Certificate of Payment No - 01: Woba Ari Woreda Finance Office
Certificate of Payment No - 01: Woba Ari Woreda Finance Office
CERTIFICATE OF PAYMENT No - 01
Project: Woba Ari Woreda Revenue Office Building
Location: Woba Ari Woreda Main Contract #REF!
Employer: Woba Ari Woreda Finance Office
Consultant: SOZ Urban Development & Construction Department Supplementry Cont.
Contractor: Hassen Abate General Contractor Varation Order
Total #REF!
15% VAT #REF!
Amount (Birr)
The value of work executed to date is Birr #REF!
Material on site -
The value of work executed and material on site is Birr #REF!
No. NetPayment
No Date Amount (Birr) VAT DEDUCTION AMOUNT (BIRR) `
Advance 1 #REF! #REF!
1. Total Previous Payment -
2. Rebate 0%
3. Retention 5% #REF!
4. Penalty
BIRR 1,240,988.61 //One Million Two Hundred Fourty Thousand Nine Hundred Eighty Eight & 61%// ONLY
SIGNITURE SIGNITURE
DATE DATE
}^ ÉU` uŸòM ÉU` uŸòM
lØ` SÓKÝ Sub Total (Birr) Total ( Birr )
Item Description ¾¨<Kታ ¾}W^ ¾¨<K
No Contract Excuted Contract
A. Sub Structure
1.0 Excavation & Earth work 4,407.80
2.0 Masonry Work 9,699.00
3.0 Concrete Work 75,422.20
Sub Total -
B. Super Structure
1.0 Concrete Work 21,482.90
2.0 Wall Work 93,904.00
3.0 Roofing & Carpentry & Joinery 46,672.00
5.0 Metal Work 16,300.00
6.0 Finishing Work 14,624.00
Sub Total -
Total (A + B) -
vat
total -
ÉU` uŸòM
Total ( Birr )
¾}W^
Excuted
89,529.00
192,982.90
282,511.90
42,376.79
324,888.69
Project: Woba Ari Revenue Office BOQ
Contractor: Hassen Abate General Contractor
Item Description Unit
የተሰራ Executed
A Sub-Structure Rate Sub-Total Total
1.0 1. Excavation and Earth Work
Clear off top vegetable soil, bushes and small trees to an
1.10 average depth of 20cm. m2 96.00 10.00 960.00
Three Coat Synthetic Paint to Thinner 0.050 Litre 0.00 Litre 0.00
Metal
Glass 1.100 m2 0.00 m2 0.00
4mm Thick Clear Glass Putty 0.400 kg 0.00 kg 0.00
Take Off Sheet Main Block
Project:- Revenue Office / MAIN BLOCK
Location:- Woba Ari Woreda Boyka Kebele
Contractor:- Hassen Abate General Contractor
Sign._____________
Take Off Sheet Main Block
Project:- Revenue Office / MAIN BLOCK
Location:- Woba Ari Woreda Boyka Kebele
Contractor:- Hassen Abate General Contractor
Sign._____________
Take Off Sheet Main Block
Project:- Revenue Office / MAIN BLOCK
Location:- Woba Ari Woreda Boyka Kebele
Contractor:- Hassen Abate General Contractor
Sign._____________
Take Off Sheet Main Block
Project:- Revenue Office / MAIN BLOCK
Location:- Woba Ari Woreda Boyka Kebele
Contractor:- Hassen Abate General Contractor
Sign._____________
Sheet No 13
Sub Structure
GFB1 --- --- --- --- --- --- --- ---
Top 14 3 2 24.80 --- --- --- --- 148.8 --- --- ---
Bottom 14 3 2 24.80 --- --- --- --- 148.8 --- --- ---
Stirrups 8 3 124 1.30 --- 483.60 --- --- --- --- --- ---
GFB-2 --- --- --- --- --- --- --- ---
Top 14 6 2 10.22 --- --- --- --- 122.64 --- --- ---
Bottom 14 6 2 10.22 --- --- --- --- 122.64 --- --- ---
Stirrups 8 6 52 1.30 --- 405.60 --- --- --- --- --- ---
GFB -3 --- --- --- --- --- --- --- ---
Top 14 4 2 16.22 --- --- --- --- 129.76 --- --- ---
Bottom 14 4 2 16.22 --- --- --- --- 129.76 --- --- ---
Stirrups 8 4 82 1.30 --- 426.40 --- --- --- --- --- ---
Floor Mesh --- --- --- --- --- --- --- ---
8 1 28 23.00 --- 644.00 --- --- --- --- --- ---
8 1 43 14.00 --- 602.00 --- --- --- --- --- ---
8 1 91 15.00 --- 1365.00 --- --- --- --- --- ---
