FM-038
Construction Start-up Checklist
Project:            Project Number and Title Here
Date:               Date Here
Prior to the on-site commencement of all Building Works Contracts the following Start-Up Checklist should be a
guide for Contract Supervisor’s (UniSA PM) in the project induction of Contractors:
      Construction Start-up meeting: Contractor to minute meeting. The Start-Up Checklist must
               be signed off by all attendees at meeting and attached to minutes for distribution.
      Contractor’s Induction:
               Contract Supervisor (UniSA Project Manager) to ensure that the successful Contractor has
               completed the UniSA Contractor’s Induction program and direct Contractor to the following
               documents on UniSA website:
                UniSA Contractor’s Induction
                    Contractors’ Induction.pdf
               (Note: On completion of the Contractor Induction, Contractor and sub-contractors are able to print the UniSA
               Induction Reference (located on last page) to be shown to FM-Assist to issue contractor Id).
                UniSA Contractors Induction Manual:
                    Contractors Induction Manual.pdf
      Reference Documents/References to be tabled at meeting by Contract Supervisor
               Form WHS27 Contractor’s Permit to Work
                   WHS27.docx;
                  Form WHS28 Contractor safety induction checklist
                   WHS28.docx;
                  Form WHS36 Confined space entry permit
                   WHS36.docx;
                  Form WHS38 Hot work permit
                   WHS38.docx;
                  Checklist WHS41 Plant and Equipment Risk Assessment
                   WHS41 Plant &Equipment Risk Assessment.docx;
                  Campus map (indicate location of FM-Assist Office)
                  Asset Register – User Guide and Template
                   User Guide Template
                  Isolation Impairment Notification Form
                   Fire Panel Isolation for Contractors
                   Isolation impairment Form.docx1;
      UniSA Safety and Wellbeing, NO Smoking, Equal Opportunity and Sexual Harassment
               Policies:
               Contract Supervisor shall direct Contractor to the links to the relevant policies and advise of their
               obligations to comply with the respective UniSA Policies.
                Safety and Wellbeing Policy:
                    Safetyandwellbeing.asp;
Construction Start-Up Checklist
                                                         Page 1 of 6
                                                                                                FM-038
                              Construction Start-up Checklist
                    The Contractor is advised that UniSA is authorised to carry out periodic inspections of all
                    UniSA premises including the site and will issue a Notice of Non-Compliance if WHS issues are
                    not being addressed.
               The Contractor will provide a copy of their Site Safety Management Plan on site.
                Equal Opportunity Policy: Equal Opportunity Policy;
                Sexual Harassment Policy: Sexual Harassment Policy;
                NO Smoking Policy: The Contractor is reminded that UniSA is a smoke-free environment.
               Smoking is prohibited on all UniSA sites including leased premises.
      Notice of Project Commencement of Construction Phase and Program (Advanced Works
               Notice):
               Contract Supervisor shall advise Campus Facilities Manager and Insurance Office of successful
               Contractor, anticipated construction program, and brief description of extent of work.
      Permits to Work:
               Contractor will complete UniSA Permit to Work Form WHS27 prior to commencement of
               construction. Form to be submitted to UniSA Project Manager at construction start-up meetings.
               Permits to work must be re-submitted at any stage of construction if the nature of the work requires
               permit.
      Roles and Lines of Communication:
               The main line of communication to the Contract Supervisor is through the Principal Consultant.
               The exceptions being for matters related to: access, hazardous materials, incidents - these are to
               be directed to the Contract Supervisor and FM-Assist. Any stakeholder related communication is to
               be via the Contract Supervisor.
      UniSA Incident Reporting Protocol:
               The Contractor will advise FM-Assist and the Contract Supervisor immediately of any incidents,
               accident or injury on site. The Contract Supervisor will follow up with a full written report which
               includes the Contractor’s incident report investigation within 24 hours.
      Site Meetings:
               Agree on a mutually convenient time, location and regularity for site meetings (normally weekly).
               The Contractor is responsible to take and distribute minutes with WHS clearly identified as an
               agenda item. Establish a list at the start up meeting of all people to be included in the distribution
               list.
