0% found this document useful (0 votes)
250 views7 pages

PROJECT: Construction of The New Link Road Between Shah Gas Field & Mezairaa Area Phase-1 (Packages 1 & 2)

Raja Nafees Majeed conducted a weekly HSE site observation of the Construction of the New Link Road between Shah Gas Field & Mezairaa Area Phase-1 project. Seven potential hazards were observed including electrical hand tools without guards, illegal live wire repairs, unsecured generator earthling system, unsafe work at heights, unprotected excavation work, damaged traffic control equipment, and poor equipment maintenance. Corrective actions were required to address the observed issues and ensure compliance with HSE plans, standards, and regulations.

Uploaded by

saqib
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
250 views7 pages

PROJECT: Construction of The New Link Road Between Shah Gas Field & Mezairaa Area Phase-1 (Packages 1 & 2)

Raja Nafees Majeed conducted a weekly HSE site observation of the Construction of the New Link Road between Shah Gas Field & Mezairaa Area Phase-1 project. Seven potential hazards were observed including electrical hand tools without guards, illegal live wire repairs, unsecured generator earthling system, unsafe work at heights, unprotected excavation work, damaged traffic control equipment, and poor equipment maintenance. Corrective actions were required to address the observed issues and ensure compliance with HSE plans, standards, and regulations.

Uploaded by

saqib
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

PROJECT: Construction of the New Link Road between Shah Gas Field & Mezairaa Area Phase-1

(Packages 1 & 2)
HEALTH, SAFETY AND ENVIRONMENT
Weekly Site Observation Report

HSE Inspection Team: Date of Inspection:-30/06/2021 Time:- 09:15 AM


Raja Nafees Majeed- Altorath HSE Engineer

SN OBSERVATION OBSERVATION PICTURES CLOSE OUT PICTURES


Observation:
Electrical hand-tools without appropriate guards.
Location:
Package-01 (CICPA)
Contractor has breached:
Method Statement:
MST-20 & 21
OSHAD-SF :
ELEMENT-1: Roles, Responsibilities and Self-Regulation
Cop-35.0 : Portable power tools
Approved HSE Plan- Rev 01:
01 5.28 Portable power tools
Musanada HSE Requirements
Musanada Key HSE requirements section-5.11
Musanada SOP:
IMS SOP 8 Hazard and Risk
Legal:
UAE Federal Law No. 08 of 1980, Article-9

HSE DEPARTMENT: CLOSEOUT REPORT SHALL BE FOLLOWED BY APPROVED CORRECTIVE ACTIONS 1

Site Visit Report for Construction of Shah Link Road: Package-1 & 2
PROJECT: Construction of the New Link Road between Shah Gas Field & Mezairaa Area Phase-1
(Packages 1 & 2)
HEALTH, SAFETY AND ENVIRONMENT
Weekly Site Observation Report

SN OBSERVATION OBSERVATION PICTURES CLOSE OUT PICTURES


Observation:
Illegal repairs to live wires
Location:
Package-1 (CICPA)
Contractor has breached:
Method Statement:
MST-20 & 21
OSHAD-SF :
ELEMENT-1: Roles, Responsibilities and Self-Regulation
Cop-40.0 False Work
Cop-15.0 Electrical Safety
02
Approved HSE Plan- Rev 01:
5.28 Portable power tools
Musanada HSE Requirements
Musanada Key HSE requirements section-5.11
Musanada SOP:
IMS SOP 8 Hazard and Risk
Legal:
UAE Federal Law No. 08 of 1980, Article-9

HSE DEPARTMENT: CLOSEOUT REPORT SHALL BE FOLLOWED BY APPROVED CORRECTIVE ACTIONS 2

Site Visit Report for Construction of Shah Link Road: Package-1 & 2
PROJECT: Construction of the New Link Road between Shah Gas Field & Mezairaa Area Phase-1
(Packages 1 & 2)
HEALTH, SAFETY AND ENVIRONMENT
Weekly Site Observation Report

SN OBSERVATION OBSERVATION PICTURES CLOSE OUT PICTURES


Observation:
Unavailability of generator earthling system. Leakage found in
multiple parts of Generator
Location:
Package-01 (CICPA)
Contractor has breached:
Method Statement:
MST-20 & 21
OSHAD-SF :
ELEMENT-1: Roles, Responsibilities and Self-Regulation
03 Cop-35.0 : Portable power tools
Cop-15.0 Electrical Safety
Approved HSE Plan- Rev 01:
5.28 Portable power tools
Musanada HSE Requirements
Musanada Key HSE requirements section-5.11
Musanada SOP:
IMS SOP 8 Hazard and Risk
Legal:
UAE Federal Law No. 08 of 1980, Article-9

HSE DEPARTMENT: CLOSEOUT REPORT SHALL BE FOLLOWED BY APPROVED CORRECTIVE ACTIONS 3

Site Visit Report for Construction of Shah Link Road: Package-1 & 2
PROJECT: Construction of the New Link Road between Shah Gas Field & Mezairaa Area Phase-1
(Packages 1 & 2)
HEALTH, SAFETY AND ENVIRONMENT
Weekly Site Observation Report

