27/11/2020                                                                      Finished.
Title: Scrum Open
               Percentage: 66.7%
                  Duration: 00:16:32
              Date started: Fri 27 Nov 2020 14:12
             Date finished: Fri 27 Nov 2020 14:28
        Feedback
        Thank you for taking the Open assessment of Scrum. Please review The Scrum Guide on Scrum.org and take this
        assessment again to improve your score.
        Ken Schwaber
             Correctly answered          Incorrectly answered       Missed correct option
        All Questions       20 Correct      2 Partially Correct   8 Incorrect
           Question 1 of 30
          When does the next Sprint begin?
          (choose the best answer)
          Correct answer: B)
          You chose: D)
          Note: This question displayed answers in random order during the test.
                A) When the Product Owner is ready.
                B) Immediately after the conclusion of the previous Sprint.
                C) Next Monday.
                D) Immediately following the next Sprint Planning.
          Feedback
https://www.classmarker.com/online-test/results/                                                                      1/16
27/11/2020                                                             Finished.
          A new Sprint starts immediately after the conclusion of the previous Sprint.
           Question 2 of 30
          True or False: It is mandatory that the product increment be released to production at the end of
          each Sprint.
          Correct answer: B)
          You chose: B)
                A) True
                B) False
          Feedback
          The product increment should be usable and releasable at the end of every Sprint, but it does not have to be
          released.
           Question 3 of 30
          The CEO asks the Development Team to add a "very important" item to a Sprint that is in
          progress. What should the Development Team do?
          (choose the best answer)
          Correct answer: D)
          You chose: C)
          Note: This question displayed answers in random order during the test.
                A) Add the item to the current Sprint and drop an item of equal size.
                B) Add the item to the current Sprint without any adjustments.
                C) Add the item to the next Sprint.
                D) Inform the Product Owner so he/she can work with the CEO.
          Feedback
          The items selected for a Sprint have been selected as most valuable with the Product Owner. The items serve
          the Sprint's goal. No changes should be made that endanger the Sprint Goal. No one external to the Scrum
          Team can force changes on the Development Team (Sprint Backlog) and the Product Owner (Product Backlog).
           Question 4 of 30
https://www.classmarker.com/online-test/results/                                                                         2/16
27/11/2020                                                              Finished.
          Which of the below are roles on a Scrum Team?
          (choose the best three answers)
          Correct answer: A) B) E)
          You chose: A) B) E)
          Note: This question displayed answers in random order during the test.
                A) Product Owner
                B) Scrum Master
                C) Users
                D) Customers
                E) Development Team
          Feedback
          The Scrum Team consists of a Product Owner, the Development Team, and a Scrum Master.
           Question 5 of 30
          How much work must a Development Team do to a Product Backlog item it selects for a Sprint?
          (choose the best answer)
          Correct answer: A)
          You chose: A)
          Note: This question displayed answers in random order during the test.
                A) As much as it has told the Product Owner will be done for every Product Backlog item it
                   selects in conformance with the definition of "Done".
                B) Analysis, design, programming, testing and documentation.
                C) As much as it can fit into the Sprint.
                D) All development work and at least some testing.
          Feedback
          The purpose of each Sprint is to deliver Increments of potentially releasable functionality that adhere to the
          Scrum Team's current definition of "Done".
           Question 6 of 30
https://www.classmarker.com/online-test/results/                                                                           3/16
27/11/2020                                                               Finished.
          What is the role of Management in Scrum?
          (choose the best answer)
          Correct answer: C)
          You chose: C)
          Note: This question displayed answers in random order during the test.
                A) Monitor the Development Team's productivity.
                B) Identify and remove people that aren't working hard enough.
                C) Support the Product Owner with insights and information into high value product and system
                   capabilities. Support the Scrum Master to cause organizational change that fosters
                   empiricism, self-organization, bottom-up intelligence, and intelligent release of software.
                D) Continually monitor staffing levels of the Development Team.
