ID   Task Name                                                  Resource Names                         Duration
1    Project:- Pedestrian walkway infornt of meden
                                                                Habtamu (Proj. Mang.),Nebiyu (site     40 days
     insurance from existing pedesrtian walk way to 20          Eng.),Mekdes (Surveyor),Caltu
     meter to the south                                         (Admin.),Meseret (Act.),Sintayehu
                                                                (Forman)
2      1. GREENERY AND TERRAZZO                                                                         34 days
3        1. Excavation and EarthWork                                                                    34 days
4          1.1 Site Clearing or/ Remove trees, Existing           Daily laborer[1,000%] Daily              1 day
           fence and other obstacles
5          1.2 Bulk Excavation in ordinary soil to a depth of     laborer[1,000%]                          1 day
           30cm from stripped top soil
6          1.3 Demolishing Existing Fence, tree, roots hush Daily laborer[1,000%] big                      1 day
           stone and any obstacle existing on the site as
7          1.4 Cartaway the excavted surplus material to a        Daily laborer[1,000%],Truckc             1 day
           distance of 5km away                                   Driver[200%]
8          1.5 Backfill fine selected materials and compacted     Truckc Driver[200%],Daily                1 day
           by roller machine well in layer not                    laborer[1,000%]
9          1.6 Back fill with fertile soil to make greenery area, Daily laborer[1,000%],Truckc             1 day
           plant locally known grass bed on top of best soil as   Driver[200%]
           per given detail on drawing. The selected soil, could
           be from a borrow pit or from
10         1.7 Planting "Duranta" tree from OGL 30cm             Daily laborer[500%],Carpenter             1 day
           height must be 30cm c/c with random
11         1.8 Planting "Picas from OGL 50-60cm height"          Daily laborer[1,000%],Carpenter           1 day
           must be must be 50cm c/c with random
12         1.9 Planting "Arucaria Jerusalem tree from OGL 80- Daily laborer[1,000%],Carpenter              1 day
           100cm height" must be 10m c/c with random
13         1.10 Planting "Cyprus tree from OGL 50-60cm height" Daily laborer[1,000%],Carpenter             1 day
           must be 10m c/c with random exchanging
14         1.11 Planting "Tuna tsidi tree from OGL 50-60cm Daily laborer[1,000%],Carpenter                 1 day
           height"must be 500cm c/c with random
15         1.12 Planting Bottle brush flower of dia 50cm and Daily laborer[1,000%],Carpenter from          1 day
           OGL 80<m height at every corner position
16         1.13 Planting "Grass"                                               concrete, filled into   Daily
                                                                               formwork and            laborer[1,
17         1.14 Apply 15cm thick basaltic stone or                             vibrated                000%],Car
           equivalent hardcore well rolled consolidated                                                penter
           blinded with hand crushed stone
18       2. CONCRETE WORK                                                                              Daily
                                                                                                       laborer[52
19         2.1 Mass Concrete, Class C-25 360Kg/m3 of                                                   0%],Maso
n[130%],Ass. Mason[260%]      1 day
                              1 day
                              21.5
                              days
                           19.5 days
ID   Task Name                                                   Resource Names                       Duration
20           2.1.a. Curb mass Concrete                           Mason[300%],Daily                        1 day
                                                                 laborer[1,800%],Mixer
                                                                 Operator,Vibrator Operator
21           2.1.b. For RHS post of fence, shade and
                                                                 Daily laborer[1,200%],Mixer          13.5 days
             bench Pad, electric pole                            Operator[200%],Vibrator
                                                                 Operator[200%],Mason[200%]
22               2.1.b.1 For RHS post of fence                                                           2 days
23               2.1.b.2 For RHS post of shade and bench Pad                                              1 day
24               2.1.b.3 For RHS post of electric pole
                                                                                                       0.5 days
25         2.2 Provide 10cm mass concrete c-25 with
           cement content of 360Kg/m3 filled over hard           Mason[200%],Daily                        1 day
           core for Terrazzo side walkway                        laborer[1,200%],Mixer
                                                                 Operator[200%],Vibrator
           2.3 Providing Fromwork                                Operator[200%]
26
                                                                                                       21 days
27           2.3.a. to Curb mass Concrete
                                                                 Carpenter,Ass. Carpenter,Daily          2 days
             2.3.b. For RHS post of fence, shade and             laborer[400%]
28
             bench Pad, electric pole                            Ass. Carpenter,Daily                  15 days
29             2.3.b.1 For RHS post of fence                     laborer[400%],Carpenter
                                                                                                         2 days
30               2.3.b.2 For RHS post of shade and bench Pad
31               2.3.b.3 For RHS post of electric pole                                                    1 day
32       3. Flooring Work                                                                              0.5 days
33         3.1 Fiber Glass bottle of dia 50-60cm and height of                                         3 days
           50-60cm
           3.2 Apply 5cm thick Terazzo tile using cement         Daily   laborer[600%],Tailer[300%]    0.5 days
34
           screed or mortar on every pedestrian passage
                                                                 Tailer[300%],Daily   laborer[600%]      2 days
35         3.3 Apply River stone on every outer part curb
           stone of that located internal greenery by            Tailer[300%],Daily laborer[600%]
36       4. STEEL WORK                                                                                    1 day
37         Supply and erect metal grill for protection of                                             11 days
           greener part of as shown on the given
                                                                                                       11 days
           drawing. Price shall include Applying two
           coats of antirust paint and super paint with
           its purpose .
