An Empirical Study On The Problems of Running Design and Build Projects in Construction
An Empirical Study On The Problems of Running Design and Build Projects in Construction
Edmond W.M. Lam, Albert P.C. Chan & Daniel W.M. Chan
                To cite this article: Edmond W.M. Lam, Albert P.C. Chan & Daniel W.M. Chan (2007)
                An Empirical Study on the Problems of Running Design and Build Projects in
                Construction, International Journal of Construction Management, 7:1, 1-15, DOI:
                10.1080/15623599.2007.10773091
Article views: 76
Download by: [University of Saskatchewan Library]                                                           Date: 12 June 2016, At: 20:16
                                                                                                An Empirical Study on the Problems of Running Design and
                                                                           The International Journal of Construction Management
                                                                                                              Build Projects      (2007) 1 - 15
                                                                                                                             in Construction                                          1
                                                                           Department of Building and Real Estate, Hong Kong Polytechnic University, Hung Hom, Kowloon, Hong Kong.
                                                                           E-mail: bselam@inet.polyu.edu.hk
                                                                           Abstract
                                                                           The drawbacks of the traditional design-bid-build procurement system (design then build) have led
Downloaded by [University of Saskatchewan Library] at 20:16 12 June 2016
                                                                           project participants in the construction industry to opt for alternative procurement systems, like design-
                                                                           build (D&B) (design and build) to deliver their projects. Previous research reported the better time
                                                                           performance of the D&B method and the benefits of the single-point contact from the contractor. While
                                                                           D&B has been popularly used in some western countries, the identification of problems in running
                                                                           D&B projects can arouse the concern of project stakeholders, namely, clients, contractors and consultants,
                                                                           especially in countries where D&B is at a germinating stage. This paper presents the empirical findings
                                                                           on the problems of running D&B projects from the perspectives of clients, contractors and consultants.
                                                                           Inter-group comparisons reveal that there is generous consensus in problem ranking in the client-consultant
                                                                           and contractor-consultant groups, while significant differences exist between the clients and the contractors
                                                                           on the ranking exercise. Based on a better understanding of the problems faced by the major participants
                                                                           in running D&B projects, the authors suggest further research on identifying the critical success factors
                                                                           for D&B projects in order to enhance the well being of the construction industry at large.
                                                                           Keywords
                                                                           Procurement, design-build, problems, cross-comparison, construction, Hong Kong
INTRODUCTION
                                                                           Design-build (D&B) is one popular alternative procurement method in the UK as it seeks less
                                                                           adversarial and more integrated project procurement strategies (Palaneeswaran and
                                                                           Kumaraswamy, 2001). In fact, D&B has been used over the world extensively for around 40
                                                                           years and its popularity has gained substantially over the last ten years (Ernzen and
                                                                           Schexnayder, 2000). More significant moves towards D&B are evident from statistics and
                                                                           examples from the UK, USA and Australia (Palaneeswaran and Kumaraswamy, 2001). In
                                                                           Japan, 10% of construction projects are acquired through D&B and the method is also gaining
                                                                           popularity in Singapore (Chan et al., 2001; Lip, 2001).
                                                                           In the last decade, D&B has been used extensively in Hong Kong to help deal with the problems
                                                                           associated with the traditional procurement method (Chan, 2000). Three forms of variants,
                                                                           namely pure D&B, enhanced D&B and novation D&B are most widely used. The pure form
                                                                           requires the contractor to accept total responsibility for both the design and construction to
                                                                           meet the requirements of the client (Lam, 1998). The enhanced D&B enables the client to
                                                                           ensure the conformance of the basic design to his requirements by retaining control of the
                                                                           initial design whereas the contractor under novation D&B is required to employ the same
                                                                           team of consultants after the award of contract (Chan, 2000; Ng and Skitmore, 2002). While
                                                                           the pure D&B form is normally used for simpler building types like residential buildings, the
                                                                           2                                     Lam, Chan and Chan
                                                                           enhanced and novation forms apply to more complex buildings like hospitals and
                                                                           slaughterhouses. Previous research reported the benefits of the D&B method, and the
                                                                           identification of problems in running D&B projects can enable project stakeholders, namely,
                                                                           clients, contractors and consultants to run D&B projects more efficiently.
                                                                           This paper investigates the problems associated with running D&B projects. It first provides
                                                                           an overview of the potential problems in running D&B projects. The techniques used in
                                                                           analyzing the responses from a questionnaire survey are then explained. The results from the
                                                                           statistical analyses on the ranking of problems and the cross-comparison of the responses are
                                                                           presented, followed by rigorous discussions of the results. The paper ends by recommending
                                                                           further research on determining the critical success factors for D&B projects in the conclusion
Downloaded by [University of Saskatchewan Library] at 20:16 12 June 2016
section.
