Brgy. Tacul Par
Brgy. Tacul Par
Municipality of Kiblawan
Province of Davao del Sur
Barangay Tacul
1) Glass Window
W-1: Bronze Glass Sliding Type Window w/ Analoc frame 1 set 6,000.00 6,000.00 6,000.00
1.60mx1.30m x 5mm thk @ the center & 0.40m x 1.30m fixed window both
sides, complete with sealants & other accessories, including
labor & installation (verify actual)
W-2: Bronze Glass Sliding Type Window w/ Analoc frame 5 sets 4,000.00 20,000.00 20,000.00
1.20mx1.30mx5mmthk , complete with sealants & other
accessories, including labor & installation (verify actual)
W-4: Bronze Glass Sliding Type Window w/ Analoc frame 1 set 3,500.00 3,500.00 3,500.00
1.40mx0.90mx5mmthk , complete with sealants & other
accessories, including labor & installation (verify actual)
W-3: Bronze Glass Awning Type Window w/ Analoc frame 2 sets 2,500.00 5,000.00 5,000.00
0.60mx0.60mx5mmthk , complete with sealants & other
accessories, including labor & installation (verify actual)
W-5: Bronze Glass Fixed Type Window w/ Analoc frame 1 sets 5,500.00 5,500.00 5,500.00
1.80mx1.30mx5mmthk , complete with sealants & other
accessories, including labor & installation (verify actual)
2) Doors:
D-1: Solid Panel Door - 900mm x 2100mmx44mmthk 1 sets 4,500.00 4,500.00 4,500.00
D-1: Solid Panel Door - 400mm x 2100mmx44mmthk 1 sets 3,000.00 3,000.00 3,000.00
D-2: Solid Panel Door - 800mm x 2100mmx44mmthk 3 sets 4,500.00 13,500.00 13,500.00
D-3: PVC Type Door w/ Louver 600mm x 2100mm w/ PVC Door 2 sets 1,500.00 3,000.00 3,000.00
Jambs with complete accessories
Door Jamb, Pre Fabricated 2"x6" (2-legs & 1-header) 6 sets 1,000.00 6,000.00 6,000.00
Door Knob, Rekeyable Cylinder w/ 3-pcs Identical Keys, Stainless 15 sets 800.00 12,000.00 12,000.00
Stainless Steel Loose Pin Hinges 4"x4"x2"x3mmthk, Heavy Duty 12 sets 310.00 3,720.00 3,720.00
Concrete Nails 4" 5 kgs. 110.00 550.00 550.00
Sub-total…..Php 86,270.00 - - - - - - 86,270.00
TPC 1,560,000.00
Difference -
Republic of the Philippines
Department of Social Welfare and Development
KALAHI-CIDSS PAMANA: IP-CDD SUB PROJECTS
Barangay TACUL
Municipality of KIBLAWAN
Province of DAVAO DEL SUR
PROGRAM OF WORK
Scope of Work %
Qty Unit Unit Price Total
(Direct Cost) Wt.
I.]SITE WORKS 0.72% 82.50 Sq.m 136.52 11,263.20
II.]EXCAVATION WORKS 0.82% 29.15 cu.m. 438.01 12,768.00
III.]BACKFILLING/COMPACTION WORKS 2.55% 23.76 cu.m. 1,677.37 39,854.40
IV.]CARPENTRY WORKS 2.77% 760.00 bd.ft 56.93 43,263.00
V.] REINFORCED CONCRETE WORKS 12.40% 16.76 Cu.m 11,538.08 193,378.20
VI.] MASONRY WORKS 11.32% 461.73 sq.m. 382.30 176,517.60
VII.] STEEL WORKS 10.32% 1,125.85 kgs 142.97 160,968.00
VIII.] ROOFING WORKS 10.15% 148.00 sq.m 1,069.83 158,334.60
IX. ]CEILING WORKS 4.78% 134.00 sq.m. 556.52 74,573.10
X.] DOORS AND WINDOWS 7.55% 17.0 sets 6,931.87 117,841.80
XI. PAINTING WORKS 7.14% 394.14 sq.m. 282.79 111,457.80
XII ELECTRICAL WORKS 3.38% 1.00 lot 52,742.10 52,742.10
XIII PLUMBING WORKS 6.78% 1.00 lot 105,792.00 105,792.00
XIV.] TILE WORKS 7.26% 93.39 sq.m 1,212.39 113,224.80
XV.]. BASIC AMENITIES 4.48% 1.00 lot 69,825.00 69,825.00
XVI.]. SPECIAL ITEMS 2.83% 1.00 lot 44,096.40 44,096.40
XVII.]. MATERIAL HAULING 4.75% 1.00 lot 74,100.00 74,100.00
Prepared by: Checked by: Reviewed by: Concurred by: Approved by: Noted By:
MERLINA M. PANDOY ROMULO M. EDO LORD WARREN S. ORBUDA, CE FERNANDO B. PANDOY FULONG GEORGIN E. DIANGA AILLYN M. ARROBIO, CE, LPT
Head, Project Preparation Team Infrastructure Chairperson Engineer III Brgy. Captain CSPMC Chairperson RCIS - Designate
IP Leader / Representative
D U R A T I O N
Work Breakdown Qty Unit AMOUNT %age Physical %age Acc DECEMBER JANUARY FEBRUARY MARCH
Structure Weight Target Equi W-1 W-2 W-3 W-4 W-5 W-6 W-7 W-8 W-9 W-10 W-11 W-12 W-13 W-14 W-15 W-16
A - DIRECT COST
Plan 0.36% 0.36% 0.36%
I.]SITE WORKS 82.50 Sq.m 11,263.20 0.72%
Actual 0.36% 0.36%
Plan 0.00% 0.27% 0.27% 0.27%
II.]EXCAVATION WORKS 29.15 cu.m. 12,768.00 0.82%
Actual 0.00%
Plan 0.00% 0.64% 0.64% 0.64% 0.64%
III.]BACKFILLING/COMPACTION WORKS 23.76 cu.m. 39,854.40 2.55%
Actual 0.00%
Plan 0.00% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46%
IV.]CARPENTRY WORKS 760.00 bd.ft 43,263.00 2.77%
Actual 0.00%
Plan 0.00% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24%
V.] REINFORCED CONCRETE WORKS 16.76 Cu.m 193,378.20 12.40%
Actual 0.00%
Plan 0.00% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42%
VI.] MASONRY WORKS 461.73 sq.m. 176,517.60 11.32%
Actual 0.00%
Plan 0.00% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29%
VII.] STEEL WORKS 1125.85 kgs 160,968.00 10.32%
Actual 0.00%
Plan 0.00% 1.45% 1.45% 1.45% 1.45% 1.45% 1.45% 1.45%
VIII.] ROOFING WORKS 148.00 sq.m 158,334.60 10.15%
Actual 0.00%
Plan 0.00% 0.96% 0.96% 0.96% 0.96% 0.96%
IX. ]CEILING WORKS 134.00 sq.m. 74,573.10 4.78%
Actual 0.00%
Plan 0.00% 2.52% 2.52% 2.52%
X.] DOORS AND WINDOWS 17.00 sets 117,841.80 7.55%
Actual 0.00%
Plan 0.00% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89%
XI. PAINTING WORKS 394.14 sq.m. 111,457.80 7.14%
Actual 0.00%
Plan 0.00% 0.68% 0.68% 0.68% 0.68% 0.68%
XII ELECTRICAL WORKS 1.00 lot 52,742.10 3.38%
Actual 0.00%
Plan 0.00% 1.70% 1.70% 1.70% 1.70%
XIII PLUMBING WORKS 1.00 lot 105,792.00 6.78%
Actual 0.00%
Plan 0.00% 1.82% 1.82% 1.82% 1.82%
XIV.] TILE WORKS 93.39 sq.m 113,224.80 7.26%
Actual 0.00%
Plan 0.00% 2.24% 2.24%
XV.]. BASIC AMENITIES 1.00 lot 69,825.00 4.48%
Actual 0.00%
Plan 0.94% 0.94% 0.94% 0.94%
XVI.]. SPECIAL ITEMS 1.00 lot 44,096.40 2.83%
Actual 0.94% 0.94%
Plan 0.79% 0.79% 0.79% 0.79% 0.79% 0.79% 0.79%
XVII.]. MATERIAL HAULING 1.00 lot 74,100.00 4.75%
Actual 0.79% 0.79%
