CAPITAL BUDGETING PROBLEMS: CHAPTER 10
REVIEW QUESTION
10–1 What is the financial manager’s goal in selecting investment projects for
the firm? Define the capital budgeting process and explain how it helps
managers achieve their goal.
    1. Step 1 of 3
        Financial manager’s goal in selecting investment projects is as same as firm’s goal i.e. to
        maximize owner’s wealth by selecting those projects which must be profitable for the firm in
        terms of efficiency and profitability.
    2. Step 2 of 3
        Capital budgeting is the process of evaluating and selecting a company’s potential investments
        proposals and deciding the acceptance criteria on the basis of its profitability. It involves the
        decision related to acquiring long term investment proposals which are expected to provide
        returns after more than one year.
    3. Step 3 of 3
        First managers will determine the cost and benefits associated with different proposals in
        terms of cash flows arising during the whole span of time whether inflows or outflows and
        then they evaluate and compare in terms of profitability arising out of these proposals to select
        the best option for the firm.
10–2 What is the payback period? How is it calculated?
    1. Step 1 of 3
        Payback period: The payback period is defined as the total amount of time required to
        recover the original investment of a project.
    2. Step 2 of 3
        Calculation of Payback period:
        In case of annuity cash inflow the payback period can be computed using the following
        equation:
    3. Step 3 of 3
        In case of mixed stream of cash flows payback period can be computed using the following
        equation:
  CAPITAL BUDGETING PROBLEMS: CHAPTER 10
10–3 What weaknesses are commonly associated with the use of the payback
period to evaluate a proposed investment?
Following are the weaknesses that are associated with the use of payback period to
evaluate the proposed investments:
• It does not consider the wealth maximization of the stockholders as does not involve
discounting cash flows to calculate the value addition to the firm.
• The payback method always ignores cash flows beyond the payback period.
• This technique does not consider the time value of money.
10–4 How is the net present value (NPV) calculated for a project with a
conventional cash flow pattern?
10–5 What are the acceptance criteria for NPV? How are they related to the
firm’s market value?
    1. Step 1 of 2
        Acceptance Criteria for NPV (Net Present Value):
        The project will be accepted if its NPV is positive i.e. NPV is greater than zero and rejected if
        NPV is negative i.e. NPV is less than zero. In case of ranking mutually exclusive proposals, the
        project with highest positive NPV is given the top priority over the lower positive NPV
        projects.
    2. Step 2 of 2
        When NPV is Positive the firm’s rate of return will be greater than its cost of capital. This
        action must rise the firm’s market value.
10–6 Explain the similarities and differences between NPV, PI, and EVA.
    1. Step 1 of 4
        Similarities between NPV, PI and EVA : These all are the capital budgeting techniques to
        evaluate the investment proposals in terms of future profitability.
        Difference between NPV, PI and EVA : There is slightly difference between all the techniques
        in terms of calculations and decision criteria.
    2. Step 2 of 4
        The Net Present Value of a proposal is the total present values of all cash inflows discounted
        at the discount rate equal to its cost of capital less the total present values all the cash outflows
        arising with the proposal. The equation for the NPV is as follows:
  CAPITAL BUDGETING PROBLEMS: CHAPTER 10
    3. Step 3 of 4
         Profitability Index: The PI technique involves discounting the future cash flows at a discount
         rate equals to cost of capital and comparing the present value of the future cash inflows with
         the present value of the future cash outflows. It is calculated as follows:
         Here CFt represents the expected future cash flows, and CF0 represents the initial cost.
    4. Step 4 of 4
         Economic Value Added: It is another method of evaluating capital budgeting decision. It
         evaluates the project’s pure economic profit which is the excess return over the competitive
         expected return in a business run.
10–7 What is the internal rate of return (IRR) on an investment? How is it
determined?
    1. Step 1 of 3
         Internal rate of return (IRR): The IRR of the proposal is defined as the discount rate which
         produces a zero NPV i.e., the IRR is the discount rate which will equate the present value of
         cash flows with the present value of cash outflows.
    2. Step 2 of 3
         From the following equation IRR can be arrived:
  CAPITAL BUDGETING PROBLEMS: CHAPTER 10
    3. Step 3 of 3
         If the IRR is more than the minimum rate i.e. the cut-off rate then the project will be accepted
         otherwise rejected. In case of ranking mutually exclusive proposals, the project with highest IRR
         is given the top priority over the lower IRR projects.
10–8 What are the acceptance criteria for IRR? How are they related to the
firm’s market value?
Step 1 of 1
Acceptance criteria: For Independent projects, the project will be accepted if its IRR is more than its
cost of capital otherwise rejected. In case of ranking mutually exclusive proposals, the project with
highest IRR is given the top priority over the lower IRR projects.