                                                                           Despite the global use of D&B over the last two decades, the management skills of applying
                                                                           the D&B method to specific project types and situations are still inadequate (Konchar et al.,
                                                                           1997). Chritamara and Ogunlana (2001) classified the major risks of running D&B projects in
                                                                           terms of technical, financial and environmental aspects. A comprehensive literature review on
                                                                           the potential problems in running D&B projects can be found in Chan et al. (2000) and the
                                                                           problems can be best portrayed at different stages of a D&B project, namely the pre-construction
                                                                           stage and the construction stage.
                                                                           client is lost, leading to a reduction of client’s control during construction in case the client is
                                                                           busy with other business activities (Smith, 1996; Works Bureau, 1999). In D&B projects, the
                                                                           single point entity requires the design professionals to work closely with the contractor who
                                                                           becomes the employer of the design teams. As a result, the design consultants may be involved
                                                                           in serious conflict of interest situations such as the change in design with an increase in cost
                                                                           (Smith, 1996). Some project team members may not be clear enough about their roles and
                                                                           responsibilities, and the contractor cannot take up the role as the team leader to control their
                                                                           consultants (Ling et al., 2000).
RESEARCH METHODOLOGY
                                                                           This paper presents some interim findings of an on-going study on developing a conceptual
                                                                           model of success for design-build projects in the public sector of Hong Kong. The questionnaires
                                                                           were piloted to the target D&B participants in the Hong Kong construction industry from
                                                                           January to March 2003, and a reminder was sent in one month’s time in case the participants
                                                                           forgot to reply. The respondents were instructed to rate the problem attributes that the D&B
                                                                           project had brought to them and other project participants. Sixteen problem attributes were
                                                                           identified in the literature and refined from a pilot study implemented at a previous stage
                                                                           (Table 1).
                                                                           4                                                   Lam, Chan and Chan
                                                                                     Table 1 Results on mean ranking and ‘intra-group’ comparisons for the problems in running D&B projects
                                                                           Nr Problem Item                                                      All         Client     Contractor Consultant
                                                                                                                                            respondents     Group        Group     Group
                                                                                                                                           Mean Rank      Mean Rank    Mean Rank Mean Rank
                                                                           1 It was difficult to get a consensus of the client’s           8.76     7     6.76    13   9.80    5    8.73    8
                                                                              requirements from the different interpretations of the
                                                                              project participants
                                                                           2 It was hard to understand the client’s requirements of this   6.32    15     5.50    15   7.36    9    5.50    15
                                                                              project
                                                                           3 There was conflict of interests between design team           10.43    5     11.71   2    9.12    6    11.30   2
                                                                              members and the contractor
                                                                           4 D&B contractors were not competent at design issues            7.49    9     8.74     8   6.53    12   7.93     9
                                                                           5 It was difficult to control design quality in this project     6.88   12     7.39    11   6.09    13   7.57    11
Downloaded by [University of Saskatchewan Library] at 20:16 12 June 2016
                                                                           6 It was difficult to control workmanship in this project        7.13   11     9.79     4   5.66    16   7.27    12
                                                                           7 Frequent changes were introduced by various clients           10.29    4     9.45     6   11.26    4   9.59     5
                                                                           8 Frequent changes were introduced by various end-users         11.11    2     9.50     5   11.95    2   11.11    3
                                                                           9 The schedule was tight
                                                                           10 There was no room for innovation in this project             14.13    1     14.66    1   14.46    1   13.34    1
                                                                           11 It was difficult to compare contractor’s proposal with the    8.80    6      9.13    7    8.35    7    9.16    6
                                                                              client’s brief                                                7.35   10      5.74   14    6.85   11    9.11    7
                                                                           12 Stress was placed on the project from the client             11.10    3     10.18    3   11.86    3   10.71    4
                                                                           13 There was ambiguity in allocating the responsibilities in     7.88    8      7.84   10    8.04    8    7.70   10
                                                                              the contract
                                                                           14 The various service installation was poorly coordinated      6.52    14     8.61     9   5.77    15   6.11    14
                                                                           15 The project participants were unclear about their roles in   6.83    13     6.95    12   6.88    10   6.70    13
                                                                              D&B
                                                                           16 The scope for this D&B project was ill-defined                4.96   16      4.05   16    6.01   14    4.18   16
                                                                              Number                                                         84             19           37           28
                                                                           Results
                                                                           Demography of data
                                                                           As there is no public release on the list of D&B contractors, the respondents were selected
                                                                           from local journals and web-pages of the client, contractor and consultant companies to identify
                                                                           the respondents who should have experience in running at least one D&B building project in
                                                                           the public sector of Hong Kong. Palaneeswaran and Kumaraswamy (2003) also adopted similar
                                                                           strategies in the knowledge mining of their procurement studies. The survey questionnaires
                                                                           were sent to 248 target D&B participants in the construction industry of Hong Kong between
                                                                           January and April 2003 by ordinary postal mail. In total, 92 valid responses were received,
                                                                           with a response rate of 41%. The respondents represented major stakeholders in a D&B project.
