Project: Cambodia Chinese Polytechnic University
Minute of Meeting
Meeting No. : #0013/CCV/CCPU
Date : 12-Dec-19
Time : 9:30am – 10:35am
Place : Name
CCPU Site Office Position Signature Remarks
Purpose : Structure and Finishing
Next Meeting : …
Participants
NHOEK Ren Independent Inspector
MAM EN Sengthai Independent Inspector
DOEM Chhai Site Engineer
KPCC
OCIC
Refer
Ite Target Comment
Previou Discussion Remarks
m Date Target
s
Structural Issues
Mr. NHOEK Ren (MAM):
- Talking about the cracking column
located in basement to be repaired as
soon as possible in order to
OK
investigate and identifying the
1
reason lead to be crack.
- Request for Method Statement for
steel roof`
Mr. EN Sengthai (MAM):
- Proposed the defect column
basement to be repaired as soon
as possible after removing
2 formwork. OK
- Request for information, what the
solution is suitable to rectify the roof
slab (Build with confuse drawing)
Mr. DOEM Chhai (KPCC):
- KPCC planned to repair the 12-Dec-19
basement column (head column
crack) by applying grout for first
step. Through this method, It can be
investigated if the crack developed.
- Informed that the water tank may be
moving to rest on elevator, so It can
3
exactly release load acting on slab
element. As a result the slab do not
need to be rectifying.
- KPCC will try to prepare the method
statement requested by Inspector
(MAM)
- Planned to repair all column
(Strengthening column) which have
formed defect after formwork
removing.
B Architectural Issues
Mr. En sengthai (MAM)
- Request for Method Statement to
insure that all construction stage can
be met the standard quality.
4 - Require the Wire mesh for plastering
work, especially all brick wall was
cut for MEP system should be
applying by this material.
Mr. Doem Chhai (KPCC)
- KPCC will make discussion with
5
and inform later about Method
Statement of finishing work.
- KPCC will respond all and
providing the Wire net for plastering
work where this material need to be
used.