. Total Length 0.00 3926.60 0.00 0.00 802.40 0.00 0.00 0.00
Kg/Meter 0.222 0.395 0.617 0.888 1.209 1.579 2.466 3.552
Weight in kg 0.00 1549.57 0.00 0.00 969.76 0.00 0.00 0.00
Sign.,______________
Sheet No 14
Super Structure --- --- --- --- --- --- --- ---
Column --- --- --- --- --- --- --- ---
14 33 4 3.65 --- --- --- --- 481.80 --- --- ---
8 33 15.0 1.30 --- 643.50 --- --- --- --- --- ---
12 10 4 2.50 --- --- --- 100.00 ---
8 10 4.0 1.30 --- 52.00
TTB1 --- --- --- --- --- --- --- ---
Top 14 4 2 24.80 --- --- --- 198.4 --- --- ---
Bottom 14 4 2 24.80 --- --- --- 198.4 --- --- ---
Stirrups 8 4 124 1.30 644.80 --- --- --- --- --- ---
TTB-2 --- --- --- --- --- --- --- ---
Top 14 8 2 10.22 --- --- --- --- 163.52 --- --- ---
Bottom 14 8 2 10.22 --- --- --- --- 163.52 --- --- ---
Stirrups 8 8 52 1.30 --- 540.80 --- --- --- --- --- ---
TTB -3 --- --- --- --- --- --- --- ---
Top 14 4 2 16.22 --- --- --- --- 129.76 --- --- ---
Bottom 14 4 2 16.22 --- --- --- --- 129.76 --- --- ---
Stirrups 8 4 82 1.30 --- 426.40 --- --- --- --- --- ---
Total Length 0.00 2307.50 0.00 100.00 1465.16 0.00 0.00 0.00
Kg/Meter 0.222 0.395 0.617 0.888 1.209 1.579 2.466 3.552
Weight in kg 0.00 911.46 0.00 88.80 1771.38 0.00 0.00 0.00
Sign.,______________
¾Åu<w wN?a‹ wN?[cx‹“ Q´x‹ ¡ML© S”Óeƒ South Nation, Nationalities & Peoples' Regional State
ዲዛይንና ግንባታ ቁጥጥር ባለስልጣን ቢሮ Construction Bureau
¾Ñî lØ`
K}W\ Y^‹ TÖnKÁ Page No.----------------------
Summary of Measurement ¾¨<M lØ`
Y^¨< Contract No :
Project:- Human Health Post
ቦታው
Place: ማሌ ወረዳ ኬላ ቀበሌ
አሰሪው መ/ቤት
Employer:- ማሌ ወረዳ የአ/አ/ ጉዳዮች ጽ/ቤት (ፒሲዲፒ)
|‰ t̉Œ
Contractor: በርታ የግንባታ ማህበር
›T"] SG”Ç=e
Consultant: - SNNPRG CDWP
¾}W^¨< Y^“ / ¨ÃU ¾k[u< n‹ ´`´`
Details of works executed and / Materials supplied
}^ ÉU` uŸòM ÉU` uŸòM
lØ` SÓKÝ Sub Total (Birr) Total ( Birr )
Item Description ¾¨<Kታ ¾}W^ ¾¨<K ¾}W^
No Contract Excuted Contract Excuted
A. Sub Structure
1.0 Excavation & Earth work 5,175.00 6,101.54
2.0 Masonry Work 11,400.00 11,095.20
3.0 Concrete Work 4,040.00 4,610.89
Sub Total 20,615.00 21,807.63
B. Super Structure
1.0 Concrete Work 5,585.00 4,893.25
2.0 Wall Work 1,760.00 1,807.80
3.0 Roofing 2,100.00 1,531.25
4.0 Carpentry & Joinery 380.00 468.00
5.0 Metal Work 300.00 300.00
6.0 Finishing Work 3,350.00 3,151.60
7.0 Painting Work 495.00 638.40
እኔ/እኛ ---------------------------------ከዚህ በላይ የተዘረዘረው ሂሣብ ትክክል መሆኑን በዚሁም መሠረት እስከ ዛሬ ድረስ የተሠራው ሥራና ወደ
ቦታው የቀረበ ዕቃ ጠቅላላ ዋጋ ብር--------------------------መሆኑን እናረጋግጣለን፡፡
I/We----------------------hereby certify that the above figures are correct and that the total
Value of work executed and/or materials delivered on site to date Birr .
-----------------------------------------------------------------------------------------------------------------------------------------------
ሥራ ተቋራጭ አማካሪ መሃንዲስ የሥራ ተቆጣጣሪ/ኢንስፔክተር
Contractor Consultant Supervisor/Inspector
Item Description Unit Qty Rate Total Sub Total
A. Sub Structure
1.03 Ditto but in hard/rocky soil formation to a depth not exceeding m3 23.00 5.00 115.00
4500mm
1.04 Back fill under hard core & sides of masonry with good, dry filling m3 17.00 5.00 85.00
from site and wet compact in layer not > 20cm.
1.05 Cart away surplus excavated material from site and deposit as m3 60.00 10.00 600.00
ordered.
1.06 25cm thick basaltic or equivalent stone hard core well consolidated & m2 5.00 5.00 25.00
blindded with crushed stone.
