                                                                                       May 18, 2020
To:
The Manager
GAISANO CITY
Arnaldo Boulevard
Roxas City, Capiz
Sudject: Request for 8th Billing (50% of Retention) 5% of Total Cost
Sir/Madam:
       This is in reference to the above mentioned subject Re:Request for 8th Billing
(50% of Retention or 5% of Total Project Cost). Please be informed that the
Construction of 11-Units Stalls Building located along Gaisano arcade, Arnaldo
Blvd., Roxas City is still on-going as of the moment and the project has Ceased for
almost Two (2) Months due to the Corona virus Pandemic and The City Government,
Requested Us to stop Because of the order of National Government to comply for the
Enhanced Community Quarantine (ECQ), With this, May I request your good office to be
Considerate enough to release 50% of the Retention Payment for Us to finish the
project the soonest time (for our Finances was exhausted due to two Months work
stoppage). With this, I am appealing to you and your good office to consider this
request and so we can finish the project the soonest time.
                  DESCRIPTION                       PERCENTAGE DONE            %     AMOUNT
     CONTRACT PRICE                                                              4,000,000.00
   st
  1 Billing (Down payment)                               20.00%         20.00%    800,000.00
  2nd Billing                                            35.94%         15.94%    637,600.00
  3rd Billing                                            50.54%         14.60%    584,000.00
  4th Billing                                            63.05%         12.51%    500,400.00
  5TH Billing                                            73.79%         10.74%    429,600.00
  6th Billing                                            86.75%         12.96%    518,400.00
  7th Billing                                            90.00%         03.25%    130,000.00
  8th Billing                                           95.00 %          5.00%    200,000.00
    TOTAL AMOUNT DUE FOR 8th BILLING                                   Php200,000.00