With the acceptable IRR the value of the firm will increase. Firm can earn minimum its required rate of
return. But amount by which value increases is not possible to judge.
10–9 Do the net present value (NPV) and internal rate of return (IRR) always
agree with respect to accept–reject decisions? With respect to ranking
decisions? Explain.
For independent projects the NPV profile shows that the IRR criteria and NPV criteria leads to the
same accept or reject decision. Now, if we assume that both the franchises are mutually exclusive.
In this case, there are chances of conflicts. The conflict in the ranking of mutually exclusive
proposals as per the NPV and the IRR techniques arises as a result of different reinvestment rate
assumptions of the two techniques acting in different ways on the proposals having time disparity
of cash inflows.
The reasons and conditions, under which different rankings may occur, can be summarized as
follows:
i) Scale or size disparity among different alternative proposals: The cost or scale of one
proposal may be different from that of others. A conflict in ranking can arise because of size
difference of different proposals. The ranking of NPV technique, which deals with absolute net
benefits, will be affected by the size of proposals. Higher the cash outflow larger would be the
expected returns in absolute terms and hence higher ranking would be. On the other hand, the
IRR deals with relative returns (i.e. in percentage form) and hence ignores the size of the
proposal.
ii) Different timing or Time Disparity among alternative proposals: The ranking of mutually
exclusive proposals as per NPV and the IRR technique may be different even when they involve
the same or almost the same outlay. The different ranking may then occur as a result of different
timing of the cash flows of different proposals.
iii) Life disparity or proposals with unequal lives also raise conflicts between NPV and IRR.
10–10 How is a net present value profile used to compare projects? What
causes conflicts in the ranking of projects via net present value and
internal rate of return?
 CAPITAL BUDGETING PROBLEMS: CHAPTER 10
10–11 Does the assumption concerning the reinvestment of intermediate cash
inflow tend to favor NPV or IRR? In practice, which technique is preferred
and why?
    1. Step 1 of 2
        The reinvestment rate assumption is the assumption regarding the rate of compounding and
        discounting the intermediate cash flows. This reinvestment rate is built into the present value
        factors which are used to find out the NPV and IRR by adjusting the future cash flows for time
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
    value of money. It is assumed that when the cash flows are received, they are immediately
    reinvested in another project or asset.
 2. Step 2 of 2
    With NPV Technique it is assumed that discounted cash flows are reinvested at the cost of
    capital which represents the value of proposal are calculated at an accuracy as the cash flows
    are discounted have time value of money is taken into account.
    With IRR Technique it is assumed that cash flows are reinvested at IRR rate but it may not be
    always possible to reinvest at the IRR rate because it more than the cost of capital.
    Thus, NPV technique is preferred.
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
Answers to Warm-Up Exercise
E10-1.    Payback period
Answer:   The payback period for Project Hydrogen is 4.29 years. The payback period for Project
          Helium is 5.75 years. Both projects are acceptable because their payback periods are less than
          Elysian Fields’ maximum payback period criterion of 6 years.
 CAPITAL BUDGETING PROBLEMS: CHAPTER 10
 E10-2.     NPV
 Answer:
E10–3 Axis Corp. is considering investment in the best of two mutually exclusive projects.
Project Kelvin involves an overhaul of the existing system; it will cost $45,000 and
generate cash inflows of $20,000 per year for the next 3 years. Project Thompson
involves replacement of the existing system; it will cost $275,000 and generate cash
inflows of $60,000 per year for 6 years. Using an 8% cost of capital, calculate each
project’s NPV, and make a recommendation based on your findings.
 CAPITAL BUDGETING PROBLEMS: CHAPTER 10
E10–4 Billabong Tech uses the internal rate of return (IRR) to select projects. Calculate
the IRR for each of the following projects and recommend the best project based on
this measure. Project T-Shirt requires an initial investment of $15,000 and generates
cash inflows of $8,000 per year for 4 years. Project Board Shorts requires an initial
             investment of $25,000 and produces cash inflows of $12,000 per year for 5 years.
 E10-4:     IRR
 Answer:    You may use a financial calculator to determine the IRR of each project. Choose the project
            with the higher IRR.
           Project T-Shirt
           PV     15,000, N    4, PMT    8,000
           Solve for I
           IRR 39.08%
           Project Board Shorts
           PV     25,000, N 5, PMT       12,000
           Solve for I
           IRR 38.62%
           Based on IRR analysis, Billabong Tech should choose project T-Shirt.
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
E10-5:    NPV
Answer:
          Note: The IRR for Project Terra is 10.68% while that of Project Firma is 10.21%.