                                                                           Almost half of the respondents (43%) worked in the contractor organisations while nearly
                                                                           one-quarter (24%) worked for the clients. One third of the respondents (33%) came from
                                                                           consultant organisations: architectural firms (11%), quantity surveying consultancy firms
                                                                           (10%), engineering consultancy firms (10%) and project management consultancy firms (2%).
                                                                           the potential problems of project partnering in construction. The technique of mean ranking
                                                                           has been applied in the current study. The respondents were asked to rate their level of agreement
                                                                           about each problem attribute on a seven-point Likert scale, where 1 represents ‘Strongly
                                                                           Disagree’ and 7 represents ‘Strongly Agree’. The sum of the ranks is calculated by the mean
                                                                           times a weighting generated by the SPSS software assigned to the rank and so it is possible
                                                                           that then mean ranks are greater than 7. The seven-point Likert scale was adopted to avoid
                                                                           ‘neutral’ responses and to differentiate the difference in perceptions of the project participants
                                                                           on the ranking exercise. The mean ranking for each problem was calculated in order to determine
                                                                           the relative ranking of different problems in descending order of importance.
                                                                           In order to compare the pattern of ranking of the problems in running D&B projects by the
Downloaded by [University of Saskatchewan Library] at 20:16 12 June 2016
respondents, the following null hypotheses (H0) have been put forward for substantiation:
                                                                              1) The ratings of problems are unrelated among all respondents and within each
                                                                                 respective group.
                                                                              2) There is no significant difference in the pattern of ranking of the individual problem
                                                                                 between the clients and the contractor-consultant group.
                                                                              3) There is no significant disagreement on the rankings of problems in the client-
                                                                                 contractor, client-consultant and contractor-consultant groups.
                                                                           Three statistical tests, namely independent- samples t-test, Kendall’s coefficient of concordance
                                                                           (W) and the Spearman rank-order correlation coefficient (rs) were used to test the above
                                                                           hypotheses in the survey.
                                                                           Kendall’s coefficient of concordance (W) and the Spearman rank-order correlation coefficient
                                                                           (rs) were used to determine the ranking of D&B problems from the perceptions of clients,
                                                                           consultants, and contractors. While the Kendall method conducts an ‘intra-group’ comparison
                                                                           within the same group of respondents, the Spearman method goes for an ‘inter-group’
                                                                           comparisons with any two separate groups of respondents and the computation was performed
                                                                           using the Statistical Package for the Social Sciences (SPSS).
Downloaded by [University of Saskatchewan Library] at 20:16 12 June 2016
RESULTS
                                                                           The main stakeholders of D&B projects are, namely, clients, contractors and consultants. Of
                                                                           the 92 responses received, 22 were solicited from the client organisation, 40 from the contractor
                                                                           organisation and 30 from the consultant organisation. However, not all respondents provided
                                                                           a complete set of answers to the list of the problems, and thus the total numbers of the client,
                                                                           contractor and consultant respondents used in the analysis of the problems in running D&B
                                                                           projects were adjusted to 19, 37 and 28 respectively. The mean scores were calculated by the
                                                                           SPSS package and the results of the ranking were shown in Table 1.
                                                                           In order to test whether the ratings of the problems in running D&B projects are unrelated
                                                                           among all respondents and within each respective group, Kendall’s coefficients of concordance
                                                                           (W) were computed for all respondents and within the groups of clients, contractors and
                                                                           consultants respectively and the results are shown in Table 1. The null hypothesis that the
                                                                           respondents’ ratings among the respondents and within the respective participant group on the
                                                                           problems of running D&B projects are unrelated to each other was rejected at 0.000 significance
                                                                           level. Thus it can be concluded that there is agreement among the respondents on the ranking
                                                                           of the problems of running D&B projects at 0.000 significance level.
                                                                           The independent-samples t-test was next employed to determine whether there is no significant
                                                                           difference in the pattern of ranking of the individual problem between the adjusted client and
                                                                           contractor groups, and the results were shown in Table 2.
