Water Supply Project Overview
Water Supply Project Overview
Overhead and
22393245.93 22393245.93
3 Contingencies
bution, Rs.
Community
Costs
891880.39
18847022.03
11914595.70
0.00
31653498.12
31653498.12
35.49
Table 4.1 : Sustainibility Analysis
A.Manpower Cost
Salary per month Salary per year
S.No. Title No. of Person
Rs. Rs.
1 Accountant cum Manager 1 13000 169000
2 Pump Operator 1 11000 143000
3 Assitant Pump Operator 8500 0
4 Plumber 1 8500 110500
5 Meter Reader 1 8500 110500
6 Chowkidar/ Helper 1 7500 97500
Sub-Total 630,500.00
B.Energy Cost
Total unit per Rate per unit Cost per Year
S.No. Description
Year KWH Rs. Rs.
Electricity cost for runnning
131400 4.5 591300
1 pumps @6 hours per day
@ 7.5 % of
2 Transformer charge 44348
electricity cost
Sub-Total 635648
C.Electro-Mechanical Cost
Initial cost of Rate of Depreciation
S.No. Item Cost per Year Rs.
Item Rs. per Year Rs.
Sustainability Funds
1 Fund for Emergency (@5% of Total) 127217
2 Fund for Capital Investment (@10% of Total) 254435
8 50mm Dia MC. G I pipe for gravel packing . 12.00 Rm 992.45 11909.40
Well development by drilling Rig machine for well size of 6'' -12''
2
dia ((water jetting ) .
125.00 m 176.00 22000.00
b.step drawdwon test (at least 4 steps to 36 hrs ) . 1.00 well 34716.00 34716.00
c. Recovery test (for 12 hrs. ) . 1.00 well 15796.00 15796.00
6 Water quality test ( parameters as per NS DWQ ) . 1.00 L. S. 3685.00 3685.00
Submission of well completion report with , pumping test analysis
7
& water quality analysis report .( 3 Copies )
1.00 Job 5500.00 5500.00
Total Section " D " 309705.00
Total ( A+B+C+D) 2195177.65
Value Added Tax (VAT) @ 13% of Total 285373.09
Grand Total 2480550.74
Abstract of Cost
Name of Project: Dhanaura Water Supply Project
Name of Work: Pipe piece and Pipe Fittings for Distribution Pipelines
Description Quantity
Total Unit
Air Pipeline Quantity Rate,Rs Amounts,Rs
S.No. Unit Washout
Structures Junctions valve End
valves
s Points
No of structure 18 3 4 15
150 mm GI Medium class pipe
1 piece-90 cm long pc 9 9 1392.30 12530.70
Description Quantity
Total Unit
Air Pipeline Quantity Rate,Rs Amounts,Rs
S.No. Unit Washout
Structures Junctions valve End
valves
s Points
No of structure 18 3 4 15
31 150/160 GI/HDPE Flange set 8 8 3400.00 27200.00
32 125/140 GI/HDPE Flange set 8 8 3200.00 25600.00
33 100/125 GI/HDPE Flange set 0 0 2600.00 0.00
34 100/110 GI/HDPE Flange set 7 7 2400.00 16800.00
35 80/90 GI/HDPE Flange set 8 2 10 1650.00 16500.00
36 65/75 GI/HDPE Flange set 2 2 4 1350.00 5400.00
37 50/63 mm brass union set 3 3 6 1472.00 8832.00
38 40/50 mm brass union set 3 3 6 870.00 5220.00
39 32/40 mm brass union set 2 2 603.00 1206.00
40 25/32 mm brass union set 1 1 426.00 426.00
41 20/25 mm brass union set 2 2 4 383.00 1532.00
42 15/20 mm brass union set 1 2 3 180.00 540.00
43 150 mm GI union set 9 9 5500.00 49500.00
44 125 mm GI union set 6 2 8 2075.00 16600.00
45 100 mm GI union set 6 2 8 1512.00 12096.00
46 80 mm GI union set 7 2 9 1335.00 12015.00
47 65 mm GI union set 1 1 570.00 570.00
48 50 mm GI union set 2 2 500.00 1000.00
49 40 mm GI union set 3 3 400.00 1200.00
50 32 mm GI union set 1 1 300.00 300.00
51 25 mm GI union pc 0 0 220.00 0.00
52 20 mm GI union 2 2 165.00 330.00
53 15 mm GI union 1 1 115.00 115.00
54 150 mm GI elbow pc 2 2 500.00 1000.00
55 150 mm GI Nipple pc 19 19 1700.00 32300.00
56 125 mm GI Nipple pc 8 2 10 1475.00 14750.00
57 100 mm Gi Nipple pc 7 2 9 446.00 4014.00
58 80mm Gi Nipple pc 14 2 2 18 378.00 6804.00
59 65mm Gi Nipple pc 4 2 6 272.00 1632.00
60 50mm Gi Nipple pc 9 8 17 250.00 4250.00
61 40mm Gi Nipple pc 9 3 12 200.00 2400.00
62 32mm Gi Nipple pc 4 4 150.00 600.00
63 25mm Gi Nipple pc 1 1 130.00 130.00
64 20mm Gi Nipple pc 5 2 7 110.00 770.00
65 15 mm Gi Nipple 3 2 5 77.00 385.00
66 150/100 mm GI reducing socket pc 1 1 1010.00 1010.00
67 125/100 mm GI reducing socket pc 2 2 655.00 1310.00
68 80/65 mm GI reducing socket pc 1 1 600.00 600.00
69 32/25 mm GI reducing socket pc 1 1 600.00 600.00
70 150/150/150 GI equal tee pc 1 1 3000.00 3000.00
71 100/100/80 GI unequal tee pc 1 1 4500.00 4500.00
72 100/80/50 GI unequal tee pc 2 2 6800.00 13600.00
73 150/150/125 GI unequal tee pc 1 1 4500.00 4500.00
74 125/80/20 GI unequal tee pc 1 1 4000.00 4000.00
75 80/80/32 GI unequal tee pc 1 1 3000.00 3000.00
Name of Project: Dhanaura Water Supply Project
Name of Work: Pipe piece and Pipe Fittings for Distribution Pipelines
Description Quantity
Total Unit
Air Pipeline Quantity Rate,Rs Amounts,Rs
S.No. Unit Washout
Structures Junctions valve End
valves
s Points
No of structure 18 3 4 15
76 150/150/65 GI unequal tee pc 1 1 3000.00 3000.00
77 150/150/15 GI unequal tee pc 1 1 2000.00 2000.00
78 125/125/50 GI unequal tee pc 1 1 2000.00 2000.00
79 150/125/20 GI unequal tee pc 1 1 3000.00 3000.00
80 125/100/40 GI unequal tee pc 1 1 4500.00 4500.00
81 80/40/40 GI unequal tee pc 1 1 4000.00 4000.00
82 150/150/20 GI unequal tee pc 0 3000 0.00
83 80/80/20 GI unequal tee pc 0 3000 0.00
84 150 mm CIDF Sluice Valve pc 5 5 14200 71000.00
85 125 mm CIDF Sluice Valve pc 3 1 4 12000 48000.00
86 100 mm CIDF Sluice Valve pc 2 1 3 9200 27600.00
87 80 mm CIDF Sluice Valve pc 5 1 6 6800 40800.00
88 65 mm CIDF Sluice Valve pc 1 1 5700 5700.00
89 50 mm Gate valve pc 3 3 5500 16500.00
90 40 mm Gate valve pc 3 3 3567 10701.00
91 32 mm gate valve pc 1 1 2624 2624.00
92 20 mm Gate valve 0 0 1143 0.00
93 15 mm Gate valve 2 2 832 1664.00
94 20 mm CI Air Valve pc 0 3880 0.00
95 150 mm dia D.I. Surface Valve box set 14 3 17 4599 78183.00
96 100 mm dia G.I. Pipe Valve box set 4 4 4735.5 18942.00
97 Valbox Key pc 14 14 657.3 9202.20
98 50 mm GI End Cap pc 8 8 250 2000.00
99 40 mm GI End Cap pc 3 3 195 585.00
100 32 mm GI End Cap pc 0 0 175 0.00
101 25 mm GI End Cap pc 0 0 90 0.00
102 20 mm GI End Cap pc 2 2 70 140.00
103 15 mm GI End Cap pc 2 2 39.5 79.00
Sub-Total : 836452.40
10 % For unforseen items 83645.24
Total 920097.64
Transportation @ 2.5% 23002.44
Total after transportation 943100.08
VAT @ 13 % 122603.01
Total Cost of Procurement 1065703.09
325
ABSTRACT OF COSTS
3 Flat Brick soling with sand in foundation 4.84 sqm 1067.87 5168.49
4 Brick soling on edge with sand in base 4.00 sqm 1848.60 7394.40
5 First class brick work in 1:4 cement mortar: 0.69 cum 15745.69 10864.53
7 P.C.C. 1:2:4 (M15) in tie beam and platform 1.67 cum 16490.55 27539.22
10 12.5mm thick plaster in 1:4 cement mortar 11.26 sqm 357.61 4026.69
21
Supply and installation of water level set #REF!
indicator #REF! 16,500.00
S. No. Description Quantity Unit Rate Amount
22
PCC 1:1:5:3 for duck foot bend with m3 #REF!
foundation #REF! 18,325.05
23 Scafolding works as necessary for
the construction and completion of
OHT 1.00 set 150,000.00 150,000.00
24
Water Proofing Compound (Silica
#REF! kg 316.60 #REF!
Admixture) @3.5kg per bag of cement
Total #REF!
Remarks
Remarks
COST ESTIMATE
2 Supply of Pipes
Supply and Installation of 200mm Dia GI
2.a 300.00 m 4351.70 1305510.00
Pipe
Miscellaneous ( GI well cap, , Elbow
2.b ,Flange , cross bar, centralizer, bottom plug , 1.00 LS 40000.00 40000.00
clamps,etc.
Supply and Installation of 200mm Dia Sluice
3 Valve 1.00 No 29233.55 29233.55
Total 1574308.11
Value Added Tax (VAT) @ 13% of Total 204660.05
Grand Total 1778968.16
NOTE: IN case of Multiple Drilling the Distance between two Borehole Should be of Minimum 300m
to prevent Drawdown
COST ESTIMATE
S.No Description of Work Quantity Unit Unit Rate Rs. Total Cost Rs. Remarks
c Column and bracing and stair case upto 6m 5.82 Cum 19521.05 113612.51
d Column and bracing and stair case upto 9m 5.82 Cum 20717.05 120573.23
e Column bracing and stari case upto 12m 7.11 Cum 21913.05 155801.79
f Column bracing and stir case upto 15m 7.11 Cum 23109.05 164305.35
g Column bracing and stair case upto 17.4m 3.07 Cum 24305.05 74616.50
h Ring beam and stair case 17m-18m 8.78 Cum 24305.05 213398.34
i Bottm dome Tie beam, conimal, Balcony 20.78 Cum 25501.05 529911.82
Remaning Portion of cylindrical wall upto 24m
j 24.37 Cum 26697.05 650607.11
above
9 Earth filling in foundation in ordinary soil 190.06 Cum 615.94 117065.56
Erection centaning and shuttering work upto
10a 40.78 Sqm 736.28 30025.50
height. Ground level.