          Furthermore, when the discount rate is zero, the sum of Project Terra’s cash flows exceed that
          of Project Firma. Hence, at any discount rate that produces a positive NPV, Project Terra
          provides the higher net present value.
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
◼    Solutions to Problems
P10-1. Payback period
        LG 2; Basic
        a. $42,000 $7,000 6 years
        b. The company should accept the project, since 6     8.
P10-2. Payback comparisons
        LG 2; Intermediate
        a. Machine 1: $14,000    $3,000   4 years, 8 months
           Machine 2: $21,000    $4,000   5 years, 3 months
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
      b. Only Machine 1 has a payback faster than 5 years and is acceptable.
      c. The firm will accept the first machine because the payback period of 4 years, 8 months is
         less than the 5-year maximum payback required by Nova Products.
      d. Machine 2 has returns that last 20 years while Machine 1 has only 7 years of returns.
         Payback cannot consider this difference; it ignores all cash inflows beyond the payback
         period. In this case, the total cash flow from Machine 1 is $59,000 ($80,000 $21,000) less
         than Machine 2.
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
P10-3. Choosing between two projects with acceptable payback periods
        LG 2; Intermediate
        a.
                             Project A                                       Project B
                        Cash      Investment                            Cash     Investment
             Year      Inflows      Balance                   Year     Inflows     Balance
             0                        $100,000                  0                    $100,000
             1         $10,000          90,000                  1      40,000          60,000
             2          20,000          70,000                  2      30,000          30,000
             3          30,000          40,000                  3      20,000          10,000
             4          40,000               0                  4      10,000               0
             5          20,000                                  5      20,000
           Both Project A and Project B have payback periods of exactly 4 years.
        b. Based on the minimum payback acceptance criteria of 4 years set by John Shell, both
           projects should be accepted. However, since they are mutually exclusive projects, John
           should accept Project B.
        c. Project B is preferred over A because the larger cash flows are in the early years of the
           project. The quicker cash inflows occur, the greater their value.
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
P10-4. Personal finance: Long-term investment decisions, payback period
        LG 4
        a. and b.
                                         Project A                      Project B
                                  Annual      Cumulative          Annual      Cumulative
             Year                Cash Flow    Cash Flow          Cash Flow    Cash Flow
             0                     $(9,000)           $(9,000)         $(9,000)      $(9,000)
             1                        2,200            (6,800)           1,500        (7,500)
             2                        2,500            (4,300)           1,500        (6,000)
             3                        2,500            (1,800)           1,500        (4,500)
             4                        2,000                              3,500        (1,000)
             5                        1,800                              4,000
             Total Cash Flow        11,000                              12,000
             Payback Period      3 1,800/2,000     3.9 years     4   1,000/4,000   4.25 years
        c.   The payback method would select Project A since its payback of 3.9 years is lower than
             Project B’s payback of 4.25 years.
        d. One weakness of the payback method is that it disregards expected future cash flows as in
           the case of Project B.
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
P10-5. NPV
        LG 3; Basic
           NPV PVn        Initial investment
      a.   N   20, I   14%, PMT      $2,000
         Solve for PV $13,246.26
         NPV $13,246.26 $10,000
         NPV $3,246.26
      Accept project
      b. N     20, I   14%, PMT      $3,000
           Solve for PV    19,869.39
          NPV     $19,869.39 $25,000
          NPV      $5,130.61
      Reject
      c.   N   20, I   14%, PMT      $5,000
           Solve for PV    $33,115.65
         NPV      $33,115.65     $30,000
         NPV      $33,115.65
         NPV      $3,115
      Accept
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
P10-6. NPV for varying cost of capital
        LG 3; Basic
        a.   10%
             N 8, I 10%, PMT $5000
             Solve for PV $26,674.63
             NPV PVn Initial investment
             NPV $26,674.63 $24,000
             NPV $2,674.63
             Accept; positive NPV
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
      b. 12%
         N 8, I 12%, PMT $5,000
         Solve for PV $24,838.20
         NPV PVn Initial investment
         NPV $24,838.20 $24,000
         NPV $838.20
         Accept; positive NPV
     CAPITAL BUDGETING PROBLEMS: CHAPTER 10
c.            14%
              N 8, I 14%, PMT $5,000
              Solve for PV $23,194.32
              NPV PVn Initial investment
              NPV $23,194.32 $24,000
              NPV -$805.68
              Reject; negative NPV
 CAPITAL BUDGETING PROBLEMS: CHAPTER 10
P10-7. NPV—independent projects
LG 3; Intermediate Project A
             N 10, I 14%, PMT $4,000
             Solve for PV $20,864.46
             NPV $20,864.46 $26,000
             NPV      $5,135.54
         Reject
         Project B—PV of Cash Inflows
             CF0 -$500,000; CF1 $100,000; CF2 $120,000; CF3 $140,000; CF4 $160,000;
             CF5 $180,000; CF6 $200,000
             Set I 14%
             Solve for NPV $53,887.93
         Accept
         Project C—PV of Cash Inflows
             CF0 -$170,000; CF1 $20,000; CF2 $19,000; CF3 $18,000; CF4 $17,000;
             CF5 $16,000; CF6 $15,000; CF7 $14,000; CF8 $13,000; CF9 $12,000; CF10
             $11,000,
             Set I 14%
             Solve for NPV -$83,668.24
         Reject
         Project D
             N 8, I 14%, PMT $230,000
             Solve for PV $1,066,939
             NPV PVn Initial investment
             NPV $1,066,939 $950,000
             NPV $116,939
         Accept
         Project E—PV of Cash Inflows
             CF0 -$80,000; CF1 $0; CF2 $0; CF3 $0; CF4 $20,000; CF5 $30,000; CF6 $0;
             CF7 $50,000; CF8 $60,000; CF9 $70,000
             Set I 14%
         Solve for NPV $9,963.63
         Accept
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
P10-8. NPV
        LG 3; Challenge
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
       a.   N 5, I 9%, PMT $385,000
            Solve for PV $1,497,515.74
            The immediate payment of $1,500,000 is not preferred because it has a higher present value
            than does the annuity.
