the employer is motivated by           Works of Civil Engineering Construction
the objective of not taking over the works any        (4th ed 1987, as amended in 1988 and 1992)
earlier than necessary so as to shift the cost of     provides in Clause 48.1 for a Taking-Over
upkeep and maintenance to the contractor for          Certificate upon request from the contractor:
as long as possible.                                    ‘When the whole of the Works have
  While the resolution of such conflicts can            been substantially completed and
be important, the outcome is usually                    have satisfactorily passed any Tests on
factually driven and dependent on the                   Completion prescribed by the Contract,
language of the relevant contractual clauses            the Contractor may give a notice to
as well as the availability of a dispute                that effect to the Engineer, with a copy
resolution process that is prompt and                   to the Employer, accompanied by a
readily available.                                      written undertaking to finish with due
  The FIDIC Conditions of Contract for                  expedition any outstanding work during
Works of Civil Engineering Construction                 the Defects Liability Period. Such notice
(4th ed 1987, as amended in 1988 and 1992)              and undertaking shall be deemed to be a
provides in Clause 37.4, Rejection:                     request by the Contractor for the Engineer
  ‘If, at the time and place agreed in accordance       to issue a Taking-Over Certificate in respect
  with Sub-Clause 37.3, the materials or Plant          to the Works. The Engineer shall, within 21
  are not ready for inspection or testing or if, as     days of the date of delivery of such notice,
  a result of the inspection or testing referred        either issue to the Contractor, with a copy
  to in this Clause, the Engineer determines            to the Employer, a Taking-Over Certificate,
  that the materials or Plant are defective             stating the date on which, in his opinion,
  or otherwise not in accordance with the               the Works were substantially completed
  Contract, he may reject the materials or              in accordance with the Contract, or give
  Plant and shall notify the Contractor thereof         instructions in writing to the Contractor
  immediately. The notice shall state the               specifying all the work which, in the
  Engineer’s objections with reasons. The               Engineer’s opinion, is required to be done
  Contractor shall then promptly make good              by the Contractor before the issue of Such
  the defect or ensure that rejected materials          Certificate. The Engineer shall also notify
  or Plant comply with the Contract.’                   the Contractor of any defects in the Works
The operative words are ‘promptly make good             affecting substantial completion that may
the defect’, which usually means the contractor         appear after such instructions and before
has the obligation to proceed without                   completion of the Works specified therein.
substantial delay. The FIDIC Conditions of              The Contractor shall be entitled to receive
Contract for Design-Build and Turnkey (1999             such Taking-Over Certificate within 21 days
edition) provides in Clause 11.5, Removal of            of completion, to the satisfaction of the
Defective Work:                                         Engineer, of the Works so specified and
  ‘If the defect or damage is such that it cannot       remedying any defects as notified.’
  be remedied expeditiously on the Site and the       The engineer is required to notify the
  Employer gives consent, the Contractor may          contractor of any defects in the works affecting
  remove from the Site for the purposes of repair     substantial completion.
  such items of Plant as are defective or damaged.      Consequently, a project with a frequently
  This consent may require the Contractor to          convening disputes resolution board may be
  increase the amount of Performance Security         able to address this issue before it becomes a
  by the full replacement cost of these items, or     major cost.
  to provide other appropriate security.’
14	                                                             Construction Law International Volume 5 Issue 4 December 2010
                        The boundary between latent                      Is the employer/owner’s decision
                        defects and fair wear and tear                   to not have the contractor fix
                                                                         the defect because of a loss of
                        Another source of tension on a construction
                                                                         confidence a failure to mitigate?
                        project is distinguishing between latent
                        defects and fair wear and tear, which            Sometimes the relationship between the
                        would normally occur as a result of use          contractor and the employer/owner has
                        and for which the employer could have            declined to the extent that the employer
                        responsibility both for its incurrence and for   has lost confidence in the contractor’s, or
                        the maintenance costs of addressing this use.    its subcontractor’s or supplier’s, ability to
                        This problem often arises after a Taking-        cure or correct a defect and chooses to have
                        Over Certificate is issued and the employer      someone else perform this work for additional
                        or owner takes beneficial occupancy of           compensation. The contractor may assert as a
                        the works and thus should assume the             defence that the expenditure by the employer
                        responsibility for its use and maintenance.      is not recoverable because the contractor
                        The contractor who may have personnel on         could have had under the relevant subcontract
                        site to perform punch list or warranty work      or purchase order the corrective work
                        may believe that many of the listed defective    performed at no or little additional charge to
                        items of work to be performed are more           the contractor, and that the employer’s actions
                        properly fair wear and tear or maintenance       are an unnecessary expenditure because of
                        work, which is the responsibility of the         a clear failure to mitigate. Such a defence is
                        employer/owner. The FIDIC Conditions             assisted by contractual language providing for
                        of Contract for Works of Civil Engineering       the contractor’s right to cure the defect and
                        Construction (4th ed 1987, as amended            a response by the contractor to notice of the
                        in 1988 and 1992) provides in Clause 49.2        defect that it will cure as soon as permitted.
