The document contains a model estimate for a well that includes details of the earth work, brick work, and flooring. It lists 6 depths of excavation totaling 28.26 cubic meters of earth work. It also lists the brick work at 15.83 cubic meters using clay fly ash bricks. The flooring is listed at 4.87 square meters using common burnt clay bricks. Abstract costs are provided for the earth work at Rs. 3673.8, brick work at Rs. 71215.2, and total estimated cost of Rs. 74889.

Uploaded by

kumardavid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
660 views2 pages

Model Estimate Well

The document contains a model estimate for a well that includes details of the earth work, brick work, and flooring. It lists 6 depths of excavation totaling 28.26 cubic meters of earth work. It also lists the brick work at 15.83 cubic meters using clay fly ash bricks. The flooring is listed at 4.87 square meters using common burnt clay bricks. Abstract costs are provided for the earth work at Rs. 3673.8, brick work at Rs. 71215.2, and total estimated cost of Rs. 74889.

Uploaded by

kumardavid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

MODEL ESTIMATE OF WELL

SN DESCRIPTION L B H Qty. REMARK

Earth work in soil within 50m Initial lead and 1.5m initial lift
1
including rough dressing and braking of clods to maximum 5 -
7 cm size as directed by the engineer in charge
1st depth = p/4 x (2.00 m)2 x 1.50 m = 4.710 cum 0.785 4 1.5 4.71
2nd depth = p/4 x (2.00 m)2 x 1.50 m = 4.710 cum 0.785 4 1.5 4.71
3rd depth = p/4 x (2.00 m)2 x 1.50 m = 4.710 cum 0.785 4 1.5 4.71
4th depth = p/4 x (2.00 m)2 x 1.50 m = 4.710 cum 0.785 4 1.5 4.71
5th depth = p/4 x (2.00 m)2 x 1.50 m = 4.710 cum 0.785 4 1.5 4.71
6th depth = p/4 x (2.00 m)2 x 1.50 m = 4.710 cum 0.785 4 1.5 4.71
Total Qty 28.26
Brick work with clay flyash F.P.S. (non modular) brick of class
2
designation 7.5 .
Cement mortar 1:6 (1 cement : 6 Coarse sand) 6.28 7.2 0.35 15.83
Total Qty 15.83

Brick on edge flooring with bricks of class designation 7.5 on


3 a bed of 12 mm cement mortar, including filling the joints
with same mortar, withcommon burnt clay non modular
bricks: Plateform for bathing
1:6 (1cement : 6 coarse sand) 3.14 3.24 10.1736 1.8
Deduction Well portion -3.14 1.69 -5.3066
Total Qty 4.87

ABSTRACT OF COST
SN DESCRIPTION UNIT QTY RATE AMOUNT REMARK

Earth work in soil within 50m Initial lead and 1.5m initial lift
including rough dressing and braking of clods to maximum 5 - CUM 28.26 130 3673.8
7 cm size as directed by the engineer in charge
1
Brick work with clay flyash F.P.S. (non modular) brick of class
CUM 15.83 4500 71215.2
2 designation 7.5 . (@460 BRICKS / Cum) 7279.776
74889
29955.6
pi R2