Carriage of Materials Data Sheet No 1 For Analysis of Rates: Code Unit Rate Day Day Day Litre Litre

This document provides a data sheet for analyzing transportation rates for carriage of materials. It includes rates for hiring trucks, labor, and fuel consumption over varying distances. The sheet calculates the total cost per trip over increasing distances from 1 to 30 kilometers, including costs of diesel, mobile oil, labor and truck hire charges. The cost per trip increases with distance but the rate of increase declines after 20 kilometers.

Uploaded by

Ratnesh Patel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
169 views14 pages

Carriage of Materials Data Sheet No 1 For Analysis of Rates: Code Unit Rate Day Day Day Litre Litre

This document provides a data sheet for analyzing transportation rates for carriage of materials. It includes rates for hiring trucks, labor, and fuel consumption over varying distances. The sheet calculates the total cost per trip over increasing distances from 1 to 30 kilometers, including costs of diesel, mobile oil, labor and truck hire charges. The cost per trip increases with distance but the rate of increase declines after 20 kilometers.

Uploaded by

Ratnesh Patel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 14

CARRIAGE OF MATERIALS

Data Sheet No 1 for Analysis of Rates


1.1 By Mechanical Transport including loading, unloading and stacking:
Code Name Unit Rate
84 Hire charges of truck without POL Day 1460
114 Beldar Day 368
115 Coolie Day 368
Market rate High Speed Diesel Litre 56.72
5001 Mobile Oil Litre 245

No. of KM Liter of Cost of Cost of


Nos of
done in diesel Diesel mobil oil
Trips
Lead ( IN KM) Average Speed ( S) IN KM one day consumed (1235) consumed
N=8/
liter @5km per @ Rs. per @ 140 km
(2L/S)+1
( 2NL+6) liter Litre per Litre

1 2 3 4 5 6 7
1 16.00 7.11 20.22 4.04 229.40 0.144
2 17.00 6.48 31.90 6.38 361.93 0.228
3 17.50 5.96 41.74 8.35 473.55 0.298
4 18.00 5.54 50.31 10.06 570.69 0.359
5 18.50 5.19 57.93 11.59 657.16 0.414
6 19.00 4.90 64.84 12.97 735.53 0.463
7 19.50 4.66 71.19 14.24 807.63 0.509
8 20.00 4.44 77.11 15.42 874.75 0.551
9 20.50 4.26 82.68 16.54 937.87 0.591
10 21.00 4.10 87.95 17.59 997.72 0.628
11 21.50 3.95 92.99 18.60 1054.86 0.664
12 22.00 3.83 97.83 19.57 1109.74 0.699
13 22.50 3.71 102.49 20.50 1162.70 0.732
14 23.00 3.61 107.02 21.40 1214.03 0.764
15 23.50 3.51 111.42 22.28 1263.95 0.796
16 24.00 3.43 115.71 23.14 1312.66 0.827
17 24.50 3.35 119.91 23.98 1360.31 0.857
18 25.00 3.28 124.03 24.81 1407.03 0.886
19 25.50 3.21 128.08 25.62 1452.93 0.915
20 26.00 3.15 132.06 26.41 1498.10 0.943
21 26.50 3.09 135.99 27.20 1542.62 0.971
22 27.00 3.04 139.86 27.97 1586.56 0.999
23 27.50 2.99 143.69 28.74 1629.99 1.026
24 28.00 2.95 147.47 29.49 1672.94 1.053
25 28.50 2.90 151.22 30.24 1715.47 1.080
26 29.00 2.86 154.94 30.99 1757.62 1.107
27 29.50 2.83 158.62 31.72 1799.42 1.133
28 30.00 2.79 162.28 32.46 1840.89 1.159
29 30.50 2.76 165.91 33.18 1882.08 1.185
30 31.00 2.73 169.52 33.90 1922.99 1.211
Notes
1 Number of trips in working day of 8 hours N=8/{(2L/S)+1)}. Where L=Lead in Km., S=Speed in Km.per hour, 1 hour is
2 Consumption of diesel taken at 5 Km. per litre.
3 Consumption of mobile oil taken at 140 Km. per litre.
4 In column 4 of 'km done' an allowance of 6.0 km has been made for movement of truck from parking place to duty &
5 (i) Cost of diesel @ (1235) per litre
(ii) Cost of mobile oil @(5001) per litre
(iii) Hire charges of truck @ (0084) for a day of 8 hours.
Average
Hiring
Cost of Cost of 6 Increase Cost per
Charges Cost Per
mobil oil Beldar Total Cost of cost per additional
of Truck trip
(5001) (0114) 6+8+9+ KM over KM after
(0084) @ Col.11/Col
@ Rs. per @ Rs. per 10 IN INR previous first 5 10
Rs. per .3 IN INR
Litre day KM In INR 20 KM In
day
INR