       b. N 5, I 9%, PV           $1,500,000
          Solve for PMT $385,638.69
       c. Present valueAnnuity Due PVordinary annuity (1 discount rate)
          $1,497,515.74 (1.09) $1,632,292
          Calculator solution: $1,632,292
          Changing the annuity to a beginning-of-the-period annuity due would cause Simes Innovations
          to prefer to make a $1,500,000 one-time payment because the present value of the annuity
          due is greater than the $1,500,000 lump-sum option.
       d. No, the cash flows from the project will not influence the decision on how to fund the
          project. The investment and financing decisions are separate.
P10-9. NPV and maximum return
        LG 3; Challenge
       a.   N 4, I 10%, PMT $4,000
            Solve for PV $12,679.46
            NPV PV Initial investment
            NPV $12,679.46 $13,000
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
           NPV –$320.54
           Reject this project due to its negative NPV.
       b. N    4, PV -$13,000, PMT       $4,000
           Solve for I 8.86%
           8.86% is the maximum required return that the firm could have for the project to be acceptable.
           Since the firm’s required return is 10% the cost of capital is greater than the expected return
           and the project is rejected.
P10-10. NPV—mutually exclusive projects
        LG 3; Intermediate
        a. and b.
             Press A
             CF0 -$85,000; CF1 $18,000; F1        8
             Set I 15%
             Solve for NPV -$4,228.21
             Reject
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
            Press B
            CF0 -$60,000; CF1 $12,000; CF2             $14,000; CF3    $16,000; CF4   $18,000;
            CF5 $20,000; CF6 $25,000
            Set I 15%
            Solve for NPV $2,584.34
            Accept
            Press C
            CF0 -$130,000; CF1 $50,000; CF2 $30,000; CF3 $20,000; CF4                  $20,000;
            CF5 $20,000; CF6 $30,000; CF7 $40,000; CF8 $50,000
            Set I 15%
            Solve for NPV   $15,043.89
            Accept
       c.   Ranking—using NPV as criterion
            Rank           Press              NPV
            1                C          $15,043.89
            2                B            2,584.34
            3                A            4,228.21
       d. Profitability Indexes
            Profitability Index     Present Value Cash Inflows        Investment
            Press A: $80,771      $85,000     0.95
            Press B: $62,588      $60,000     1.04
            Press C: $145,070      $130,000     1.12
       e. The profitability index measure indicates that Press C is the best, then Press B, then Press A
          (which is unacceptable). This is the same ranking as was generated by the NPV rule.
P10-11. Personal finance: Long-term investment decisions, NPV method
        LG 3
               Key information:
               Cost of MBA program                     $100,000
               Annual incremental benefit              $ 20,000
               Time frame (years)                       40
               Opportunity cost                         6.0%
                Calculator Worksheet Keystrokes:
                CF0        100,000
                CF1      20,000
                F1       40
                Set I    6%
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
            Solve for NPV   $200,926
            The financial benefits outweigh the cost of the MBA program.
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
P10-12. Payback and NPV
        LG 2, 3; Intermediate
       a.