          Feedback
          Management has no active role in the actual product development through Scrum. However, management
          external to the Scrum team is incredibly important in setting the vision and strategy to guide the overall direction
          of the organization.
           Question 7 of 30
          When many Development Teams are working on a single product, what best describes the
          definition of "Done?"
          (choose the best answer)
          Correct answer: D)
          You chose: D)
          Note: This question displayed answers in random order during the test.
                A) Each Development Team defines and uses its own. The differences are discussed and
                   reconciled during a hardening Sprint.
                B) It depends.
                C) Each Development Team uses its own but must make their definition clear to all other teams
                   so the differences are known.
                D) All Development Teams must have a definition of "Done" that makes their combined work
                   potentially releasable.
          Feedback
          Scrum requires an Increment to be releasable. This is an Increment of product. Many teams working on a single
          product are expected to deliver such an Increment.
https://www.classmarker.com/online-test/results/                                                                                 4/16
27/11/2020                                                           Finished.
           Question 8 of 30
          Which of the following services are appropriate for a Scrum Master in regard to the Daily Scrum?
          (choose the best answer)
          Correct answer: A)
          You chose: D)
          Note: This question displayed answers in random order during the test.
                A) Teach the Development Team to keep the Daily Scrum within the 15 minute time-box.
                B) Lead the discussions of the Development Team.
                C) Facilitate in a way that ensures each team member has a chance to speak.
                D) All answers apply.
                E) Ensure that all 3 questions have been answered.
          Feedback
          The Scrum Master ensures that the Development Team has the meeting, but the Development Team is
          responsible for conducting the Daily Scrum. The Scrum Master teaches the Development Team to keep the
          Daily Scrum within the 15-minute time-box. The Scrum Master enforces the rule that only Development Team
          members participate in the Daily Scrum.
           Question 9 of 30
          Who should know the most about the progress toward a business objective or a release, and be
          able to explain the alternatives most clearly?
          (choose the best answer)
          Correct answer: B)
          You chose: A)
          Note: This question displayed answers in random order during the test.
                A) The Scrum Master
                B) The Product Owner
                C) The Project Manager
                D) The Development Team
          Feedback
https://www.classmarker.com/online-test/results/                                                                     5/16
27/11/2020                                                             Finished.
          The Product Owner is the sole person responsible for managing the Product Backlog, which includes that the
          Product Backlog is visible, transparent, and clear to all, and shows what the Scrum Team will work on next.
           Question 10 of 30
          The time-box for a Daily Scrum is?
          (choose the best answer)
          Correct answer: A)
          You chose: A)
          Note: This question displayed answers in random order during the test.
                A) 15 minutes.
                B) 15 minutes for a 4 week sprint. For shorter Sprints it is usually shorter.
                C) 4 hours.
                D) Two minutes per person.
                E) The same time of day every day.
          Feedback
          The length of a daily Scrum is time-boxed at 15 minutes, it does not change with the length of a Sprint.
           Question 11 of 30
          Who is on the Scrum Team?
          (choose the best three answers)
          Correct answer: A) B) C)
          You chose: A) B) C)
                A) The Scrum Master
                B) The Product Owner
                C) The Development Team
                D) Project Manager
                E) None of the above
          Feedback
https://www.classmarker.com/online-test/results/                                                                        6/16
27/11/2020                                                            Finished.
          The Scrum Team consists of the Scrum Master (manages the process), the Product Owner (decides what to do)
          and the Development Team (does the work).
           Question 12 of 30
          The time-box for the Sprint Planning meeting is?
          (choose the best answer)
          Correct answer: C)
          You chose: C)
          Note: This question displayed answers in random order during the test.
                A) Whenever it is done.
                B) 4 hours.
                C) 8 hours for a monthly Sprint. For shorter Sprints it is usually shorter.
                D) Monthly.
          Feedback
          Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the event
          is usually shorter.