Column
b Upto 4m height 51.20 Sqm 1096.10 56120.32
c Upto 7m height 40.80 Sqm 1402.39 57217.51
d Upto 10m height 38.40 Sqm 2194.51 84269.18
e Upto 13m height 38.40 Sqm 2617.27 100503.17
f Upto 16m height 38.40 Sqm 2954.63 113457.79
g Upto 17.40m height 17.92 Sqm 3320.24 59498.70
Tank from height 17.40m to 25.65m wall
h 277.84 Sqm 3118.07 866324.57
portion
i Dome portion Beam 161.84 Sqm 3118.07 504628.45
Beams:-
j Upto 4m height 21.60 Sqm 1021.10 22055.76
k Upto 7m height 21.60 Sqm 1324.57 28610.71
l Upto 10m height 21.60 Sqm 2119.52 45781.63
m Upto 13m height 21.60 Sqm 2542.06 54908.50
n Upto 16m height 21.60 Sqm 2873.34 62064.14
Staircase:-
o Upto 4m height 8.04 Sqm 1200.10 9648.80
p Upto 7m height 4.20 Sqm 1480.97 6220.07
q Upto 10m height 6.42 Sqm 2275.92 14611.41
r Upto 13m height 6.42 Sqm 2698.46 17324.11
s Upto 16m height 6.42 Sqm 3035.82 19489.96
t Upto 19m height 6.42 Sqm 3373.19 21655.88
u Upto 19.65m height 4.03 Sqm 3373.19 13593.96
11 Steel Work for R.C.C. 24261.03 kg 129.56 3143259.05
Total 18173.35
Value Added Tax (VAT) @ 13% of Total 2362.54
Grand Total 20535.89
same 1100
COST ESTIMATE
Name of Project: Dhanaura Water Supply Project
Name of Work: Installation of Surface Valve Box (For Valve Ø 50mm and above)
Unit Rate Total Cost
S.No. Description of Works Quantity Unit Remarks
Rs. Rs.
1 Earthwork in excavation in ordinary soil 0.90 cum 615.94 554.35
3 Flat brick soling on the top of sand layer 0.20 cum 1067.87 213.57
Total 4885.44
Value Added Tax (VAT) @ 13% of Total 635.11
Grand Total 5520.55
1980
same
COST ESTIMATE
Name of Project: Dhanaura Water Supply Project
Name of Work: Installation of GI Pipe Valve Box (For Valve Ø up to 40 mm)
Unit Rate Total Cost
S.No. Description of Works Quantity Unit Remarks
Rs. Rs.
Earthwork in excavation for foundation in
1 0.60 cum 615.94 369.56
ordinary soil
Total 2343.87
Value Added Tax (VAT) @ 13% of Total 304.70
Grand Total 2648.57
QUANTITY AND COST ESTIMATE
Name of Project: Dhanaura Water Supply Project
Name of Work: Office Building
S.NO. DETAILS Nos. LENGTH BREADTH HEIGHT QUANTITY UNIT RATE AMOUNT REMARKS
2
Earth work in excavation in foundation in
ordinary soil lead up to 30m lift up to 1.50 m
steaking the soil.10 m away from foundation
trenches as per specification & instruction of site
engineer
For Column 15 1.524 1.524 1.524 53.09 cu.m.
For tie beam A-A,C-C,E-E 3 12.478 0.3 0.875 9.82 cu.m.
For tie beam 1-1,3-3,4-4,6-6,7-7 5 9.43 0.3 0.875 12.37 cu.m.
Wall D-D 1 3.501 0.45 0.5 0.78 cu.m.
Wall 2-2 1 3.656 0.45 0.5 0.82 cu.m.
Wall 5-5 1 3.658 0.45 0.5 0.82 cu.m.
Wall 6-6 1 7.316 0.45 0.5 1.64 cu.m.
Deductions 30 1.524 0.3 0.875 12.00 cu.m.
67.34 cu.m. 615.94 41477.39
3 Earth back filling in foundation trenches with
compaction
Total quantity of excavated earth 67.34 cu.m.
Back filling Quanitity ( 10% of excavated) 6.73 cu.m. 615.94 4145.27
5 Concreting work
Plain cement concrete M 15 (1:2:4) with cement,
sand &10 to 38mm stone ballast Proper mixing ,
laying &compaction , curing the Job all complete
Foundation 15 1.524 1.524 0.075 2.61 cu.m.
For tie beam A-A,C-C,E-E 3 12.478 0.23 0.075 0.64 cu.m.
For tie beam 1-1,3-3,4-4,6-6,7-7 5 9.43 0.23 0.075 0.81 cu.m.
Meeting Hall 1 5.6134 3.937 0.05 1.10 cu.m.
Verandah 1 4.572 1.524 0.05 0.34 cu.m.
Cash Counter 1 2.413 3.2766 0.05 0.39 cu.m.
Toilet and Space 1 3.937 1.3716 0.05 0.26 cu.m.
Staircase 1 3.937 1.98 0.05 0.38 cu.m.
Passage 1 3.201 1.219 0.05 0.19 cu.m.
Chairman Office 1 3.937 3.6322 0.05 0.71 cu.m.
Accountant office 1 3.7338 3.5052 0.05 0.65 cu.m.
Wall D-D 1 3.501 0.45 0.05 0.07 cu.m.
Wall 2-2 1 3.656 0.45 0.05 0.08 cu.m.
Wall 5-5 1 3.658 0.45 0.05 0.08 cu.m.
Wall 6-6 1 7.316 0.45 0.05 0.16 cu.m.
Deductions 30 1.524 0.23 0.075 0.78 cu.m.
7.69 cu.m. 16490.55 126812.32
6 R.C.C. work
Plain cement concrete M 20(1:1.5:3) work for
R.C.C column, beam & slab with cement, sand
&10 to 38mm stone ballast Proper mixing ,
laying &compaction with vibrator , curing the
Job all complete
16 Cement Wash on Inner & Outer Walls 512.41 Sqm 370.70 189950.38
17 Enamel Paint Works in Doors & Windows (Double the Area of Flush Door) 24.66 Sqm 307.74 7588.86
18 MS Grill Work for Window and Door 1 13.50 Sq.m. 33.93 458.06 Kg 129.56 59346.25
Sub-Total(A) 11702868.03
Total 2809808.48
Value Added Tax (VAT) @ 13% of Total 365275.10
Grand Total 3175083.58
ABSTRACT OF COST
S Item Unit Unit Rate Breadth Height Transmission Line Distribution Line Total Total Total
No. Rs. Length m Qty. Amount Length Qty. Amount Length m Qty. Amount(Rs)
A E/W in excavation in
i) Ordinary soil m3 615.94 0.45 0.9 0.00 0.00 20509 8306.15 5116090.03 20509 8306.15 5116090.03
ii) Ordinary Soil m3 615.94 0.60 0.9 0 0.00 0.00 9691 5233.14 3223300.25 9691 5233.14 3223300.25
0.00 0
B Back filling of pipe line 0.00 0
trench 0.00 0
i) Ordinary soil m3 615.94 0.45 0.9 0 0.00 0.00 20509 8306.15 5116090.03 20509 8306.15 5116090.03
ii) Ordinary Soil m3 615.94 0.60 0.9 0 0.00 0.00 9691 5233.14 3223300.25 9691 5233.14 3223300.25
Sub Total (A+B) 0.00 16678780.56 0 16678780.56
Vat 13% 0.00 2168241.47 0 2168241.47
Total (A+B) 0 0.00 30200 18847022.03 30200 18847022.03
Total: 1 74 932.65
Value Added Tax (VAT) @ 13% of Total 22 741.24
Grand Total 1 97 673.89
COST ESTIMATE
Name of Project: Dhanaura Water Supply Project
Name of Work: Sanitation - Awareness Programme
Unit Rate Total Cost
S.No. Description of Works Unit Quantity Remarks
Rs. Rs.
A Development Phase Activities (Project Level)
Stakeholders Meeting at District Level: Program
preparation and appraisal meeting of District Water
1 No. 2 7260.00 14520.00
Orientation to head master,
Supply and Sanitation secretaryCommittee
Coordination of village
development
members and committee, chairperson
other stakeholders of School
(30 Persons)
Management Committees and Parent-Teacher's
Associations, Water Supply and Sanitation Users
2 Committees, Women's Groups, local NGOs and Clubs, No. 2 65521.50 131043.00
and prominent social workers (No. of participants :25;
Duration: 3 days)
B1 School associated program ( SLTS)
Orientation to teachers, School Management
1 Committee and Parent Teacher Association personnel No. 5232.70
(1 day)
2 Orientation to members of Child Club (1 day) No. 3025.00
3 Establishment of sanitation multi facet table No. 4840.00
4 Construction of toilet and urinal % 121000.00
5 Provision for water supply facilities % 30250.00
Establishment of fund for maintenance of water supply
6 % 3630.00
and sanitation facilities
Sub-Total [B1] 0.00
B2 VDC/Community associated program
Discussion meeting with facilitator, community
1 No. 4 665.50 2662.00
mobilizer, women group etc. (for 1 day)
Social mapping, establishment of sanitation notice
2 No. 4 3630.00 14520.00
board and creation of awareness materials
Monitoring of sanitation activities of schools and
3 communities by Water Supply and Sanitation No. 8 8470.00 67760.00
Division/Sub-Division Office
Monitoring and facilitation of sanitation of sanitation
4 activities of schools and communities through local No. 8 2420.00 19360.00
NGO/Club/Women's group/ CBO
Facilitation for sanitation promotion and construction
5 of sanitary latrines in project service area through local No. 242.00 0.00
NGO/Club/Women's group/CBO
Appreciation-Recognition/Establishment of Revolving
6 Fund/Support (for construction of household sanitary No. 1452.00 0.00
latrines)
Promotion of sanitation activities in the communities
7 for the continuation of total sanitation after attaining No. 121.00 0.00
open defecation free state
Sub-Total [B2] 104302.00
Total [B1+B2] 104302.00
Grand Total [A+B] 249865.00
.
6600.00
59565.00
4757.00
2750.00
4400.00
110000.00
27500.00
3300.00
605.00
3300.00
7700.00
2200.00
220.00
1320.00
110.00
ABSTRACT OF COST
Working Working
Working Pressure Working Pressure
Pressure 2.5 Pressure 4.0
Pipe size Kg/sqcm (Series Kg/sqcm (Series 6.0 Kg/sqcm (Series 10.00 Kg/sqcm Pipe size
Outside IV) (Series V) Outside
II) III)
Diameter Diameter
mm Average Average Average Average mm
Price Price Price Price
Weight Weight Weight Weight
Rs./m Rs./m Rs./m Rs./m
Kg/m Kg/m Kg/m Kg/m
16 0 0.00 0.00 0.092 25.02 16
20 0 0.00 0.00 0.134 36.45 20
25 0 0.00 0.00 0.202 54.94 25
32 0 0.00 0.226 61.47 0.334 90.85 32
40 0 0.251 68.27 0.35 95.20 0.514 139.81 40
50 0.00 0.378 102.82 0.542 147.42 0.796 216.51 50
63 0.403 109.62 0.585 159.12 0.85 231.20 1.269 345.17 63
75 0.557 151.50 0.846 230.11 1.191 323.95 1.782 484.70 75
90 0.779 211.89 1.22 331.84 1.715 466.48 2.568 698.50 90
110 1.185 322.32 1.703 463.22 2.545 692.24 3.801 1033.87 110
125 1.53 416.16 2.289 622.61 3.293 895.70 4.962 1349.66 125
140 1.897 515.98 2.901 789.07 4.15 1128.80 6.209 1688.85 140
160 2.453 667.22 3.773 1026.26 5.355 1456.56 8.079 2197.49 160
180 3.148 856.26 4.762 1295.26 6.8 1849.60 10.256 2789.63 180
200 3.876 1054.27 5.89 1602.08 8.391 2282.35 12.62 3432.64 200
225 4.822 1311.58 7.445 2025.04 10.544 2867.97 16.014 4355.81 225
250 6.012 1635.26 9.187 2498.86 13.041 3547.15 19.757 5373.90 250
280 7.417 2017.42 11.455 3115.76 16.327 4440.94 24.708 6720.58 280
315 9.417 2561.42 14.508 3946.18 20.691 5627.95 31.16 8475.52 315
350 11.957 3252.30 18.382 4999.90 26.243 7138.10 39.635 10780.72 350
400 16.221 4412.11 23.343 6349.30 33.309 9060.05 50.344 13693.57 400
450 19.163 5212.34 29.251 7956.27 42.065 11441.68 63.598 17298.66 450
500 23.836 6483.39 36.406 9902.43 51.9 14116.80 78.735 21415.92 500
Note: Above rates are calculated as per the weight chart specified in NS 40.