                Project                          Payback Period
                A                          $40,000     $13,000     3.08 years
                B                   3     ($10,000    $16,000)     3.63 years
                C                     2    ($5,000    $13,000)     2.38 years
            Project C, with the shortest payback period, is preferred.
       b. Worksheet keystrokes
            Year          Project A              Project B              Project C
            0             $40,000                 $40,000               $40,000
            1             13,000                   7,000                19,000
            2             13,000                  10,000                16,000
            3             13,000                  13,000                13,000
            4             13,000                  16,000                10,000
            5             13,000                  19,000                 7,000
            Solve for     $2,565.82               $322.53           $5,454.17
            NPV
                           Accept                 Reject                Accept
            Project C is preferred using the NPV as a decision criterion.
       c. At a cost of 16%, Project C has the highest NPV. Because of Project C’s cash flow
          characteristics, high early-year cash inflows, it has the lowest payback period and the
          highest NPV.
P10-13. NPV and EVA
       LG 3; Intermediate
       a. NPV        $2,500,000     $240,000        0.09     $166,667
       b. Annual EVA        $240,000 – ($2,500,000 x 0.09)         $15,000
       c. Overall EVA       $15,000       0.09     $166,667
            In this case, NPV and EVA give exactly the same answer.
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
P10-14. IRR—Mutually exclusive projects
        LG 4; Intermediate
        IRR is found by solving:
        $0                   initial investment
                 (1 IRR)t
       Most financial calculators have an ―IRR‖ key, allowing easy computation of the internal rate of
       return. The numerical inputs are described below for each project.
       Project A
       CF0      $90,000; CF1 $20,000; CF2 $25,000; CF3 $30,000; CF4 $35,000; CF5              $40,000
       Solve for IRR 17.43%
       If the firm’s cost of capital is below 17%, the project would be acceptable.
       Project B
       CF0     $490,000; CF1 $150,000; CF2 $150,000; CF3 $150,000; CF4 $150,000
       [or, CF0    $490,000; CF1 $150,000, F1 4]
       Solve for IRR 8.62%
       The firm’s maximum cost of capital for project acceptability would be 8.62%.
       Project C
       CF0     $20,000; CF1 $7500; CF2 $7500; CF3 $7500; CF4 $7500; CF5 $7500
       [or, CF0    $20,000; CF1 $7500; F1 5]
       Solve for IRR 25.41%
       The firm’s maximum cost of capital for project acceptability would be 25.41%.
       Project D
       CF0     $240,000; CF1 $120,000; CF2 $100,000; CF3 $80,000; CF4 $60,000
       Solve for IRR 21.16%
       The firm’s maximum cost of capital for project acceptability would be 21% (21.16%).
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
P10-15. IRR—Mutually exclusive projects
        LG 4; Intermediate
        a. and b.
             Project X
                $100,000    $120,000      $150,000   $190,000   $250,000
           $0                                                              $500,000
                (1 IRR)1    (1 IRR)2      (1 IRR)3   (1 IRR)4   (1 IRR)5
           CF0 -$500,000; CF1 $100,000; CF2 $120,000; CF3 $150,000; CF4        $190,000
           CF5 $250,000
           Solve for IRR 15.67; since IRR cost of capital, accept.
           Project Y
                $140,000    $120,000       $95,000    $70,000    $50,000
           $0                                                              $325,000
                (1 IRR)1    (1 IRR)2      (1 IRR)3   (1 IRR)4   (1 IRR)5
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
P10-16. Personal Finance: Long-term investment decisions, IRR method
        LG 4; Intermediate
        IRR is the rate of return at which NPV equals zero
        Computer inputs and output:
        N 5, PV $25,000, PMT $6,000
        Solve for IRR 6.40%
        Required rate of return: 7.5%
        Decision: Reject investment opportunity
P10-17. IRR, investment life, and cash inflows
        LG 4; Challenge
        a. N 10, PV -$61,450, PMT $10,000
           Solve for I 10.0%
           The IRR cost of capital; reject the project.
        b. I    15%, PV      $61,450, PMT     $10,000
             Solve for N 18.23 years
             The project would have to run a little over 8 more years to make the project acceptable with
             the 15% cost of capital.
        c.   N 10, I 15%, PV $61,450
             Solve for PMT $12,244.04
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
P10-18. NPV and IRR
        LG 3, 4; Intermediate
        a. N 7, I 10%, PMT $4,000
           Solve for PV $19,473.68
           NPV PV Initial investment
           NPV $19,472 $18,250
           NPV $1,223.68
        b. N 7, PV $18,250, PMT $4,000
           Solve for I 12.01%
        c. The project should be accepted since the NPV   0 and the IRR   the cost of capital.