           Question 13 of 30
          Development Team membership should change:
          (choose the best answer)
          Correct answer: C)
          You chose: D)
          Note: This question displayed answers in random order during the test.
                A) Never, because it reduces productivity.
                B) Every Sprint to promote shared learning.
                C) As needed, while taking into account a short term reduction in productivity.
                D) As needed, with no special allowance for changes in productivity.
          Feedback
          Teams typically go through some steps before achieving a state of increased performance. Changing
          membership typically reduces cohesion, affecting performance and productivity in the short term.
https://www.classmarker.com/online-test/results/                                                                             7/16
27/11/2020                                                           Finished.
           Question 14 of 30
          What does it mean to say that an event has a time-box?
          (choose the best answer)
          Correct answer: A)
          You chose: A)
          Note: This question displayed answers in random order during the test.
                A) The event can take no more than a maximum amount of time.
                B) The event must happen by a given time.
                C) The event must take at least a minimum amount of time.
                D) The event must happen at a set time.
          Feedback
          Time-boxed events are events that have a maximum duration.
           Question 15 of 30
          The Product Backlog is ordered by:
          (choose the best answer)
          Correct answer: E)
          You chose: E)
          Note: This question displayed answers in random order during the test.
                A) Size, where small items are at the top and large items are at the bottom.
                B) Items are randomly arranged.
                C) Risk, where safer items are at the top, and riskier items are at the bottom.
                D) Least valuable items at the top to most valuable at the bottom.
                E) Whatever is deemed most appropriate by the Product Owner.
          Feedback
          The Product Owner decides what makes the most sense to optimize the value of the work being done by the
          Development Team.
https://www.classmarker.com/online-test/results/                                                                    8/16
27/11/2020                                                              Finished.
           Question 16 of 30
          Which statement best describes the Sprint Review?
          (choose the best answer)
          Correct answer: A)
          You chose: B)
          Note: This question displayed answers in random order during the test.
                A) It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out
                   what to do next.
                B) It is a demo at the end of the Sprint for everyone in the organization to check on the work
                   done.
                C) It is a mechanism to control the Development Team's activities during a Sprint.
          Feedback
          Every event in Scrum, besides the Sprint which is a container for the other events, is an opportunity to Inspect
          AND Adapt.
           Question 17 of 30
          The length of a Sprint should be:
          (choose the best answer)
          Correct answer: D)
          You chose: D)
                A) Short enough to keep the business risk acceptable to the Product Owner.
                B) Short enough to be able to synchronize the development work with other business events.
                C) No more than one month.
                D) All of these answers are correct.
          Feedback
          All of these choices are appropriate considerations in determining the length of a Sprint.
           Question 18 of 30
https://www.classmarker.com/online-test/results/                                                                             9/16
27/11/2020                                                            Finished.
          What is the recommended size for a Development Team (within the Scrum Team)?
          (choose the best answer)
          Correct answer: D)
          You chose: D)
          Note: This question displayed answers in random order during the test.
                A) 9
                B) Minimal 7
                C) 7 plus or minus 2
                D) 3 to 9
          Feedback
          Optimal Development Team size is small enough to remain nimble and large enough to complete significant
          work. Fewer than three Development Team members decreases interaction and results in smaller productivity
          gains. More than nine members simply requires too much coordination.
           Question 19 of 30
          When is a Sprint over?
          (choose the best answer)
          Correct answer: C)
          You chose: A)
          Note: This question displayed answers in random order during the test.
                A) When all the tasks are completed.
                B) When all Product Backlog items meet their definition of done.
                C) When the time-box expires.
                D) When the Product Owner says it is done.
          Feedback
          The duration of a Sprint is fixed and cannot be shortened or lengthened.
           Question 20 of 30
          The Development Team should not be interrupted during the Sprint. The Sprint Goal should
          remain intact. These are conditions that foster creativity, quality and productivity.
https://www.classmarker.com/online-test/results/                                                                      10/16
27/11/2020                                                           Finished.