                                                                                                      An Empirical Study on the Problems of Running Design and
                                                                                                                    Build Projects in Construction                                           7
                                                                                  Table 2 Comparison between adjusted client’s and contractors’ rankings on the D&B problem attributes
                                                                               Nr Items                                                                  T    Significance Conclusion
                                                                               1 It was difficult to get a consensus of the client’s requirements -1.803          0.075      Accept H0
                                                                                  from the different interpretations of the project participants
                                                                               2 It was hard to understand the client’s requirements of this project -1.699       0.093      Accept H0
                                                                               3 There was conflict of interests between design team members          2.417      *0.018      Reject H0
                                                                                  and the contractor
                                                                               4 D&B contractors were not competent at design issues                  2.533      *0.013      Reject H0
                                                                               5 It was difficult to control design quality in this project           1.722       0.089      Accept H0
                                                                               6 It was difficult to control workmanship in this project              2.968      #0.005      Reject H0
                                                                               7 Frequent changes were introduced by various clients                  -2.382     *0.019      Reject H0
                                                                               8 Frequent changes were introduced by various end-users                -3.265     #0.002      Reject H0
                                                                               9 The schedule was tight                                               -1.990      0.052      Accept H0
Downloaded by [University of Saskatchewan Library] at 20:16 12 June 2016
                                                                               10 There was no room for innovation in this project                    -0.509      0.612      Accept H0
                                                                               11 It was difficult to compare contractor’s proposal with the client’s 0.270       0.788      Accept H0
                                                                                  brief
                                                                               12 Stress was placed on the project from the client                    -2.174     *0.032      Reject H0
                                                                               13 There was ambiguity in allocating the responsibilities in the
                                                                                  contract                                                            -0.312      0.756      Accept H0
                                                                               14 The various service installation was poorly coordinated             2.317      *0.023      Reject H0
                                                                               15 The project participants were unclear about their roles in D&B      0.292       0.771      Accept H0
                                                                               16 The scope for this D&B project was ill-defined                      -2.006     *0.048      Reject H0
                                                                           #
                                                                               P<0.01(2-tailed); *P<0.05(2-tailed); T=t-statistic; H0=No significant difference in mean score
                                                                           The independent-samples t-test shows that the adjusted client-contractor comparisons on the
                                                                           eight problem attributes, namely (1) ‘There was conflict of interests between design team
                                                                           members and the contractor’, (2) ‘D&B contractors were not competent at design issues’,
                                                                           (3) ‘It was difficult to control workmanship in that project’, (4) ‘Frequent changes were
                                                                           introduced by various clients’, (5) ‘Frequent changes were introduced by various end-users’,
                                                                           (6) ‘Stress was placed on the project from the client’, (7) ‘The various service installation was
                                                                           poorly coordinated’ and (8) ‘The scope for that D&B project was ill-defined’, were significant
                                                                           at the specified significance level (P = 0.05 or P = 0.01). The null hypothesis that there is no
                                                                           significance difference in the pattern of ranking between the adjusted client and the adjusted
                                                                           contractor groups on these eight problem attributes was rejected at P = 0.05 or P = 0.01.
                                                                           A further attempt was made to investigate whether there is any significant disagreement on
                                                                           the rankings of problems in the client-contractor, client-consultant and contractor-consultant
                                                                           groups by the Spearman rank-order correlation test (Table 3). Thus the null hypothesis is
                                                                           accepted that no significant disagreement exists between clients and consultants, and contractors
                                                                           and consultants on the ranking of problems in running D&B projects. However, significant
                                                                           disagreement exists between clients and contractors on the ranking exercise.
                                                                                         Table 3 Comparison of Spearman rank correlation coefficients among the client-consultant,
                                                                                                  contractor-consultant and client-contractor groups for D&B problems
                                                                               Comparison                                              rs              Significance             Conclusion
                                                                               Client ranking versus contractor ranking                0.485           0.057                    Reject H0
                                                                               Client ranking versus consultant ranking                0.747           0.001                    Accept H0
                                                                               Contractor ranking versus consultant ranking            0.812           0.000                    Accept H0
                                                                           H0: No significant disagreement on the rankings of problems between any two respondents’ groups
                                                                           8                                      Lam, Chan and Chan
                                                                           In general, all respondents apply the same standard in ranking the problems of running D&B
                                                                           projects, as illustrated in Table 1, where the results are all significant at P=0.000. The Kendall’s
                                                                           coefficients of concordance (W) of the individual groups are greater in magnitude than the W
                                                                           of all respondents, indicating that there is a stronger level of agreement within the individual
                                                                           groups. This can be explained by the similar background of the respondents that influences
                                                                           the perceptions of the respective group. The consultant group has generated a value for W the
                                                                           same as that of all respondents, which may be explained by the more diversified categorisation
                                                                           of the consultant respondents forming a miniature of all respondents.
