Tentative Cost Estimation

This document provides a tentative cost estimate for constructing a commercial building that is a RCC frame structure with a ground floor plus two and a half stories. It lists the total floor area for each level and applies a rate per square foot to calculate the construction amount for that level, totaling to NRs 29,296,638 or approximately $292,996.38. The rate per square foot is based on factors like the building's structure, materials, finishes, location, and aesthetic and commercial value.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2K views1 page

Tentative Cost Estimation

This document provides a tentative cost estimate for constructing a commercial building that is a RCC frame structure with a ground floor plus two and a half stories. It lists the total floor area for each level and applies a rate per square foot to calculate the construction amount for that level, totaling to NRs 29,296,638 or approximately $292,996.38. The rate per square foot is based on factors like the building's structure, materials, finishes, location, and aesthetic and commercial value.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Date : Nov 30 ,2018

TENTATIVE COST ESTIMATE:

Technical Details of the Building:

Type of Structure : RCC Frame structure

Commercial Building

Number of Storey:

As per Approved Drawing :Ground + 2 & half

The rate per unit built up area of the building is adopted based on its structural system,
type of materials used for construction, type of finishing works etc. Besides, the building’s location, its
aesthetic and commercial values are also considered while adopting its rate per unit built up area to
calculate the total value of the building as a whole.

Description Total Floor area Rate per sq.ft Amount

A)Ground Floor with raft foundation 1480.74 6500 9624810

B) First Floor 1545.22 5500 8498710

C)Second Floor 1545.22 5500 8498710

E) Top Floor 486.21 5500 2674155

TOTAL : NRs 2929638

In words : Two Crore Ninty Two Lakhs Ninty Nine Thousand Six Hundred And Thirty Eight
Only