Scheduling/Leveling Report - 16-Jul-21 - PM.
exe
===============================================
     Default Project..................................................NIZ-IZK-3
      Projects:
            NIZ-IZK-
3........................................................UPGRADING NIZWA GS to 220
kV AND ADDING ONE 500MVA 400/200kV TRANSFORMER AT NEW IZKI GS BL
Scheduling/Leveling Settings:
-----------------------------
      General
      -------
      Scheduling ......................................................Yes
      Leveling ........................................................No
      Ignore relationships to and from other projects .................No
      Make open-ended activities critical .............................No
      Use Expected Finish Dates .......................................Yes
      Schedule automatically when a change affects dates ..............No
      Level resources during scheduling ...............................No
      Recalculate assignment costs after scheduling ...................No
      When scheduling progressed activities use .......................Retained
Logic
      Calculate start-to-start lag from ...............................Early Start
      Define critical activities as Total Float less than or equal to .0
      Compute Total Float As ..........................................Finish Float
      Calculate float based on finish date of .........................Each project
      Calendar for scheduling Relationship Lag ........................Predecessor
Activity Calendar
     Advanced
     --------
     Calculate multiple float paths...................................No
Statistics:
-----------
      # Projects.......................................................1
      # Activities.....................................................360
      # Not Started....................................................360
      # In Progress....................................................0
      # Completed......................................................0
      # Relationships..................................................457
      # Activities with Constraint.....................................2
            Project:    NIZ-IZK-3   Activity:  NIZ-MS-70   Reciept of Permits for
Izki GS : Excavation / Municipality
            Project:    NIZ-IZK-3   Activity:  NIZ-MS-80   Reciept of Permits for
Nizwa GS : Excavation / Municipality
Errors:
-------
Warnings:
---------
      Activities without predecessors..................................4
            Project:    NIZ-IZK-3   Activity:  NIZ-MAS-1   Material Submission for
Structural Works
            Project:    NIZ-IZK-3   Activity:  NIZ-MS-10   Receipt of LOI
            Project:    NIZ-IZK-3   Activity:  NIZ-MS-70   Reciept of Permits for
Izki GS : Excavation / Municipality
            Project:    NIZ-IZK-3  Activity:   NIZ-MS-80   Reciept of Permits for
Nizwa GS : Excavation / Municipality
      Activities without successors....................................5
            Project:    NIZ-IZK-3   Activity:  NIZ-MS-40   Nizwa-Electrical Access
of 220kV GIS Building
            Project:    NIZ-IZK-3   Activity:  NIZ-MS-50   Nizwa-Electrical Access
of 220kV Control Building (included LVAC Room)
            Project:    NIZ-IZK-3   Activity:  NIZ-MS-60   Handover - 500MVA
Tranformer Foundation
            Project:    NIZ-IZK-3   Activity:  NIZ-SNG-01 Snagging & Desnagging-
Nizwa GS
            Project:    NIZ-IZK-3   Activity:  NIZ-SNG-11 Snagging & Desnagging-
New Izki GS
     Out-of-sequence activities.......................................0
     Activities with Actual Dates > Data Date.........................0
      Milestone Activities with invalid relationships..................21