8 9 10 11 12 13 14
35.39 2208.00 1460.00 3932.79 553.05
55.83 2208.00 1460.00 4085.76 630.89
73.05 2208.00 1460.00 4214.60 707.45
88.04 2208.00 1460.00 4326.73 781.21
101.38 2208.00 1460.00 4426.53 852.41
113.47 2208.00 1460.00 4517.00 921.23 68.82
124.59 2208.00 1460.00 4600.21 987.87 66.64
134.94 2208.00 1460.00 4677.69 1052.48 64.61 64.76
144.68 2208.00 1460.00 4750.55 1115.22 62.74
153.91 2208.00 1460.00 4819.63 1176.22 61.00
162.73 2208.00 1460.00 4885.59 1235.60 59.38
171.20 2208.00 1460.00 4948.93 1293.47 57.87
179.37 2208.00 1460.00 5010.07 1349.93 56.46
187.28 2208.00 1460.00 5069.31 1405.08 55.15
194.99 2208.00 1460.00 5126.94 1459.00 53.91
53.64
202.50 2208.00 1460.00 5183.16 1511.76 52.76
209.85 2208.00 1460.00 5238.16 1563.43 51.67
217.06 2208.00 1460.00 5292.09 1614.09 50.66
224.14 2208.00 1460.00 5345.06 1663.78 49.70
231.11 2208.00 1460.00 5397.20 1712.57 48.79
237.97 2208.00 1460.00 5448.59 1760.51 47.94
244.75 2208.00 1460.00 5499.32 1807.65 47.13
251.45 2208.00 1460.00 5549.44 1854.02 46.37
258.08 2208.00 1460.00 5599.02 1899.67 45.65
264.64 2208.00 1460.00 5648.11 1944.64 44.97
44.78
271.14 2208.00 1460.00 5696.76 1988.96 44.32
277.59 2208.00 1460.00 5745.01 2032.66 43.71
44.78

283.99 2208.00 1460.00 5792.88 2075.78 43.12


290.34 2208.00 1460.00 5840.42 2118.35 42.57
296.65 2208.00 1460.00 5887.65 2160.39 42.04

ed in Km.per hour, 1 hour is allowed for loading / unloading.

rom parking place to duty & back.


1.0 Carriage Of Materials
1.1 By Mechanical Transport including, loading, unloading and stacking
Cost Per Trip Per Unit i/c 1

Net 12 of data sheet


quantity Net qua
CP &
payble
Capacity Unit of Over 1 KM
Code Material after
Per Trip Rates Head @
deduction
15 %
for
looseness

1 2 3 4 5 6 7
1.1.1 Lime, moorum, Building rubish 8 8 cum 0.15 79.50
1.1.2 Earth 8 6.4 cum 0.15 99.38
1.1.3 Manure/Sludge 8 7.36 cum 0.15 86.41
1.1.4 Excavated rock 8 4 cum 0.15 159.00
1.1.5 Sand stone aggregate below 40mm nominal size
8 8 cum 0.15 79.50
1.1.6 Stone aggregate 40mm nominal size and above
8 7.36 cum 0.15 86.41
1.1.7 Soling stone 8 6.8 cum 0.15 93.53
1.1.8 Brick 3000 3000 1000 nos 0.15 212.00
1.1.9 Brick tiles 5000 5000 1000 nos 0.15 127.20
1.1.10 Cement, Stone block, G.I..C.I., A.C., & C.C.
Pipes below 100 mm dia & other heavy materials 9 9 Tonne 0.15 70.67

