FEED: Dahej Project
S.No Scope items
1 Safety
a Hazop studies (HS1, HS2, HS3)
b QRA-Storage tanks and Reactor
c Hazardous Area classification
e Fire fighting resource including philosophy
f OBRA
2 Process
a PFD's for process & utilities
b P&ID's for process & utilities
c Process description & operating philosophy
d Heat & Mass balance calculation (basic)
e Equipment process data sheet-MPI
f Instrument process data sheet
g Packaged unit functional specifications
h Emergency shutdown philosophy (ESD), ONEP
i Relief study-RST, scrubber, relief valves
3 Mechanical
a Equipment general specifications-MPI
b Equipment data sheet-MPI
c RFQ (Requisition for quotation)-MPI
d Technical bid tabulation
4 Plant Layout
a General plot layout
b Plan view (floor wise plan)
c Elevation view
5 Piping & Installation
a Piping line diagram
6 Piping/Material
a General specifications for piping material
b Piping Material Class Specifications
c Standard drawings for piping
d Piping MTO
e Piping stress design basis
7 Intrumentation & Control
a Instruments general specification
b Instrument data sheets
c Systems specifications and architecture and drawings
d Systems I/O count
e Cable routing drawings
f Control room location & design
g Control system display philosophy
8 Electrical
a Single line diagram
b Electrical consumers list
c Equipment general specification
d Equipment data sheet
e Design of standard equipment (MPI) with drawings
f bulk MTO of cables upto PCC
g Equipment arrangement drawings
h Cable routing drawings
i Electrical fault calculation & load calculation
j Solar plant provision in electrical design
9 Civil:
a Soil investigation specification
b Design specifications for foundation
c Design specifications for superstructure
d Tender document for civil work
e Steel & concrete costing on floor plan layout
f Foundation drawings for main building
g Building architecture drawing
h Civil material BOQ (materia take-off)
10 Utility
a Boiler basic specifications
b Nitrogen requirement
c Raw water storage & filtration basic design
d Cooling tower secifications
e AO chiller specifications
f Air compressor specifications
g Utility tanks, Chimney requirement
11 ETP
a Basic design, including sizing, hydraulic calculation
b Primary, secondary & tertiary treatment basic
c HFD (Hydraulic flow diagram)
d Treatability study
e Technology selection & design
12 SUSOP
a Boiler design for non fossil fuel (baggase)
b Green electricity from outside
c Solar PV-onsite
d Green building certification
e Digitilization (Industry 4.0)
13 Quality standards
a Assessment for Excipact
b Clean room basis, Bird net, rapid door
c Water purification & piping MOC
d CIP
e Lab capability
14 Bulk tankfarm
a Sizing & MOC (layout)
b Count of tanks for manufacturing/process
c Automation for storage tanks