            Project:    NIZ-IZK-3   Activity:   IZK-DD16    Receipt of Structural
IFC drawings Compound Wall
            Project:    NIZ-IZK-3   Activity:   IZK-DD18    Receipt of Structural
IFC drawings Outdoor Equipments
            Project:    NIZ-IZK-3   Activity:   IZK-DD19    Receipt of Structural
IFC drawings Cable Tunnel / Trenches
            Project:    NIZ-IZK-3   Activity:   IZK-DD20    Receipt of Structural
IFC drawings Box Culvert & Duct Banks
            Project:    NIZ-IZK-3   Activity:   IZK-DD24    Receipt of Structural
IFC drawings - Transformer Shed
            Project:    NIZ-IZK-3   Activity:   IZK-DD25    Receipt of Structural
IFC drawings - Road Works
            Project:    NIZ-IZK-3   Activity:   IZK-DD26    Receipt of Structural
IFC drawings - Cable Compound
            Project:    NIZ-IZK-3   Activity:   NIZ-DD-IFC-01     Receipt of
Structural IFC drawings GIS building
            Project:    NIZ-IZK-3   Activity:   NIz-DD-IFC-02     Receipt of
Structural IFC drawings 220 kV Control building
            Project:    NIZ-IZK-3   Activity:   NIz-DD-IFC-104    Receipt of
Architectural IFC drawings Pump Room
            Project:    NIZ-IZK-3   Activity:   NIz-DD-IFC-114    Receipt of
Structural IFC drawings - Transformer Shed
            Project:    NIZ-IZK-3   Activity:   NIz-DD-IFC-124    Receipt of
Structural IFC drawings - Road Works
            Project:    NIZ-IZK-3   Activity:   NIz-DD-IFC-134    Receipt of
Structural IFC drawings - Cable Compound
            Project:    NIZ-IZK-3   Activity:   NIz-DD-IFC-14     Receipt of
Structural IFC drawings Compound Wall
            Project:    NIZ-IZK-3   Activity:   NIz-DD-IFC-24     Receipt of
Structural IFC drawings Pump Room
            Project:    NIZ-IZK-3   Activity:   NIz-DD-IFC-54     Receipt of
Structural IFC drawings Outdoor Equipments
            Project:    NIZ-IZK-3   Activity:   NIz-DD-IFC-64     Receipt of
Structural IFC drawings Cable Tunnel / Trenches
            Project:    NIZ-IZK-3   Activity:   NIz-DD-IFC-74     Receipt of
Structural IFC drawings Box Culvert & Duct Banks
            Project:    NIZ-IZK-3   Activity:   NIZ-DD-IFC-84     Receipt of
Architectural IFC drawings GIS building
            Project:    NIZ-IZK-3   Activity:   NIz-DD-IFC-94     Receipt of
Architectural IFC drawings 220 kV Control building
            Project:    NIZ-IZK-3  Activity:   NIZ-MS-20   Initial mobilisation
Scheduling/Leveling Results:
----------------------------
      # Projects Scheduled/Leveled.....................................1
      # Activities Scheduled/Leveled...................................360
      # Relationships with other projects..............................0
      Data Date........................................................15-Jul-21
      Earliest Early Start Date........................................15-Jul-21
      Latest Early Finish Date.........................................30-Apr-22
Exceptions:
-----------
      Critical Activities..............................................47
            Project:    NIZ-IZK-3   Activity:  NIZ-BSM-G13-010   Wall Scaffolding-
External
            Project:    NIZ-IZK-3   Activity:  NIZ-BSM-G13-040   Wall scaffolding
- Internal face
            Project:    NIZ-IZK-3   Activity:  NIZ-BSM-G13-080   Column scaffolding
            Project:    NIZ-IZK-3   Activity:  NIZ-BSM-G13-090   Column
reinforcement
            Project:    NIZ-IZK-3   Activity:  NIZ-BSM-G13-100   Column Shutter
fixing
            Project:    NIZ-IZK-3   Activity:  NIZ-BSM-G13-110   Column Concrete
            Project:    NIZ-IZK-3   Activity:  NIZ-BSM-G13-130   Deshuttering
columns
            Project:    NIZ-IZK-3   Activity:  NIZ-BSM-G13-140   Staging for Beams
and GF slab
            Project:    NIZ-IZK-3   Activity:  NIZ-BSM-G13-150   Shutter fixing for
