Project: Baladna Dairy Farm Phase-2: Definition of Inspection and Test Plan Symbols

The document defines the symbols used in an inspection and test plan for a dairy farm project. It provides definitions for hold points, witness points, surveillance points, and review points. Work cannot proceed beyond hold points without approval, while it can continue after witness points without notification. Surveillance points allow inspection of ongoing work and documentation. Review points require available quality records for verification before work can continue.

Uploaded by

Melih SENTURK
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
81 views2 pages

Project: Baladna Dairy Farm Phase-2: Definition of Inspection and Test Plan Symbols

The document defines the symbols used in an inspection and test plan for a dairy farm project. It provides definitions for hold points, witness points, surveillance points, and review points. Work cannot proceed beyond hold points without approval, while it can continue after witness points without notification. Surveillance points allow inspection of ongoing work and documentation. Review points require available quality records for verification before work can continue.

Uploaded by

Melih SENTURK
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Employer :

Engineer :
PROJECT: BALADNA DAIRY FARM PHASE-2 Consultant :
Contractor :

DEFINITION OF INSPECTION AND TEST PLAN SYMBOLS

"H" HOLD POINT - A Point beyond which work shall not proceed with out formal approval from the Engineer.
Inspection for Hold Points shall be notified to the Engineer through Inspection Requests.

"W" WITNESS POINT - A Point beyond which work can proceed without formal approval from the Engineer.
Inspection for witness points will not be notified to any of the inspection parties.

"S" SURVEILLANCE POINT - A Point where inspection parties may carry-out surveillance of work in progress
and relevant documentation without any notification.

"R" REVIEW POINT - A Point where appropriate quality records shall be available for verification.
Work can proceed if all the documents are appropriate as per project requirements.

"M" MANDATORY POINT - A Mandatory activity to be carried-out by the contractor as per contractual requirement.

"NA" - Not Applicable