Downloaded by [University of Saskatchewan Library] at 20:16 12 June 2016
                                                                           All participants ranked ‘the schedule was tight’ as the highest, which is a common problem in
                                                                           the Hong Kong construction industry and as a result, stress was placed on the project from the
                                                                           client, which results in the third problem by the client and contractor respondents and the
                                                                           fourth by the consultant respondents. The consultants were harsh in approving the design by
                                                                           the contractor (Chan et al., 2000). Frequent changes could be detrimental to D&B projects,
                                                                           which were ranked the second and the fourth problems by the participants. Chan et al. (2000)
                                                                           reported that the large number of end-users in a D&B office building made it time consuming
                                                                           to deal with the different parties.
                                                                           The contractor interviewees reported in the study claimed that there were abortive works
                                                                           since design runs parallel with construction. For some public sector projects, such as the
                                                                           hospital project, the end-users are the different departments with specific needs for operations.
                                                                           If there is inadequate coordination among user departments, frequent changes may result,
                                                                           which may produce ‘knock-on’ effects to the overall planning of the hospital if the changes
                                                                           are critical. In fact, D&B can restrict the client from making changes to project requirements
                                                                           once the tender is accepted (Akintoye, 1994). Indeed, changes may inhibit the smooth running
                                                                           of the D&B method.
                                                                           Traditionally, the designers work for the aesthetics aspect while the contractors focus on the
                                                                           cost issue, which may sacrifice the quality of the D&B project. The architects no longer work
                                                                           close to the client but work in the best interests of the contractor (Chan et al., 2000). The
                                                                           design team members may find it difficult to work with the client’s objectives since the
                                                                           contractor is in charge of the project. In fact, the Hong Kong Institute of Architects (HKIA)
                                                                           also revealed possible conflicts in engaging the architects in the D&B method, such as the
                                                                           compromise of time and design, and a decreased cost with inferior quality (HKIA, 1998).
Figure 1 Comparing perceptions of clients and consultant on the problems of running D&B projects
                                                                           The client and consultant groups consider ‘The schedule was tight’ and ‘There was conflict of
                                                                           interests between design team members and the contractor’ as the foremost problems in running
                                                                           D&B projects. The attempt to achieve design certainty has indeed exerted time pressure on
                                                                           the design consultants (Chan et al., 2000). The lack of sufficient time indeed hinders the
                                                                           consultants to produce good design solutions (Akintoye and Fitzgerald, 1995). The latter can
                                                                           be explained by Pearson and Skues (1999) who claimed that it is difficult for the consultants
                                                                           to criticize the employer, who is in fact the D&B contractor. However, the contractor
                                                                           respondents ranked ‘There was conflict of interests between design team members and the
                                                                           contractor’ as sixth. While the client and consultant respondents considered ‘D&B contractors
                                                                           were not competent at design issues’ as a moderately important problem (ranked eighth and
                                                                           ninth respectively), the contractors considered it less important (ranked twelfth) probably
                                                                           because of the confidence of the contractor to produce a buildable design. Such findings
                                                                           coincide with the research of Akintoye and Fitzgerald (1995) where architects were of the
                                                                           opinion that D&B contractors generally lack imagination in design.
                                                                           10                                         Lam, Chan and Chan
                                                                           The client and consultant respondents also agree that ‘Frequent changes were introduced by
                                                                           various end-users’ and ‘Stress was placed on the project from the client’ as the more important
                                                                           problems, ‘It was difficult to control design quality in this project’ as moderately important,
                                                                           and ‘The scope for this D&B project was ill-defined’ as the least important. Akintoye and
                                                                           Fitzgerald (1995) found out that consultants perceive D&B as involving sacrificing product
                                                                           quality and design innovation. Chan (2000) also reported that the quality of project would be
                                                                           lowered due to inadequate supervision of projects. Although both clients and consultants
                                                                           considered ‘It was hard to understand the client’s requirements of this project’ as somehow
                                                                           not important (ranked fifteenth), the contractors ranked it as the ninth important problem. As
                                                                           the brief is drafted by the clients with the help of the consultants, it is not uncommon that both
                                                                           parties spend their utmost effort in preparing an understandable and clear client’s brief. Chan
Downloaded by [University of Saskatchewan Library] at 20:16 12 June 2016
                                                                           et al. (2000) also reported that it was hard to understand what should have been included in
                                                                           the design development compared with a variation. The inaccuracies in the client’s brief are
                                                                           even considered as one dispute area (Ndekugri and Turner, 1994).