          (Which one the following answers is FALSE?)
          Correct answer: C)
          You chose: C)
          Note: This question displayed answers in random order during the test.
                A) The Development Team may work with the Product Owner to remove or add work if it finds it
                   has more or less capacity than it expected.
                B) As a decomposition of the selected Product Backlog Items, the Sprint Backlog changes and
                   may grow as the work emerges.
                C) The Sprint Backlog is fully formulated in the Sprint Planning meeting and does not change
                   during the Sprint.
                D) The Product Owner can help clarify or optimize the Sprint when asked by the Development
                   Team.
          Feedback
          The Sprint Backlog makes visible all of the work that the Development Team identifies as necessary to meet the
          Sprint Goal. The Development Team modifies the Sprint Backlog throughout the Sprint, and the Sprint Backlog
          emerges during the Sprint.
           Question 21 of 30
          During a Sprint, a Development Team determines that it will not be able to finish the complete
          forecast. Who should be present to review and adjust the Sprint work selected?
          (choose the best answer)
          Correct answer: D)
          You chose: D)
          Note: This question displayed answers in random order during the test.
                A) The Product Owner and all stakeholders.
                B) The Development Team.
                C) The Scrum Master, the project manager and the Development Team.
                D) The Product Owner and the Development Team.
          Feedback
          During the Sprint, scope may be clarified and re-negotiated between the Product Owner and Development Team
          as more is learned.
https://www.classmarker.com/online-test/results/                                                                           11/16
27/11/2020                                                            Finished.
           Question 22 of 30
          What is the main reason for the Scrum Master to be at the Daily Scrum?
          (choose the best answer)
          Correct answer: C)
          You chose: C)
          Note: This question displayed answers in random order during the test.
                A) To write down any changes to the Sprint Backlog, including adding new items, and tracking
                    progress on the burn-down.
                B) To make sure every team member answers the three questions.
                C) He or she does not have to be there; he or she only has to ensure the Development Team
                   has a Daily Scrum.
                D) To gather status and progress information to report to management.
          Feedback
          The Scrum Master enforces the rule that only Development Team members participate in the Daily Scrum.
           Question 23 of 30
          The three pillars of empirical process control are:
          (choose the best answer)
          Correct answer: D)
          You chose: D)
          Note: This question displayed answers in random order during the test.
                A) Planning, Demonstration, Retrospective
                B) Transparency, Eliminating Waste, Kaizen
                C) Respect For People, Kaizen, Eliminating Waste
                D) Inspection, Transparency, Adaptation
                E) Planning, Inspection, Adaptation
          Feedback
          Scrum is founded on empirical process control theory, or empiricism. Empiricism asserts that knowledge comes
          from experience and making decisions based on what is known.
          Three pillars uphold every implementation of empirical process control: transparency, inspection, and adaptation.
https://www.classmarker.com/online-test/results/                                                                              12/16
27/11/2020                                                             Finished.
           Question 24 of 30
          Which statement best describes Scrum?
          (choose the best answer)
          Correct answer: C)
          You chose: C)
          Note: This question displayed answers in random order during the test.
                A) A defined and predictive process that conforms to the principles of Scientific Management.
                B) A cookbook that defines best practices for software development.
                C) A framework within which complex products in complex environments are developed.
                D) A complete methodology that defines how to develop software.
          Feedback
          Scrum is not a process or a technique for building products; rather, it is a framework within which you can
          employ various processes and techniques.
           Question 25 of 30
          True or False: When multiple teams work together on the same product, each team should
          maintain a separate Product Backlog.
          Correct answer: B)
          You chose: A)
                A) True
                B) False
          Feedback
          Products have one Product Backlog, regardless of how many teams are used. Any other setup makes it difficult
          for the Development Team to determine what it should work on.
           Question 26 of 30
          Which statement best describes a Product Owner's responsibility?
