                                    Muhammad Asam Zia
    www.linkedin.com/in/muhammad-   Lean Manufacturing, Engineering, Procurement, Design and Project
    asam-zia-b7186a3a (LinkedIn)    Management
                                    Pakistan
    Top Skills
    5S                              Summary
    Continuous Improvement
                                    Experience of leadership, change management, project
    FMCG
                                    management, manufacturing, supply chain management.
                                    Engineering background coupled with business and management
                                    acumen gives unique blend of critical analysis skill that are proved
                                    through successful deliveries of complex projects and turning around
                                    factory performance
                                    Specialist of cost reduction, manufacturing, operations and project
                                    management
                                    Experience of developing strategies, business continuity plans,
                                    feasibilities for projects, manufacturing support for new launches
                                    Experience in leading and maintaining industrial peace and harmony
                                    for increased productivity and production whilst exceeding KPI’s and
                                    bringing environmental hazard to a minimum
                                    Extensive Leadership & recruiting experience as part of senior team
                                    of leading manufacturing firm
                                    Full time People & Career Management experience including
                                    mentoring, coaching & performance management
                                    Experience
                                    PHILIP MORRIS (PAKISTAN) LIMITED
                                    10 years 1 month
                                    Engineering Manager
                                    June 2014 - April 2016 (1 year 11 months)
                                    Sahiwal
                                    Managing multi-million USD annual budget (FME) for the factory operation and
                                    capacity enhancement project budget (CapEx) of multi –million USD
                                    Heading the entire Engineering operations including, Maintenance, projects,
                                    Asset Management, Inventory management, Legal compliance
                                    Increased manufacturing reliability by enhanced utilities uptime and
                                    productivity initiatives
                                                                      Page 1 of 4
                                               
    Devising financial strategies to ensure cost avoidance and ensuring reduction
    in FME costs through controlled growth in organization
    Implementation of lean manufacturing tools, increased performance through
    continuous engagement of workforce, implementation of literacy program for
    illiterate workforce whilst induction of skilled labour and phasing out of illiterate
    workforce to ensure maximum output
    Development & implementation of preventative maintenance plans which
    resulted in increased factory uptime and reduced the maintenance cost
    Planning and implementation of Business Continuity Plans, including planning
    and execution of capacity enhancement projects of multi-million USD.
    Successfully met and exceeded production targets within the defined
    parameter such as quality, productivity, cost, safety, delivery time, industrial /
    environmental health, continuous improvement spirit and at given budget
    which resulted in factory being declared as most cost effective production
    centre in Pakistan
    Implementation of Environment, Health & Safety procedures and ISO
    certification of the factory
    Manager Planning & Execution Project IBEX
    April 2012 - May 2014 (2 years 2 months)
    Karachi
    Planning and Budgeting of complete project of USD 56 Mio including
    infrastructure development, Design Engineering, administration & technical
    permitting, Building , Utilities, Information services, security,process equipment
    Detail engineering design of project including civil, mechanical & electrical by
    3rd party and in-house validation by project team by coordination with regional
    team to ensure compliance with PMI procedures
    Developed strategy to minimize the project execution timeline and cost.
    Established, hired and completed project organization for brown field project in
    Kotri & Sahiwal
    Achieved one million safe man-hours without any accident during coarse of
    execution of project
    Responsible for making strategies for fund disbursements based on criticality
    of activities and output, ensuring the project deadline is met
    Ensuring Project Execution Plan incorporates best practices for project
    reporting and Project Control (cost & time) and coordination with technical and
    execution departments
    Completed brown field project of Kotri factory which includes installation of new
    primary line worth USD 32 Mio in committed timeline and budget
                                         Page 2 of 4
                                             
    Completed utilities upgrade including, electrical infrastructure upgrade,
    generators, boilers, compressors, WWTP, air-conditioning in Sahiwal worth
    USD 8 Mio.
    Contractor Management for the complete project
    Contract management for the complete project
    Subject Matter Expert Factory Operations (SAP-P1 Implementation)
    January 2012 - March 2012 (3 months)
    Karachi
    Aligned local SAP system with PMI SAP system
    Developed existing process mapping system for factories.
    Developed to be process mapping for factories without conflict.
    Factory Engineer
    July 2011 - December 2011 (6 months)
    Sahiwal
    Developed strategy for preventive maintenance of utilities
    Ensured continuous supply of electricity, compressed air, steam, vacuum,
    chilled water to the factory without breakdown
    Devised a backup utility strategy to ensure proper utilization of assets by
    capacity management.
    Managed & completed factory capex projects of $ 5 Mio.
    Responsible for setting milestones and KPI’s to measure engineering
    performance and efficiency
    Manager Primary Processing
    July 2009 - June 2011 (2 years)
    Sahiwal
    Devised strategy to operate primary at its maximum capacity due to loss of
    Karachi factory by supporting organization to deliver production targets without
    any loss to the market share.
    Developed organizational capability equipped with blend of soft and technical
    skills by mentoring and project assignments to ensure quality talent available
    to cater market requirements.
    Development and implementation of STPs for primary processing to accurately
    forecast production requirements to avoid inventory cost
    Implemented lean manufacturing techniques to maximize business
    advantages and consistently improved primary yield starting from 103% to
    104%
                                       Page 3 of 4
                                            
    Initiated short recovery addback from secondary to maximize use of tobacco
    for improved performance of tobacco utilization and minimizing tobacco
    wastage
    Implemented ripper yield monitoring and mass balance exercise to gauge
    accountable and unaccountable losses for improved manufacturing
    performance
    Achieved best KPIs for primary processing in Pakistan for year 2011
    Managed machinery upgrade project in primary for $ 1.0 Mio
    Planned activities and implemented product traceability system and
    successfully achieved intertek license for export to KSA market.
    Assistant Manager Primary Processing
    July 2007 - June 2009 (2 years)
    Sahiwal
    Daily production plan development based on SKUs volume to accurately cater
    secondary requirements by assuring zero downtime due to unavailability of
    cutfiller
    Developed and implemented preventive maintenance plan and primary uptime
    monitoring system to guage efficiency of preventive maintenance plans
    Developed a system for KPI monitoring on daily basis and used analytical
    techniques to measure favourable and unfavourable elements through PDCA.
    Management Trainee
    April 2006 - June 2007 (1 year 3 months)
    Sahiwal
    Process mapping of factory.
    5S implementation
    Poka Yoke implementation
    Kanban implementation
    Education
    University of Engineering and Technology, Lahore
    Bachelor of Engineering (BE), Industrial & Manufacturing · (2002 - 2006)