The above prices are Ex-factory price excluding Value Added Tax.
TRANSPORTATION COST OF MAJOR CONSTRUCTION MATERIALS
1 Reinforcement M. Ton 1000.0 6 66 1 0 67 4.15 1340.87 3.041 1581.32 1604.42 90000.00 91604.42 M.Ton
2 Cement Bag 50.0 120 66 1 0 67 4.15 67.04 3.041 1581.32 80.22 850.00 930.22 Bag
3 Bricks Nos. 3.0 2000 37 3 0 40 2.90 2.81 1.880 977.60 3.30 12.50 15.80 Nos.
4 Aggregate (5-10) mm Cum 1596.0 3.76 49 1 0 50 3.30 1701.44 2.310 1201.20 2020.91 1450.00 3470.91 Cum
5 Aggregate (10-20) mm Cum 1596.0 3.76 49 1 0 50 3.30 1701.44 2.310 1201.20 2020.91 1800.00 3820.91 Cum
6 Aggregate (20-40) mm Cum 1596.0 3.76 49 1 0 50 3.30 1701.44 2.310 1201.20 2020.91 1320.00 3340.91 Cum
7 Sand Cum 1500.0 4.00 49 1 0 50 3.30 1599.35 2.310 1201.20 1899.65 600.00 2499.65 Cum
8 Local Wood Cum 700.0 8.57 66 1 0 67 4.15 938.77 3.041 1581.32 1123.29 48000.00 49123.29 Cum
9 Other Kg 1.0 6000 66 1 0 67 4.15 1.34 3.041 1581.32 1.60 0 1.60 Kg
10 Stone Cum 1700.0 3.53 49 1 0 50 3.30 1812.30 2.310 1201.20 2152.58 1162.50 3315.08 Cum
NOTES
* A Truck Capacity of 6 Ton has been taken for the calculation
* Truck Speed of 40, 20 and 10 km per hour has been assumed for Metalled Road, Gravel Road and Earthen Road, respectively.
* Loading and unloading time of 0.75 hour has been assumed
* Average time for one trip = 2 times traveling time + Loading and un loading time has been taken
* 400 Nos. of Bricks = 1 cubic meter of Bricks
* Transportation Rate 1938.61
* Unskilled Labour Wage 520.00 (NRs./Day) has been taken
* Constant Loading and unloading coefficient of 2.5 has been taken for Cement & reinforcement bar.
*Collection of Stone = 2.5 @MD Rs 1162.5
TRANSPORTATION OF CONSTRUCTION MATERIALS BY TRUCK
( FY 2076/077)
Rent of Truck
Truck Cost of 6 MT Capacity (A) NRs. 4400000
Total Working Hours (B) Hrs 10000.00
Working Hour per Year (C) Hrs 2000.00
Diesel per liter NRs. 97.00
Mobil per liter NRs. 715.00
Gear oil per liter NRs. 715.00
Grease per kg NRs. 715.00
Driver's Salary per day (W) NRs. 676.50
Truck Helper wage per Day (V) NRs. 511.50
Cost of one Tyre(T) NRs. 23100.00
II Operation Cost
1 Maintenance Cost
a. Over hauling cost/hour 0.55*A/B NRs. 242
b. Maintenance & Repair cost/hour 0.23*A/B NRs. 101.2
Sub total of (II-1) NRs./hour 343.20
2 Net Operating Cost Per Hour
a) Fuel and lubricant cost per hour
H.S.Disel 5.5 liter 533.50
Mobil 0.1 liter 71.50
Gear oil 0.03 liter 21.45
Grease 0.015 liter 10.73
Sub total of (a) NRs./hour 637.18
b) Spare Parts
Life Span of Tyre (L) 2000 Hrs
Cost of Tyres per hour 6*(T/L) NRs. 69.30
Miscellaneous items NRs. 9.60
Extra NRs. 3.20
Sub total of (b) NRs./hour 82.10
c) Salary
Working Hour per day (N) 8 Hrs
Driver wages per hour W/N NRs. 84.56
Helper wages per hour V/N NRs. 63.94
Loading/Unloading NRs. 95.63
Sub total of (c) NRs./hour 244.13
d) Improvement and other minor repair
Lump Sum NRs./Hour 16.00
Sub total of (d) NRs./Hour 16.00
302.5
0 nos. in 1 pac
613.32
ANALYSIS OF RATES
FISCAL YEAR: 076/077
Item rate
S.No. Description of Work Rate per Unit rate Cost Total cost Contractor's
including CP, Norms
Category Unit Quantity unit Cost Rs. Type Unit Quantity excluding excluding excluding profit (CP)
Rs. (without No.
Rs. VAT, Rs. VAT, Rs. VAT, Rs. @ 15%, Rs.
VAT)
1 Site clearence: Excavating Labourer m.d. 0.16 520.00 83.20 Tools & Plant 3% of labour cost 2.50 85.70 12.86 98.56
15-20cm top soil -For 1 m2 ( T& P)
3 Earthwork in excavation in
boulder and gravel mixed soil with a
with a lift up to 1.5 m and disposal up
to 10 m - For 1 m3 Labourer m.d. 1.59 520.00 826.80 Tools & Plant 3% of labour cost 24.80 851.60 127.74 979.34
4 Earthwork in excavation in
hard soil with a lift up
to 1.5 m and disposal up
to 10 m - For 1 m3 Labourer m.d. 1.25 520.00 650.00 Tools & Plant 3% of labour cost 19.50 669.50 100.43 769.93
8 Flat brick soling with sand Mason m.d. 0.05 760.00 38.00 Brick No. 42.00 15.80 663.60
- For 1 m2 Labourer m.d. 0.10 520.00 52.00 Sand cum 0.07 2499.65 174.98
90.00 838.58 928.58 139.29 1067.87
9 Plain cement concrete work Mason m.d. 1.00 760.00 760.00 Cement Kg 320.00 18.60 5952.00
(P.C.C. 1:2:4) in foundation Labourer m.d. 4.00 520.00 2080.00 Aggregates
and wall including collection 40mm Cum 0.52 3470.91 1804.87
of materials and a lead of 20mm Cum 0.22 3820.91 840.60
30 m - For 1 m3 10mm Cum 0.11 3340.91 367.50
Sand Cum 0.45 2499.65 1124.84
2840.00 10089.81 12929.81 1939.47 14869.28
10 Plain cement concrete work Mason m.d. 1.00 760.00 760.00 Cement Kg 220.00 18.60 4092.00
(P.C.C. 1:3:6) in foundation Labour m.d. 4.00 520.00 2080.00 Aggregates
and wall -For 1 m3 40 mm cum 0.65 3470.91 2256.09
20 mm cum 0.24 3820.91 917.02
Sand Cum 0.47 3340.91 1570.23
2840.00 8835.34 11675.34 1751.30 13426.64
a. 1:4 Mason m.d. 1.50 760.00 1140.00 Cement Kg 100.00 18.60 1860.00
Labourer m.d. 2.20 520.00 1144.00 Sand Cum 0.28 2499.65 699.90
Brick No. 560.00 15.80 8848.00
2284.00 11407.90 13691.90 2053.79 15745.69
a. 1:6 Mason m.d. 1.50 760.00 1140.00 Cement Kg 70.00 18.60 1302.00
Labourer m.d. 2.20 520.00 1144.00 Sand Cum 0.30 2499.65 749.90
Brick No. 560.00 15.80 8848.00
2284.00 10899.90 13183.90 1977.59 15161.49
15 Brick bat filling For-1 m 3 Mason m.d. 1.00 760.00 760.00 Brick bats Cum 1.10 9383.00 10321.30
760.00 10321.30 11081.30 1662.20 12743.50
16 Gravel packing in foundation For -1 m 3 Mason m.d. 1.00 760.00 760.00 Gravel Cum 1.10 3820.91 4203.00
760.00 4203.00 4963.00 744.45 5707.45
17 Salwood work in chaukhat Carpenter m.d. 34.00 760.00 25840.00 Salwood Cum 1.10 195123.29 214635.62
(Door Frame) - For 1 m3 Labor m.d. 3.40 520.00 1768.00 Holdfast No. 92.00 0.00 0.00
Screw No. 184.00 0.00 0.00
27608.00 214635.62 242243.62 36336.54 278580.16
18 Fixing of Salwood Shutter for Door Carpenter m.d. 10.00 760.00 7600.00 Salwood Cum 0.084 195123.29 16390.36
and Windows per 2.11 sqm Labor m.d. 1.00 520.00 520.00 Kabja 150 mm No. 6.00 51.00 306.00
0.00
Cheskini 150 No. 1.00 80.00 80.00
mm
Cheskini 250 No. 1.00 0.00 0.00
mm
Cheskini 300
No. 1.00 0.00 0.00
mm
Locking Set No. 1.00 270.00 270.00
Handle No. 2.00 50.00 100.00
Screw LS 1.00 50.00 50.00
8120.00 17196.36 25316.36 3797.45 29113.81
Rate Per Sqm 13798.01
19 38 mm thick Salwood framed Sk. Labour m.d. 9.00 760.00 6840.00 Salwood cum 0.0490 195123.29 9561.04
glazed shutter for windows- Labour m.d. 0.90 520.00 468.00 3 mm glass sqm 1.085 0.00 0.00
For 1.829*1.22 =2.23 m2 100 mm bolt no. 4.00 74.00 296.00
75 mm hinge no. 8.00 22.00 176.00
Handle no. 2.00 50.00 100.00
Nails kg 0.25 50.00 12.50
7308.00 10145.54 17453.54 2618.03 20071.57
Rate Per Sqm 9000.70
a. 1:2 Mason m.d. 12.00 760.00 9120.00 Cement Kg 900.00 18.60 16740.00
Labor m.d. 16.00 520.00 8320.00 Sand Cum 1.22 2499.65 3049.57
17440.00 19789.57 37229.57 5584.44 42814.01
Rate Per Cum 428.14
b. 1:3 Mason m.d. 12.00 760.00 9120.00 Cement Kg 625.00 18.60 11625.00
Labor m.d. 16.00 520.00 8320.00 Sand Cum 1.28 2499.65 3199.55
17440.00 14824.55 32264.55 4839.68 37104.23
Rate Per Cum 371.04
c. 1:4 Mason m.d. 12.00 760.00 9120.00 Cement Kg 538.00 18.60 10006.80
Labor m.d. 16.00 520.00 8320.00 Sand Cum 1.46 2499.65 3649.49
17440.00 13656.29 31096.29 4664.44 35760.73
Rate Per Cum 357.61
d. 1:6 Mason m.d. 12.00 760.00 9120.00 Cement Kg 382.00 18.60 7105.20
Labor m.d. 16.00 520.00 8320.00 Sand Cum 1.57 2499.65 3924.45
17440.00 11029.65 28469.65 4270.45 32740.10
Rate Per Cum 327.40
20 mm Thick Cement Sand Plaster per
23
100 Sqm
a. 1:3 Mason m.d. 14.00 760.00 10640.00 Cement Kg 960.00 18.60 17856.00
Labor m.d. 19.00 520.00 9880.00 Sand Cum 1.95 2499.65 4874.32
20520.00 22730.32 43250.32 6487.55 49737.87
Rate Per Cum 497.38
b. 1:4 Mason m.d. 14.00 760.00 10640.00 Cement Kg 810.00 18.60 15066.00
Labor m.d. 19.00 520.00 9880.00 Sand Cum 2.20 2499.65 5499.23
20520.00 20565.23 41085.23 6162.78 47248.01
Rate Per Cum 472.48
c. 1:6 Mason m.d. 14.00 760.00 10640.00 Cement Kg 570.00 18.60 10602.00
Labor m.d. 19.00 520.00 9880.00 Sand Cum 2.35 2499.65 5874.18
20520.00 16476.18 36996.18 5549.43 42545.61
Rate Per Cum 425.46
24 3 mm Thick Cement Punning in 1:1 Mason m.d. 0.10 760.00 76.00 Cement Kg 3.36 18.60 62.50
Labor m.d. 0.10 520.00 52.00 Sand Cum 0.00 2499.65 0.00
128.00 62.50 190.50 28.58 219.08
Rate Per Sqm 219.08
25 Brick Soling on Edge Per 10 Sqm Mason m.d. 1.00 760.00 760.00 Brick No. 750 15.80 11850.00
Labor m.d. 3.25 520.00 1690.00 Sand Cum 0.71 2499.65 1774.75
2450.00 13624.75 16074.75 2411.21 18485.96
Rate Per Sqm 1848.60
Two Coats of WPC paint over a coat of
26 Painter m.d. 5.00 760.00 3800.00 WPC Paint Kg 316.60 81.60 25834.56
primer per 100 Sqm
Labor m.d. 5.00 520.00 2600.00
6400.00 25834.56 32234.56 4835.18 37069.74
Rate Per Sqm 370.70
Two Coats of enamel painting on Door
27 Painter m.d. 12.00 760.00 9120.00 Enamel Paint Ltr. 16.00 631.60 10105.60
& Windows per 100 Sqm
Labor m.d. 8.00 520.00 4160.00 Primer Ltr. 8.10 416.60 3374.46
13280.00 13480.06 26760.06 4014.01 30774.07
Rate Per Sqm 307.74
Two Coats of Aluminium painting on
28 Painter m.d. 10.75 760.00 8170.00 Aluminum Paint Ltr. 10.76 631.60 6796.02
Door & Windows per 100 Sqm
Labor m.d. 10.75 520.00 5590.00 Primer Ltr. 8.10 416.60 3374.46
Khaski No. 4.00 0.00 0.00
13760.00 10170.48 23930.48 3589.57 27520.05
Rate Per Sqm 275.20
29 Sand Filling per Cum Labor m.d. 0.65 520.00 338 Sand Cum 1.10 2499.65 2749.62
338 2749.62 3087.62 463.14 3550.76
Rate Per Cum 3550.76
Wooden formwork for RCC & PCC
including selection, collection of
materials, cutting, nailing, fixing in
position as per Drg. Removal and
30 disposal with a lead of 30 m- For 1
Sqm (Quanitity of required for 1 Sqm
formwork=0.526 Cum. Wood can be
used 8 times for the formwork and after
then 25% cost of the wood is
recovered. So the quantity of wood
required for 1 Sqm = 0.00658 Cum)
Carpenter m.d. 0.172 760.00 130.72 Wood Cum 0.00658 49123.29 322.99
Labor m.d. 0.257 520.00 133.64 Nail Kg 0.250 211.60 52.90
264.36 375.89 640.25 96.04 736.29
Rate Per Sqm 736.29
Wooden Formwok for the ovehead
31 tank which include the supply of
materials fitting dismantling of
formwork nails etc.
