HSE Observation Report
Date: 7-12-2022
Potential
Location Action required /
S.no Issues Photograph Risk Rectification Close Out Photo
Recommendations
Level
Found operative was Life
Contractor need to Critical
standing on the A-
Basement- frame ladder without conduct awareness One
1
2 training to the workers working
support (repeated by day
regarding Ladder Safety
Meras operatives)
Contractor need to
Operative was found provide a safe & proper Life
working unsafe working platform and Critical
2 Basement- while performing the conduct awareness
One
1 working
job, potential risk of training to the workforce day
fall from height regarding safe working
platform
HSE Observation Report
Potential
Location Action required /
S.no Issues Photograph Risk Rectification Close Out Photo
Recommendations
Level
Observed that duct
Contractor need to use Non-Life
tape was used to tie
Proper fittings (Clamps) Critical
the ladder of
instead of ropes/ tape , 1>3
3 Basement- Scaffold, Green tag must be checked and working
2 in place, evidence day
supervise by competed
that no inspection
scaffold inspector
conducted
Contractor ensure that Non-Life
Observed that all operatives using Critical
4 Basement- damaged disc was power tools are trained 1>3
2 using for cutting by & competent, damaged working
Meras operative disc must remove and day
strictly not to use on site
HSE Observation Report
Potential
Location Action required /
S.no Issues Photograph Risk Rectification Close Out Photo
Recommendations
Level
Contractor need to
ensure that all power Non-Life
Damaged cable tools must be inspected Critical
Basement- cables using on the 1>3
5 prior to use. All working
2 site for power tools damaged electrical cable day
must be repaired and
fixed properly
Non-Life
Contractor need to Critical
Skid loader was
Basement- found on site with ensure that all plant & 1>3
6 working
1 equipment must have
defective head light day
operational head light
HSE Observation Report
Potential
Location Action required /
S.no Issues Photograph Risk Rectification Close Out Photo
Recommendations
Level
Operatives were Non-Life
Contractor must instruct
found using Critical
their operatives do not
Ground pedestrian stair 1>3
7 use pedestrian access for
Floor access for working
material shifting, and day
transferring the
provide signage’s
material
Contractor need to Non-Life
Operative was found ensure that all operatives Critical
8 Basement- using damaged PPE working at site must 1>3
2 ( gloves) while provide proper / good working
performing the job conditioned PPE , day
replace the damaged
HSE Observation Report
Potential
Location Action required /
S.no Issues Photograph Risk Rectification Close Out Photo
Recommendations
Level
Contractor need to
replace the damaged Non-Life
Poor illumination Critical
bulb, ensure that toilets
Ground was observed at 1>3
9 are well illuminated,
Floor office toilets due working
Inspection must be day
failure of bulb
conducted in regular
basis.
Contractor need to
advise their sub
Poor housekeeping contractor remove the Non-Life
was observed at waste from site on Critical
1>3
10 Basement- several places, regular basis, and working
1 evidence of Poor maintain a good day
Housekeeping housekeeping at all
over the building
premises
Prepared by:
Mohammed Vajid Ali
HSE Observation Report
Life Critical Major failure e.g. fatality, LTI, major injury, or Immediate> 1 Working day (if not temporary suspended)
dangerous occurrence
Non-Life Critical Potential Minor injury Incident, Environmental or 1 > 3 working day
Welfare Issue.
Good Practice N/A None however look to share good practice