      Access to Site:
               The Contractor will organise on a daily basis with FM-Assist access to the construction site. All
               Contractor’s representatives and subcontractors will report daily to FM-Assist to sign in and out.
      Contractor’s Key Representatives Contact Details:
               Obtain from the Contractor the contact details of all key project personnel.
      Identification Badges:
               All contractors’ personnel will wear company identification badges on their clothing to indicate that
               they represent the Contractor on site and carry at all times a UniSA Induction card for this project.
      Site Entry Signage:
               The Contractor is to provide appropriate signage outlining any specific instructions, maps for
               alternative evacuation or entry points, and project title/time frame. The sign should include the
               Facilities Management co-branding logo and be displayed by the Contractor at all entry points for
               the site. Consideration should also be given to size of sign and text to ensure readability.
Construction Start-Up Checklist
                                                       Page 2 of 6
                                                                                                 FM-038
                              Construction Start-up Checklist
      Egress for Emergency Access:
               The Contract Supervisor is to provide the Contractor with building plan(s) that nominate clear
               access/egress points during construction works in case of an emergency or building evacuation.
               Egress paths cannot be changed without the approval of the Campus Facilities Manager. Principal
               Consultant to provide egress path if changed.
      Identification of Adjacent Teaching Spaces:
               The Contract Supervisor in conjunction with the Campus Facilities Manager are to identify adjacent
               teaching spaces/ and sensitive areas which are likely to be impacted by the construction process.
               In the case of Teaching Spaces, a calendar of bookings should be obtained so that the
               construction program can work around critical times. The Campus Facilities Manager is to advise
               all affected of the project program and anticipated impact.
      General Amenities:
               Advise the Contractor where the closest amenities are located including, toilets and wash facilities
               (where appropriate).
      Parking:
               Advise Contractor of parking arrangements for contractors on the campus. Agree arrangements
               with Campus Facilities Manager.
      Contractor’s Bin/ Skip Location:
               Discuss and agree a location and frequency of removal for the Contractor’s skip with the
               Contractor and Campus Facilities Manager.
      Contractor’s Container/Compound:
               Discuss and agree a location for the Contractor’s storage container with the Contractor and
               Campus Facilities Manager.
      Transport of Goods and Waste to and from Site/Campus:
               Advise the contractor that they must ensure that all goods/waste being transported to and from
               campus must be properly secured to prevent any littering on public property/roadways.
               Advise the contractor that any vehicles entering or departing site/campus must not drag debris
               (e.g. soil, building and construction materials, rocks, sand) onto roadways.
      Protection of Surfaces - lift cars, corridor walls and doors, ceiling tiles:
               The Contractor is responsible to ensure that all existing surfaces are appropriately protected
               including lift cars and corridor floors and walls. Contractor is to prepare dilapidation report prior to
               commencing work on site.
      Fire Extinguishers:
               Advise the Contractor where existing Fire Extinguishers are located within (or adjacent) to the work
               site. In addition, instruct Contractor to return all existing fire extinguishers to the Campus Facilities
               Coordinator for storage. Consultation with the Contract Supervisor shall occur if additional fire
               extinguishers are required to meet legislative requirements and a bill forwarded to the Contract
               Supervisor on approval of such items.
      Mechanical Equipment and Smoke Detectors:
               The Contractor is responsible for protecting existing mechanical infrastructure by installing
               temporary pre-filters on all return air grilles within the construction area.
      Fire Evacuation Procedures:
Construction Start-Up Checklist
                                                        Page 3 of 6
                                                                                              FM-038
                              Construction Start-up Checklist
               The Contractor must evacuate on alarm and follow the instructions of UniSA fire wardens. Advise
               the Contractor of the assembly location in the event of an alarm. Contractors are to advise
               subcontractors accordingly and nominate a fire warden during the contract period.
      Fire Detection System Isolation (may require an Advanced Works Notice):
               The Contractor is required to identify Fire Alarm Zones which may be impacted by the planned
               works and will arrange with Security daily the isolation and resetting of these Fire Alarm Zones.