a. For foundation per 10 Sqm Carpenter m.d. 1.72 760.00 1307.20 Wood Cum 0.06575 49123.29 3229.86
Labor m.d. 2.57 520.00 1336.40 Nail Kg 2.500 211.60 529.00
2643.60 3758.86 6402.46 960.37 7362.83
Rate Per Sqm 736.28
b. For column per 10 Sqm
i.Height up to 4m Carpenter m.d. 3.75 760.00 2850.00 Wood Cum 0.06575 49123.29 3229.86
Labor m.d. 5.62 520.00 2922.40 Nail Kg 2.500 211.60 529.00
5772.40 3758.86 9531.26 1429.69 10960.95
Rate Per Sqm 1096.10
ii.Height up to 4m - 7m Carpenter m.d. 4.75 760.00 3610.00 Wood Cum 0.08225 49123.29 4040.39
Labor m.d. 7.62 520.00 3962.40 Nail Kg 2.750 211.60 581.90
7572.40 4622.29 12194.69 1829.20 14023.89
Rate Per Sqm 1402.39
iii.Height up to 7m - 10m Carpenter m.d. 5.75 760.00 4370.00 Wood Cum 0.18475 49123.29 9075.53
Labor m.d. 9.62 520.00 5002.40 Nail Kg 3.000 211.60 634.80
9372.40 9710.33 19082.73 2862.41 21945.14
Rate Per Sqm 2194.51
iv.Height up to 10m - 13m Carpenter m.d. 6.75 760.00 5130.00 Wood Cum 0.221 49123.29 10856.25
Labor m.d. 11.60 520.00 6032.00 Nail Kg 3.500 211.60 740.60
11162.00 11596.85 22758.85 3413.83 26172.68
Rate Per Sqm 2617.27
v.Height up to 13m - 16m Carpenter m.d. 7.75 760.00 5890.00 Wood Cum 0.243 49123.29 11936.96
Labor m.d. 13.60 520.00 7072.00 Nail Kg 3.750 211.60 793.50
12962.00 12730.46 25692.46 3853.87 29546.33
Rate Per Sqm 2954.63
v.Height up to 16m - 18m Carpenter m.d. 8.75 760.00 6650.00 Wood Cum 0.27 49123.29 13263.29
Labor m.d. 15.60 520.00 8112.00 Nail Kg 4.00 211.60 846.40
14762.00 14109.69 28871.69 4330.75 33202.44
Rate Per Sqm 3320.24
c. Water Tank
i. Dome portion of the floor & top slab
Carpenter m.d. 7.60 760.00 5776.00 Cum 0.27 49123.29 13263.29
at 17.4 m height per 10 Sqm Wood
Labor m.d. 13.90 520.00 7228.00 Nail Kg 4.00 211.60 846.40
13004.00 14109.69 27113.69 4067.05 31180.74
Rate Per Sqm 3118.07
ii. Wall of the tank Carpenter m.d. 6.44 760.00 4894.40 Wood Cum 0.27 49123.29 13263.29
Labor m.d. 12.10 520.00 6292.00 Nail Kg 4.00 211.60 846.40
11186.40 14109.69 25296.09 3794.41 29090.50
Rate Per Sqm 2909.05
d. Stairs
i. Height up to 4m Carpenter m.d. 4.20 760.00 3192.00 Wood Cum 0.07 49123.29 3438.63
Labor m.d. 6.30 520.00 3276.00 Nail Kg 2.50 211.60 529.00
6468.00 3967.63 10435.63 1565.34 12000.97
Rate Per Sqm 1200.10
ii. Height up to 4m - 7m Carpenter m.d. 5.20 760.00 3952.00 Wood Cum 0.082 49123.29 4028.11
Labor m.d. 8.30 520.00 4316.00 Nail Kg 2.75 211.60 581.90
8268.00 4610.01 12878.01 1931.70 14809.71
Rate Per Sqm 1480.97
iii. Height up to 7m - 10m Carpenter m.d. 6.20 760.00 4712.00 Wood Cum 0.185 49123.29 9087.81
Labor m.d. 10.30 520.00 5356.00 Nail Kg 3.000 211.60 634.80
10068.00 9722.61 19790.61 2968.59 22759.20
Rate Per Sqm 2275.92
iv. Height up to 10m - 13m Carpenter m.d. 7.20 760.00 5472.00 Wood Cum 0.221 49123.29 10856.25
Labor m.d. 12.30 520.00 6396.00 Nail Kg 3.500 211.60 740.60
11868.00 11596.85 23464.85 3519.73 26984.58
Rate Per Sqm 2698.46
v. Height up to 13m - 16m Carpenter m.d. 8.20 760.00 6232.00 Wood Cum 0.243 49123.29 11936.96
Labor m.d. 14.30 520.00 7436.00 Nail Kg 3.750 211.60 793.50
13668.00 12730.46 26398.46 3959.77 30358.23
Rate Per Sqm 3035.82
vi. Height up to 16m - 18m Carpenter m.d. 9.20 760.00 6992.00 Wood Cum 0.265 49123.29 13017.67
Labor m.d. 16.30 520.00 8476.00 Nail Kg 4.000 211.60 846.40
15468.00 13864.07 29332.07 4399.81 33731.88
Rate Per Sqm 3373.19
e. Beam
i. Height up to 4m Carpenter m.d. 3.30 760.00 2508.00 Wood Cum 0.066 49123.29 3242.14
Labor m.d. 5.00 520.00 2600.00 Nail Kg 2.500 211.60 529.00
5108.00 3771.14 8879.14 1331.87 10211.01
Rate Per Sqm 1021.10
ii. Height up to 4m - 7m Carpenter m.d. 4.30 760.00 3268.00 Wood Cum 0.082 49123.29 4028.11
Labor m.d. 7.00 520.00 3640.00 Nail Kg 2.750 211.60 581.90
6908.00 4610.01 11518.01 1727.70 13245.71
Rate Per Sqm 1324.57
iii. Height up to 7m - 10m Carpenter m.d. 5.30 760.00 4028.00 Wood Cum 0.185 49123.29 9087.81
Labor m.d. 9.00 520.00 4680.00 Nail Kg 3.000 211.60 634.80
8708.00 9722.61 18430.61 2764.59 21195.20
Rate Per Sqm 2119.52
iv. Height up to 10m - 13m Carpenter m.d. 6.30 760.00 4788.00 Wood Cum 0.221 49123.29 10856.25
Labor m.d. 11.00 520.00 5720.00 Nail Kg 3.500 211.60 740.60
10508.00 11596.85 22104.85 3315.73 25420.58
Rate Per Sqm 2542.06
v. Height up to 13m - 16m Carpenter m.d. 7.30 760.00 5548.00 Wood Cum 0.243 49123.29 11936.96
Labor m.d. 13.00 520.00 6760.00 Nail Kg 3.500 211.60 740.60
12308.00 12677.56 24985.56 3747.83 28733.39
Rate Per Sqm 2873.34
vi. Height up to 16m - 18m Carpenter m.d. 8.30 760.00 6308.00 Wood Cum 0.27 49123.29 13263.29
Labor m.d. 15.00 520.00 7800.00 Nail Kg 4.00 211.60 846.40
14108.00 14109.69 28217.69 4232.65 32450.34
Rate Per Sqm 3245.03
Concreting on superstructure, Deck
32 slab & beam for 1 Cum including
materials
a. RCC (1: 1.5 :3) up to 3 m height Mason m.d. 0.80 760.00 608.00 Cement Kg 400.00 18.60 7440.00
Labor m.d. 7.00 520.00 3640.00 Aggregate
40 mm Cum 0.00 3470.91 0.00
20 mm Cum 0.57 3820.91 2177.92
10 mm Cum 0.29 3470.91 1006.56
Sand Cum 0.425 2499.65 1062.35
4248.00 11686.83 15934.83 2390.22 18325.05
Rate Per Cum 18325.05
b. RCC (1: 1.5 :3) 3m - 6m height Mason m.d. 0.80 760.00 608.00 Cement Kg 400.00 18.60 7440.00
Labor m.d. 9.00 520.00 4680.00 Aggregate
40 mm Cum 0.00 3470.91 0.00
20 mm Cum 0.57 3820.91 2177.92
10 mm Cum 0.29 3470.91 1006.56
Sand Cum 0.425 2499.65 1062.35
5288.00 11686.83 16974.83 2546.22 19521.05
Rate Per Cum 19521.05
c. RCC (1: 1.5 :3) 6m - 9m height Mason m.d. 0.80 760.00 608.00 Cement Kg 400.00 18.60 7440.00
Labor m.d. 11.00 520.00 5720.00 Aggregate
40 mm Cum 0.00 3470.91 0.00
20 mm Cum 0.57 3820.91 2177.92
10 mm Cum 0.29 3470.91 1006.56
Sand Cum 0.425 2499.65 1062.35
6328.00 11686.83 18014.83 2702.22 20717.05
Rate Per Cum 20717.05
d. RCC (1: 1.5 :3) 9m - 12m height Mason m.d. 0.80 760.00 608.00 Cement Kg 400.00 18.60 7440.00
Labor m.d. 13.00 520.00 6760.00 Aggregate
40 mm Cum 0.00 3470.91 0.00
20 mm Cum 0.57 3820.91 2177.92
10 mm Cum 0.29 3470.91 1006.56
Sand Cum 0.425 2499.65 1062.35
7368.00 11686.83 19054.83 2858.22 21913.05
Rate Per Cum 21913.05
e. RCC (1: 1.5 :3) 12m - 15m height Mason m.d. 0.80 760.00 608.00 Cement Kg 400.00 18.60 7440.00
Labor m.d. 15.00 520.00 7800.00 Aggregate
40 mm Cum 0.00 3470.91 0.00
20 mm Cum 0.57 3820.91 2177.92
10 mm Cum 0.29 3470.91 1006.56
Sand Cum 0.425 2499.65 1062.35
8408.00 11686.83 20094.83 3014.22 23109.05
Rate Per Cum 23109.05
f. RCC (1: 1.5 :3) 15m - 18m height Mason m.d. 0.80 760.00 608.00 Cement Kg 400.00 18.60 7440.00
Labor m.d. 17.00 520.00 8840.00 Aggregate
40 mm Cum 0.00 3470.91 0.00
20 mm Cum 0.57 3820.91 2177.92
10 mm Cum 0.29 3470.91 1006.56
Sand Cum 0.425 2499.65 1062.35
9448.00 11686.83 21134.83 3170.22 24305.05
Rate Per Cum 24305.05
g. RCC (1: 1.5 :3) 18m - 21m height Mason m.d. 0.80 760.00 608.00 Cement Kg 400.00 18.60 7440.00
Labor m.d. 19.00 520.00 9880.00 Aggregate
40 mm Cum 0.00 3470.91 0.00
20 mm Cum 0.57 3820.91 2177.92
10 mm Cum 0.29 3470.91 1006.56
