Gaisano 7th Billing

This document is a request from a construction company to their client, Gaisano City, for the 8th billing of a construction project. It explains that construction has been on hold for two months due to the pandemic lockdown and requests the release of 50% of retention funds to help cover costs and allow work to resume. It provides details of the project cost, previous billings issued, and amounts paid. The total amount requested for the 8th billing is PHP 200,000 which is 5% of the total project cost.

Uploaded by

RamilArtates
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
67 views1 page

Gaisano 7th Billing

This document is a request from a construction company to their client, Gaisano City, for the 8th billing of a construction project. It explains that construction has been on hold for two months due to the pandemic lockdown and requests the release of 50% of retention funds to help cover costs and allow work to resume. It provides details of the project cost, previous billings issued, and amounts paid. The total amount requested for the 8th billing is PHP 200,000 which is 5% of the total project cost.

Uploaded by

RamilArtates
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

◙ ENGINEERS ◙ BUILDERS ◙ CONTRACTORS ◙

RENDON BUILDING, LEGASPI STREET, ROXAS CITY, CAPIZ


TEL. NO.: (036) 6217-802/(036)6431-831
Mob. No.: +639196319591
Email:ramilsartates@gmail.com
___________________________________________________________________________________________________
May 18, 2020

To:
The Manager
GAISANO CITY
Arnaldo Boulevard
Roxas City, Capiz

Sudject: Request for 8th Billing (50% of Retention) 5% of Total Cost

Sir/Madam:

This is in reference to the above mentioned subject Re:Request for 8th Billing
(50% of Retention or 5% of Total Project Cost). Please be informed that the
Construction of 11-Units Stalls Building located along Gaisano arcade, Arnaldo
Blvd., Roxas City is still on-going as of the moment and the project has Ceased for
almost Two (2) Months due to the Corona virus Pandemic and The City Government,
Requested Us to stop Because of the order of National Government to comply for the
Enhanced Community Quarantine (ECQ), With this, May I request your good office to be
Considerate enough to release 50% of the Retention Payment for Us to finish the
project the soonest time (for our Finances was exhausted due to two Months work
stoppage). With this, I am appealing to you and your good office to consider this
request and so we can finish the project the soonest time.

DESCRIPTION PERCENTAGE DONE % AMOUNT


CONTRACT PRICE 4,000,000.00
st
1 Billing (Down payment) 20.00% 20.00% 800,000.00
2nd Billing 35.94% 15.94% 637,600.00
3rd Billing 50.54% 14.60% 584,000.00
4th Billing 63.05% 12.51% 500,400.00
5TH Billing 73.79% 10.74% 429,600.00
6th Billing 86.75% 12.96% 518,400.00
7th Billing 90.00% 03.25% 130,000.00
8th Billing 95.00 % 5.00% 200,000.00
TOTAL AMOUNT DUE FOR 8th BILLING Php200,000.00

Very truly yours,

ENGR. RAMIL S. ARTATES

We Build your building /Structure upon a ROCK