beam & Slab
            Project:    NIZ-IZK-3   Activity:  NIZ-BSM-G13-160   Reinforcement
fixing for beam and Slab
            Project:    NIZ-IZK-3   Activity:  NIZ-BSM-G13-330   Reinforcement
fixing for beam and Slab
            Project:    NIZ-IZK-3   Activity:  NIZ-BSM-G13-340   Inserts and Box
outs fixing
            Project:    NIZ-IZK-3   Activity:  NIZ-BSM-G13-350   Inspection and
Slab Casting (Grid 1-7)
            Project:    NIZ-IZK-3   Activity:  NIZ-DD-IFC-01     Receipt of
Structural IFC drawings GIS building
            Project:    NIZ-IZK-3   Activity:  NIZ-EXT-DW-010    Installation of
Doors as per schedule
            Project:    NIZ-IZK-3   Activity:  NIZ-EXT-DW-020    Installation of
Rolling Shutter as per schedule
            Project:    NIZ-IZK-3   Activity:  NIZ-EXT-DW-030    Installation of
Windows as per schedule
            Project:    NIZ-IZK-3   Activity:  NIZ-GF-ARCH-WF-010      Blockwork
from GF slab to Roof beam
            Project:    NIZ-IZK-3   Activity:  NIZ-GF-ARCH-WF-280      External
plastering
            Project:    NIZ-IZK-3   Activity:  NIZ-GF-STR-010    Column scaffolding
            Project:    NIZ-IZK-3   Activity:  NIZ-GF-STR-020    Column
reinforcement
            Project:    NIZ-IZK-3   Activity:  NIZ-GF-STR-030    Column Shutter
fixing
            Project:    NIZ-IZK-3   Activity:  NIZ-GF-STR-040    Column Concrete
till roof lvl
            Project:    NIZ-IZK-3   Activity:  NIZ-GF-STR-110    Column scaffolding
            Project:    NIZ-IZK-3   Activity:  NIZ-GF-STR-120    Column
reinforcement
            Project:    NIZ-IZK-3   Activity:   NIZ-GF-STR-130     Column Shutter
fixing
            Project:    NIZ-IZK-3   Activity:   NIZ-GF-STR-140     Column Concrete
till roof lvl
            Project:    NIZ-IZK-3   Activity:   NIZ-GF-STR-150     Staging for Beams
and GF slab
            Project:    NIZ-IZK-3   Activity:   NIZ-GF-STR-160     Shutter fixing for
beam & Slab
            Project:    NIZ-IZK-3   Activity:   NIZ-GF-STR-170     Reinforcement
fixing for beam and Slab
            Project:    NIZ-IZK-3   Activity:   NIZ-GF-STR-180     Inserts and Box
outs fixing
            Project:    NIZ-IZK-3   Activity:   NIZ-GF-STR-190     Inspection and
Clearance
            Project:    NIZ-IZK-3   Activity:   NIZ-GF-STR-200    Roof Slab Concrete
            Project:    NIZ-IZK-3   Activity:   NIZ-GF-STR-220    Deshuttering
            Project:    NIZ-IZK-3   Activity:   NIZ-MS-10   Receipt of LOI
            Project:    NIZ-IZK-3   Activity:   NIZ-MS-70   Reciept of Permits for
Izki GS : Excavation / Municipality
            Project:    NIZ-IZK-3   Activity:   NIZ-MS-80     Reciept of Permits for
Nizwa GS : Excavation / Municipality
            Project:    NIZ-IZK-3   Activity:   NIZ-SNG-01    Snagging & Desnagging-
Nizwa GS
            Project:    NIZ-IZK-3   Activity:   NIZ-STR-010   Excavation & Levelling
            Project:    NIZ-IZK-3   Activity:   NIZ-STR-020   Anti termite
            Project:    NIZ-IZK-3   Activity:   NIZ-STR-030   PCC
            Project:    NIZ-IZK-3   Activity:   NIZ-STR-040   Waterproofing
            Project:    NIZ-IZK-3   Activity:   NIZ-STR-050   Formwork- Raft -Grid 1-3
            Project:    NIZ-IZK-3   Activity:   NIZ-STR-060   Reinforcement - Raft
-Grid 1-3
            Project:    NIZ-IZK-3   Activity:   NIZ-STR-170 Reinforcement - Raft -
Grid 5-7
            Project:    NIZ-IZK-3   Activity:   NIZ-STR-180 Inspection and clearance
            Project:    NIZ-IZK-3   Activity:   NIZ-STR-200 Concrete - Raft
     Activities with unsatisfied constraints..........................0
     Activities with unsatisfied relationships........................0
     Activities with external dates...................................0