Sand Cum 0.425 2499.65 1062.35
10488.00 11686.83 22174.83 3326.22 25501.05
Rate Per Cum 25501.05
h. RCC (1: 1.5 :3) 21m - 24m height Mason m.d. 0.80 760.00 608.00 Cement Kg 400.00 18.60 7440.00
Labor m.d. 21.00 520.00 10920.00 Aggregate
40 mm Cum 0.00 3470.91 0.00
20 mm Cum 0.57 3820.91 2177.92
10 mm Cum 0.29 3470.91 1006.56
Sand Cum 0.425 2499.65 1062.35
11528.00 11686.83 23214.83 3482.22 26697.05
Rate Per Cum 26697.05
i. RCC (1: 1.5 :3) 24m - 27m height Mason m.d. 0.80 760.00 608.00 Cement Kg 400.00 18.60 7440.00
Labor m.d. 23.00 520.00 11960.00 Aggregate
40 mm Cum 0.00 3470.91 0.00
20 mm Cum 0.57 3820.91 2177.92
10 mm Cum 0.29 3470.91 1006.56
Sand Cum 0.425 2499.65 1062.35
12568.00 11686.83 24254.83 3638.22 27893.05
Rate Per Cum 27893.05
2 32 mm O.D. Pipes Plumber m.d. 0.001 620.00 0.62 T&P day 0.00100 500.00 0.50
Helper m.d. 0.001 520.00 0.52 Fuel litre 0.00025 97 0.02
Labourer m.d. 0.003 520.00 1.56 Contingencies 2.51 % of labor cost 0.07
2.7 0.59 3.29 0.49 3.78
3 40 & 50 mm O.D. Pipes Plumber m.d. 0.0015 620.00 0.93 T&P day 0.00100 500.00 0.50
Helper m.d. 0.0015 520.00 0.78 Fuel litre 0.00037 97 0.04
Labourer m.d. 0.0030 520.00 1.56 Contingencies 2.51 % of labor cost 0.08
3.27 0.62 3.89 0.58 4.47
4 63,75 & 90 mm O.D. Plumber m.d. 0.02 620.00 12.4 T&P day 0.02 500.00 10.00
Pipes Helper m.d. 0.02 520.00 10.4 Fuel litre 0.01 97 0.97
Labourer m.d. 0.04 520.00 20.8 Contingencies 2.51 % of labor cost 1.09
43.6 12.06 55.66 8.35 64.01
5 110 & 125 mm O.D. Pipes Plumber m.d. 0.03 620.00 18.6 T&P day 0.02 500.00 10.00
Helper m.d. 0.03 520.00 15.6 Fuel litre 0.01 97 0.97
Labourer m.d. 0.06 520.00 31.2 Contingencies 2.51 % of labor cost 1.64
65.4 12.61 78.01 11.70 89.71
6 140,160 &180 mm O.D. Plumber m.d. 0.04 620.00 24.8 T&P day 0.04 500.00 20.00
Pipes Helper m.d. 0.04 520.00 20.8 Fuel litre 0.02 97 1.94
Labourer m.d. 0.08 520.00 41.6 Contingencies 2.51 % of labor cost 2.19
87.2 24.13 111.33 16.70 128.03
7 200,225 & 250 mm O.D. Plumber m.d. 0.06 620.00 37.2 T&P day 0.04 500.00 20.00
Pipes Helper m.d. 0.06 520.00 31.2 Fuel litre 0.03 97 2.91
Labourer m.d. 0.12 520.00 62.4 Contingencies 2.51 % of labor cost 3.28
130.8 26.19 156.99 23.55 180.54
8 280, 315 & 355 mm O.D. Plumber m.d. 0.08 620.00 49.6 T&P day 0.06 500.00 30.00
Pipes Helper m.d. 0.08 520.00 41.6 Fuel litre 0.04 97 3.88
Labourer m.d. 0.16 520.00 83.2 Contingencies 2.51 % of labor cost 4.38
174.4 38.26 212.66 31.90 244.56
35 Rig Setting and Site Preparation
Mason m.d. 2.00 760.00 1520.00
Rig setting up and preparation of mud
a Labor m.d. 10.00 520.00 5200.00
pit
6720.00 6720.00 1008.00 7728.00
36 Assembling centering and sinking of Mason m.d. 2.50 760.00 1900.00 Bentonine Ton 1.00 1600.00 1600.00
Guide Pipe (Conductor of pipe) Of size Helper m.d. 32.50 511.50 16623.75 Barite Ton 0.25 1600.00 400.00
22'' dia.to a depth of 10m. Labourer m.d. 45.00 520.00 23400.00 Drill bit No 0.125 0.00 0.00
Pickup Truck Hrs 10.00 0.00 0.00
Water Pump Hrs 20.00 0.00 0.00
41923.75 2000.00 43923.75 6588.56 50512.31
Rate per M 5051.23
37 Drilling of pilot hole by std bit ranging Mason m.d. 5.00 760.00 3800.00 Bentonine Ton 1.50 1600 2400.00
from 7 5/8'' to 9 7/8'' dia for the first Helper m.d. 65.00 511.50 33247.50 Barite Ton 0.25 1600 400.00
initial depth of 100m with drilling Labourer m.d. 110.00 520.00 57200.00 Drill bit No 0.33 0 0.00
rigmachine in Soft formation Oxygen gas Cylinder 0.20 0 0.00
( consists of clay , silt and sand below Acetelyne gas Cylinder 0.10 0 0.00
partical size of 4.75 mm) penetration Bucket No 2.00 0 0.00
rate is fixed at 3 Liner No 0.50 0 0.00
Piston rod No 0.50 0 0.00
Gland packing Set 2.00 0 0.00
Swivel Packing Set 1.00 0 0.00
( consists of clay , silt and sand below
partical size of 4.75 mm) penetration
rate is fixed at 3
38 Drilling Of pilot hole by std bit ranging Mason m.d. 7.50 760.00 5700.00 Bentonine Ton 1.75 1600
2800.00
from 7 5/8'' to 9 7/8'' dia for the first Helper m.d. 97.50 511.50 49871.25 Barite Ton 0.37 1600
592.00
initial depth of 100m with drilling Labourer m.d. 135.00 520.00 70200.00 Drill bit No 0.50 00.00
rigmachine in Medium formation Oxygen gas Cylinder 0.20 00.00
( consists of gravel fine to medium ) Acetelyne gas Cylinder 0.10 00.00
penetration rate is fixed at 2m per hour. No 3.50
Bucket 00.00
125771.25 3392.00 129163.25 19374.49 148537.74
Add 15% of all costs for periodic repairs of machinery ,small tools ,small spare parts unforseen items that may be machinery servicing etc 22280.66
170818.40
Rate per M 1708.18
Note - In all works drilling rig is inclusive of mud pump also, whether it be a part or separate unit of the drilling rig.
39 Drilling Of pilot hole by std bit ranging Mason m.d. 10.00 760.00 7600.00 Bentonine Ton 3.00 1600
4800.00
from 7 5/8'' to 9 7/8'' dia for the first Helper m.d. 130.00 511.50 66495.00 Barite Ton 0.50 1600
800.00
initial depth of 100m with drilling Labourer m.d. 180.00 520.00 93600.00 Drill bit No 1.00 00.00
rigmachine in Hard Oxygen gas Cylinder 0.20 00.00
formation( consists of particle size Acetelyne gas Cylinder 0.10 00.00
including and above coarse gravel ) No 5.00
Bucket 00.00
penetration rate is fixed at 1.5m per
hour Liner No 1.25 00.00
167695.00 5600.00 173295.00 25994.25 199289.25
Add 15% of all costs for periodic repairs of machinery ,small tools ,small spare parts unforseen items that may be machinery servicing etc 29893.39
229182.64
Rate per M 2291.83
Note - In all works drilling rig is inclusive of mud pump also, whether it be a part or separate unit of the drilling rig.
40 Drilling Of pilot hole by std bit ranging Mason m.d. 0.30 760.00 228.00 Bentonine Ton 0.07 1600
112.00
from 7 5/8'' to 9 7/8'' dia for a depth Helper m.d. 3.90 511.50 1994.85 Barite Ton 0.015 160024.00
beyond 100 m with drilling rigmachine Labourer m.d. 5.40 520.00 2808.00 Drill bit No 0.00 0 0.00
in Medium formation( consists of Oxygen gas Cylinder 0.00 0 0.00
particle size gravel fine to coarse Acetelyne gas Cylinder 0.00 0 0.00
gravel ) penetration rate is fixed at 2 m Bucket No 0.24 0 0.00
per hour Liner No 0.06 0 0.00
Piston rod No 0.06 0 0.00
5030.85 136.00 5166.85 775.03 5941.88
Add 15% of all costs for periodic repairs of machinery ,small tools ,small spare parts unforseen items that may be machinery servicing etc 891.28
6833.16
Rate per M 68.33
Note - In all works drilling rig is inclusive of mud pump also, whether it be a part or separate unit of the drilling rig.
41 Drilling Of pilot hole by std bit ranging Mason m.d. 0.40 760.00 304.00 Bentonine Ton 0.12 1600
192.00
from 7 5/8'' to 9 7/8'' dia for the depths Helper m.d. 5.20 511.50 2659.80 Barite Ton 0.02 160032.00
over and beyond 100m for every Labourer m.d. 7.20 520.00 3744.00 Drill bit No 0.00 0 0.00
additional 100m depth by drilling Oxygen gas Cylinder 0.00 0 0.00
rigmachine in hard formation ( consists Acetelyne gas Cylinder 0.00 0 0.00
of particle size including and above No 0.32
Bucket 0 0.00
coarse gravel .