          (choose the best answer)
https://www.classmarker.com/online-test/results/                                                                         13/16
27/11/2020                                                              Finished.
          Correct answer: D)
          You chose: D)
          Note: This question displayed answers in random order during the test.
                A) Directing the Development Team.
                B) Keep stakeholders from distracting the Development Team.
                C) Managing the project and ensuring that the work meets the commitments to the
                   stakeholders.
                D) Optimizing the value of the work the Development Team does.
          Feedback
          The Product Owner is responsible for maximizing the value of the product and the work of the Development
          Team.
           Question 27 of 30
          Select three incorrect, untrue, or misleading statements about Scrum?
          (choose the best three answers)
          Correct answer: A) D) F)
          You chose: D)
          Note: This question displayed answers in random order during the test.
                A) Scrum is a methodology where you can pick and choose which parts of Scrum you think will
                   work for your environment.
                B) Scrum is a framework for developing and sustaining complex products.
                C) Each component of Scrum serves a specific purpose and is essential to Scrum's success
                   and your usage of Scrum to develop complex products.
                D) Scrum is like traditional processes but with self-organization to replace Project Managers.
                E) Scrum is based on empirical process control theory.
                F) Scrum is a framework that eliminates complexity.
          Feedback
              1. Scrum is meant to be implemented as prescribed in the Scrum Guide. For example, the five events
                 in the Scrum Guide are mandatory, each event has a specific purpose.
              2. Scrum does not eliminate the complexity that is inherent in delivering a product in today’s world,
                 instead it offers a framework for dealing with complexity. By regularly delivering increments of value
                 teams gain the ability to inspect and rapidly adapt based on the feedback received.
              3. Project Managers are not simply replaced by self-organizing teams. Scrum is a framework for
                 optimizing decision making based on the knowledge and experience of the entire team.
https://www.classmarker.com/online-test/results/                                                                          14/16
27/11/2020                                                             Finished.
           Question 28 of 30
          The Development Team should have all the skills needed to:
          (choose the best answer)
          Correct answer: B)
          You chose: B)
          Note: This question displayed answers in random order during the test.
                A) Complete the project as estimated when the date and cost are committed to the Product
                   Owner.
                B) Turn the Product Backlog items it selects into an increment of potentially releasable product
                   functionality.
                C) Do all of the development work, except for specialized testing that requires additional tools
                   and environments.
          Feedback
          The Development Team consists of professionals who do the work of delivering a potentially releasable
          Increment of "Done" product at the end of each Sprint. Development Teams are cross-functional, with all of the
          skills as a team necessary to create a product Increment.
           Question 29 of 30
          When might a Sprint be abnormally cancelled?
          (choose the best answer)
          Correct answer: C)
          You chose: C)
          Note: This question displayed answers in random order during the test.
                A) When the sales department has an important new opportunity.
                B) When it becomes clear that not everything will be finished by the end of the Sprint.
                C) When the Sprint Goal becomes obsolete.
                D) When the Development Team feels that the work is too hard.
          Feedback
          A Sprint can be cancelled before the Sprint time-box is over. A Sprint would be cancelled if the Sprint Goal
          becomes obsolete. This might occur if the company changes direction or if market or technology conditions
          change.
https://www.classmarker.com/online-test/results/                                                                           15/16
27/11/2020                                                            Finished.
           Question 30 of 30
          Which two things does the Development Team do during the first Sprint?
          (choose the best two answers)
          Correct answer: C) E)
          You chose: D) E)
          Note: This question displayed answers in random order during the test.
                A) Develop a plan for the rest of the release.
                B) Create the complete Product Backlog to be developed in subsequent Sprints.
                C) Develop and deliver at least one piece of functionality.
                D) Determine the complete architecture and infrastructure for the product.
                E) Deliver an increment of potentially releasable software.
          Feedback
          The heart of Scrum is a Sprint, a time-box of one month or less during which a "Done", useable, and potentially
          releasable product Increment is created. This applies to every Sprint.