Plan 2.10%
COLUMN TOTAL….. 1,560,000.00 100.00%
Actual 2.10%
PLAN WEEKLY %AGE ACCOMPLISHMENT 2.10% 2.37% 1.22% 0.91% 2.78% 2.78% 2.34% 3.12% 5.20% 6.65% 8.94% 12.13% 13.95% 13.95% 11.97% 9.60%
COMM WEEKLY %AGE ACCOMPLISHMENT 2.10% 4.46% 5.68% 6.59% 9.37% 12.16% 14.50% 17.61% 22.81% 29.46% 38.40% 50.53% 64.48% 78.42% 90.40% 100.00%
ACT WEEKLY %AGE ACCOMPLISHMENT 2.10%
COMM ACT WEEKLY %AGE ACCOMPLISHMENT 2.10%
PHYSICAL
WEEKLY %AGE VARIANCE 0.00%
COMM WEEKLY %AGE VARIANCE 0.00%
Prepared by: Checked by: Reviewed by: Approved by: Noted By:
FULONG GEORGIN E. DIANGA
MERLINA M. PANDOY ROMULO M. EDO LORD WARREN S. ORBUDA, CE CSPMC Chairperson AILLYN M. ARROBIO, CE, LPT
Head, Project Preparation Team Infrastructure Chairperson Engineer III IP Leader / Representative RCIS
Concurred by:
MARK BRYAN L. ESTOPA, CE FERNANDO B. PANDOY
Technical Facilitator Brgy. Captain
Barangay Sub-Project Work Schedule & Physical Progress Report
As of December 18,2019
Total Sub-Project Cost
Name of Sub-Project : Construction of KASFALA Hall : Php 1,560,000.00
Physical Target : 82.50 square meter Date Started : 10-Dec-19
Region : XI Target Completion Date : 8-Apr-20
Province : Davao del Sur Date of Completion :
Municipality : Kiblawan Mode of Implementation : By Contract
Barangay : Tacul
D U R A T I O N
Work Breakdown Qty Unit AMOUNT %age Physical %age Acc DECEMBER JANUARY FEBRUARY MARCH
Structure Weight Target Equi W-1 W-2 W-3 W-4 W-5 W-6 W-7 W-8 W-9 W-10 W-11 W-12 W-13 W-14 W-15 W-16
A - DIRECT COST
Plan 0.72% 0.36% 0.36%
I.]SITE WORKS 82.50 Sq.m 11,263.20 0.72%
Actual 0.72% 0.36% 0.36%
Plan 0.27% 0.27% 0.27% 0.27%
II.]EXCAVATION WORKS 29.15 cu.m. 12,768.00 0.82%
Actual 0.27% 0.27%
Plan 0.00% 0.64% 0.64% 0.64% 0.64%
III.]BACKFILLING/COMPACTION WORKS 23.76 cu.m. 39,854.40 2.55%
Actual 0.64% 0.64%
Plan 0.00% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46%
IV.]CARPENTRY WORKS 760.00 bd.ft 43,263.00 2.77%
Actual 0.46% 0.46%
Plan 0.00% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24%
V.] REINFORCED CONCRETE WORKS 16.76 Cu.m 193,378.20 12.40%
Actual 1.24% 1.24%
Plan 0.00% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42%
VI.] MASONRY WORKS 461.73 sq.m. 176,517.60 11.32%
Actual 0.00%
Plan 0.00% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29%
VII.] STEEL WORKS 1125.85 kgs 160,968.00 10.32%
Actual 0.00%
Plan 0.00% 1.45% 1.45% 1.45% 1.45% 1.45% 1.45% 1.45%
VIII.] ROOFING WORKS 148.00 sq.m 158,334.60 10.15%
Actual 0.00%
Plan 0.00% 0.96% 0.96% 0.96% 0.96% 0.96%
IX. ]CEILING WORKS 134.00 sq.m. 74,573.10 4.78%
Actual 0.00%
Plan 0.00% 2.52% 2.52% 2.52%
X.] DOORS AND WINDOWS 17.00 sets 117,841.80 7.55%
Actual 0.00%
Plan 0.00% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89%
XI. PAINTING WORKS 394.14 sq.m. 111,457.80 7.14%
Actual 0.00%
Plan 0.00% 0.68% 0.68% 0.68% 0.68% 0.68%
XII ELECTRICAL WORKS 1.00 lot 52,742.10 3.38%
Actual 0.00%
Plan 0.00% 1.70% 1.70% 1.70% 1.70%
XIII PLUMBING WORKS 1.00 lot 105,792.00 6.78%
Actual 0.00%
Plan 0.00% 1.82% 1.82% 1.82% 1.82%
XIV.] TILE WORKS 93.39 sq.m 113,224.80 7.26%
Actual 0.00%
Plan 0.00% 2.24% 2.24%
XV.]. BASIC AMENITIES 1.00 lot 69,825.00 4.48%
Actual 0.00%
Plan 1.89% 0.94% 0.94% 0.94%
XVI.]. SPECIAL ITEMS 1.00 lot 44,096.40 2.83%
Actual 0.94% 0.94%
Plan 1.58% 0.79% 0.79% 0.79% 0.79% 0.79% 0.79%
XVII.]. MATERIAL HAULING 1.00 lot 74,100.00 4.75%
Actual 0.79% 0.79%
Plan 4.46%
COLUMN TOTAL….. 1,560,000.00 100.00%
Actual 5.07%
PLAN WEEKLY %AGE ACCOMPLISHMENT 2.10% 2.37% 1.22% 0.91% 2.78% 2.78% 2.34% 3.12% 5.20% 6.65% 8.94% 12.13% 13.95% 13.95% 11.97% 9.60%
COMM WEEKLY %AGE ACCOMPLISHMENT 2.10% 4.46% 5.68% 6.59% 9.37% 12.16% 14.50% 17.61% 22.81% 29.46% 38.40% 50.53% 64.48% 78.42% 90.40% 100.00%
ACT WEEKLY %AGE ACCOMPLISHMENT 2.10% 2.97%
COMM ACT WEEKLY %AGE ACCOMPLISHMENT 2.10% 5.07%
PHYSICAL
WEEKLY %AGE VARIANCE 0.00% 0.60%
COMM WEEKLY %AGE VARIANCE 0.00% 0.60%
Prepared by: Checked by: Reviewed by: Approved by: Noted By:
FULONG GEORGIN E. DIANGA
MERLINA M. PANDOY ROMULO M. EDO LORD WARREN S. ORBUDA, CE CSPMC Chairperson AILLYN M. ARROBIO, CE, LPT
Head, Project Preparation Team Infrastructure Chairperson Engineer III IP Leader / Representative RCIS
Concurred by:
MARK BRYAN L. ESTOPA, CE FERNANDO B. PANDOY
Technical Facilitator Brgy. Captain
Barangay Sub-Project Work Schedule & Physical Progress Report
As of December 25,2019
Total Sub-Project Cost
Name of Sub-Project : Construction of KASFALA Hall : Php 1,560,000.00
Physical Target : 82.50 square meter Date Started : 10-Dec-19
Region : XI Target Completion Date : 8-Apr-20
Province : Davao del Sur Date of Completion :
Municipality : Kiblawan Mode of Implementation : By Contract
Barangay : Tacul
D U R A T I O N
Work Breakdown Qty Unit AMOUNT %age Physical %age Acc DECEMBER JANUARY FEBRUARY MARCH
Structure Weight Target Equi W-1 W-2 W-3 W-4 W-5 W-6 W-7 W-8 W-9 W-10 W-11 W-12 W-13 W-14 W-15 W-16
A - DIRECT COST
Plan 0.72% 0.36% 0.36%
I.]SITE WORKS 82.50 Sq.m 11,263.20 0.72%
Actual 0.72% 0.36% 0.36%
Plan 0.55% 0.27% 0.27% 0.27%
II.]EXCAVATION WORKS 29.15 cu.m. 12,768.00 0.82%
Actual 0.82% 0.27% 0.55%
Plan 0.00% 0.64% 0.64% 0.64% 0.64%
III.]BACKFILLING/COMPACTION WORKS 23.76 cu.m. 39,854.40 2.55%
Actual 1.28% 0.64% 0.64%
Plan 0.00% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46%
IV.]CARPENTRY WORKS 760.00 bd.ft 43,263.00 2.77%
Actual 0.92% 0.46% 0.46%
Plan 0.00% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24%
V.] REINFORCED CONCRETE WORKS 16.76 Cu.m 193,378.20 12.40%
Actual 2.48% 1.24% 1.24%
Plan 0.00% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42%