38           FOR FENCE
                                                                                                         8 days
ID   Task Name                                                 Resource Names                             Duration
39            4.1 Posting SHS dia. 40*40*2.5mm with height of Ass. Welder[400%],Daily                       2 days
              1.25m fence work                                laborer[600%],Welder[200%]
40            4.2 Welding SHS Vertical section of             Daily                                         3 days
              30*30*1.5mm with height of 60cm between top laborer[600%],Welder[200%],Ass.
              and horizontal member of the fence.             Welder[400%]
41            4.3 Welding SHS horizontal section of           Daily                                         2 days
              40*40*2.5mm at the top and bottom of the fence. laborer[600%],Welder[200%],Ass.
                                                              Welder[400%]
42            4.4 Circular metal copper and use sharp (spear) Ass. Welder[200%],Daily                        1 day
              metal on the top For SHS post                   laborer[400%],Welder
43           FOR DUST PARTICLE STORAGE                                                                      3 days
44             4.6 Welding SHS Vertical section of             Welder[200%],Ass.                             1 day
               30*30*1.5mm with height of 1.30m at             Welder[400%],Daily laborer[600%]
45             4.7 Welding SHS horizontal section of           Welder,Ass. Welder[200%],Daily                1 day
               30*30*1.5mm at the top and bottom ceircular     laborer[400%]
46             4.8 Circular Metal sheet (lamera) for water     Daily laborer[400%],Welder,Ass.               1 day
               Storage                                         Welder[200%]
47       5. Electrical Work                                                                               28 days
48         5.1 60*60*80cm MAN HOLE with cover                  Daily laborer[400%],Mason,barbender,Carp      1 day
                                                               Electrician,Daily laborer[700%] Daily  e
49         5.2 Octagonal light pole of dia 120mm at base and                                              0.5 days
           dia. 60mm at top length 3000mm above                laborer,Electrician
50         5.3 POWER CABLES 0.6/1KV,3x2.5nsq.mm for                                                          1 day
           electrical 1.3m pole and 0m greenery light          Daily laborer,Electrician
51         5.4 HPK 100*1*HPE,250W with lamp reflector                                                        1 day
           and accessories
52       6. Bench and Shed                                                                                 6 days
                                                               Welder[200%],Ass.
53         6.1 RHS dia. 60*60*2.5mm thick vertical for leg     Welder[400%],Daily laborer[600%]              1 day
           post of bench as per drawing.                       Welder[200%],Ass.
54         6.2 RHS dia. 60*40*2.5mm thick vertical and         Welder[400%],Daily laborer[600%]              1 day
           horizontal member as per drawing.                   Welder,Ass. Welder[200%],Daily
55         6.3 SHS dia. 60*60*2.5mm thick vertical and         laborer[400%],Carpenter,Ass.                  1 day
           horizontal of shed as per drawing.                  Carpenter
                                                               Daily laborer[400%],Carpenter,Ass.
56         6.4 Timber pinus 10*4cm thick pinus purlin for      Carpenter                                     1 day
           horizontal member of bench as per drawing           Daily laborer[400%],Carpenter,Ass.
57         6.5 Timber pinus 10*5cm thick pinus purlin for      Carpenter                                     1 day
           horizontal member of shed as per drawing            Daily laborer[400%],Carpenter,Ass.
58         6.6 Timber pinus 5*4cm thick pinus purlin for       Carpenter                                     1 day
           vertical horizontal member of bench as per
ID   Task Name                                                       Resource Names                            Duration
59       7. Roofing                                                                                              1 day
60         7.1 Translucent polycarbonate sheet bullan, bushan,   Daily laborer[400%],Carpenter,Ass.               1 day
           roofing fixed to 10x5cm pinus purlin and truss nailed Carpenter
           by doom headed nail and plastec
61       8. Sanitary Works                                                                                       1 day
62         8.1 Supply, lay and fix polypropelene pipe (PPR)          Daily laborer[200%],Plumber                  1 day
           32mm dia and gate valve, phoset use all
63     2. DITCH COVER                                                                                          40 days
64       1- CLEARING WORK                                                                                       2 days
65         1.1 Clearing Drain floor to the right and Left and        Daily laborer[1,000%],Chiesler[300%]         1 day
           closing concrete sewerage pipe
66         1.2 Cartaway the solid or liquid waste from site.         Daily laborer[1,000%]                        1 day
67       2. REINFORCED CONCRETE WORK                                                                            7 days
68         2.1 Reinforced concrete in class C-25                                                                 2 days
69           2.1.a Pre-cast or in-situ ditch slab cover with steel   Mason[200%],Daily laborer[1,200%],Mixer     2 days
             handling fixed in mold                                  Operator[200%],Vibrator Operator[200%]
70         2.2 Form work                                                                                         2 days
71           2.2.a Under and sides of ditch slab cover               Carpenter,Ass. Carpenter,Daily              2 days
                                                                     laborer[400%]
72         2.3 RINFORCEMENT WORK                                                                                 2 days
73           2.3.a Diameter 10mm, deformed bar                       Daily laborer[200%],barbender[200%]         2 days
74       3. FINISHING WORK                                                                                      9 days
75         3.1 Apply three coats of plaster in cement mortar for     Plasterer[200%],Daily laborer[400%]          1 day
           top and outside for curb mass concrete
76         3.2 apply three coats of approved make weather            Painter[200%],Daily laborer[200%]            1 day
           resistant plastic zebra paint to edge external
77       4. TERAZZO TILE                                                                                         1 day
78         4.1 20x20x5cm terrazzo tile or othre interlock shape Daily laborer[600%],Tailer[300%]                  1 day
           terazzo as soon you cast at the same time