0% found this document useful (0 votes)
422 views2 pages

Multi-Purpose Building Construction Plan

This document provides detailed calculations on the cost of providing safety and health programs for a construction project to repair and rehabilitate local infrastructure. It lists the various safety equipment needed such as helmets, shoes, vests, gloves, etc. for each job classification and item of work, along with the quantity of workers and days required to complete each task. The total cost can be determined from these inputs to ensure adequate budget for construction worker safety.

Uploaded by

Momie Marquez
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
422 views2 pages

Multi-Purpose Building Construction Plan

This document provides detailed calculations on the cost of providing safety and health programs for a construction project to repair and rehabilitate local infrastructure. It lists the various safety equipment needed such as helmets, shoes, vests, gloves, etc. for each job classification and item of work, along with the quantity of workers and days required to complete each task. The total cost can be determined from these inputs to ensure adequate budget for construction worker safety.

Uploaded by

Momie Marquez
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

DETAILED CALCULATIONS ON COST OF CONSTRUCTION SAFETY AND HEALTH PROGRAM

PROJECT NAME: LOCAL PROGRAM: Construction/Repair/Rehabilitation/Improvement of Various Infrastructure Duration: 60 C.D.


Including Local Projects - Local Infrastructure Program
Construction of Multi-Purpose Building
LOCATION: Brgy. Sapinit, San Jorge, Samar

OUTPUT/H NO. OF SAFETY SAFETY SAFETY WORKING RAIN DUST/GAS EAR BODY RUBBER EYE
ITEM NO./ DESCRIPTION QUANTITY WORKERS DAYS MAN-DAYS LANYARD
OUR PERSONNEL HELMET SHOES VEST GLOVES COATS MASK MUFF HARNESS BOOTS GOGGLES

B.5 Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.04 0 0 0 0 0 0


1.00 1.00 Skilled Laborer 1 0.13 0.13 0.13 0.13 0.13 0.13 0.04 0 0 0 0 0 0
Project Billboard/ Sign Board
Unskilled Laborer 1 0.13 0.13 0.13 0.13 0.13 0.13 0.04 0 0 0 0 0 0
803(1)a Foreman 1 0.39 0.39 0.39 0.39 0.39 0.39 0.12 0 0 0 0 0 0
62.91 20.00 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Structure Excavation (Common Soil)
Unskilled Laborer 3 0.39 1.17 1.17 1.17 1.17 1.17 0.35 0 0 0 0 0 0
804(1)a Foreman 1 0.79 0.79 0.79 0.79 0.79 0.79 0.24 0 0 0 0 0 0
62.51 9.84 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Embankment (From Structure Excavation)
Unskilled Laborer 3 0.79 2.37 2.37 2.37 2.37 2.37 0.71 0 0 0 0 0 0
804(4) Foreman 1 0.29 0.29 0.29 0.29 0.29 0.29 0.09 0 0 0 0 0 0
2.80 1.20 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Gravel Fill
Unskilled Laborer 3 0.29 0.87 0.87 0.87 0.87 0.87 0.26 0 0 0 0 0 0
900(1)c1 Foreman 1 1.44 1.44 1.44 1.44 1.44 1.44 0.43 0 0 0 0 1.44 0
16.10 1.40 Skilled Laborer 4 1.44 5.76 5.76 5.76 5.76 5.76 1.73 0 0 0 0 5.76 0
Structural Concrete (Class A), 28 days
Unskilled Laborer 8 1.44 11.52 11.52 11.52 11.52 11.52 3.46 0 0 0 0 11.52 0
902(1)a Foreman 1 2.19 2.19 2.19 2.19 2.19 2.19 0.66 0 0 0 0 0 0
2,512.21 143.438 Skilled Laborer 3 2.19 6.57 6.57 6.57 6.57 6.57 1.97 0 0 0 0 0 0
Reinforcing Steel (Deformed), Grade 40
Unskilled Laborer 12 2.19 26.28 26.28 26.28 26.28 26.28 7.88 0 0 0 0 0 0
903(1) Foreman 2 0.13 0.26 0.26 0.26 0.26 0.26 0.08 0 0 0 0 0 0
1.00 1.00 Skilled Laborer 2 0.13 0.26 0.26 0.26 0.26 0.26 0.08 0 0 0 0 0 0
Formworks and Falseworks
Unskilled Laborer 10 0.13 1.3 1.3 1.3 1.3 1.3 0.39 0 0 0 0 0 0
1000(1) Foreman 1 0.02 0.02 0.02 0.02 0.02 0.02 0.01 0 0 0 0 0 0
0.72 5.40 Skilled Laborer 1 0.02 0.02 0.02 0.02 0.02 0.02 0.01 0 0 0 0 0 0
Soil Poisoning
Unskilled Laborer 2 0.02 0.04 0.04 0.04 0.04 0.04 0.01 0 0 0 0 0 0
1001(8) Foreman 1 2.00 2 2 2 2 2 0.6 0 0 0 0 2 0
1.00 1.00 Skilled Laborer 1 2.00 2 2 2 2 2 0.6 0 0 0 0 2 0
Sewer Line Works
Unskilled Laborer 2 2.00 4 4 4 4 4 1.2 0 0 0 0 4 0
1013(2)a1 Foreman 1 0.16 0.16 0.16 0.16 0.16 0.16 0.05 0 0 0 0 0 0
13.00 10.00 Skilled Laborer 1 0.16 0.16 0.16 0.16 0.16 0.16 0.05 0 0 0 0 0 0
Fabricated Metal Roofing Accessory, Gauge 26 (Ridge Rolls)
Unskilled Laborer 1 0.16 0.16 0.16 0.16 0.16 0.16 0.05 0 0 0 0 0 0
1013(2)a2 Foreman 1 0.22 0.22 0.22 0.22 0.22 0.22 0.07 0 0 0 0 0 0
17.40 10.00 Skilled Laborer 1 0.22 0.22 0.22 0.22 0.22 0.22 0.07 0 0 0 0 0 0
Fabricated Metal Roofing Accessory, Gauge 26 (Flashings)
Unskilled Laborer 1 0.22 0.22 0.22 0.22 0.22 0.22 0.07 0 0 0 0 0 0
1013(2)b1 Foreman 1 0.28 0.28 0.28 0.28 0.28 0.28 0.08 0 0 0 0 0 0
26.00 11.80 Skilled Laborer 1 0.28 0.28 0.28 0.28 0.28 0.28 0.08 0 0 0 0 0 0
Fabricated Metal Roofing Accessory, Gauge 26 (Gutters)
Unskilled Laborer 1 0.28 0.28 0.28 0.28 0.28 0.28 0.08 0 0 0 0 0 0
1014(1)b2 Foreman 1 11.01 11.01 11.01 11.01 11.01 11.01 3.3 0 0 0 0 0 0
243.81 2.769 Skilled Laborer 1 11.01 11.01 11.01 11.01 11.01 11.01 3.3 0 0 0 0 0 0
Prepainted Metal Sheets, above 0.427mm, Rib Type (Long Span)
Unskilled Laborer 2 11.01 22.02 22.02 22.02 22.02 22.02 6.61 0 0 0 0 0 0
PROJECT NAME: LOCAL PROGRAM: Construction/Repair/Rehabilitation/Improvement of Various Infrastructure Duration: 60 C.D.
Including Local Projects - Local Infrastructure Program
Construction of Multi-Purpose Building
LOCATION: Brgy. Sapinit, San Jorge, Samar