VI.] MASONRY WORKS 461.73 sq.m. 176,517.60 11.32%
Actual 0.00%
Plan 0.00% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29%
VII.] STEEL WORKS 1125.85 kgs 160,968.00 10.32%
Actual 0.00%
Plan 0.00% 1.45% 1.45% 1.45% 1.45% 1.45% 1.45% 1.45%
VIII.] ROOFING WORKS 148.00 sq.m 158,334.60 10.15%
Actual 0.00%
Plan 0.00% 0.96% 0.96% 0.96% 0.96% 0.96%
IX. ]CEILING WORKS 134.00 sq.m. 74,573.10 4.78%
Actual 0.00%
Plan 0.00% 2.52% 2.52% 2.52%
X.] DOORS AND WINDOWS 17.00 sets 117,841.80 7.55%
Actual 0.00%
Plan 0.00% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89%
XI. PAINTING WORKS 394.14 sq.m. 111,457.80 7.14%
Actual 0.00%
Plan 0.00% 0.68% 0.68% 0.68% 0.68% 0.68%
XII ELECTRICAL WORKS 1.00 lot 52,742.10 3.38%
Actual 0.00%
Plan 0.00% 1.70% 1.70% 1.70% 1.70%
XIII PLUMBING WORKS 1.00 lot 105,792.00 6.78%
Actual 0.00%
Plan 0.00% 1.82% 1.82% 1.82% 1.82%
XIV.] TILE WORKS 93.39 sq.m 113,224.80 7.26%
Actual 0.00%
Plan 0.00% 2.24% 2.24%
XV.]. BASIC AMENITIES 1.00 lot 69,825.00 4.48%
Actual 0.00%
Plan 2.83% 0.94% 0.94% 0.94%
XVI.]. SPECIAL ITEMS 1.00 lot 44,096.40 2.83%
Actual 0.94% 0.94%
Plan 1.58% 0.79% 0.79% 0.79% 0.79% 0.79% 0.79%
XVII.]. MATERIAL HAULING 1.00 lot 74,100.00 4.75%
Actual 0.79% 0.79%
Plan 5.68%
COLUMN TOTAL….. 1,560,000.00 100.00%
Actual 7.95%
PLAN WEEKLY %AGE ACCOMPLISHMENT 2.10% 2.37% 1.22% 0.91% 2.78% 2.78% 2.34% 3.12% 5.20% 6.65% 8.94% 12.13% 13.95% 13.95% 11.97% 9.60%
COMM WEEKLY %AGE ACCOMPLISHMENT 2.10% 4.46% 5.68% 6.59% 9.37% 12.16% 14.50% 17.61% 22.81% 29.46% 38.40% 50.53% 64.48% 78.42% 90.40% 100.00%
ACT WEEKLY %AGE ACCOMPLISHMENT 2.10% 2.97% 2.89%
COMM ACT WEEKLY %AGE ACCOMPLISHMENT 2.10% 5.07% 7.95%
PHYSICAL
WEEKLY %AGE VARIANCE 0.00% 0.60% 1.67%
COMM WEEKLY %AGE VARIANCE 0.00% 0.60% 2.27%
Prepared by: Checked by: Reviewed by: Approved by: Noted By:
FULONG GEORGIN E. DIANGA
MERLINA M. PANDOY ROMULO M. EDO LORD WARREN S. ORBUDA, CE CSPMC Chairperson AILLYN M. ARROBIO, CE, LPT
Head, Project Preparation Team Infrastructure Chairperson Engineer III IP Leader / Representative RCIS
Concurred by:
MARK BRYAN L. ESTOPA, CE FERNANDO B. PANDOY
Technical Facilitator Brgy. Captain
Barangay Sub-Project Work Schedule & Physical Progress Report
As of January 1, 2020
Total Sub-Project Cost
Name of Sub-Project : Construction of KASFALA Hall : Php 1,560,000.00
Physical Target : 82.50 square meter Date Started : 10-Dec-19
Region : XI Target Completion Date : 8-Apr-20
Province : Davao del Sur Date of Completion :
Municipality : Kiblawan Mode of Implementation : By Contract
Barangay : Tacul
D U R A T I O N
Work Breakdown Qty Unit AMOUNT %age Physical %age Acc DECEMBER JANUARY FEBRUARY MARCH
Structure Weight Target Equi W-1 W-2 W-3 W-4 W-5 W-6 W-7 W-8 W-9 W-10 W-11 W-12 W-13 W-14 W-15 W-16
A - DIRECT COST
Plan 0.72% 0.36% 0.36%
I.]SITE WORKS 82.50 Sq.m 11,263.20 0.72%
Actual 0.72% 0.36% 0.36%
Plan 0.82% 0.27% 0.27% 0.27%
II.]EXCAVATION WORKS 29.15 cu.m. 12,768.00 0.82%
Actual 0.82% 0.27% 0.55%
Plan 0.64% 0.64% 0.64% 0.64% 0.64%
III.]BACKFILLING/COMPACTION WORKS 23.76 cu.m. 39,854.40 2.55%
Actual 2.55% 0.64% 0.64% 1.28%
Plan 0.00% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46%
IV.]CARPENTRY WORKS 760.00 bd.ft 43,263.00 2.77%
Actual 2.77% 0.46% 0.46% 1.85%
Plan 0.00% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24%
V.] REINFORCED CONCRETE WORKS 16.76 Cu.m 193,378.20 12.40%
Actual 7.44% 1.24% 1.24% 4.96%
Plan 0.00% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42%
VI.] MASONRY WORKS 461.73 sq.m. 176,517.60 11.32%
Actual 3.40% 3.40%
Plan 0.00% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29%
VII.] STEEL WORKS 1125.85 kgs 160,968.00 10.32%
Actual 0.00%
Plan 0.00% 1.45% 1.45% 1.45% 1.45% 1.45% 1.45% 1.45%
VIII.] ROOFING WORKS 148.00 sq.m 158,334.60 10.15%
Actual 0.00%
Plan 0.00% 0.96% 0.96% 0.96% 0.96% 0.96%
IX. ]CEILING WORKS 134.00 sq.m. 74,573.10 4.78%
Actual 0.00%
Plan 0.00% 2.52% 2.52% 2.52%
X.] DOORS AND WINDOWS 17.00 sets 117,841.80 7.55%
Actual 0.00%
Plan 0.00% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89%
XI. PAINTING WORKS 394.14 sq.m. 111,457.80 7.14%
Actual 0.00%
Plan 0.00% 0.68% 0.68% 0.68% 0.68% 0.68%
XII ELECTRICAL WORKS 1.00 lot 52,742.10 3.38%
Actual 0.00%
Plan 0.00% 1.70% 1.70% 1.70% 1.70%
XIII PLUMBING WORKS 1.00 lot 105,792.00 6.78%
Actual 0.00%
Plan 0.00% 1.82% 1.82% 1.82% 1.82%
XIV.] TILE WORKS 93.39 sq.m 113,224.80 7.26%
Actual 0.00%
Plan 0.00% 2.24% 2.24%
XV.]. BASIC AMENITIES 1.00 lot 69,825.00 4.48%
Actual 0.00%
Plan 2.83% 0.94% 0.94% 0.94%
XVI.]. SPECIAL ITEMS 1.00 lot 44,096.40 2.83%
Actual 0.94% 0.94%
Plan 1.58% 0.79% 0.79% 0.79% 0.79% 0.79% 0.79%
XVII.]. MATERIAL HAULING 1.00 lot 74,100.00 4.75%
Actual 0.79% 0.79%
Plan 6.59%
COLUMN TOTAL….. 1,560,000.00 100.00%
Actual 19.43%
PLAN WEEKLY %AGE ACCOMPLISHMENT 2.10% 2.37% 1.22% 0.91% 2.78% 2.78% 2.34% 3.12% 5.20% 6.65% 8.94% 12.13% 13.95% 13.95% 11.97% 9.60%
COMM WEEKLY %AGE ACCOMPLISHMENT 2.10% 4.46% 5.68% 6.59% 9.37% 12.16% 14.50% 17.61% 22.81% 29.46% 38.40% 50.53% 64.48% 78.42% 90.40% 100.00%
ACT WEEKLY %AGE ACCOMPLISHMENT 2.10% 2.97% 2.89% 11.48%
COMM ACT WEEKLY %AGE ACCOMPLISHMENT 2.10% 5.07% 7.95% 19.43%
PHYSICAL
WEEKLY %AGE VARIANCE 0.00% 0.60% 1.67% 10.57%
COMM WEEKLY %AGE VARIANCE 0.00% 0.60% 2.27% 12.84%
Prepared by: Checked by: Reviewed by: Approved by: Noted By:
FULONG GEORGIN E. DIANGA
MERLINA M. PANDOY ROMULO M. EDO LORD WARREN S. ORBUDA, CE CSPMC Chairperson AILLYN M. ARROBIO, CE, LPT
Head, Project Preparation Team Infrastructure Chairperson Engineer III IP Leader / Representative RCIS
Concurred by:
MARK BRYAN L. ESTOPA, CE FERNANDO B. PANDOY
Technical Facilitator Brgy. Captain