6707.80 224.00 6931.80 1039.77 7971.57
Add 15% of all costs for periodic repairs of machinery ,small tools ,small spare parts unforseen items that may be machinery servicing etc 1195.74
9167.31
Rate per M 91.67
Note - In all works drilling rig is inclusive of mud pump also, whether it be a part or separate unit of the drilling rig.
42 First Reaming of pilot hole by std bit Mason m.d. 2.50 760.00 1900.00 Bentonine Ton 1.00 1600
1600.00
above 9 7/8'' and below 17 1/2'' dia for Helper m.d. 32.50 511.50 16623.75 Barite Ton 0.25 1600400.00
the first initial depth of 100m with Labourer m.d. 45.00 520.00 23400.00 Drill bit No 0.20 0 0.00
drilling rigmachine in soft formation Oxygen gas Cylinder 0.10 0 0.00
( consists of clay , silt and sand ) Acetelyne gas Cylinder 0.05 0 0.00
penetration rate is fixed at 9m per hour. No 1.00
Bucket 0 0.00
41923.75 2000.00 43923.75 6588.56 50512.31
Add 8% of all costs for periodic repairs of machinery ,small tools ,small spare parts unforseen items that may be machinery servicing etc 4040.98
54553.29
Rate per M 545.53
43 First Reaming of pilot hole by std bit Mason m.d. 3.75 760.00 2850.00 Bentonine Ton 1.00 1600 1600.00
above 9 7/8'' and below 17 1/2 '' dia for Helper m.d. 48.75 511.50 24935.63 Barite Ton 0.25 1600 400.00
the first initial depth of 100m with Labourer m.d. 67.50 520.00 35100.00 Drill bit No 0.25 0 0.00
drilling rig machine in medium Oxygen gas Cylinder 0.10 0 0.00
formation ( consists of gravel fine to Acetelyne gas Cylinder 0.05 0 0.00
medium ) penetration rate is fixed at
6m per hour.
43 First Reaming of pilot hole by std bit
above 9 7/8'' and below 17 1/2 '' dia for
the first initial depth of 100m with
drilling rig machine in medium
formation ( consists of gravel fine to
medium ) penetration rate is fixed at No 1.75
Bucket 0 0.00
6m per hour.
Liner No 0.40 0 0.00
62885.63 2000.00 64885.63 9732.84 74618.47
Add 8% of all costs for periodic repairs of machinery ,small tools ,small spare parts unforseen items that may be machinery servicing etc 5969.48
80587.95
Rate per M 805.88
44 First Reaming of pilot hole by std bit Mason m.d. 5.00 760.00 3800.00 Bentonine Ton 1.25 1600 2000.00
above 9 7/8'' and below 17 1/2'' dia for Helper m.d. 65.00 511.50 33247.50 Barite Ton 0.25 1600 400.00
the first initial depth of 100m with Labourer m.d. 90.00 520.00 46800.00 Drill bit No 0.33 0 0.00
drilling rig machine in hard formation ( Oxygen gas Cylinder0.10 0 0.00
consists of above coarse gravel ) Acetelyne gas Cylinder0.05 0 0.00
penetration rate is fixed at 4.5m per No 2.50
Bucket 0 0.00
hour.
83847.50 2400.00 86247.50 12937.13 99184.63
Add 8% of all costs for periodic repairs of machinery ,small tools ,small spare parts unforseen items that may be machinery servicing etc 7934.77
107119.40
Rate per M 1071.19
45 First Reaming of pilot hole by std bit Mason m.d. 0.15 760.00 114.00 Bentonine Ton 0.04 1600 64.00
above 9 7/8'' and below 17 1/2'' dia for Helper m.d. 1.95 511.50 997.43 Barite Ton 0.01 1600 16.00
the first initial depth of 100m for each Labourer m.d. 2.70 520.00 1404.00 Drill bit No 0.00 0 0.00
additional 100m with drilling rig Oxygen gas Cylinder0.00 0 0.00
machine in medium formation Acetelyne gas Cylinder0.00 0 0.00
( consists of gravel fine to medium ) No 0.16
Bucket 0 0.00
2515.43 80.00 2595.43 389.31 2984.74
Add 8% of all costs for periodic repairs of machinery ,small tools ,small spare parts unforseen items that may be machinery servicing etc 238.78
3223.52
Rate per M 32.24
46 First Reaming of pilot hole by std bit Mason m.d. 0.20 760.00 152.00 Bentonine Ton 0.05 1600 80.00
above 9 7/8'' and below 17 1/2'' dia for Helper m.d. 2.60 511.50 1329.90 Barite Ton 0.01 1600 16.00
the first initial depth of 100m for each Labourer m.d. 3.60 520.00 1872.00 Drill bit No 0.00 0 0.00
additional 100m with drilling rig Oxygen gas Cylinder0.00 0 0.00
machine in hard formation ( consists of Acetelyne gas Cylinder0.00 0 0.00
gravel fine to medium ) No 0.24
Bucket 0 0.00
3353.90 96.00 3449.90 517.49 3967.39
Add 8% of all costs for periodic repairs of machinery ,small tools ,small spare parts unforseen items that may be machinery servicing etc 317.39
4284.78
Rate per M 42.85
47 Second Reaming of pilot hole by std bit Mason m.d. 2.50 760.00 1900.00 Bentonine Ton 1.00 1600 1600.00
above 17 1/2'' up to depth of 100m Helper m.d. 32.50 511.50 16623.75 Barite Ton 0.25 1600 400.00
with drilling rig machine in Soft
formation ( consists of clay,silt and
sand sand below partical size of 4.75
penetration rate is fixed at 9m/hour )
47 Second Reaming of pilot hole by std bit
above 17 1/2'' up to depth of 100m
with drilling rig machine in Soft Labourer m.d. 45.00 520.00 23400.00 Drill bit No 0.125 0 0.00
formation ( consists of clay,silt and Oxygen gas Cylinder 0.10 0 0.00
sand sand below partical size of 4.75 Acetelyne gas Cylinder 0.05 0 0.00
penetration rate is fixed at 9m/hour ) No 1.00
Bucket 0 0.00
41923.75 2000.00 43923.75 6588.56 50512.31
Add 8% of all costs for periodic repairs of machinery ,small tools ,small spare parts unforseen items that may be machinery servicing etc 4040.98
54553.29
Rate per M 545.53
48 Second Reaming of pilot hole by std bit Mason m.d. 3.75 760.00 2850.00 Bentonine Ton 1.00 1600 1600.00
above 17 1/2'' up to depth of 100m Helper m.d. 48.75 511.50 24935.63 Barite Ton 0.25 1600 400.00
with drilling rig machine in Medium Labourer m.d. 67.50 520.00 35100.00 Drill bit No 0.167 0 0.00
formation ( gravel fine to medium is Oxygen gas Cylinder 0.10 0 0.00
fixed at 6m/hour ) Acetelyne gas Cylinder 0.05 0 0.00
Add 8% of all costs for periodic repairs of machinery ,small tools ,small spare parts unforseen items that may be machinery servicing etc 5969.48
80587.95
Rate per M 805.88
49 Second Reaming of pilot hole by std bit Mason m.d. 5.00 760.00 3800.00 Bentonine Ton 1.25 1600 2000.00
above 17 1/2'' up to depth of 100m Helper m.d. 65.00 511.50 33247.50 Barite Ton 0.25 1600 400.00
with drilling rig machine in hard Labourer m.d. 90.00 520.00 46800.00 Drill bit No 0.25 0 0.00
formation ( consists above coarse Oxygen gas Cylinder 0.10 0 0.00
gravel penetration is fixed at Acetelyne gas Cylinder 0.05 0 0.00
4.5m/hour )
83847.50 2400.00 86247.50 12937.13 99184.63
Add 8% of all costs for periodic repairs of machinery ,small tools ,small spare parts unforseen items that may be machinery servicing etc 7934.77
107119.40
Rate per M 1071.19
Mason m.d. 7.50 760.00 5700.00 Bentonine Ton 0.50 1600 800.00
Labourer m.d. 13.50 520.00 7020.00 Barite Ton 0.25 1600 400.00
Drill bit No 0.05 0 0.00
Rig Machine Hrs 6.00 0 0.00
Reconditioning of hole before lowering Elec. Generator Hrs 2.00 0 0.00
of pipe assembly 6-12'' dia. to a depth Water Truck Hrs 2.00
50 up to 100m. 0 0.00
Cargo Truck Hrs 4.00 0 0.00
Pickup Truck Hrs 8.00 0 0.00
52 Well development by drilling rig Mason m.d. 1.00 760.00 760.00 Bucket No 1.00 0 0.00
machine of 6- 12'' ( Back washing and Helper m.d. 5.00 520.00 2600.00 Liner No 0.25 0 0.00
inner washing) Labourer m.d. 9.00 520.00 4680.00 Piston rod No 0.25 0 0.00
8040.00 0.00 8040.00 1206.00 9246.00
Rate per M 92.46
Note - In all works drilling rig is inclusive of mud pump also, whether it be a part or separate unit of the drilling rig.
53 Well development by drilling rig Mason m.d. 5.00 760.00 3800.00 Bucket No 1.00 0 0.00
machine of 6-12'' ( Water Jeting) Labourer m.d. 9.00 520.00 4680.00 Liner No 0.25 0 0.00
Water Pump Hrs 11.00 0 0.00
Welding Generator Hrs 1.00 0 0.00
8480.00 0.00 8480.00 1272.00 9752.00
Rate per M 97.52
Mason m.d. 7.00 760.00 5320.00 Rig Machine Hrs 4.00 0 0.00
Well development by Compressor Helper m.d. 27.00 520.00 14040.00 compressor Hrs 72.00 0.00 0.00
54
machine for well size 6-12'' . Labourer m.d. 36.00 520.00 18720.00 Elec. Generator Hrs 30.00 0 0.00
38080.00 0.00 38080.00 5712.00 43792.00
Mason m.d. 5.00 760.00 3800.00 Gasket Set 4.00 0.00 0.00
Helper m.d. 14.00 520.00 7280.00 Grand Packing Set 6.00 0 0.00
55 Well development by pump (6-12'') Submersible pump
Labourer m.d. 35.00 520.00 18200.00 25 hp Hrs 50.00 0 0.00
29280.00 0.00 29280.00 4392.00 33672.00
Mason m.d. 2.00 760.00 1520.00 Gasket Set 4.00 0.00 0.00
Helper m.d. 4.00 520.00 2080.00 Grand Packing Set 6.00 0.00 0.00
Pump test for deep tube well ( draw Elec. Generator Hrs 24.00 0.00 0.00
56 indicator Hrs 24.00 0.00 0.00
down test )
6''pipe tee Hrs 24.00 0.00 0.00
Pickup Truck Hrs 3.00 0.00 0.00
Tripod sets Hrs 24.00 0.00 0.00
18680.00 0.00 18680.00 2802.00 21482.00
Mason m.d. 2.00 760.00 1520.00 Elec. Generator Hrs 6.00 0.00 0.00
Helper m.d. 4.00 520.00 2080.00 indicator Hrs 16.00 0.00 0.00
57 Recovery test for deep tube well 18.00 Hrs 2.00
Labourer m.d. 520.00 9360.00 Pickup Truck 0.00 0.00
12960.00 0.00 12960.00 1944.00 14904.00
Mason m.d. 3.00 760.00 2280.00 Gasket Set 4.00 0.00 0.00
Helper m.d. 6.00 520.00 3120.00 Grand Packing Set 6.00 0.00 0.00
Submersible pump
Labourer m.d. 30.00 520.00 15600.00 25 hp Hrs 24.00 0.00 0.00
Step Draw Down test For deep tube Elec. Generator Hrs 24.00 0.00 0.00
58
well. indicator Hrs 24.00 0.00 0.00
6''pipe tee Hrs 24.00 0.00 0.00
Pickup Truck Hrs 3.00 0.00 0.00
21000.00 0.00 21000.00 3150.00 24150.00
Mason m.d. 2.00 760.00 1520.00 Power cell Nos 6.00 0 0.00
Electric Logging of bore hole after Helper m.d. 4.00 520.00 2080.00 Elec. logging mchHrs 12.00 0 0.00
59 drilling of pilot hole for 100m depth. Labourer m.d. 8.00 520.00 4160.00
7760.00 0.00 7760.00 1164.00 8924.00
Add 3% of all costs for periodic repairs of machinery ,small tools ,small spare parts unforseen items that may be machinery servicing etc 267.72
Rate per well (Nrs.) 9191.72
ABSTRACT OF COSTS
Name of Project: Dhanaura Water Supply Project
Name of Work: Supply of Pipe Fittings for Distribution Pipelines
Total Unit Rate
S.No. Pipe fitting details Unit Amount Rs. Remarks
Quantity Rs.