SN OBSERVATION OBSERVATION PICTURES CLOSE OUT PICTURES


Observation:
Unsafe Condition unsecure work at height with respect to
original ground level
Location:
UBR-02
Contractor has breached:
Method Statement:
54200-00SIT-ZZ-AJC-CIV-MST-0017
OSHAD-SF :
Cop 23.0 Work at Height
04 Approved HSE Plan- Rev 01:
5.20 Barricading Hazards
Musanada HSE Requirements
Musanada Key HSE requirements section-5.7
Musanada SOP:
IMS SOP 8 Hazard and Risk
Legal:
UAE Federal Law No. 08 of 1980
Ministerial Order 32 section Article-19-1(b)

HSE DEPARTMENT: CLOSEOUT REPORT SHALL BE FOLLOWED BY APPROVED CORRECTIVE ACTIONS 4

Site Visit Report for Construction of Shah Link Road: Package-1 & 2
PROJECT: Construction of the New Link Road between Shah Gas Field & Mezairaa Area Phase-1
(Packages 1 & 2)
HEALTH, SAFETY AND ENVIRONMENT
Weekly Site Observation Report

SN OBSERVATION OBSERVATION PICTURES CLOSE OUT PICTURES


Observation:
Excavation adjacent to under-construction detour to be
protected properly.
Location:
Package-02
Contractor has breached:
Method Statement:
54200-00SIT-ZZ-AJC-CIV-MST-0010
54200-00SIT-ZZ-AJC-CIV-MST-0017
OSHAD-SF :
CoP 29.0 Excavation Work.
05 Cop 33.0 Work adjacent to Live Road
Approved HSE Plan- Rev 01:
5.20 Excavation and Trenchs
Musanada HSE Requirements
Musanada Key HSE requirements section-5.12
Musanada SOP:
IMS SOP 8 Hazard and Risk
Legal:
UAE Federal Law No. 08 of 1980
Ministerial Order 32 section Article-19(1)

HSE DEPARTMENT: CLOSEOUT REPORT SHALL BE FOLLOWED BY APPROVED CORRECTIVE ACTIONS 5

Site Visit Report for Construction of Shah Link Road: Package-1 & 2
PROJECT: Construction of the New Link Road between Shah Gas Field & Mezairaa Area Phase-1
(Packages 1 & 2)
HEALTH, SAFETY AND ENVIRONMENT
Weekly Site Observation Report

SN OBSERVATION OBSERVATION PICTURES CLOSE OUT PICTURES


Observation:
Damaged sand bags to be replaced with new one
Location:
Package-02
Contractor has breached:
Method Statement:
MST-6,7,8 & 13
OSHAD-SF :
CoP 44.0 Traffic Management and Logistics
COP 17.0 Poor Signage Management
6 Approved HSE Plan- Rev 01:
4.5-OSH Risk Management
5.3 Traffic management Plan
Musanada HSE Requirements
Musanada Key HSE requirements section-5.18
Musanada SOP:
IMS SOP 8 Hazard and Risk
Legal:
UAE Federal Law No. 08 of 1980
Ministerial Order 32 section Article-10

HSE DEPARTMENT: CLOSEOUT REPORT SHALL BE FOLLOWED BY APPROVED CORRECTIVE ACTIONS 6

Site Visit Report for Construction of Shah Link Road: Package-1 & 2
PROJECT: Construction of the New Link Road between Shah Gas Field & Mezairaa Area Phase-1
(Packages 1 & 2)
HEALTH, SAFETY AND ENVIRONMENT
Weekly Site Observation Report

SN OBSERVATION OBSERVATION PICTURES CLOSE OUT PICTURES


Observation:
Poor maintenance of Equipment. Curtains to be removed from
operator cabin.
Location:
CH:11+200
Contractor has breached:
Method Statement:
MST-20 & 21
OSHAD-SF :
CoP 36.0 Plant & Equipment
7
Approved HSE Plan- Rev 01:
5.12 Plant and Equipment
Musanada HSE Requirements
Musanada Key HSE requirements section-5.17
Musanada SOP:
IMS SOP 8 Hazard and Risk
Legal:
UAE Federal Law No. 08 of 1980
Ministerial Order no. 32 of 1982 A.D. & section Article-17
Prepared by: Closed by: Accepted By:
Consultant HSE Engineer: Main Contractor HSE Contractor’s PM
Raja Nafees Majeed Delowar Hussain Baha Al Awar

Close-Out Checked by: Closeout approved by:


Consultant HSE Engineer: Resident Engineer
Raja Nafees Majeed Muhammad Ibrahim Soomro

HSE DEPARTMENT: CLOSEOUT REPORT SHALL BE FOLLOWED BY APPROVED CORRECTIVE ACTIONS 7

Site Visit Report for Construction of Shah Link Road: Package-1 & 2

You might also like