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
P10-19. NPV, with rankings
        LG 3, 4; Intermediate
       a.   NPVA $45,665.50 (N 3, I 15, PMT $20,000) $50,000
            NPVA -$4,335.50
            Or, using NPV keystrokes
            CF0     $50,000; CF1 $20,000; CF2 $20,000; CF3 $20,000
            Set I 15%
            NPVA      $4,335.50
            Reject
            NPVB Key strokes
              CF0     $100,000; CF1 $35,000; CF2         $50,000; CF3     $50,000
              Set I 15%
              Solve for NPV $1,117.78
              Accept
            NPVC Key strokes
              CF0    $80,000;      CF1         $20,000; CF2       $40,000; CF3   $60,000
              Set I 15%
              Solve for NPV $7,088.02
              Accept
            NPVD Key strokes
              CF0     $180,000; CF1 $100,000; CF2          $80,000; CF3     $60,000
              Set I 15%
              Solve for NPV $6,898.99
              Accept
       b.
            Rank            Press          NPV
            1                C           $7,088.02
            2                D            6,898.99
            3                B            1,117.78
            4                A             4335.50
       c.   Using the calculator, the IRRs of the projects are:
            Project           IRR
            A                  9.70%
            B                 15.63%
            C                 19.44%
            D                 17.51%
            Since the lowest IRR is 9.7%, all of the projects would be acceptable if the cost of capital
            was 9.7%.
            Note: Since Project A was the only rejected project from the four projects, all that was
            needed to find the minimum acceptable cost of capital was to find the IRR of A.
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
P10-20. All techniques, conflicting rankings
        LG 2, 3, 4: Intermediate
        a.
                           Project A                                         Project B
                          Cash       Investment                             Cash       Investment
             Year        Inflows       Balance                  Year       Inflows       Balance
             0                           $150,000                 0                      $150,000
             1           $45,000          105,000                 1        $75,000         75,000
             2            45,000           60,000                 2         60,000         15,000
             3            45,000           15,000                 3         30,000         15,000
             4            45,000           30,000                 4         30,000              0
             5            45,000                                            30,000
             6            45,000                                            30,000
                           $150,000
             Payback A                   3.33 years     3 years 4 months
                            $45,000
                                      $15,000
             Payback B     2 years            years 2.5 years         2 years 6 months
                                      $30,000
        b. At a discount rate of zero, dollars have the same value through time and all that is needed is a
           summation of the cash flows across time.
           NPVA ($45,000 6) - $150,000 $270,000 $150,000 $120,000
           NPVB $75,000 $60,000 $120,000 $150,000 $105,000
        c.   NPVA:
               CF0       $150,000; CF1    $45,000; F1    6
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
               Set I 9%
               Solve for NPVA    $51,886.34
           NPVB:
             CF0     $150,000; CF1 $75,000; CF2           $60,000; CF3   $120,000
             Set I 9%
             Solve for NPV $51,112.36
             Accept
      d. IRRA:
            CF0     $150,000; CF1 $45,000; F1         6
            Solve for IRR 19.91%
               IRRB:
               CF0     $150,000; CF1 $75,000; CF2         $60,000; CF3   $120,000
               Solve for IRR 22.71%
      e.
                                              Rank
           Project          Payback           NPV            IRR
           A                    2              1               2
           B                    1              2               1
           The project that should be selected is A. The conflict between NPV and IRR is due partially
           to the reinvestment rate assumption. The assumed reinvestment rate of Project B is 22.71%,
           the project’s IRR. The reinvestment rate assumption of A is 9%, the firm’s cost of capital. On
           a practical level Project B may be selected due to management’s preference for making
           decisions based on percentage returns and their desire to receive a return of cash quickly.
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
P10-21. Payback, NPV, and IRR
        LG 2, 3, 4; Intermediate
        a. Payback period
           Balance after 3 years: $95,000 $20,000 $25,000 $30,000 $20,000
           3 ($20,000 $35,000) 3.57 years
        b. NPV computation
           CF0      $95,000; CF1 $20,000; CF2 $25,000; CF3 $30,000; CF4 $35,000
           CF5 $40,000
           Set I 12%
           Solve for NPV $9,080.60
                  $20,000    $25,000      $30,000     $35,000      $40,000
       c.   $0                                                                  $95,000
                 (1 IRR)1   (1 IRR)2     (1 IRR)3    (1 IRR)4     (1 IRR)5
            CF0     $95,000; CF1 $20,000; CF2    $25,000; CF3    $30,000; CF4    $35,000
            CF5 $40,000
            Solve for IRR 15.36%
       d. NPV $9,080; since NPV 0; accept
          IRR 15%; since IRR 12% cost of capital; accept
          The project should be implemented since it meets the decision criteria for both NPV and
          IRR.
 CAPITAL BUDGETING PROBLEMS: CHAPTER 10
 P10-22. NPV, IRR, and NPV profiles
         LG 3, 4, 5; Challenge
         a. and b.