1 GI pipe ( 90 cm long)
250mm dia MC pc
200mm dia MC pc 6.00 2500.00 15,000.00
150mm dia MC pc 6.00 2488.00 14,928.00
100mm dia MC pc 8.00 1525.00 12,200.00
80mm dia MC pc 14.00 1020.00 14,280.00
65mm dia MC pc 4.00 820.00 3,280.00
50mm dia (2") MC pc 4.00 642.00 2,568.00
40mm dia MC pc 6.00 468.00 2,808.00
32mm dia MC pc 4.00 407.00 1,628.00
2 GI Union
80mm dia MC no 28.00 1462.00 40,936.00
65mm dia MC no 8.00 1046.00 8,368.00
50mm dia (2") MC no 8.00 565.00 4,520.00
40mm dia MC no 24.00 405.00 9,720.00
32mm dia MC 16.00 305.00 4,880.00
3 GI Nipple 6" long
250mm dia MC no
200mm dia MC no 18.00 1500.00 27,000.00
150mm dia MC no 18.00 1350.00 24,300.00
100mm dia MC no 24.00 673.00 16,152.00
80mm dia MC no 42.00 507.00 21,294.00
65mm dia MC no 12.00 348.00 4,176.00
50mm dia (2") MC no 12.00 233.00 2,796.00
40mm dia MC no 18.00 176.00 3,168.00
32mm dia MC no 12.00 113.00 1,356.00
4 Gate valve
100mm dia MC no 8.00 6235 49,880.00
80mm dia MC no 14.00 5780 80,920.00
65mm dia MC no 4.00 5300 21,200.00
50mm dia (2") MC no 4.00 5150 20,600.00
40mm dia MC no 6.00 3520 21,120.00
32mm dia MC no 4.00 3120 12,480.00
5 CI Sluice Valve
200mm dia MC 6.00 29000 174,000.00
180mm dia MC 6.00 28000 168,000.00
6 GI Equal Tee
250mm dia MC no
200mm dia MC no
150mm dia MC no 1.00 1449 1,449.00
100mm dia MC no 1.00 1449 1,449.00
7 DI Un equal Tee
200*200*150 mm no 1.00 23115 23,115.00
180*180*65 mm no 1.00 23115 23,115.00
125*125*75 mm no 3.00 23115 69,345.00
125*125*40 mm no 2.00 23115 46,230.00
140*140*110 mm 2.00 23115 46,230.00
8 GI Equal Cross Tee
150mm dia MC no 1.00 2000 2,000.00
100mm dia MC no 2.00 1700 3,400.00
9 Air valve
20mm dia MC 3.00 3850.00 11,550.00
10 Valve Box
100 mm dia 6.00 4510 27,060.00
11 HDP/GI Flange Set with adoptor
250/200mm dia no
225/200mm dia no
200/200mm dia no 8.00 3725 29,800.00
180/150mm dia no 9.00 3320 29,880.00
160/150mm dia no 12.00 3075 36,900.00
140/150 mm dia no
110/100 mm dia no 25.00 2110 52,750.00
90/80 mm dia no 35.00 1710 59,850.00
75/65 mm dia no 11.00 1600 17,600.00
63/50 mm dia no 12.00 1606 19,272.00
12 Saddle/Ferrule heavy duty
250 mm
225 mm
200 mm no 1.00 3245 3,245.00
180 mm no 2.00 2331 4,662.00
160 mm
140 mm no 2.00 1215 2,430.00
125 mm no 3.00 914 2,742.00
110 mm no 5.00 555 2,775.00
90 mm no 4.00 450 1,800.00
75 mm no 8.00 410 3,280.00
63 mm no 3.00 315 945.00
13 End cap
100mm dia MC
80mm dia MC no 6.00 445 2,670.00
65mm dia MC no 2.00 216 432.00
50mm dia (2") MC no 5.00 116 580.00
40mm dia MC no 6.00 92 552.00
Total 1310666.00
Value Added Tax (VAT) @ 13% of Total 170386.58
Grand Total 1481052.58
Light
With
socket
0.364
0.521
0.68
0.961
1.42
2.03
2.61
3.29
4.18
5.92
6.98
10.2
-
-
Procurement of Pipes
Dougha Lift water supply project
Estimated
S.No. Pipe size and series Unit
Quantity Rate Amount
1 HDPE pipes
PATHARIYA VDC
KAILALI
Considering 60% blockage of slots during design period, ie, for 40%
usable area, The Circumferential area required (a2=a1/0.40) 0.00 m2
Length of screen (h=a/(p*D) 0.00 m
Designed Length of Screen (h) 24 m
Abstract of costs
Pipeline Works
Dougha Lift water supply project Scheme no :
Sn Description Length Breadth Height Quantity Unit Rate Amount
Unit
A Transmission line
E/W in excavation in hard soil(63-90) 2070 0.45 0.90 838.35 cum 577.45 484105.21
E/W in backfilling with hard soil(63-90) 2070 0.45 0.90 838.35 cum 291.03 243985.00
3 Laying & Jointing of GI Pipes
100mm GI-welded joints 1648 1648 m 574.47 946726.56
90 mmØ PPR pipe 2070 2070 m 45.91 95033.7
Sub-total 3718 1769850.47
Vat @ 13 % 230080.5611
Total cost of transmission pipe line works 1999931
B Distribution line
1 E/W in excavation in hard soil(110-125) 1270 0.60 0.90 685.80 cum 577.45 396015.21
E/W in excavation in hard soil(63-90) 1430 0.45 0.90 579.15 cum 577.45 334430.17
E/W in excavation in hard soil(20-50) 1010 0.35 0.90 318.15 cum 577.45 183715.72
2 E/W in backfilling with hard soil(110-125) 1270 0.60 0.90 685.80 cum 291.03 199588.37
3 E/W in backfilling with hard soil(63-90) 1430 0.45 0.90 579.15 cum 291.03 168550.02
4 E/W in backfilling with hard soil(20-50) 1010 0.35 0.90 318.15 cum 291.03 92591.19
3 Laying & Jointing of Pipes
32 mmØ HDPE pipe 210 210.00 m 2.72 571.20
40,50 mmØ HDPE pipe 800 800.00 m 3.29 2632.00
63-90 mmØ HDPE pipe 1430 1430.00 m 45.99 65765.70
110,125 mmØ HDPE pipe 1270 1270.00 m 66.50 84455.00
125mmØ GI- weld joint 780 780.00 m 727.76 567652.80
100 mmØ GI- weld joint 810 810.00 m 574.47 465320.70
80 mmØ GI- weld joint 430 430.00 m 424.22 182414.60
40 mmØ GI- weld joint 1770 1770.00 m 264.41 468005.70
32 mmØ GI- weld joint 1320 1320.00 m 171.94 226960.80
20 mmØ GI- socketed joint 150 150.00 m 45.93 6889.50
Sub-total 8970 8970.00 3445559
Value Added Tax @ 13.00 % 447923
Total cost of distribution pipeline works 3893482
Total cost of pipeline works 12688 5893413.00
34
Detailed Quantity Estimate
45
Detailed Quantity Estimate
Inlet VC 1 1.53 1.76 0.10 0.27
46
Detailed Quantity Estimate
47
Detailed Quantity Estimate
48
Detailed Quantity Estimate
49
Detailed Quantity Estimate
50
Item Rates for Estimating
Rate Per Unit
Sn. Norms no Items Unit ( without VAT
)
Earth Works
1 1-8 Site clearance m2 71.76
2 2-9 Earthwork in Excavation in ordinary soil m3 461.96
3 2-12 Earthwork in Excavation in hard soil m3 577.45
4 2-14 Earthwork in Excavation in boulder mixed soil m3 734.51
5 2-15a Earthwork in Excavation in soft rock m3 1,385.87
6 2-15b Earthwork in Excavation in medium rock m3 2,078.80
7 2-16b Earthwork in Excavation in hard rock with chiselling m3 11,641.27
8 2-25a Earthwork in backfilling in ordinary soil m3 230.98
9 2-39c Earthwork in backfilling with hard soil m3 291.03
10 2-39d Earthwork in backfilling with boulder mixed soil m3 277.17
11 2-39e Earthwork in backfilling with soft rock m3 508.15
Stone Works
11 6-5 Stone soling work m3 2,374.98
12 11-16 Stone Pitching with sand m3 5,616.32
13 6-2.1 Dry stone masonry work m3 3,089.88
14 6-2.2 Stone masonry in mud mortar m3 3,484.56
15 6-3.1 R.R. masonry in 1:3 cement mortar m3 9,272.77
16 6-3.2 R.R. masonry in 1:4cement mortar m3 8,733.26
17 6-3.3 R.R. masonry in 1:6cement mortar m3 7,849.89
Concrete Works
18 7-2c Plain cement concrete (1:3:6) in sub Structure m3 11,101.49
19 7-2d Plain cement concrete (1:2:4) sub Structure m3 13,123.51
20 7-4 b Plain cement concrete (1:1:5:3) sub Structure m3 15,298.08
21 7-2 d Plain cement concrete (1:2:4) in super structure m3 14,342.51
22 7-4 b Plain cement concrete (1:1.5:3) in super structure m3 16,517.08
23 7-2d Plain cement concrete (1:2:4) substructure with 2% WPC m3 13,011.85
24 7-4 b Plain cement concrete (1:1:5:3) substructure with 2% WPC m3 14,504.52
Miscelleneous Works
23 7-5 Mild steel reinforcement kg 111.17
24 8-2a Form work for concrete work in simple slab and structure m2 413.10
Form work for concrete work in arch,dome,etc
( Assuming form work canbe used 4 times) m2 853.52
25 DWSS HDPE pipe formwork for ferro-cement works m2 204.52
Bar binding works including chicken wire, MS rods, GI plain
26 DWSS wires etc m2 1,417.34
27 24-6 Barbed wire fencing m 53.50
Barbed wire fencing on wooden posts (2 diagonals & 5
28 24-7 horizontals) @ 3m c\c m 334.08
29 10-17 Wood works for door window frame m3 48,680.31
38 mm thick wooden shutter with 24 SWG plain sheet on one
30 side m2 3,634.17
38 mm thick panelled wooden shutter m2 4,332.05
31 9-1 CGI sheet roofing m2 921.89
32 Laying of one layer of 500 G of Polythene sheet m2 27.83
Rate Per Unit
Sn. Norms no Items Unit ( without VAT
)
Making gabion boxes including cutting, wire, netting etc. and
placing in site and tying all complete : Mesh size: hex.