                                                                                Figure 2 Comparing perceptions of contractor and consultant on the problems of running D&B projects
                                                                                               An Empirical Study on the Problems of Running Design and
                                                                                                             Build Projects in Construction                              11
                                                                           The contractors and the consultants ranked ‘The schedule was tight’, ‘Frequent changes were
                                                                           introduced by various end-users’ and ‘Stress was placed on the project from the client’ as the
                                                                           major problems in running D&B projects. Indeed, D&B provides for design to be done at a
                                                                           staggering speed into the construction stage (Akintoye, 1994). Moreover, this group of
                                                                           respondents ranked ‘There was no room for innovation in this project’ and ‘There was ambiguity
                                                                           in allocating the responsibilities in the contract’ as the moderate problems, and ‘The scope for
                                                                           this D&B project was ill-defined’ as the less important problem. Indeed, the client hardly
                                                                           gives contractors free hands in terms of design ideas and materials specifications (Akintoye,
                                                                           1994).
                                                                           While both contractors and consultants considered ‘It was difficult to control workmanship in
Downloaded by [University of Saskatchewan Library] at 20:16 12 June 2016
                                                                           this project’ and ‘The various service installation was poorly coordinated’ as the less important
                                                                           problems, the clients ranked them important and moderately important respectively. Chan et
                                                                           al. (2000) reported that there is insufficient time for an architect to complete thorough design
                                                                           and detailing for a D&B project. As the consultant works as a team with the contractor in the
                                                                           D&B method, the client may find it difficult to control workmanship which is rather remote
                                                                           from supervision. The two parties also work closely to coordinate the various services
                                                                           installations to minimise operation problems whereas the client may not be satisfied with the
                                                                           coordination. The client ranked ‘It was difficult to compare contractor’s proposal with the
                                                                           client’s brief’ with low importance while the contractors and the consultants unanimously
                                                                           classified it as a moderate problem. This is because the two parties are held responsible to
                                                                           make sure that the client’s brief is strictly followed in drafting the proposal while the client
                                                                           has systematic procedures to make sure the requirements are met.
                                                                           The clients ranked ‘There was conflict of interests between design team members and the
                                                                           contractor’ and ‘It was difficult to control workmanship in this project’as important problems
                                                                           while the contractors ranked them as moderately important and least important respectively.
                                                                           This finding is consistent with the research work of Chan (2000) where the contractors also
                                                                           ranked ‘poor workmanship’ as the least important. In fact, the client may agree that there is
                                                                           conflict of interest between the designer and the contractor, which is essentially the single
                                                                           D&B team that is too financially focused. The client may also suffer from poor workmanship
                                                                           since the control is remote and the consultants can no longer safeguard the monitoring of the
                                                                           works on its behalf.
                                                                           By contrast, the clients ranked ‘It was difficult to get a consensus of the client’s requirements
                                                                           from the different interpretations of the project participants’ and ‘It was hard to understand
                                                                           the client’s requirements of this project’ as the least important while the contractors ranked
                                                                           them as important and moderately important respectively. Ndekugri and Turner (1994)
                                                                           12                                         Lam, Chan and Chan
Downloaded by [University of Saskatchewan Library] at 20:16 12 June 2016
Figure 3 Contrasting perceptions of clients and contractors on ranking the problems of runnign D&B projects
                                                                           identified conflicts between the brief and the contractor’s proposal as one dispute area. This is
                                                                           because the scope of the D&B project is defined by the client, which, if drafted ambiguously,
                                                                           may result in claims from the contractor. Moreover, disputes may be resulted from the different
                                                                           interpretations of the project participants in the D&B team which is coordinated by the
                                                                           contractor and the client may hold different views from those of the contractor.
                                                                           The contractors considered ‘D&B contractors were not competent at design issues’ and ‘The
                                                                           various service installations were poorly coordinated’ as the least important while the client
                                                                           ranked them as moderately important. Chan et al. (2000) also reported that D&B contractors
                                                                           were quite experienced but with poor design knowledge. This may result from the management
                                                                           and leadership of the D&B contractor who should be confident enough to coordinate both
                                                                           design and construction works. One abnormality was observed in the ranking of the problem
                                                                           attribute “Stress was placed on the project from the client” as the responses of the consultants
                                                                           have been incorporated in the t-statistic, which may be contrasting and result in difference in
                                                                           ranking from that by the respective client and contractor groups.