                        that fair wear and tear is excepted from the     The employer’s position is strengthened by
                        obligation of the contractor to deliver the      the absence of a contractual obligation to
                        works in the condition required by contract.     afford the contractor a right to cure, a failure
                        Likewise, the FIDIC Conditions of Contract       of the contractor to assert a right to cure and
                        for Design-Build and Tur nkey (1999              a history of failed attempts by the contractor,
                        edition) provides in Clause 11.1 Completion      its subcontractor or supplier to address the
                        of Outstanding Work and Remedying                problem successfully. The FIDIC Conditions
                        Defects that fair wear and tear are excepted.    of Contract for Works of Civil Engineering
                        The employer/owner might be withholding          Construction (4th ed 1987, as amended in 1988
                        the Defects Liability Certificate, certificate   and 1992) provides in Clause 49.4, Contractor’s
                        of final completion or acceptance on the         Failure to Carry Out Instructions:
                        basis that the contractor has not addressed         ‘In case of a default on the part of the
                        some of these disputed items. The FIDIC             Contractor in carrying out such instruction
                        Conditions of Contract For Works of Civil           within a reasonable time, the Employer
                        Engineering Construction (4th ed 1987,              shall be entitled to employ and pay other
                        as amended in 1988 and 1992) provides               persons to carry out the same and if such
                        in Clause 61.1, Approval only by Defects            work is work which, in the opinion of the
                        Liability Certificate: ‘only the Defects            Engineer, the Contractor was liable to do
                        Liability Certificate, referred to in Clause        at his own cost under the Contract, then
                        62, shall be deemed to constitute approval          all costs consequent thereon or incidental
                        of the Works.’                                      thereto shall, after due consultation with
                           Under Clause 62.1 the contract shall not         the Employer and the Contractor, be
                        be considered as completed until the                determined by the Engineer and shall
                        Defects Liability Certificate is executed.          be recoverable from the Contractor by
                        Once again the ability to address these             the Employer, and may be deducted by
                        issues through a disputes resolution                the Employer from any monies due or
                        process is dependant on its speed and               to become due to the Contractor and
                        availability. Often such issues are                 the Engineer shall notify the Contractor
                        compromised by contractors in order to              accordingly, with a copy to the Employer.’
                        finish a project and to get its own personnel    The FIDIC Conditions of Contract for Design-
                        and that of its subcontractors and suppliers     Build and Turnkey (1999 edition) provides in
                        off the site.                                    Clause 11.4, Failure to Remedy Defects:
Construction Law International Volume 5 Issue 4 December 2010	                                                        15
feature article
 ‘If the Contractor fails to remedy any              Does the contract require that the corrective
 defect or damage within a reasonable                work be completed within a stated period
 time, a date may be fixed by (or on                 after receipt of notice? Alternatively, does
 behalf of) the Employer on or by which              it give the contractor until the end of the
 the defect or damage is to be remedied.             Defects Liability Period plus 14 days, or until
 The contractor shall be given reasonable            Final Completion of the Project to finish
 notice of this date.’                               the corrective action? Has the contractor
Then the Employer’s alternatives are set forth.      responded promptly to the notice from the
                                                     employer/owner that it is impractical or
                                                     uneconomical to undertake the corrective
The contractor who refuses to fix                    fix at that time because of some verifiable
defective work promptly on the                       factual reason, such as the unavailability
basis that the repair can more                       of replacement parts or the necessar y
economically be performed later                      presence of a factory representative of the
Where circumstances arise that the                   manufacturer which cannot be obtained
employer/owner provides notice of a                  for some time, or the necessity of bringing
construction defect and the contractor               back on site a large crane which would
chooses to wait until sometime later                 more economically occur at some later
to per for m the cor rective work, the               date in conjunction with other work. It
Contractor’s position is dependent in part           then becomes incumbent on the employer/
on the contractual provisions providing for          owner to respond that such delay is not in
such correction. The FIDIC Conditions of             compliance with the contract provisions
Contract for Works of Civil Engineering              and will be a critical controlling delay to
Construction (4th ed 1987, as amended in             either the completion of the project or
1988 and 1992) provides in Clause 49.2,              the carrying out of necessary performance
Completion of Outstanding Work and                   testing or other required functions.
Remedying Defects:                                      Depending on the contractual language and
  ‘To the intent that the Works shall, at            the facts, the employer/owner may be able to
  or as soon as                                                                    justify having the
  practicable after   ‘Where circumstances arise that                              corrective    work
  the expiration                                                                   per formed
  of the Defects
                      the employer/owner provides notice                           by others.