              Project A
              CF0     $130,000; CF1 $25,000; CF2 $35,000; CF3 $45,000
              CF4 $50,000; CF5 $55,000
              Set I 12%
              NPVA $15,237.71
              Based on the NPV the project is acceptable since the NPV is greater than zero.
              Solve for IRRA 16.06%
Based on the IRR the project is acceptable since the IRR of 16% is greater than the 12% cost of capital.
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
           Project B
           CF0    $85,000; CF1 $40,000; CF2 $35,000; CF3 $30,000
           CF4 $10,000; CF5 $5,000
           Set I 12%
           NPVB $9,161.79
           Based on the NPV the project is acceptable since the NPV is greater than zero.
           Solve for IRRB 17.75%
           Based on the IRR the project is acceptable since the IRR of 17.75% is greater than the 12%
           cost of capital.
      c.
                      Data for NPV Profiles
                                            NPV
           Discount Rate              A             B
            0%                    $80,000         $35,000
           12%                    $15,238           $9,161
           15%                         —           $ 4,177
           16%                          0               —
           18%                         —                 0
      d. The net present value profile indicates that there are conflicting rankings at a discount rate
         less than the intersection point of the two profiles (approximately 15%). The conflict in
         rankings is caused by the relative cash flow pattern of the two projects. At discount rates
         above approximately 15%, Project B is preferable; below approximately 15%, Project A is
         better. Based on Thomas Company’s 12% cost of capital, Project A should be chosen.
      e. Project A has an increasing cash flow from Year 1 through Year 5, whereas Project B has a
         decreasing cash flow from Year 1 through Year 5. Cash flows moving in opposite directions
         often cause conflicting rankings. The IRR method reinvests Project B’s larger early cash
         flows at the higher IRR rate, not the 12% cost of capital.
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
P10-23. All techniques—decision among mutually exclusive investments
        LG 2, 3, 4, 5, 6; Challenge
                                                             Project
                                                   A            B            C
        Cash inflows (years 1 5)               $20,000     $ 31,500     $ 32,500
        a. Payback*                             3 years    3.2 years    3.4 years
        b. NPV*                                $10,345     $ 10,793      $ 4,310
        c. IRR*                                   19.86%       17.33%       14.59%
       *
        Supporting calculations shown below:
       a.   Payback Period: Project A: $60,000 $20,000            3 years
                            Project B: $100,000 $31,500           3.2 years
                            Project C: $110,000 $32,500           3.4 years
       b. NPV
          Project A
          CF0     $60,000; CF1 $20,000; F1 5
          Set I 13%
          Solve for NPVA $10,344.63
          Project B
          CF0     $100,000; CF1 $31,500; F1 5
          Set I 13%
          Solve for NPVB $10,792.78
          Project C
          CF0     $110,000; CF1 $32,500; F1 5
          Set I 13%
          Solve for NPVC $4,310.02
       c.   IRR
            Project A
            CF0    $60,000; CF1      $20,000; F1   5
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
           Solve for IRRA 19.86%
           Project B
           CF0     $100,000; CF1 $31,500; F1       5
           Solve for IRRB 17.34%
           Project C
           CF0     $110,000; CF1 $32,500; F1       5
           Solve for IRRC 14.59%
      d.
                           Data for NPV Profiles
                                              NPV
           Discount Rate           A           B             C
            0%                   $40,000     $57,500       $52,500
           13%                   $10,340      10,793         4,310
           15%                        —           —              0
           17%                         —               0         —
           20%                         0               —         —
           The difference in the magnitude of the cash flow for each project causes the NPV to compare
           favorably or unfavorably, depending on the discount rate.
      e.   Even though A ranks higher in Payback and IRR, financial theorists would argue that B is
           superior since it has the highest NPV. Adopting B adds $448.15 more to the value of the firm
           than does adopting A.
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
P10-24. All techniques with NPV profile—mutually exclusive projects
        LG 2, 3, 4, 5, 6; Challenge
        a. Project A
           Payback period
           Year 1 Year 2 Year 3        $60,000
           Year 4                      $20,000
           Initial investment          $80,000
            Payback   3 years ($20,000    30,000)
            Payback   3.67 years
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
           Project B
              Payback period
              $50,000 $15,000   3.33 years
      b. Project A
            CF0     $80,000; CF1 $15,000; CF2 $20,000; CF3     $25,000; CF4   $30,000;
            CF5 $35,000
            Set I 13%
            Solve for NPVA $3,659.68
         Project B
            CF0     $50,000; CF1 $15,000; F1 5
            Set I 13%
            Solve for NPVB $2,758.47
      c.   Project A
              CF0     $80,000; CF1 $15,000; CF2 $20,000; CF3   $25,000; CF4   $30,000;
              CF5 $35,000
              Solve for IRRA 14.61%
           Project B
              CF0     $50,000; CF1 $15,000; F1 5
              Solve for IRRB 15.24%
      d.
