Minutes of The Meeting: Attendees

The minutes summarize Meeting No. 5 that took place on July 6, 2021 for the proposed Avenida Towers project located in Manila. Key discussion topics included JQICI resubmitting the project schedule and safety forms by July 10, submitting other safety plans and permits by July 10 as well, and tentative dates in July for trial mix, excavation/sheet piling works, and structural designs to be signed. Other matters discussed were providing blueprints to WTAPS, developing a combined services drawing, and looking ahead to structural designs in August. The 3-week look ahead schedule was also presented.

Uploaded by

ADEN LIU
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
63 views3 pages

Minutes of The Meeting: Attendees

The minutes summarize Meeting No. 5 that took place on July 6, 2021 for the proposed Avenida Towers project located in Manila. Key discussion topics included JQICI resubmitting the project schedule and safety forms by July 10, submitting other safety plans and permits by July 10 as well, and tentative dates in July for trial mix, excavation/sheet piling works, and structural designs to be signed. Other matters discussed were providing blueprints to WTAPS, developing a combined services drawing, and looking ahead to structural designs in August. The 3-week look ahead schedule was also presented.

Uploaded by

ADEN LIU
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

MINUTES OF THE MEETING

PROJECT: PROPOSED AVENIDA TOWERS LOCATION: Rizal Avenue, Soler St., Sta. Cruz, Manila
AGENDA: WEEKLY MINUTES OF MEETING NO. 5 DATE: 6-Jul-21

ATTENDEES:
(Name) (Pos)/(Company) (Name) (Pos)/(Company)
Mr. Aden Liu PM/JQICI Suzenne Tang Donovan PM/ WTAPS
Winston Reaport B. Coordinator/ JQICI Emilio Cua P.I.C/ WTAPS
Ron Jason Selga P.I.C/JQICI Emor Paul Toribio Proj. Engr/WTAPS
Al Noel Tordilla Civil E./ JQICI Mario Clarianes Proj. Engr/WTAPS
Jake Mondares T. Head / JQICI Richard Domantay S.O. / WTAPS
Fergus Andojar Surveyor / JQICI Peter Garcia Appleland
Sonny Auditor S.O. / JQICI
Christian Periamesa P.I.C / ASDEC
Robert Melendrez Sup. / ASDEC

DISCUSSION TOPICS
Item Particular Action by/ Action Req'd Due By Status / Remarks
1.0 GENERAL REQUIREMENTS

A. Avenida Master Project Schedule inc. Executive Summary Schedule JQICI/Re-submit

7/10/2021 - Adopt WTAPS format/ safety forms are


B. Const'n General Forms & Safety forms JQICI/Re-submit already submitted

C. PAINTING OF PERIMETER FENCE JQICI 2nd week of July - complied


2.0 SAFETY REQUIREMENTS
A. Contractor's Health & Safety Plan (EHS) JQICI/For Submission 7/10/2021
B. Covid Case Action Plan(Flow Chart) JQICI/For Submission 7/10/2021
C. Emergency Response Plan Inc. Evac. Plan including ASDEC JQICI/For Submission 7/10/2021 -already submitted for mgt. review
D. Job Safety Analysis (Temfacil) JQICI/For Submission 7/10/2021
E. Excavation Permit (form) JQICI/For Submission 7/10/2021
JQICI/For Submission 7/10/2021 -issuance of employee warning notice
F. Violation of Management Protocol -JQICI will not implement penalties
3.0 STRUCTURAL
A. Methodology / Method Statement / Risk Assessment 7/5/2021 submiited and for review
- Excavation 7/5/2021 submiited and for review
- Sheetpiling 7/5/2021 - For checking of verticality every 2m
- Pile Hacking 7/5/2021 not yet complied
- Slope Protection 7/5/2021

B. Schedule of materials and specs. (Sheet pile, Soldier pile, etc.)

Design report / calculations and duly signed by geodetic (structural) - Tentative date July 7-14, 2021 -
C. To be signed by Structural Engineer
engineer or consultant.

D. Keyplans / shopdrawings (connection details, sections and phase sequence)

E. Certificate of equipments JQICI/On-going - TPI will be on site together with Project


manager representative.

- Include Equipment Specs and Capacities

4.0 AGENDA

A. Trial Mix (Powermix) -tentative date July 15-22,2020

B. Excavation/Sheetpiling Works
C. Rebar Supplier
D. Waterstop Supplier
E. Soil Poisoning Supplier

5.0 OTHER MATTERS


- PM Aden Liu said that the Owner will
A. Project management ask JQICI to provide Blueprints of FCD for project site. provide us a copy of Blueprints of FCD
- JQICI to provide 2 Copies of Blue prints to
B. Request of FCD CAD files from designers WTAPS
- waiting for the designated trade
contractors for MEPF and clarification of
contract regarding the development of full
C. Combined Services Drawing (CSD) combined services drawings

D. TOWER CRANE DETAIL CONNECTION & FTG. STRUCTURAL DESIGN & Earliest August 2021
ANALYSIS W/ SIGNED BY STRUCTURAL ENGR.

E. Alimak Detail Connection w/ signed by Structural Engr. Earliest August 2021

F. SITE UTILIZATION PLAN 7/6/2021 -already submitted for mgt. review

G.
JQICIto submit RFA proposed RC wall Instead of Precast wall as light
precast wall and equivalent strength

H. Material
conduct of crack mapping / existing survey for bldg.finding point
I. list
(structural ,
J. Order
3 of Rebar
supplier ) 3 supplier Quantity and value
K. 3 incident Report (FFUP)
L. LINK ZOOM MEETING W/ OWNER & PM

Prepared by: RON JASON SELGA Noted by:


PIC-JQICI WTAPS- MANAGEMENT

Noted by: MR. ADEN LIU


PM-JQICI
1 of 3
MINUTES OF THE MEETING

PROJECT: PROPOSED AVENIDA TOWERS LOCATION: Rizal Avenue, Soler St., Sta. Cruz, Manila
AGENDA: WEEKLY MINUTES OF MEETING NO. 5 DATE: 6-Jul-21

2 of 3
Project Name : : Avenida Towers and Commercial Center Date: July 07, 2021
Location : : Rizal Ave., cor. Soler St. , Sta. Cruz, Manila, MM
Subject : : 3-Week Look ahead Schedule

DURATION Week- 1 Week- 2 Week- 3


ITEM ACTIVITIES (days) 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1 TEMFACIL
- Office Supplies 18 X X X X X X X X X X X X X X X X X X
- Temporary CR near Offices 5 X X X X X
-Warehouse/ Isolation area 3 X X X

2 Dewatering 21 X X X X X X X X X X X X X X X X X X X X X
3 Delivery of Materials: Sheet Pile, I-beams 18 X X X X X X X X X X X X X X X X X X
4 Sheet Pile Driving 18 X X X X X X X X X X X X X X X X X X
5 Hauling-out of Excavated Soil and Debris 4 X X X X
6 Survey works 18 X X X X X X X X X X X X X X X X X X

PREPARED BY: CHECKED BY: NOTED BY:


ENGR. JAKE MONDARES ENGR. RON JASON SELGA MR. ADEN LIU
TECH.HEAD/STRUCTURAL ENGR. PROJECT-IN-CHARGE PROJECT MANAGER