  Liability Period,   of a construction defect and the                               The        FIDIC
  be delivered to                                                                  Conditions      of
  the Employer in     contractor chooses to wait until                             Contract       For
                                                                                   Works of Civil
  the condition       sometime later to perform the                                Engineering
  required by the
  Contract, fair      corrective work, the contractor’s                            Construction
  wear and tear                                                                    provide for such
  excepted, to the
                      position is dependent in part on the                         right in Clause
  satisfaction of     contractual provisions providing for                         49.4; and the
  the Engineer, the                                                                FIDIC Conditions
  Contractor shall:   such correction.’                                            of Contract for
                                                                                   Design-Build and
    (a) complete
                                                     Turnkey provide for such right in Clause
  the work, if any, outstanding on the date
                                                     12.4(a). Alternatively, the contractor may
  stated in the Taking-Over Certificate as soon
                                                     assert that the costs incurred by the
  as practicable after such date, and
                                                     employer/owner were incurred in non-
    (b) execute all such work of amendment,          compliance with the contractual language
  reconstruction, and remedying defects,             and are an unjustified failure to mitigate and
  shrinkages or other faults as the Engineer         can not be recovered from the contractor.
  may, during the Defects Liability Period or        Either way a failure of the participants to
  within 14 days after its expiration, as a result   agree will likely lead to a contractual dispute.
  of an inspection made by or on behalf of the
  Engineer prior to its expiration, instruct the
  Contractor to execute.’
16	                                                           Construction Law International Volume 5 Issue 4 December 2010
                                                                        the objective of such laws is to prevent
‘Giving the contractor the opportunity to                               unnecessary litigation by first requiring
inspect and cure before the employer/owner                              consumers to comply with               statutory
                                                                        procedures. The typical statute will require
undertakes the correction of defects should                             the homeowner to provide the contractor
                                                                        with written notice of the alleged defect,
avoid some unnecessary disputes and thus                                often 60 days or 90 days prior to filing suit. In
should normally be part of the contractual                              most states the legislation provides the
                                                                        contractor with a stated period such as 30
terms and conditions.’                                                  days to request an inspection of the home,
                                                                        offer to repair the defect, negotiate a
                                                                        monetary settlement, or reject the claim
                                                                        altogether and proceed to litigation. If
                        Alternatively the contractor wants              arbitration was called for by the contract,
                        to promptly repair the defect and               such statutes usually preserve this election of
                        the employer/owner wishes the                   disputes resolution procedures. See Darin T
                        work to be performed during a                   Allen, Construction Defects Litigation And
                        plant shut-down which will cost the             The ‘Right To Cure’ Revolution, Construction
                        contractor more                                 Briefings N0.2006-03 (March 2006) and G
                                                                        William Quatman and Herber O Gonzalez,
                        Here the roles are reversed with the            Right-to-Cure Laws Try to Cool Off Condo’s
                        employer/owner not wanting its plant taken      Hottest Claims, 27-5 The Construction Lawyer
                        out of ser vice until a scheduled routine       13 (Summer 2007).
                        maintenance shut-down so as not to lose           What is clear from the enactment of Right
                        revenue, and the delay presumably costing       to Cure legislation, is that giving the
                        the contractor more because of the costs and    contractor the opportunity to inspect and
                        travel expenses to re-mobilise the necessary    cure before the employer/owner undertakes
                        personnel and equipment together with the       the correction of defects should avoid some
                        extended overhead to oversee and support        unnecessary disputes and thus should
                        this operation. The contractor may also be      normally be part of the contractual terms
                        concerned that the delay will increase the      and conditions.
                        fair wear and tear on the effected equipment
                        increasing the replacement work beyond
                        that which should be necessary. Paramount
                                                                         Donald G Gavin is a partner at Akerman Senterfitt
                        is the applicable contractual language,
                                                                         LLP in Vienna, Virginia, US. This paper was utilised by
                        the notices and responses provided by the
                                                                         the author as part of his participation in the ICP
                        employer/owner and the contractor, and           Subcommittee presentation at the IBA Annual
                        how compelling are the facts that can be         Conference in Vancouver in October 2010.
                        raised by both.
                          Because such factual circumstances create
                        significant potential disputes, contracts
                        often provide some fairly detailed
                        obligations on the parties. The FIDIC
                        Conditions of Contract for Work of Civil
                        Engineering Construction Clauses 13.1,
                        37.4, 48.1 and 49.2 are relevant and under
                        the FIDIC Conditions of Contract for
                        Design-Build and Turnkey Clauses 11.1,
                        11.2 and 11.4 are relevant.
                          Another approach has been taken in the
                        United States by approximately half of the
                        states which have enacted legislation
                        providing for ‘right to cure’, or ‘notice and
                        opportunity to repair’ rights. Such statutes
                        are generally applicable to home building
                        and do not deprive homeowners of any
                        remedy they would otherwise have. Instead,
Construction Law International Volume 5 Issue 4 December 2010	                                                                17