Barangay Sub-Project Work Schedule & Physical Progress Report
As of January 8, 2020
Total Sub-Project Cost
Name of Sub-Project : Construction of KASFALA Hall : Php 1,560,000.00
Physical Target : 82.50 square meter Date Started : 10-Dec-19
Region : XI Target Completion Date : 8-Apr-20
Province : Davao del Sur Date of Completion :
Municipality : Kiblawan Mode of Implementation : By Contract
Barangay : Tacul
D U R A T I O N
Work Breakdown Qty Unit AMOUNT %age Physical %age Acc DECEMBER JANUARY FEBRUARY MARCH
Structure Weight Target Equi W-1 W-2 W-3 W-4 W-5 W-6 W-7 W-8 W-9 W-10 W-11 W-12 W-13 W-14 W-15 W-16
A - DIRECT COST
Plan 0.72% 0.36% 0.36%
I.]SITE WORKS 82.50 Sq.m 11,263.20 0.72%
Actual 0.72% 0.36% 0.36%
Plan 0.82% 0.27% 0.27% 0.27%
II.]EXCAVATION WORKS 29.15 cu.m. 12,768.00 0.82%
Actual 0.82% 0.27% 0.55%
Plan 1.28% 0.64% 0.64% 0.64% 0.64%
III.]BACKFILLING/COMPACTION WORKS 23.76 cu.m. 39,854.40 2.55%
Actual 2.55% 0.64% 0.64% 1.28%
Plan 0.46% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46%
IV.]CARPENTRY WORKS 760.00 bd.ft 43,263.00 2.77%
Actual 2.77% 0.46% 0.46% 1.85%
Plan 0.00% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24%
V.] REINFORCED CONCRETE WORKS 16.76 Cu.m 193,378.20 12.40%
Actual 9.92% 1.24% 1.24% 4.96% 2.48%
Plan 0.00% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42%
VI.] MASONRY WORKS 461.73 sq.m. 176,517.60 11.32%
Actual 7.92% 3.40% 4.53%
Plan 0.00% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29%
VII.] STEEL WORKS 1125.85 kgs 160,968.00 10.32%
Actual 3.10% 3.10%
Plan 0.00% 1.45% 1.45% 1.45% 1.45% 1.45% 1.45% 1.45%
VIII.] ROOFING WORKS 148.00 sq.m 158,334.60 10.15%
Actual 0.00%
Plan 0.00% 0.96% 0.96% 0.96% 0.96% 0.96%
IX. ]CEILING WORKS 134.00 sq.m. 74,573.10 4.78%
Actual 0.00%
Plan 0.00% 2.52% 2.52% 2.52%
X.] DOORS AND WINDOWS 17.00 sets 117,841.80 7.55%
Actual 0.00%
Plan 0.89% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89%
XI. PAINTING WORKS 394.14 sq.m. 111,457.80 7.14%
Actual 0.00%
Plan 0.00% 0.68% 0.68% 0.68% 0.68% 0.68%
XII ELECTRICAL WORKS 1.00 lot 52,742.10 3.38%
Actual 0.00%
Plan 0.00% 1.70% 1.70% 1.70% 1.70%
XIII PLUMBING WORKS 1.00 lot 105,792.00 6.78%
Actual 0.00%
Plan 0.00% 1.82% 1.82% 1.82% 1.82%
XIV.] TILE WORKS 93.39 sq.m 113,224.80 7.26%
Actual 0.00%
Plan 0.00% 2.24% 2.24%
XV.]. BASIC AMENITIES 1.00 lot 69,825.00 4.48%
Actual 0.00%
Plan 2.83% 0.94% 0.94% 0.94%
XVI.]. SPECIAL ITEMS 1.00 lot 44,096.40 2.83%
Actual 0.94% 0.94%
Plan 2.38% 0.79% 0.79% 0.79% 0.79% 0.79% 0.79%
XVII.]. MATERIAL HAULING 1.00 lot 74,100.00 4.75%
Actual 0.79% 0.79%
Plan 9.37%
COLUMN TOTAL….. 1,560,000.00 100.00%
Actual 29.54%
PLAN WEEKLY %AGE ACCOMPLISHMENT 2.10% 2.37% 1.22% 0.91% 2.78% 2.78% 2.34% 3.12% 5.20% 6.65% 8.94% 12.13% 13.95% 13.95% 11.97% 9.60%
COMM WEEKLY %AGE ACCOMPLISHMENT 2.10% 4.46% 5.68% 6.59% 9.37% 12.16% 14.50% 17.61% 22.81% 29.46% 38.40% 50.53% 64.48% 78.42% 90.40% 100.00%
ACT WEEKLY %AGE ACCOMPLISHMENT 2.10% 2.97% 2.89% 11.48% 10.10%
COMM ACT WEEKLY %AGE ACCOMPLISHMENT 2.10% 5.07% 7.95% 19.43% 29.54%
PHYSICAL
WEEKLY %AGE VARIANCE 0.00% 0.60% 1.67% 10.57% 7.32%
COMM WEEKLY %AGE VARIANCE 0.00% 0.60% 2.27% 12.84% 20.16%
Prepared by: Checked by: Reviewed by: Approved by: Noted By:
FULONG GEORGIN E. DIANGA
MERLINA M. PANDOY ROMULO M. EDO LORD WARREN S. ORBUDA, CE CSPMC Chairperson AILLYN M. ARROBIO, CE, LPT
Head, Project Preparation Team Infrastructure Chairperson Engineer III IP Leader / Representative RCIS
Concurred by:
MARK BRYAN L. ESTOPA, CE FERNANDO B. PANDOY
Technical Facilitator Brgy. Captain
Barangay Sub-Project Work Schedule & Physical Progress Report
As of January 15, 2020
Total Sub-Project Cost
Name of Sub-Project : Construction of KASFALA Hall : Php 1,560,000.00
Physical Target : 82.50 square meter Date Started : 10-Dec-19
Region : XI Target Completion Date : 8-Apr-20
Province : Davao del Sur Date of Completion :
Municipality : Kiblawan Mode of Implementation : By Contract
Barangay : Tacul
D U R A T I O N
Work Breakdown Qty Unit AMOUNT %age Physical %age Acc DECEMBER JANUARY FEBRUARY MARCH
Structure Weight Target Equi W-1 W-2 W-3 W-4 W-5 W-6 W-7 W-8 W-9 W-10 W-11 W-12 W-13 W-14 W-15 W-16
A - DIRECT COST
Plan 0.72% 0.36% 0.36%
I.]SITE WORKS 82.50 Sq.m 11,263.20 0.72%
Actual 0.72% 0.36% 0.36%
Plan 0.82% 0.27% 0.27% 0.27%
II.]EXCAVATION WORKS 29.15 cu.m. 12,768.00 0.82%
Actual 0.82% 0.27% 0.55%
Plan 1.91% 0.64% 0.64% 0.64% 0.64%
III.]BACKFILLING/COMPACTION WORKS 23.76 cu.m. 39,854.40 2.55%
Actual 2.55% 0.64% 0.64% 1.28%
Plan 0.92% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46%
IV.]CARPENTRY WORKS 760.00 bd.ft 43,263.00 2.77%
Actual 2.77% 0.46% 0.46% 1.85%
Plan 0.00% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24%
V.] REINFORCED CONCRETE WORKS 16.76 Cu.m 193,378.20 12.40%
Actual 12.40% 1.24% 1.24% 4.96% 2.48% 2.48%
Plan 0.00% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42%
VI.] MASONRY WORKS 461.73 sq.m. 176,517.60 11.32%
Actual 11.32% 3.40% 4.53% 3.40%
Plan 0.00% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29%
VII.] STEEL WORKS 1125.85 kgs 160,968.00 10.32%
Actual 8.26% 3.10% 5.16%
Plan 0.00% 1.45% 1.45% 1.45% 1.45% 1.45% 1.45% 1.45%
VIII.] ROOFING WORKS 148.00 sq.m 158,334.60 10.15%
Actual 0.00%
Plan 0.00% 0.96% 0.96% 0.96% 0.96% 0.96%
IX. ]CEILING WORKS 134.00 sq.m. 74,573.10 4.78%
Actual 0.00%
Plan 0.00% 2.52% 2.52% 2.52%
X.] DOORS AND WINDOWS 17.00 sets 117,841.80 7.55%
Actual 0.76% 0.76%
Plan 1.79% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89%
XI. PAINTING WORKS 394.14 sq.m. 111,457.80 7.14%
Actual 0.59% 0.59%
Plan 0.00% 0.68% 0.68% 0.68% 0.68% 0.68%