                                                                                                 An Empirical Study on the Problems of Running Design and
                                                                                                               Build Projects in Construction                                       13
                                                                           In general, all respondents perceived ‘The scope for this D&B project was ill-defined’ as one
                                                                           least important problem and so the participants can in general understand the client’s
                                                                           requirements, whose problem was rated at the second least significant. Moreover, it is revealed
                                                                           that project participants are experienced enough to coordinate various services of the D&B
                                                                           project and to control the quality of design and workmanship of the project.
CONCLUSIONS
                                                                           The traditional design-bid-build method has been in use for years, but the undesirable project
                                                                           delay and the adversarial relationships have urged the client to consider other alternative
Downloaded by [University of Saskatchewan Library] at 20:16 12 June 2016
                                                                           procurement systems. The current study examines the problems in running D&B projects and
                                                                           compares different perceptions on the ranking exercise from the major stakeholders of a D&B
                                                                           project, namely the client, the contractor and the consultant.
                                                                           Findings from the literature show that the problems of running D&B projects can be categorised
                                                                           into those at the pre-construction stage and the construction stage, and major problems identified
                                                                           are Unclear project scope with insufficient innovative ingredients, Deviation of contractors’
                                                                           proposals from the client’s requirements, Inexperience of project participants with unclear
                                                                           roles and objectives and Frequent changes on tight time schedule. The identified problems
                                                                           are further synthesised into 16 problem attributes, which form the framework of data for
                                                                           conducting the empirical study with D&B participants in the Hong Kong construction industry.
                                                                           Mean ranking on the 16 problem attributes was conducted and the top five problems in running
                                                                           D&B projects are ‘The schedule was tight’, ‘Frequent changes were introduced by various
                                                                           end-users’, ‘Stress was placed on the project from the client’, ‘Frequent changes were introduced
                                                                           by various clients’ and ‘There was conflict of interests between design team members and the
                                                                           contractor’. Both intra-group and inter-group comparisons are also carried out to compare the
                                                                           level of agreement in the ranking exercise. The results reported in this paper have provided a
                                                                           sound basis for future research in identifying the barriers to the development, and the reasons
                                                                           for wider adoption of the design-build procurement method for comparison. A further research
                                                                           focus is hereby suggested on determining the critical success factors for D&B projects.
ACKNOWLEDGEMENTS
                                                                           The authors gratefully acknowledge The Hong Kong Polytechnic University for providing
                                                                           funding to support this research effort. Special thanks are also given to the respondents for
                                                                           their kind cooperation and generous contributions in completing the empirical survey
                                                                           questionnaire for this research.
REFERENCES
                                                                           Akintoye, A. (1994). ‘Design and Build: A Survey of Construction Contractors’ Views”, Construction
                                                                              Management and Economics, 12(2), 155-163.
                                                                           Akintoye, A., and Fitzgerald, E. (1995). “Design and Build: A Survey of Architects’ Views”, Engineering,
                                                                              Construction and Architectural Management, 2(1), 27-44.
                                                                           Chan, A. P. C. (1998). “Perception on Variations - A Tale of Three Cities”, Australian Institute of Quantity
                                                                              Surveyors Refereed Journal, 2(1), 42-54.
                                                                           14                                      Lam, Chan and Chan
                                                                           Chan, A. P. C. (2000). “Evaluation of Enhanced Design and Build System - A Case Study of a Hospital
                                                                              Project”, Construction Management and Economics, 18, 863-871.
                                                                           Chan, A. P. C., Chan, D. W. M., and Ho, K. S. K. (2003). “Partnering in Construction: Critical Study of
                                                                              Problems for Implementation”, Journal of Management in Engineering, 19(3), 126-135.
                                                                           Chan, A. P. C., Ho, D. C. K., and Tam, C. M. (2001). “Evaluation Criteria of Public-Sector
                                                                               Design and Build Projects in Hong Kong”, Journal of Construction Research, 2(2), 135-145.
                                                                           Chan, A. P. C., Tam, C. M., and Ho, D. C. K. (2000). “Research Monograph - Evaluation of Integrated
                                                                               Procurement Systems in Hong Kong”, Department of Building and Real Estate, The Hong Kong
                                                                               Polytechnic University.
                                                                           Chritamara, S., and Ogunlana, S. O. (2001). “Problems Experienced on D/B Projects in Thailand”,
                                                                               Journal of Construction Procurement, 7(1), 73-93.
Downloaded by [University of Saskatchewan Library] at 20:16 12 June 2016
                                                                           Dulami, M. F., Morris, G. K., and Baxendale, T. (1995). “The Role of Design Management in Improving
                                                                               the Effectiveness of Design and Build Projects”, Design and Build Projects - International
                                                                               Experiences, International Congress on Construction, 5-6 October 1995, Singapore, 83-89.
