I.
Construction Phase
A. Construction Schedule Management
GRAPHICAL SCHEDULE
WORK START END
GENERAL REQUIREMENTS MARCH 1, 2020 MARCH 7, 2020
ON-SITE WATER/SEWER MARCH 8, 2020 MARCH 28, 2020
EXCAVATION & MARCH 28, 2020 MAY 7, 2020
EARTHWORKS
STRUCTURAL WORKS: APRIL 28, 2020 JULY 21, 2020
GROUND FLOOR TO 10TH
FLOOR
STRUCTURAL WORKS: JULY 21, 2020 JULY 28, 2020
ROOFDECK
PLUMBING APRIL 28, 2020 JULY 21, 2020
ELECTRICAL APRIL 28, 2020 JULY 21, 2020
MECHANICAL APRIL 28, 2020 JULY 21, 2020
FINISHING: WINDOWS/ JULY 21, 2020 AUGUST 21, 2020
EXTERIOR DOORS
FINISHING: EXTERIOR JULY 21, 2020 AUGUST 21, 2020
FINISHING JULY 21, 2020 AUGUST 21, 2020
INSULATION
FINISHING: JULY 21, 2020 AUGUST 21, 2020
DRYWALL/PLASTER
FINISHING: INTERIOR JULY 28, 2020 SEPTEMBER 7, 2020
FINISH