SAFETY OBSERVATION REPORT
Date: 27-02-2020
Observer: HSE TEAM
PROJECT : Science Museum
Action taken/ Responsi Statu
Sr. Observation Photo Before Risk Photo After
Recommendation bility s
1 Unprotected Opening Floor opening (hole) should Construc High
be Covered using single and tion
strong piece of plywood, For
additional support and firm
position, cover was nailed
properly from all four side.
2 COSHH: Ensure that all liquid Construc Medium
It was observed that drinking chemicals are stored in tion
water bottle used to decant proper container with
chemicals without any identification or label.
identification or label. It could
be easily mistaken as water
and consumed accidentally
by other workers.
3 Construc High
Welfare Facilities (Toilet): Check the leakage and tion
It was observed that the proper maintenance are
wastewater pipe of the toilet required and clean the area,
was leaking located at parcel also advised to cleaner to
A-02 1st level maintain the welfare facilities
in Good Condition.
SAFETY OBSERVATION REPORT
Date: 27-02-2020
Observer: HSE TEAM
PROJECT : Science Museum
4 Power Tools: All the power tools are Construc High
Sub con for tile work(Noor al inspected by the competent tion
hawa) using power tool person prior to use .
without inspection and color
coding.
5 COSHH: All the chemicals are stored Construc Medium
It was observed that chemical in the chemical storage area, tion
are placed on the ground a bundling system should be
without secondary protection applied to minimize the
or misused by the any one. environmental hazards
6 Flammable material: Construc Low
Hessian cloth are store in an Store all the flammable tion
improper place , open material in a proper storage
environment in dry condition. area, in wet condition.
SAFETY OBSERVATION REPORT
Date: 27-02-2020
Observer: HSE TEAM
PROJECT : Science Museum
7 Access / Agrees Construc High
Observed that their is no Scaffolding access should tion
be provided for the operator
access for operator of the
Tower Crane 3.
8 Medium
9 Medium
SAFETY OBSERVATION REPORT
Date: 27-02-2020
Observer: HSE TEAM
PROJECT : Science Museum
10 Medium
Reviewed By: Syed Mazhar Signature:-------------------------
Reported To: Samy Mansour Signature:-------------------------