1.1.11 Steel 9 9 Tonne 0.15 70.67


1.1.12 Timber 7 7 cum 0.15 90.86
1.1.13 Tar Bitumen 8 8 Tonne 0.15 79.50
1.1.14 Solvent and diesel 80 80 Qtl 0.15 7.95
1.1.15 Steam coal 7 7 Tonne 0.15 90.86
1.1.16 SW Pipe
16.1 100 mm Dia 600 600 100 m 0.15 106.00
16.2 150 mm Dia 300 300 100 m 0.15 212.00
16.3 200 mm Dia 180 180 100 m 0.15 353.34
16.4 250 mm Dia 105 105 100 m 0.15 605.72
16.5 300 mm Dia 84 84 100 m 0.15 757.15
16.6 350 mm Dia 60 60 100 m 0.15 1060.01
16.7 400 mm Dia 42 42 100 m 0.15 1514.30
16.8 450 mm Dia 33 33 100 m 0.15 1927.29
16.9 500 mm Dia 30 30 100 m 0.15 2120.02
16.10 600 mm Dia 24 24 100 m 0.15 2650.02
17.0 RCC Pipe, AC Pipes, Steel cylinder, RC Pipes, CI
Pipes, CI Pipes & unreinforced cement pipe
17.1 100 mm Dia 366 366 100 m 0.15 173.77
17.2 125 mm Dia 274 274 100 m 0.15 232.12
17.3 150 mm Dia 219.6 219.6 100 m 0.15 289.62
17.4 200 mm Dia 135 135 100 m 0.15 471.12
17.5 250 mm Dia 95 95 100 m 0.15 669.48
17.6 300 mm Dia 76.86 76.86 100 m 0.15 827.49
17.7 350 mm Dia 54.9 54.9 100 m 0.15 1158.48
17.8 400 mm Dia 40.26 40.26 100 m 0.15 1579.75
17.9 450 mm & 500 mm Dia 32.94 32.94 100 m 0.15 1930.80
17.10 600, 700, 750 & 800 mm Dia 21.96 21.96 100 m 0.15 2896.20
17.1 900 mm Dia 14.64 14.64 100 m 0.15 4344.30
17.12 1000, 1100 & 1200 mm Dia 10.98 10.98 100 m 0.15 5792.40
ost Per Trip Per Unit i/c 15% CP & OH
Cost Per trip as per col.
2 of data sheet
Net quantity payble `
Beyond Beyond Beyond
2KM 3 KM 4 KM 5 KM 5km up to 10km up 20km per
Remarks
10 km per to 20 km ADDL.
KM per KM per KM

8 9 10 11 12 13 14
90.69 101.70 112.30 122.53 9.31 7.71 6.44
113.36 127.12 140.37 153.17 11.64 9.64 8.05
98.58 110.54 122.06 133.19 10.12 8.38 7.00
181.38 203.39 224.60 245.07 18.62 15.42 12.87

90.69 101.70 112.30 122.53 9.31 7.71 6.44

98.58 110.54 122.06 133.19 10.12 8.38 7.00

106.69 119.64 132.12 144.16 10.95 9.07 7.57


241.84 271.19 299.47 326.76 24.83 20.56 17.17
145.10 162.71 179.68 196.05 14.90 12.34 10.30

80.61 90.40 99.82 108.92 8.28 6.85 5.72

80.61 90.40 99.82 108.92 8.28 6.85 5.72


103.65 116.22 128.34 140.04 10.64 8.81 7.36
90.69 101.70 112.30 122.53 9.31 7.71 6.44
9.07 10.17 11.23 12.25 0.93 0.77 0.64
103.65 116.22 128.34 140.04 10.64 8.81 7.36