XII ELECTRICAL WORKS 1.00 lot 52,742.10 3.38%
Actual 0.00%
Plan 0.00% 1.70% 1.70% 1.70% 1.70%
XIII PLUMBING WORKS 1.00 lot 105,792.00 6.78%
Actual 0.00%
Plan 0.00% 1.82% 1.82% 1.82% 1.82%
XIV.] TILE WORKS 93.39 sq.m 113,224.80 7.26%
Actual 0.00%
Plan 0.00% 2.24% 2.24%
XV.]. BASIC AMENITIES 1.00 lot 69,825.00 4.48%
Actual 0.00%
Plan 2.83% 0.94% 0.94% 0.94%
XVI.]. SPECIAL ITEMS 1.00 lot 44,096.40 2.83%
Actual 1.89% 0.94% 0.94%
Plan 3.17% 0.79% 0.79% 0.79% 0.79% 0.79% 0.79%
XVII.]. MATERIAL HAULING 1.00 lot 74,100.00 4.75%
Actual 3.17% 0.79% 2.38%
Plan 12.16%
COLUMN TOTAL….. 1,560,000.00 100.00%
Actual 45.23%
PLAN WEEKLY %AGE ACCOMPLISHMENT 2.10% 2.37% 1.22% 0.91% 2.78% 2.78% 2.34% 3.12% 5.20% 6.65% 8.94% 12.13% 13.95% 13.95% 11.97% 9.60%
COMM WEEKLY %AGE ACCOMPLISHMENT 2.10% 4.46% 5.68% 6.59% 9.37% 12.16% 14.50% 17.61% 22.81% 29.46% 38.40% 50.53% 64.48% 78.42% 90.40% 100.00%
ACT WEEKLY %AGE ACCOMPLISHMENT 2.10% 2.97% 2.89% 11.48% 10.10% 15.70%
COMM ACT WEEKLY %AGE ACCOMPLISHMENT 2.10% 5.07% 7.95% 19.43% 29.54% 45.23%
PHYSICAL
WEEKLY %AGE VARIANCE 0.00% 0.60% 1.67% 10.57% 7.32% 12.92%
COMM WEEKLY %AGE VARIANCE 0.00% 0.60% 2.27% 12.84% 20.16% 33.08%
Prepared by: Checked by: Reviewed by: Approved by: Noted By:
FULONG GEORGIN E. DIANGA
MERLINA M. PANDOY ROMULO M. EDO LORD WARREN S. ORBUDA, CE CSPMC Chairperson AILLYN M. ARROBIO, CE, LPT
Head, Project Preparation Team Infrastructure Chairperson Engineer III IP Leader / Representative RCIS
Concurred by:
MARK BRYAN L. ESTOPA, CE FERNANDO B. PANDOY
Technical Facilitator Brgy. Captain
Barangay Sub-Project Work Schedule & Physical Progress Report
As of January 22, 2020
Total Sub-Project Cost
Name of Sub-Project : Construction of KASFALA Hall : Php 1,560,000.00
Physical Target : 82.50 square meter Date Started : 10-Dec-19
Region : XI Target Completion Date : 8-Apr-20
Province : Davao del Sur Date of Completion :
Municipality : Kiblawan Mode of Implementation : By Contract
Barangay : Tacul
D U R A T I O N
Work Breakdown Qty Unit AMOUNT %age Physical %age Acc DECEMBER JANUARY FEBRUARY MARCH
Structure Weight Target Equi W-1 W-2 W-3 W-4 W-5 W-6 W-7 W-8 W-9 W-10 W-11 W-12 W-13 W-14 W-15 W-16
A - DIRECT COST
Plan 0.72% 0.36% 0.36%
I.]SITE WORKS 82.50 Sq.m 11,263.20 0.72%
Actual 0.72% 0.36% 0.36%
Plan 0.82% 0.27% 0.27% 0.27%
II.]EXCAVATION WORKS 29.15 cu.m. 12,768.00 0.82%
Actual 0.82% 0.27% 0.55%
Plan 2.55% 0.64% 0.64% 0.64% 0.64%
III.]BACKFILLING/COMPACTION WORKS 23.76 cu.m. 39,854.40 2.55%
Actual 2.55% 0.64% 0.64% 1.28%
Plan 1.39% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46%
IV.]CARPENTRY WORKS 760.00 bd.ft 43,263.00 2.77%
Actual 2.77% 0.46% 0.46% 1.85%
Plan 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24%
V.] REINFORCED CONCRETE WORKS 16.76 Cu.m 193,378.20 12.40%
Actual 12.40% 1.24% 1.24% 4.96% 2.48% 2.48%
Plan 0.00% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42%
VI.] MASONRY WORKS 461.73 sq.m. 176,517.60 11.32%
Actual 11.32% 3.40% 4.53% 3.40%
Plan 0.00% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29%
VII.] STEEL WORKS 1125.85 kgs 160,968.00 10.32%
Actual 9.29% 3.10% 5.16% 1.03%
Plan 0.00% 1.45% 1.45% 1.45% 1.45% 1.45% 1.45% 1.45%
VIII.] ROOFING WORKS 148.00 sq.m 158,334.60 10.15%
Actual 0.00%
Plan 0.00% 0.96% 0.96% 0.96% 0.96% 0.96%
IX. ]CEILING WORKS 134.00 sq.m. 74,573.10 4.78%
Actual 1.43% 1.43%
Plan 0.00% 2.52% 2.52% 2.52%
X.] DOORS AND WINDOWS 17.00 sets 117,841.80 7.55%
Actual 1.51% 0.76% 0.76%
Plan 1.79% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89%
XI. PAINTING WORKS 394.14 sq.m. 111,457.80 7.14%
Actual 0.59% 0.59%
Plan 0.00% 0.68% 0.68% 0.68% 0.68% 0.68%
XII ELECTRICAL WORKS 1.00 lot 52,742.10 3.38%
Actual 0.00%
Plan 0.00% 1.70% 1.70% 1.70% 1.70%
XIII PLUMBING WORKS 1.00 lot 105,792.00 6.78%
Actual 0.68% 0.68%
Plan 0.00% 1.82% 1.82% 1.82% 1.82%
XIV.] TILE WORKS 93.39 sq.m 113,224.80 7.26%
Actual 0.00%
Plan 0.00% 2.24% 2.24%
XV.]. BASIC AMENITIES 1.00 lot 69,825.00 4.48%
Actual 0.00%
Plan 2.83% 0.94% 0.94% 0.94%
XVI.]. SPECIAL ITEMS 1.00 lot 44,096.40 2.83%
Actual 1.89% 0.94% 0.94%
Plan 3.17% 0.79% 0.79% 0.79% 0.79% 0.79% 0.79%
XVII.]. MATERIAL HAULING 1.00 lot 74,100.00 4.75%
Actual 3.17% 0.79% 2.38%
Plan 14.50%
COLUMN TOTAL….. 1,560,000.00 100.00%
Actual 49.13%
PLAN WEEKLY %AGE ACCOMPLISHMENT 2.10% 2.37% 1.22% 0.91% 2.78% 2.78% 2.34% 3.12% 5.20% 6.65% 8.94% 12.13% 13.95% 13.95% 11.97% 9.60%
COMM WEEKLY %AGE ACCOMPLISHMENT 2.10% 4.46% 5.68% 6.59% 9.37% 12.16% 14.50% 17.61% 22.81% 29.46% 38.40% 50.53% 64.48% 78.42% 90.40% 100.00%
ACT WEEKLY %AGE ACCOMPLISHMENT 2.10% 2.97% 2.89% 11.48% 10.10% 15.70% 3.90%
COMM ACT WEEKLY %AGE ACCOMPLISHMENT 2.10% 5.07% 7.95% 19.43% 29.54% 45.23% 49.13%
PHYSICAL
WEEKLY %AGE VARIANCE 0.00% 0.60% 1.67% 10.57% 7.32% 12.92% 1.56%
COMM WEEKLY %AGE VARIANCE 0.00% 0.60% 2.27% 12.84% 20.16% 33.08% 34.64%
Prepared by: Checked by: Reviewed by: Approved by: Noted By:
FULONG GEORGIN E. DIANGA
MERLINA M. PANDOY ROMULO M. EDO LORD WARREN S. ORBUDA, CE CSPMC Chairperson AILLYN M. ARROBIO, CE, LPT
Head, Project Preparation Team Infrastructure Chairperson Engineer III IP Leader / Representative RCIS
Concurred by:
MARK BRYAN L. ESTOPA, CE FERNANDO B. PANDOY
Technical Facilitator Brgy. Captain
Barangay Sub-Project Work Schedule & Physical Progress Report
As of January 29, 2020
Total Sub-Project Cost
Name of Sub-Project : Construction of KASFALA Hall : Php 1,560,000.00
Physical Target : 82.50 square meter Date Started : 10-Dec-19
Region : XI Target Completion Date : 8-Apr-20
Province : Davao del Sur Date of Completion :
Municipality : Kiblawan Mode of Implementation : By Contract