Total Carried to Summary 1,320.00
2. Masonry Work
2.01 40cm thick at top and 80cm thick at bottom retaining stone masonry m3 36.00 80.00 2,880.00
wall inside the pit bedded in cement mortar
2.02 Ditto but 40cm thick above NGL m3 2.00 80.00 160.00
Total Carried to Summary 3,040.00
3. Concrete Work
3.01 5cm thick class C-5 concrete under masonry foundation m2 10.00 60.00 600.00
3.02 Class C-25 reinforced concret foundation beam as shown on the m 3
1.00 120.00 120.00
drawing
3.03 Class C-25 reinforced concret 100mm thick ground slab m2 5.00 80.00 400.00
3.07 Provide cut & fix in position sawn zigba wood or steel formwork -
whichever appropriate
a) For floor slab, and sides of foundation beam m2 11.00 50.00 550.00
3.08 Mild steel reinforcement according to structural drawings. Price shall -
include cutting,bending, placing in position and tying wire.
B Super Structure
4. Concrete Work
4.01 C-20 reinforced concrete, minimum cement content of 320kg/m3 -
filled in to form work & vibrated around mild steel. Steel &
formwork measured separately
6.02 25cm wide Keraro fascia board. Price includes one coat of primer & Ml 14.00 20.00 280.00
two coats of oil paint.
Total Carried to Summary 840.00
Item Description Unit Qty Rate Total Sub Total
7.02 Supply & fix 50*70mm zigba wood purlins as per the detail drawing. Ml 7.00 15.00 105.00
Price shall include anti termite treatment and all the other necessary
accessories.
7.03 Suuply and fix chicken wire mesh with frames and on gable side for m2 1.00 20.00 20.00
ventillation
9.02 Apply pointing to external HCB wall & exposed masonry wall with m2 20.00 30.00 600.00
cement sand mortar (1:3)
9.03 50mm thick broom finish cement sand screed (1:3) floor finish. All m2 5.00 10.00 50.00
as per supervisors instruction. Price shall include cement sand screed
skirting in 10cm height.
9.04 100cm wide semi dressed stone pavement around the bldg bedded in m2 15.00 7.00 105.00
cement sand mortar (1:3). Unit price includes excavation for laying
and 100mm thick red ash bedding & pointing to drssed stone
pavement.
9.05 Supply and fix dia. 100mm PVC vent pipe with insect trap at the top ML 6.00 20.00 120.00
¾Ñî lØ`
K}W\ Y^‹ TÖnKÁ Page No.----------------------
Summary of Measurement ¾¨<M lØ`
Y^¨< Contract No :
Project:- Human Health Post
ቦታው
Place: ማሌ ወረዳ ኬላ ቀበሌ
አሰሪው መ/ቤት
Employer:- ማሌ ወረዳ የአ/አ/ ጉዳዮች ጽ/ቤት (ፒሲዲፒ)
|‰ t̉Œ
Contractor: በርታ የግንባታ ማህበር
›T"] SG”Ç=e
Consultant: - SNNPRG CDWP
¾}W^¨< Y^“ / ¨ÃU ¾k[u< n‹ ´`´`
Details of works executed and / Materials supplied
}^ ÉU` uŸòM ÉU` uŸòM
lØ` SÓKÝ Sub Total (Birr) Total ( Birr )
Item Description ¾¨<Kታ ¾}W^ ¾¨<K ¾}W^
No Contract Excuted Contract Excuted
A. Sub Structure
1.0 Excavation & Earth work 1,515.00 1,515.00
2.0 Concrete Work 3,202.50 3,202.50
3.0 Masonry Work 3,025.00 3,025.00
5.0 Metal Work 1,200.00 1,200.00
6.0 Finishing Work 640.00 640.00
እኔ/እኛ ---------------------------------ከዚህ በላይ የተዘረዘረው ሂሣብ ትክክል መሆኑን በዚሁም መሠረት እስከ ዛሬ ድረስ የተሠራው ሥራና ወደ
ቦታው የቀረበ ዕቃ ጠቅላላ ዋጋ ብር--------------------------መሆኑን እናረጋግጣለን፡፡
I/We----------------------hereby certify that the above figures are correct and that the total
Value of work executed and/or materials delivered on site to date Birr .
-----------------------------------------------------------------------------------------------------------------------------------------------
ሥራ ተቋራጭ አማካሪ መሃንዲስ የሥራ ተቆጣጣሪ/ኢንስፔክተር
Contractor Consultant Supervisor/Inspector
½¬ú>ú a _____________ የክፍያ ምስክር ወረቀት ቁጥር yg{ q$_R______
Contract No Certificate of Measurment No. Page No
ቁጥር
Item
No መ ግ ለ ጫ DESCRIPTION UNIT Quantity
Unit
Contract Executd Price Sub-Total Total birr
A SUB STRUCTURE
1. SUPER STRUCTURE
Site clearing to remove top vegetable soil to an
1.01 average depth of 200mm. m2 21.00 21.00 5.00 105.00
Bulk excavation in ordinary soil to a depth not
1.02 exceeding 1500mm m3 3.00 3.00 30.00 90.00
Trench excavation for dtone masonry
1.03 foundation wall and beam under masonry m2 2.50 2.50 30.00 75.00