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
                      Data for NPV Profiles
                                       NPV
            Discount Rate            A                  B
               0%                      $45,000       $25,000
              13%                       $3,655         2,755
            14.6%                            0            —
            15.2%                           —              0
            Intersection—approximately 14%
            If cost of capital is above 14%, conflicting rankings occur.
            The calculator solution is 13.87%.
       e.   Both projects are acceptable. Both have similar payback periods, positive NPVs, and
            equivalent IRRs that are greater than the cost of capital. Although Project B has a slightly
            higher IRR, the rates are very close. Since Project A has a higher NPV, accept Project A.
P10-25. Integrative—Multiple IRRs
        LG 6; Basic
       a.   First the project does not have an initial cash outflow. It has an inflow, so the payback is
            immediate. However, there are cash outflows in later years. After 2 years, the project’s
            outflows are greater than its inflows, but that reverses in year 3. The oscillating cash flows
            (positive-negative-positive-negative-positive) make it difficult to even think about how the
            payback period should be defined.
       b. CF0 $200,000, CF1     920,000, CF2 $1,592,000, CF3               $1,205,200, CF4    $343,200
          Set I 0%; Solve for NPV $0.00
          Set I 5%; Solve for NPV    $15.43
          Set I 10%; Solve for NPV $0.00
          Set I 15%; Solve for NPV $6.43
          Set I 20%; Solve for NPV $0.00
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
           Set I   25%; Solve for NPV     $7.68
           Set I   30%; Solve for NPV    $0.00
           Set I   35%, Solve for NPV    $39.51
      c.   There are multiple IRRs because there are several discount rates at which the NPV is zero.
      d. It would be difficult to use the IRR approach to answer this question because it is not clear
         which IRR should be compared to each cost of capital. For instance, at 5%, the NPV is
         negative, so the project would be rejected. However, at a higher 15% discount rate the NPV
         is positive and the project would be accepted.
      e.   It is best simply to use NPV in a case where there are multiple IRRs due to the changing
           signs of the cash flows.
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
P10-26. Integrative—Conflicting Rankings
        LG 3, 4, 5; Intermediate
       a.   Plant Expansion
            CF0     $3,500,000, CF1 1,500,000, CF2 $2,000,000, CF3 $2,500,000, CF4 $2,750,000
            Set I 20%; Solve for NPV $1,911,844.14
            Solve for IRR 43.70%
            CF1 1,500,000, CF2 $2,000,000, CF3 $2,500,000, CF4 $2,750,000
            Set I 20%; Solve for NPV $5,411,844.14 (This is the PV of the cash inflows)
            PI $5,411,844.14 $3,500,000 1.55
            Product Introduction
            CF0    $500,000, CF1 250,000, CF2 $350,000, CF3             $375,000, CF4   $425,000
            Set I 20%; Solve for NPV $373,360.34
            Solve for IRR 52.33%
            CF1 250,000, CF2 $350,000, CF3 $375,000, CF4            $425,000
            Set I 20%; Solve for NPV $873,360.34 (This is the PV of the cash inflows)
            PI $873,360.34 $500,000 1.75
       b.
                                                    Rank
                   Project              NPV         IRR            PI
            Plant Expansion               1            2            2
            Product Introduction          2            1            1
       c.   The NPV is higher for the plant expansion, but both the IRR and the PI are higher for the
            product introduction project. The rankings do not agree because the plant expansion has a
            much larger scale. The NPV recognizes that it is better to accept a lower return on a larger
            project here. The IRR and PI methods simply measure the rate of return on the project and
            not its scale (and therefore not how much money in total the firm makes from each project).
       d. Because the NPV of the plant expansion project is higher, the firm’s shareholders would be
          better off if the firm pursued that project, even though it has a lower rate of return.
CAPITAL BUDGETING PROBLEMS: CHAPTER 10
P10-27. Ethics problem
        LG 1, 6; Intermediate
        Expenses are almost sure to increase for Gap. The stock price would almost surely decline in the
        immediate future, as cash expenses rise relative to cash revenues. In the long run, Gap may be able
        to attract and retain better employees (as does Chick-fil-A, interestingly enough, by being closed
        on Sundays), new human rights and environmentally conscious customers, and new investor demand
        from the burgeoning socially responsible investing mutual funds. This long-run effect is not
        assured, and we are again reminded that it’s not merely shareholder wealth maximization we’re
        after—but maximizing shareholder wealth subject to ethical constraints. In fact, if Gap was
        unwilling to renegotiate worker conditions, Calvert Group (and others) might sell Gap shares and
        thereby decrease shareholder wealth.