Barangay : Tacul
D U R A T I O N
Work Breakdown Qty Unit AMOUNT %age Physical %age Acc DECEMBER JANUARY FEBRUARY MARCH
Structure Weight Target Equi W-1 W-2 W-3 W-4 W-5 W-6 W-7 W-8 W-9 W-10 W-11 W-12 W-13 W-14 W-15 W-16
A - DIRECT COST
Plan 0.72% 0.36% 0.36%
I.]SITE WORKS 82.50 Sq.m 11,263.20 0.72%
Actual 0.72% 0.36% 0.36%
Plan 0.82% 0.27% 0.27% 0.27%
II.]EXCAVATION WORKS 29.15 cu.m. 12,768.00 0.82%
Actual 0.82% 0.27% 0.55%
Plan 2.55% 0.64% 0.64% 0.64% 0.64%
III.]BACKFILLING/COMPACTION WORKS 23.76 cu.m. 39,854.40 2.55%
Actual 2.55% 0.64% 0.64% 1.28%
Plan 1.85% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46%
IV.]CARPENTRY WORKS 760.00 bd.ft 43,263.00 2.77%
Actual 2.77% 0.46% 0.46% 1.85%
Plan 2.48% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24%
V.] REINFORCED CONCRETE WORKS 16.76 Cu.m 193,378.20 12.40%
Actual 12.40% 1.24% 1.24% 4.96% 2.48% 2.48%
Plan 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42%
VI.] MASONRY WORKS 461.73 sq.m. 176,517.60 11.32%
Actual 11.32% 3.40% 4.53% 3.40%
Plan 0.00% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29%
VII.] STEEL WORKS 1125.85 kgs 160,968.00 10.32%
Actual 9.29% 3.10% 5.16% 1.03%
Plan 0.00% 1.45% 1.45% 1.45% 1.45% 1.45% 1.45% 1.45%
VIII.] ROOFING WORKS 148.00 sq.m 158,334.60 10.15%
Actual 5.08% 5.08%
Plan 0.00% 0.96% 0.96% 0.96% 0.96% 0.96%
IX. ]CEILING WORKS 134.00 sq.m. 74,573.10 4.78%
Actual 2.39% 1.43% 0.96%
Plan 0.00% 2.52% 2.52% 2.52%
X.] DOORS AND WINDOWS 17.00 sets 117,841.80 7.55%
Actual 1.51% 0.76% 0.76%
Plan 1.79% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89%
XI. PAINTING WORKS 394.14 sq.m. 111,457.80 7.14%
Actual 2.14% 0.59% 1.55%
Plan 0.00% 0.68% 0.68% 0.68% 0.68% 0.68%
XII ELECTRICAL WORKS 1.00 lot 52,742.10 3.38%
Actual 0.00%
Plan 0.00% 1.70% 1.70% 1.70% 1.70%
XIII PLUMBING WORKS 1.00 lot 105,792.00 6.78%
Actual 2.71% 0.68% 2.03%
Plan 0.00% 1.82% 1.82% 1.82% 1.82%
XIV.] TILE WORKS 93.39 sq.m 113,224.80 7.26%
Actual 0.00%
Plan 0.00% 2.24% 2.24%
XV.]. BASIC AMENITIES 1.00 lot 69,825.00 4.48%
Actual 0.00%
Plan 2.83% 0.94% 0.94% 0.94%
XVI.]. SPECIAL ITEMS 1.00 lot 44,096.40 2.83%
Actual 1.89% 0.94% 0.94%
Plan 3.17% 0.79% 0.79% 0.79% 0.79% 0.79% 0.79%
XVII.]. MATERIAL HAULING 1.00 lot 74,100.00 4.75%
Actual 3.17% 0.79% 2.38%
Plan 17.61%
COLUMN TOTAL….. 1,560,000.00 100.00%
Actual 58.75%
PLAN WEEKLY %AGE ACCOMPLISHMENT 2.10% 2.37% 1.22% 0.91% 2.78% 2.78% 2.34% 3.12% 5.20% 6.65% 8.94% 12.13% 13.95% 13.95% 11.97% 9.60%
COMM WEEKLY %AGE ACCOMPLISHMENT 2.10% 4.46% 5.68% 6.59% 9.37% 12.16% 14.50% 17.61% 22.81% 29.46% 38.40% 50.53% 64.48% 78.42% 90.40% 100.00%
ACT WEEKLY %AGE ACCOMPLISHMENT 2.10% 2.97% 2.89% 11.48% 10.10% 15.70% 3.90% 9.62%
COMM ACT WEEKLY %AGE ACCOMPLISHMENT 2.10% 5.07% 7.95% 19.43% 29.54% 45.23% 49.13% 58.75%
PHYSICAL
WEEKLY %AGE VARIANCE 0.00% 0.60% 1.67% 10.57% 7.32% 12.92% 1.56% 6.50%
COMM WEEKLY %AGE VARIANCE 0.00% 0.60% 2.27% 12.84% 20.16% 33.08% 34.64% 41.14%
Prepared by: Checked by: Reviewed by: Approved by: Noted By:
FULONG GEORGIN E. DIANGA
MERLINA M. PANDOY ROMULO M. EDO LORD WARREN S. ORBUDA, CE CSPMC Chairperson AILLYN M. ARROBIO, CE, LPT
Head, Project Preparation Team Infrastructure Chairperson Engineer III IP Leader / Representative RCIS
Concurred by:
MARK BRYAN L. ESTOPA, CE FERNANDO B. PANDOY
Technical Facilitator Brgy. Captain
Barangay Sub-Project Work Schedule & Physical Progress Report
As of February 5, 2020
Total Sub-Project Cost
Name of Sub-Project : Construction of KASFALA Hall : Php 1,560,000.00
Physical Target : 82.50 square meter Date Started : 10-Dec-19
Region : XI Target Completion Date : 8-Apr-20
Province : Davao del Sur Date of Completion :
Municipality : Kiblawan Mode of Implementation : By Contract
Barangay : Tacul
D U R A T I O N
Work Breakdown Qty Unit AMOUNT %age Physical %age Acc DECEMBER JANUARY FEBRUARY MARCH
Structure Weight Target Equi W-1 W-2 W-3 W-4 W-5 W-6 W-7 W-8 W-9 W-10 W-11 W-12 W-13 W-14 W-15 W-16
A - DIRECT COST
Plan 0.72% 0.36% 0.36%
I.]SITE WORKS 82.50 Sq.m 11,263.20 0.72%
Actual 0.72% 0.36% 0.36%
Plan 0.82% 0.27% 0.27% 0.27%
II.]EXCAVATION WORKS 29.15 cu.m. 12,768.00 0.82%
Actual 0.82% 0.27% 0.55%
Plan 2.55% 0.64% 0.64% 0.64% 0.64%
III.]BACKFILLING/COMPACTION WORKS 23.76 cu.m. 39,854.40 2.55%
Actual 2.55% 0.64% 0.64% 1.28%
Plan 2.31% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46%
IV.]CARPENTRY WORKS 760.00 bd.ft 43,263.00 2.77%
Actual 2.77% 0.46% 0.46% 1.85%
Plan 3.72% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24%
V.] REINFORCED CONCRETE WORKS 16.76 Cu.m 193,378.20 12.40%
Actual 12.40% 1.24% 1.24% 4.96% 2.48% 2.48%
Plan 2.83% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42%
VI.] MASONRY WORKS 461.73 sq.m. 176,517.60 11.32%
Actual 11.32% 3.40% 4.53% 3.40%
Plan 1.29% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29%
VII.] STEEL WORKS 1125.85 kgs 160,968.00 10.32%
Actual 9.29% 3.10% 5.16% 1.03%
Plan 0.00% 1.45% 1.45% 1.45% 1.45% 1.45% 1.45% 1.45%
VIII.] ROOFING WORKS 148.00 sq.m 158,334.60 10.15%
Actual 9.14% 5.08% 4.06%
Plan 0.00% 0.96% 0.96% 0.96% 0.96% 0.96%
IX. ]CEILING WORKS 134.00 sq.m. 74,573.10 4.78%
Actual 2.39% 1.43% 0.96%
Plan 0.00% 2.52% 2.52% 2.52%
X.] DOORS AND WINDOWS 17.00 sets 117,841.80 7.55%
Actual 3.78% 0.76% 0.76% 2.27%
Plan 1.79% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89%
XI. PAINTING WORKS 394.14 sq.m. 111,457.80 7.14%
Actual 2.14% 0.59% 1.55%
Plan 0.00% 0.68% 0.68% 0.68% 0.68% 0.68%
XII ELECTRICAL WORKS 1.00 lot 52,742.10 3.38%
Actual 0.00%
Plan 0.00% 1.70% 1.70% 1.70% 1.70%
XIII PLUMBING WORKS 1.00 lot 105,792.00 6.78%
Actual 3.39% 0.68% 2.03% 0.68%