100×120mm, Mesh wire-10SWG, selvedge wire-7 SWG) : size
33 16-2a+14-5a 2×1×1 m no 3,099.11
34 16-11 Filling of Gabion box with stone m3 1,784.63
35 Gravel packing 20,25 mm dia m 3 6,407.37
35 10-17 Wood work for beams, rafters,etc. m 3 33,297.27
35 10-19 25 mm thick eavesboard m² 682.05
Plastering, Punning and Pointing works
36 12-1a 12.5 mm thick 1:2 c-s plaster m2 338.39
37 12-1b 12.5 mm thick 1:3 c-s plaster m2 291.41
38 12-1c 12.5 mm thick 1:4 c-s plaster m2 280.75
39 12-4a 20 mm thick 1:3 c-s plaster m2 394.14
40 12-4b 20 mm thick 1:4 c-s plaster m 2 374.20
41 12-4c 20 mm thick 1:6 c-s plaster m 2 335.74
12-1a 12.5 mm thick 1:2 c-s plaster with 2% WPC m 2 338.39
12-1b 12.5 mm thick 1:3 c-s plaster with 2% WPC m 2 291.41
12-4a 20 mm thick 1:3 c-s plaster with 2% WPC m 2 394.14
42 13-10 3 mm thick 1:1 c-s punning m2 173.42
43 14-2c 1:3 c-s Flush ruled pointing work m2 196.50
Painting Works
44 13-5 Two coats of enamel painting with one coat of primer m2 215.69
45 13-12b Two coats snowcem painting m 2 96.35
46 13-10 Two coats of bitumen painting m 2 57.85
Pipe Jointing Works
HDPE Pipes
47 17-2 Laying and joining of 20,25 mmØ HDPE pipe with butt-weld joint m 2.26
48 17-2 Laying and joining of 32 mmØ HDPE pipe with butt-weld joints m 2.72
49 17-2 Laying and joining of 40,50 mmØ HDPE pipe with butt-weld joint m 3.29
50 17-2 Laying and joining of 63-90 mmØ HDPE pipe with butt-weld join m 45.91
17-2 Laying and joining of 110,125 mmØ HDPE pipe with butt-weld jo m 66.42
17-2 Laying and joining of 140-180 mmØ HDPE pipe with butt-weld jo m 91.83
51 DWSS Laying and joining of 200-250 mmØ HDPE pipe with butt-weld jo m 134.29
GI Pipes
52 17-4a Laying and joining of 15,20 mmØ GI pipe with socket joints m 45.93
53 17-4a Laying and joining of 25,32 mmØ GI pipe with socket joints m 62.75
54 17-4a Laying and joining of 40,50 mmØ GI pipe with socket joints m 85.71
55 17-4a Laying and joining of 65,80 mmØ GI pipe with socket joints m 114.82
17-4a Laying and joining of 100 mmØ GI pipe with socket joints m 143.93
56 17-4a Laying and joining of 125 mmØ GI pipe with socket joints m 175.30
Standard mild steel angle ( 25×25×3 mm size ) framed grill gate no 1,690.67
Supply and fixing of standard manhole cover ( 45×45 cm) set 2,288.83
Supply and fixing of standard manhole cover of 60cm diameter set 2,084.39
Supply and fixing of standard manhole cover ( 60×60 cm) set 3,004.18
Fly proof net fixing m² 302.09
Transportation work
Rate Per Unit
Sn. Norms no Items Unit ( without VAT
)
57 Convenient load from store to site kg 0.4
58 Transportation of pipes and fittings from store(Tamghas) to project kg 0.47
Reference
No.
F4
F5
F6
F7
F8
F9
F10
F11
F12
F13
F14
F16
F17
F18
F19
F20
F21
F22
F24
F25
F26
F27
F28
F29
F30
F32
F33
F34
F35
F36
F37
F38
F39
F40
F41
F42
F43
Reference
No.
F44
F45
F46
F47
F48
F50
F51
F52
F53
F54
F55
F56
F57
F58
F59
F60
F62
F63
F64
F67
F68
F69
F70
F71
F72
F73
F75
F76
F77
F78
F79
F80
F81
F82
F83
F84
F85
Reference
No.
F87
F83
Analysis of Item Rates
This rate analysis is based on the HMG/N approved Norms 2041 ( Including second revision )
Name of Project : Arunodaya Water Supply & Sanitation Project
Rate
Hard soil Boulder/Gravel mixedsoil Ordinary Soil Soft rock Medium rock
Materials and labours Unit (Norms No 2-12) (Norms No 2-14) (Norms No 2-9) (Norms No 2-15a) (Norms No 2-15b)
Rs/unit
Quantity Cost Rs. Quantity Cost Rs. Quantity Cost Rs. Quantity Cost Rs. Quantity Cost Rs.
Coolie Rs/day 390.00 1.25 487.50 1.59 620.10 1.00 390.00 3.00 1170.00 4.50 1755.00
Tools and plants % 3.00% 14.63 3.00% 18.60 3.00% 11.70 3.00% 35.10 3.00% 52.65
Subtotal 502.13 638.70 401.70 1205.10 1807.65
Contracror's Overhead % 15.00% 75.32 95.81 60.26 180.77 271.15
Rate/m³ ( Without VAT ) 577.45 734.51 461.96 1385.87 2078.8
Earthwork in excavation with 10m lead and 1.5 m lift in pipeline trench in :
Rate
Hard rock
Materials and labours Unit (Norms No. 2-16b)
Rs/unit
Quantity Cost Rs.
Coolie Rs/day 390.00 25.20 9 828.00
Tools and plants % 3.00% 294.84
Subtotal 10 122.84
Contracror's Overhead % 15.00% 1 518.43
Rate/m³ ( Without VAT ) 11 641.27
Earthwork in back filling for pipe line trench with compaction in layers of 20cm with water sprinkling and site clearance
Boulder/Gravel mixed soil
Hard soil Ordinary Soil Soft rock Site clearance per m²
Rate (Norms
Materials and labours Unit (Norms No 2-39c) (Norms No ) (Norms No 2-39e) N(1-8)
Rs/unit No 2-39d)
Quantity Cost Rs. Quantity Cost Rs. Quantity Cost Rs. Quantity Cost Rs. Quantity Cost Rs.
Coolie Rs/day 390.00 0.63 245.70 0.6 234.00 0.5 195.00 1.1 429.00 0.16 62.40
Tools and plants % 3.00% 7.37 3.00% 7.02 3.00% 5.85 3.00% 12.87 0.00
Subtotal 253.07 241.02 200.85 441.87 62.40
Contracror's Overhead % 15.00% 37.96 36.15 30.13 66.28 9.36
Rate/m³ ( Without VAT ) 291.03 277.17 230.98 508.15 71.76
Quantity Cost Rs. Quantity Cost Rs. Quantity Cost Rs. Quantity Cost Rs. Quantity Cost Rs.
Cement kg 15.35 - - - 159 2440.65 106 1627.10
Sand m³ 2270.30 - - 0.45 1021.64 0.47 1067.04
Block Stone m³ 1233.50 1.20 1480.20 1.10 1356.85 1.10 1356.85 1.10 1356.85 1.10 1356.85
Mud m³ 585.00 - - 0.42 245.70 - -
Mason no 550.00 - 1.00 550.00 1.00 550.00 1.50 825.00 1.50 825.00
Coolie no 390.00 1.50 585.00 2.00 780.00 2.25 877.50 5.00 1950.00 5.00 1950.00
Subtotal 2 065.20 2 686.85 3 030.05 7 594.14 6 825.99
Contracror's Overhead % 15.00% 309.78 403.03 454.51 1 139.12 1 023.90
Rate/m³ ( Without VAT ) 2 374.98 3 089.88 3 484.56 8 733.26 7 849.89
Quantity Cost Rs. Quantity Cost Rs. Quantity Cost Rs. Quantity Cost Rs. Quantity Cost Rs.
Steel bar kg 80.41 1.05 84.43 - 2.593 208.5
Binding wire kg 96.35 0.01 0.96 - 0.083 8 0.111 10.69
GI Plain wire kg 78.35 - - 2.083 163.2
Chicken wire m 376.64 - - 1.806 680.21
Nail kg 100.35 - 0.25 25.09 0.014 1.4
Hold fast no 30.35 92 2792.2
Screw no 0.50 184 92
Wood m³ 17655.00 - 0.0526/4x0.75 139.3 1.1 19420.5
Bamboo no 100.00 - - 0.333 33.3
32mmf HDP pipe m - 40.00
Skiled labour no 550.00 0.012 6.6 0.172 94.6 0.167 91.85 0.25 137.5 34 18700
coolie no 390.00 0.012 4.68 0.257 100.23 0.111 43.29 0.083 32.37 3.4 1326
Subtotal 96.67 359.22 177.84 1232.47 42330.7
Contracror's Overhead % 15.00% 14.50 53.88 26.68 184.87 6349.61
Rate / Unit ( Without VAT ) 111.17 413.1 204.52 1417.34 48680.31
Quantity Cost Rs. Quantity Cost Rs. Quantity Cost Rs. Quantity Cost Rs. Quantity Cost Rs.
Cement kg 15.35 3.36 51.58 3.06 46.97
Sand m3
2270.30 0.0023 5.22 0.0063 14.30
GI Barbed wire m 16.22 - 1.1 17.84 8.333 135.16
Local wood m3
17655.00 0.006 105.93
CGI sheet-26G m2 516.37 - 1.20 619.64
Nuts & bolts no 12.54 - 3.00 37.62
J - hook no 14.05 - 2.50 35.13
U - hook no 2.00 LS 1.78 2.567 5.13
Skilled labours no 550.00 0.10 55.00 0.1 55.00 0.01076 5.92 0.033 18.15 0.11 60.50
Collies no 390.00 0.10 39.00 0.14 54.60 0.0538 20.98 0.067 26.13 0.125 48.75
Subtotal 150.80 170.87 46.52 290.50 801.64
Contracror's Overhead % 15.00% 22.62 25.63 6.98 43.58 120.25
Rate / Unit ( Without VAT ) 173.42 196.50 53.50 334.08 921.89
Quantity Cost Rs. Quantity Cost Rs. Quantity Cost Rs. Quantity Cost Rs. Quantity Cost Rs.
Primer L 275.35 0.081 22.30
Enamel L 425.35 0.16 68.06
Bitumen L 87.35 - 0.19 16.60
Snowcem L 45.35 - 0.5 22.68
GI Plain wire (10 SWG) kg 78.35 24.15 1892.15
Selvage wire (7 SWG) kg 78.35 3.15 246.80
Tying wire (12 SWG) kg 78.35 0.95 74.43
Block Stone m³ 1233.50 1.1 1356.85
Skilled labours no 550.00 0.12 66.00 0.04 22.00 0.065 35.75 0.45 247.50
Collies no 390.00 0.08 31.20 0.03 11.70 0.065 25.35 0.6 234.00 0.5 195.00
Subtotal 187.56 50.3 83.78 2694.88 1551.85
Contracror's Overhead % 15.00% 28.13 7.55 12.57 404.23 232.78
Rate/m² ( Without VAT ) 215.69 57.85 96.35 3099.11 1784.63
Red lead , Hemp etc. 10% 106.50 145.50 198.75 266.25 333.75
Contingencies 2.50% 26.63 36.38 49.69 66.56 83.44
Subtotal 1198.13 1636.88 2235.94 2995.31 3754.69
Contracror's Overhead % 15.00% 179.72 245.53 335.39 449.30 563.20
Grand Total 1377.85 1882.41 2571.33 3444.61 4317.89
Rate /m 45.93 62.75 85.71 114.82 143.93
Note:- 1. The rate per m is taken assuming one joint for a 6 m piece of pipe length
2. If generator is supplied by office, take zero rate of hire of generator.
Shuttering work for staging work for culvert, Wood work for beams,
Rate arch,dome,etc(per m2) bridge, dome, etc.(per rafters,etc. per m³
Materials and labours Unit N8-2a m³) N15-31a N10-I7
Rs/unit