OUTPUT/H NO. OF SAFETY SAFETY SAFETY WORKING RAIN DUST/GAS EAR BODY RUBBER EYE
ITEM NO./ DESCRIPTION QUANTITY WORKERS DAYS MAN-DAYS LANYARD
OUR PERSONNEL HELMET SHOES VEST GLOVES COATS MASK MUFF HARNESS BOOTS GOGGLES

1017(1)c Foreman 1 1 1 1 1 1 1 0.3 0 0 0 0 0 0


8.00 1.00 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Roof Drain with Strainer (100mm dia.)
Unskilled Laborer 1 1 1 1 1 1 1 0.3 0 0 0 0 0 0
1032(1)c Foreman 1 29.62 29.62 29.62 29.62 29.62 29.62 8.89 0 0 0 0 0 0
473.92 2.00 Skilled Laborer 2 29.62 59.24 59.24 59.24 59.24 59.24 17.77 0 0 0 0 0 0
Painting Works (Steel)
Unskilled Laborer 1 29.62 29.62 29.62 29.62 29.62 29.62 8.89 0 0 0 0 0 0
1047(1) Foreman 1 10.80 10.80 10.80 10.80096 10.80 10.80 3.24 0 0 0 0 0 0
1.00 1.00 Skilled Laborer 2 9.97 19.94 19.94 19.94111 19.94 19.94 5.98 0 0 0 0 0 0
Structural Steel
Unskilled Laborer 2 12.52 25.04 25.04 25.03775 25.04 25.04 7.51 0 0 0 0 0 0
A. TOTAL, PERSONNEL/MAN-DAYS 108 292 292 292 292 292 88 0 0 0 0 87 0
B. SERVICE LIFE, DAYS 730 365 180 3 730 1 730 730 730 365 60
C. PURCHASE COST, PPh 180.55 1,012.00 400.00 23.00 245.00 63.25 602.60 1,263.85 1,083.30 506.00 169.05
D. UNIT COST/MAN-DAY (C ÷ B) 0.25 2.77 2.22 7.67 0.34 63.25 0.83 1.73 1.48 1.39 2.82
E. DIRECT COST FOR PPE's (D x A(Man-days)) 73.05 809.42 648.71 2,241.25 29.81 0.00 0.00 0.00 0.00 120.54 0.00 3,922.78
F. SAFETY OFFICER/PRACTITIONER (PART TIME) @ P 15,000.00/MONTH (AS PER D.O. 56, S2005, consider atleast 4 hours per week) 2,500.00
G. HEALTH PERSONNEL (FULL TIME) @ P8,400.00/MONTH (AS PER D.O. 56, S2005) 16,800.00
H. TOTAL DIRECT COST (E + F + G) 23,222.78
I. OCM 0.00% of E -
J. PROFIT 10.00% of H 2,322.28
K. VAT 5.00% of (H+J) 1,277.25
L. TOTAL COST (H+I+J+K) 26,822.31

Prepared by: Checked by:

JOHN REY R. BERNATE ROSTER L. ANDAYA


Engineer II OIC Chief, Planning and Design Section