Plan 0.00% 1.82% 1.82% 1.82% 1.82%
XIV.] TILE WORKS 93.39 sq.m 113,224.80 7.26%
Actual 0.00%
Plan 0.00% 2.24% 2.24%
XV.]. BASIC AMENITIES 1.00 lot 69,825.00 4.48%
Actual 0.00%
Plan 2.83% 0.94% 0.94% 0.94%
XVI.]. SPECIAL ITEMS 1.00 lot 44,096.40 2.83%
Actual 1.89% 0.94% 0.94%
Plan 3.96% 0.79% 0.79% 0.79% 0.79% 0.79% 0.79%
XVII.]. MATERIAL HAULING 1.00 lot 74,100.00 4.75%
Actual 4.75% 0.79% 2.38% 1.58%
Plan 22.81%
COLUMN TOTAL….. 1,560,000.00 100.00%
Actual 67.34%
PLAN WEEKLY %AGE ACCOMPLISHMENT 2.10% 2.37% 1.22% 0.91% 2.78% 2.78% 2.34% 3.12% 5.20% 6.65% 8.94% 12.13% 13.95% 13.95% 11.97% 9.60%
COMM WEEKLY %AGE ACCOMPLISHMENT 2.10% 4.46% 5.68% 6.59% 9.37% 12.16% 14.50% 17.61% 22.81% 29.46% 38.40% 50.53% 64.48% 78.42% 90.40% 100.00%
ACT WEEKLY %AGE ACCOMPLISHMENT 2.10% 2.97% 2.89% 11.48% 10.10% 15.70% 3.90% 9.62% 8.59%
COMM ACT WEEKLY %AGE ACCOMPLISHMENT 2.10% 5.07% 7.95% 19.43% 29.54% 45.23% 49.13% 58.75% 67.34%
PHYSICAL
WEEKLY %AGE VARIANCE 0.00% 0.60% 1.67% 10.57% 7.32% 12.92% 1.56% 6.50% 3.39%
COMM WEEKLY %AGE VARIANCE 0.00% 0.60% 2.27% 12.84% 20.16% 33.08% 34.64% 41.14% 44.53%
Prepared by: Checked by: Reviewed by: Approved by: Noted By:
FULONG GEORGIN E. DIANGA
MERLINA M. PANDOY ROMULO M. EDO LORD WARREN S. ORBUDA, CE CSPMC Chairperson AILLYN M. ARROBIO, CE, LPT
Head, Project Preparation Team Infrastructure Chairperson Engineer III IP Leader / Representative RCIS
Concurred by:
MARK BRYAN L. ESTOPA, CE FERNANDO B. PANDOY
Technical Facilitator Brgy. Captain
Barangay Sub-Project Work Schedule & Physical Progress Report
As of February 12, 2020
Total Sub-Project Cost
Name of Sub-Project : Construction of KASFALA Hall : Php 1,560,000.00
Physical Target : 82.50 square meter Date Started : 10-Dec-19
Region : XI Target Completion Date : 8-Apr-20
Province : Davao del Sur Date of Completion :
Municipality : Kiblawan Mode of Implementation : By Contract
Barangay : Tacul
D U R A T I O N
Work Breakdown Qty Unit AMOUNT %age Physical %age Acc DECEMBER JANUARY FEBRUARY MARCH
Structure Weight Target Equi W-1 W-2 W-3 W-4 W-5 W-6 W-7 W-8 W-9 W-10 W-11 W-12 W-13 W-14 W-15 W-16
A - DIRECT COST
Plan 0.72% 0.36% 0.36%
I.]SITE WORKS 82.50 Sq.m 11,263.20 0.72%
Actual 0.72% 0.36% 0.36%
Plan 0.82% 0.27% 0.27% 0.27%
II.]EXCAVATION WORKS 29.15 cu.m. 12,768.00 0.82%
Actual 0.82% 0.27% 0.55%
Plan 2.55% 0.64% 0.64% 0.64% 0.64%
III.]BACKFILLING/COMPACTION WORKS 23.76 cu.m. 39,854.40 2.55%
Actual 2.55% 0.64% 0.64% 1.28%
Plan 2.77% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46%
IV.]CARPENTRY WORKS 760.00 bd.ft 43,263.00 2.77%
Actual 2.77% 0.46% 0.46% 1.85%
Plan 4.96% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24%
V.] REINFORCED CONCRETE WORKS 16.76 Cu.m 193,378.20 12.40%
Actual 12.40% 1.24% 1.24% 4.96% 2.48% 2.48%
Plan 4.25% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42%
VI.] MASONRY WORKS 461.73 sq.m. 176,517.60 11.32%
Actual 11.32% 3.40% 4.53% 3.40%
Plan 2.58% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29%
VII.] STEEL WORKS 1125.85 kgs 160,968.00 10.32%
Actual 10.32% 3.10% 5.16% 1.03% 1.03%
Plan 1.45% 1.45% 1.45% 1.45% 1.45% 1.45% 1.45% 1.45%
VIII.] ROOFING WORKS 148.00 sq.m 158,334.60 10.15%
Actual 10.15% 5.08% 4.06% 1.02%
Plan 0.00% 0.96% 0.96% 0.96% 0.96% 0.96%
IX. ]CEILING WORKS 134.00 sq.m. 74,573.10 4.78%
Actual 4.78% 1.43% 0.96% 2.39%
Plan 0.00% 2.52% 2.52% 2.52%
X.] DOORS AND WINDOWS 17.00 sets 117,841.80 7.55%
Actual 7.55% 0.76% 0.76% 2.27% 3.78%
Plan 1.79% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89%
XI. PAINTING WORKS 394.14 sq.m. 111,457.80 7.14%
Actual 7.14% 0.59% 1.55% 5.00%
Plan 0.00% 0.68% 0.68% 0.68% 0.68% 0.68%
XII ELECTRICAL WORKS 1.00 lot 52,742.10 3.38%
Actual 3.38% 3.38%
Plan 0.00% 1.70% 1.70% 1.70% 1.70%
XIII PLUMBING WORKS 1.00 lot 105,792.00 6.78%
Actual 6.78% 0.68% 2.03% 0.68% 3.39%
Plan 0.00% 1.82% 1.82% 1.82% 1.82%
XIV.] TILE WORKS 93.39 sq.m 113,224.80 7.26%
Actual 7.26% 7.26%
Plan 0.00% 2.24% 2.24%
XV.]. BASIC AMENITIES 1.00 lot 69,825.00 4.48%
Actual 0.00%
Plan 2.83% 0.94% 0.94% 0.94%
XVI.]. SPECIAL ITEMS 1.00 lot 44,096.40 2.83%
Actual 1.89% 0.94% 0.94%
Plan 4.75% 0.79% 0.79% 0.79% 0.79% 0.79% 0.79%
XVII.]. MATERIAL HAULING 1.00 lot 74,100.00 4.75%
Actual 4.75% 0.79% 2.38% 1.58%
Plan 29.46%
COLUMN TOTAL….. 1,560,000.00 100.00%
Actual 94.58%
PLAN WEEKLY %AGE ACCOMPLISHMENT 2.10% 2.37% 1.22% 0.91% 2.78% 2.78% 2.34% 3.12% 5.20% 6.65% 8.94% 12.13% 13.95% 13.95% 11.97% 9.60%
COMM WEEKLY %AGE ACCOMPLISHMENT 2.10% 4.46% 5.68% 6.59% 9.37% 12.16% 14.50% 17.61% 22.81% 29.46% 38.40% 50.53% 64.48% 78.42% 90.40% 100.00%
ACT WEEKLY %AGE ACCOMPLISHMENT 2.10% 2.97% 2.89% 11.48% 10.10% 15.70% 3.90% 9.62% 8.59% 27.24%
COMM ACT WEEKLY %AGE ACCOMPLISHMENT 2.10% 5.07% 7.95% 19.43% 29.54% 45.23% 49.13% 58.75% 67.34% 94.58%
PHYSICAL
WEEKLY %AGE VARIANCE 0.00% 0.60% 1.67% 10.57% 7.32% 12.92% 1.56% 6.50% 3.39% 20.59%
COMM WEEKLY %AGE VARIANCE 0.00% 0.60% 2.27% 12.84% 20.16% 33.08% 34.64% 41.14% 44.53% 65.12%
Prepared by: Checked by: Reviewed by: Approved by: Noted By:
FULONG GEORGIN E. DIANGA
MERLINA M. PANDOY ROMULO M. EDO LORD WARREN S. ORBUDA, CE CSPMC Chairperson AILLYN M. ARROBIO, CE, LPT
Head, Project Preparation Team Infrastructure Chairperson Engineer III IP Leader / Representative RCIS
Concurred by:
MARK BRYAN L. ESTOPA, CE FERNANDO B. PANDOY
Technical Facilitator Brgy. Captain
Barangay Sub-Project Work Schedule & Physical Progress Report
As of February 19, 2020
Total Sub-Project Cost
Name of Sub-Project : Construction of KASFALA Hall : Php 1,560,000.00
Physical Target : 82.50 square meter Date Started : 10-Dec-19