120.92 135.59 149.73 163.38 12.41 10.28 10.28


241.84 271.19 299.47 326.76 24.83 20.56 20.56
403.07 451.98 499.11 544.59 41.38 34.27 34.27
690.97 774.83 855.62 933.59 70.93 58.74 58.74
863.72 968.53 1069.52 1166.99 88.66 73.43 73.43
1209.20 1355.95 1497.33 1633.78 124.13 102.80 102.80
1727.44 1937.07 2139.04 2333.97 177.33 146.86 146.86
2198.55 2465.36 2722.42 2970.51 225.69 186.91 186.91
2418.41 2711.90 2994.66 3267.56 248.26 205.60 205.60
3023.01 3389.87 3743.32 4084.45 310.32 257.00 257.00
198.23 222.29 245.46 267.83 20.35 16.85 14.07
264.79 296.92 327.88 357.76 27.18 22.51 18.80
330.38 370.48 409.11 446.39 33.91 28.09 23.45
537.42 602.64 665.48 726.12 55.17 45.69 38.15
763.71 856.39 945.68 1031.86 78.40 64.93 54.21
943.95 1058.51 1168.87 1275.39 96.90 80.25 67.00
1321.54 1481.91 1636.42 1785.55 135.66 112.35 93.80
1802.09 2020.79 2231.49 2434.84 184.99 153.21 127.91
2202.56 2469.85 2727.37 2975.92 226.10 187.25 156.34
3303.84 3704.78 4091.06 4463.88 339.15 280.88 234.51
4955.76 5557.17 6136.59 6695.82 508.72 421.32 351.77
6607.68 7409.56 8182.12 8927.76 678.30 561.75 469.02
Rate
Note : Considering 200 Km lead of all the Material in whic
Unit Distance

Sandy Track (
Distance
S.No Description Should
Increased by
40)

14
1.1.1 Lime, moorum, Building rubish cum 19.6
Up to 5 KM
Up to 5 TO 30KM
Up to 5 KM
1.1.2 Earth cum
1.1.3 Manure/Sludge cum
1.1.4 Excavated rock cum
1.1.5 Sand stone aggregate below 40mm nominal size cum
1.1.6 Stone aggregate 40mm nominal size and above cum
1.1.7 Soling stone cum
1.1.8 Brick 1000 nos
1.1.9 Brick tiles 1000 nos
1.1.10 Cement, Stone block, G.I..C.I., A.C., & C.C. Pipes below 100 mm dia &
other heavy materials Tonne
1.1.11 Steel Tonne
1.1.12 Timber cum
1.1.13 Tar Bitumen Tonne
1.1.14 Solvent and diesel Qtl
1.1.15 Steam coal Tonne
1.1.16 SW Pipe
16.1 100 mm Dia 100 m
16.2 150 mm Dia 100 m
16.3 200 mm Dia 100 m
16.4 250 mm Dia 100 m
16.5 300 mm Dia 100 m
16.6 350 mm Dia 100 m
16.7 400 mm Dia 100 m
16.8 450 mm Dia 100 m
16.9 500 mm Dia 100 m
16.1 600 mm Dia 100 m
17 RCC Pipe, AC Pipes, Steel cylinder, RC Pipes, CI Pipes, CI Pipes &
unreinforced cement pipe
17.1 100 mm Dia 100 m
17.2 125 mm Dia 100 m
17.3 150 mm Dia 100 m
17.4 200 mm Dia 100 m
17.5 250 mm Dia 100 m
17.6 300 mm Dia 100 m
17.7 350 mm Dia 100 m
17.8 400 mm Dia 100 m
17.9 450 mm & 500 mm Dia 100 m
17.1 600, 700, 750 & 800 mm Dia 100 m
17.11 900 mm Dia 100 m
17.12 1000, 1100 & 1200 mm Dia 100 m

Note
Rates of Materials
f all the Material in which 14 Km is consider as sandy track & 2 km is consider as cart track
Distance

Cart Track
( Distance Metal Track
Should ( No Total Cost Per Total Basic Blasting Crushing Loading
Increased Allowance ) Distance KM Cost Cost Charges Charges Charges
by 10)

2 0
2.2 184 205.8
art track

Unloading Stacking Segniorage Total


Charges Charges Charges Cost