                                                                           Ernzen, J. J., and Schexnayder, C. (2000). “One Company’s Experience with Design/Build: Labor Cost
                                                                               Risk and Profit Potential”, Journal of Construction Engineering and Management, 126(1), 10-14.
                                                                           Foo, J., Low, C., Goh, B. H., and Ofori, G. (1999). “Design and Build Procurement of Construction
                                                                               Projects: Hybrids in Singapore”. In: Profitable partnering in construction procurement, E&FN Spon,
                                                                               383-392.
                                                                           HKIA (1998). Report of the design & build task force. Hong Kong Institute of Architects.
                                                                           Konchar, M. D., Sanvido, V. E., and Moore, S. D. (1997). “The Benefits of Design-Build Contracting in
                                                                               the United States”, Proceedings of the International Conference on Construction Process Re-
                                                                               engineering, Australia, 14-15 July 1997, 191-201.
                                                                           Lam, K. C. (2000). “Management of Building Services Procurement for Highly Serviced Healthcare
                                                                               Facilities”, Building Journal Hongkong China, Jun-00, 70-81.
                                                                           Lam, T. (1998). “Experience Sharing of ‘Design & Build’ Contract Practice”, HKIA Journal, 15(2),
                                                                               61-63.
                                                                           Lewis, D. (1999). “Preparation of Design and Build Contract Documents to Minimize Future Disputes”,
                                                                               Seminar Proceedings on Design and Build Procurement System, January 1999, Hong Kong, 1-7.
                                                                           Ling, F. Y. Y., Ofori, G., and Low, S. P. (2000). “Importance of Design Consultants’ Soft Skills in
                                                                               Design/Build Projects”, Engineering, Construction and Architectural Management, 7(4), 389-398.
                                                                           Lip, E. (2001). “Design-Build: Evolution or Revolution?” International seminar on project procurement
                                                                               and cost management: perspectives from different nations, HKIS and PAQS, 23 May 2001, Hong
                                                                               Kong.
                                                                           Masterman, J. W. E. (2002). An introduction to building procurement systems, E&FN Spon.
                                                                           Mo, J. K. W., and Ng, L. Y. (1997). “Design and Build Procurement Method in Hong Kong -An
                                                                               Overview”, CIB W92 Symposium Procurement - a key to innovation, University de Montreal, 20-23
                                                                               May 1997, 453-462.
                                                                           Ndekugri, I., and Turner, A. (1994). “Building Procurement by Design and Build Approach”, Journal of
                                                                               Construction Engineering and Management, 120(2), 243-255.
                                                                           Ng, S. T., and Skitmore, R. M. (2002). “Contractors’ Risks in Design, Novate and Construct Contracts”,
                                                                               International Journal of Project Management, 20(2), 119-126.
                                                                           Palaneeswaran, E., and Kumaraswamy, M. M. (2001). “Reinforcing Design-Build Contractor Selection:
                                                                               A Hong Kong Perspective”, The Hong Kong Institution of Engineers Transactions, 8(1), 7-12.
                                                                           Palaneeswaran, E., and Kumaraswamy, M. M. (2003). “Knowledge Mining of Information Sources for
                                                                               Research in Construction Management”, Journal of Construction Engineering and Management,
                                                                               129(2), 182-191.
                                                                           Pavkov, T. W., and Pierce, K. A. (2001). Ready, set, go! A student guide to SPSS 10.0 for Windows,
                                                                               Mayfield Publishing Company.
                                                                                               An Empirical Study on the Problems of Running Design and
                                                                                                             Build Projects in Construction                              15
                                                                           Pearson, M., and Skues, D. (1999). “Control of Projects Implemented through Design and Build
                                                                              Contracts”, Seminar Proceedings on Design and Build Procurement System, January 1999, Hong
                                                                              Kong, 49-60.
                                                                           Smith, T. E. (1996). “D/B: The Architects’ Perception in the HK Context”, Design/Build Symposium,
                                                                              The Architectural Services Department, May 1996, Hong Kong.
                                                                           Tao, H. (1996). “Design & Build: Challenge & Response”, Design/Build Symposium, The Architectural
                                                                              Services Department, May 1996, Hong Kong.
                                                                           Works Bureau (1999). “Administrative Procedures for Use with The Government of The Hong Kong
                                                                              Special Administrative Region General Conditions of Contract for Design and Build Contracts”,
                                                                              HKSARG, 1999.
Downloaded by [University of Saskatchewan Library] at 20:16 12 June 2016