Region : XI Target Completion Date : 8-Apr-20
Province : Davao del Sur Date of Completion : 19-Feb-20
Municipality : Kiblawan Mode of Implementation : By Contract
Barangay : Tacul
D U R A T I O N
Work Breakdown Qty Unit AMOUNT %age Physical %age Acc DECEMBER JANUARY FEBRUARY MARCH
Structure Weight Target Equi W-1 W-2 W-3 W-4 W-5 W-6 W-7 W-8 W-9 W-10 W-11 W-12 W-13 W-14 W-15 W-16
A - DIRECT COST
Plan 0.72% 0.36% 0.36%
I.]SITE WORKS 82.50 Sq.m 11,263.20 0.72%
Actual 0.72% 0.36% 0.36%
Plan 0.82% 0.27% 0.27% 0.27%
II.]EXCAVATION WORKS 29.15 cu.m. 12,768.00 0.82%
Actual 0.82% 0.27% 0.55%
Plan 2.55% 0.64% 0.64% 0.64% 0.64%
III.]BACKFILLING/COMPACTION WORKS 23.76 cu.m. 39,854.40 2.55%
Actual 2.55% 0.64% 0.64% 1.28%
Plan 2.77% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46%
IV.]CARPENTRY WORKS 760.00 bd.ft 43,263.00 2.77%
Actual 2.77% 0.46% 0.46% 1.85%
Plan 6.20% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24% 1.24%
V.] REINFORCED CONCRETE WORKS 16.76 Cu.m 193,378.20 12.40%
Actual 12.40% 1.24% 1.24% 4.96% 2.48% 2.48%
Plan 5.66% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42%
VI.] MASONRY WORKS 461.73 sq.m. 176,517.60 11.32%
Actual 11.32% 3.40% 4.53% 3.40%
Plan 3.87% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29% 1.29%
VII.] STEEL WORKS 1125.85 kgs 160,968.00 10.32%
Actual 10.32% 3.10% 5.16% 1.03% 1.03%
Plan 2.90% 1.45% 1.45% 1.45% 1.45% 1.45% 1.45% 1.45%
VIII.] ROOFING WORKS 148.00 sq.m 158,334.60 10.15%
Actual 10.15% 5.08% 4.06% 1.02%
Plan 0.96% 0.96% 0.96% 0.96% 0.96% 0.96%
IX. ]CEILING WORKS 134.00 sq.m. 74,573.10 4.78%
Actual 4.78% 1.43% 0.96% 2.39%
Plan 0.00% 2.52% 2.52% 2.52%
X.] DOORS AND WINDOWS 17.00 sets 117,841.80 7.55%
Actual 7.55% 0.76% 0.76% 2.27% 3.78%
Plan 2.68% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89% 0.89%
XI. PAINTING WORKS 394.14 sq.m. 111,457.80 7.14%
Actual 7.14% 0.59% 1.55% 5.00%
Plan 0.00% 0.68% 0.68% 0.68% 0.68% 0.68%
XII ELECTRICAL WORKS 1.00 lot 52,742.10 3.38%
Actual 3.38% 3.38%
Plan 1.70% 1.70% 1.70% 1.70% 1.70%
XIII PLUMBING WORKS 1.00 lot 105,792.00 6.78%
Actual 6.78% 0.68% 2.03% 0.68% 3.39%
Plan 0.00% 1.82% 1.82% 1.82% 1.82%
XIV.] TILE WORKS 93.39 sq.m 113,224.80 7.26%
Actual 7.26% 7.26%
Plan 0.00% 2.24% 2.24%
XV.]. BASIC AMENITIES 1.00 lot 69,825.00 4.48%
Actual 4.48% 4.48%
Plan 2.83% 0.94% 0.94% 0.94%
XVI.]. SPECIAL ITEMS 1.00 lot 44,096.40 2.83%
Actual 2.83% 0.94% 0.94% 0.94%
Plan 4.75% 0.79% 0.79% 0.79% 0.79% 0.79% 0.79%
XVII.]. MATERIAL HAULING 1.00 lot 74,100.00 4.75%
Actual 4.75% 0.79% 2.38% 1.58%
Plan 38.40%
COLUMN TOTAL….. 1,560,000.00 100.00%
Actual 100.00%
PLAN WEEKLY %AGE ACCOMPLISHMENT 2.10% 2.37% 1.22% 0.91% 2.78% 2.78% 2.34% 3.12% 5.20% 6.65% 8.94% 12.13% 13.95% 13.95% 11.97% 9.60%
COMM WEEKLY %AGE ACCOMPLISHMENT 2.10% 4.46% 5.68% 6.59% 9.37% 12.16% 14.50% 17.61% 22.81% 29.46% 38.40% 50.53% 64.48% 78.42% 90.40% 100.00%
ACT WEEKLY %AGE ACCOMPLISHMENT 2.10% 2.97% 2.89% 11.48% 10.10% 15.70% 3.90% 9.62% 8.59% 27.24% 5.42%
COMM ACT WEEKLY %AGE ACCOMPLISHMENT 2.10% 5.07% 7.95% 19.43% 29.54% 45.23% 49.13% 58.75% 67.34% 94.58% 100.00%
PHYSICAL
WEEKLY %AGE VARIANCE 0.00% 0.60% 1.67% 10.57% 7.32% 12.92% 1.56% 6.50% 3.39% 20.59% -3.52%
COMM WEEKLY %AGE VARIANCE 0.00% 0.60% 2.27% 12.84% 20.16% 33.08% 34.64% 41.14% 44.53% 65.12% 61.60%
Prepared by: Checked by: Reviewed by: Approved by: Noted By:
FULONG GEORGIN E. DIANGA
MERLINA M. PANDOY ROMULO M. EDO LORD WARREN S. ORBUDA, CE CSPMC Chairperson AILLYN M. ARROBIO, CE, LPT
Head, Project Preparation Team Infrastructure Chairperson Engineer III IP Leader / Representative RCIS
Concurred by:
MARK BRYAN L. ESTOPA, CE FERNANDO B. PANDOY
Technical Facilitator Brgy. Captain
CONSTRUCTION OF KASFALA HALL
Municipality of Kiblawan
Province of Davao del Sur
Barangay Tacul
1) Glass Window
W-1: Bronze Glass Sliding Type Window w/ Analoc frame 1 set 6,000.00 6,000.00 6,000.00
1.60mx1.30m x 5mm thk @ the center & 0.40m x 1.30m fixed window both
sides, complete with sealants & other accessories, including
labor & installation (verify actual)
W-2: Bronze Glass Sliding Type Window w/ Analoc frame 5 sets 4,000.00 20,000.00 20,000.00
1.20mx1.30mx5mmthk , complete with sealants & other
accessories, including labor & installation (verify actual)
W-4: Bronze Glass Sliding Type Window w/ Analoc frame 1 set 3,500.00 3,500.00 3,500.00
1.40mx0.90mx5mmthk , complete with sealants & other
accessories, including labor & installation (verify actual)
W-3: Bronze Glass Awning Type Window w/ Analoc frame 2 sets 2,500.00 5,000.00 5,000.00
0.60mx0.60mx5mmthk , complete with sealants & other
accessories, including labor & installation (verify actual)
W-5: Bronze Glass Fixed Type Window w/ Analoc frame 1 sets 5,500.00 5,500.00 5,500.00
1.80mx1.30mx5mmthk , complete with sealants & other
accessories, including labor & installation (verify actual)
2) Doors:
D-1: Solid Panel Door - 900mm x 2100mmx44mmthk 1 sets 4,500.00 4,500.00 4,500.00
D-1: Solid Panel Door - 400mm x 2100mmx44mmthk 1 sets 3,000.00 3,000.00 3,000.00
D-2: Solid Panel Door - 800mm x 2100mmx44mmthk 3 sets 4,500.00 13,500.00 13,500.00
D-3: PVC Type Door w/ Louver 600mm x 2100mm w/ PVC Door 2 sets 1,500.00 3,000.00 3,000.00
Jambs with complete accessories
Door Jamb, Pre Fabricated 2"x6" (2-legs & 1-header) 6 sets 1,000.00 6,000.00 6,000.00
Door Knob, Rekeyable Cylinder w/ 3-pcs Identical Keys, Stainless 15 sets 800.00 12,000.00 12,000.00
Stainless Steel Loose Pin Hinges 4"x4"x2"x3mmthk, Heavy Duty 12 sets 310.00 3,720.00 3,720.00
Concrete Nails 4" 5 kgs. 110.00 550.00 550.00
Sub-total…..Php 86,270.00 - - - - - - 86,270.00
TPC 1,560,000.00
Difference -