               The Contractor is to organise for the temporary relocation of fire detectors, so that the project area
               can be isolated, and that the block plans in the Fire Indicator Panel have been temporarily
               upgraded to suit. Contractor is responsible for updating both copies of fire block plans (including
               legends where applicable), including company name and date and copy to be provided to Contract
               Supervisor for forwarding to UniSA Spatial information Officer for updating.
               Note: FM-Assist to notify Insurance Office if isolation is required for longer than 8 hours. The
               UniSA Isolation Impairment Notification Form is to be completed by the Contractor and provided to
               FM-Assist and copied to Contract Supervisor. Note - any call-outs to the MFS will be charged to
               the Contractor.
      Isolation of Services (may require an Advanced Works Notice):
               The Contractor is responsible for providing advanced warning (not less than 96 working hours’
               notice) of any requirement to isolate services at each site meeting. The Contractor is to negotiate
               with Campus Facility Manager the period of isolation. Service isolation work will not proceed
               without approval of the Campus Facility Manager.
      Identification of Hazardous Materials:
               Advise the Contractor that in the event of discovering hazardous material which will impact on the
               Work and that is not documented or labelled, the Contractor shall cease work, notify FM-Assist
               initially, then the Principal Consultant and the Contract Supervisor and wait on instructions.
      Electrical Equipment – No Live Working:
               Advise the Contractor that working on live electrical equipment is generally not allowed. Should it
               be demonstrably impracticable to isolate the equipment e.g. switchboard, a detailed Safe Work
               Method Statement (SWMS) must be provided and written approval given by the Contract
               Supervisor.
      Electrical Equipment- extension cords:
               Advise the Contractor that all power tools, extension leads and associated portable electrical
               equipment must have a current test tag attached prior to use on a UniSA site.
      Essential Safety Provisions:
               If during construction, any work impacts on Essential Safety Provisions, the Contract Supervisor
               and Principal Consultant must be notified prior to commencing work on site. Contractor to update
               both copies of fire block plans including company name and date in the FIP with any changes
               (including legends if applicable). The Contractor is to provide updated copy to Contract Supervisor
               to forward to FMU Spatial Information Officer for updating.
      Danger and Out of Service Tags:
               Advise the Contractor of the use of ‘Danger’ and ‘Out of Service’ tags associated with any plant or
               equipment within their work area. Contractor to isolate /tag out/lock out all electrical circuits as
               necessary to maintain safe workspace; remove tags/locks when work complete and advise
               Contract Supervisor if there are continuing safety reasons why a circuit should remain
               tagged/locked out for UniSA to address.
      Noise:
Construction Start-Up Checklist
                                                      Page 4 of 6
                                                                                           FM-038
                              Construction Start-up Checklist
               Remind Contractor that in accordance with UniSA Preliminaries clauses, all noisy work exceeding
               50 dB measured in affected areas will take place before 8.30am or after 5:30pm. Advanced
               warning of noisy activity shall be communicated to UniSA not less than 24 hours prior to works
               being undertaken and discussed at all site meetings.
      Items to be returned to UniSA:
               Establish with the Campus Facilities Coordinator and the Contractor an agreed location for
               returning UniSA items as required under the contract.
      Contracts:
               Contracts should be executed prior to the first claim being submitted.
      Insurance:
               The Contractor must provide to UniSA all insurance cover notes prior to commencement on site.
Construction Start-Up Checklist
                                                      Page 5 of 6
                                                                                       FM-038
                              Construction Start-up Checklist
Project:            Project Number and Title Here
Date:               Date Here
      Key Personnel for this Project:
    Organisation                  Position             Name           Contact Number    Sign & Date
    UniSA                         Campus Facilities
                                  Manager/Facilities
                                  Coordinator/FM-
                                  Assist
    UniSA                         Project
                                  Manager/Contract
                                  Supervisor
    UniSA                         Stakeholder (if
                                  applicable)
    Contractor:                   Project Manager
    Contractor:                   Site Supervisor
    Principal
    Consultant
    Other
Construction Start-Up Checklist
                                                        Page 6 of 6