Inspection and Test Plan Piping work Activities                                                                                            LOGO COMPANY
Project : Pure DC - Data Center Project                                                                    Location : LOGOS Metrolink Logistic Hub, Bekasi, Indonesia
         Contractors / Vendor                  : PT. Trakindo Utama
         Scope                                 : Piping work
         Date of Issue                         : 12/11/2021                                                                                                                                                     ITP Reference Number          :           PDC-LSI-CO-….W-XX-XX
         Revision                              : Revision 00
                                                                                                                    H : Hold Points                                       T : Test                              I : Inspect                   SR: Spot Review                   D: Document Preparation
                                                                                                                    W : Witness                                           R : Review                            SW : Spot Witness             A: Approval
                                                                                                                                                                                                                                                                   Inspection & Acceptance
                                                                                   CODE / Standard/Acceptance                                                                                                                                                                               3rd
Item #         Activity / Description                 Verification Aspect                                                         Reference Documents                                Verifying Documents                 Frequency                                    CONSUL                       OWNER/ Inspection/ Check Sheet Form No.
                                                                                             criteria                                                                                                                                             TRA       TATA                   LSI     Party ;
                                                                                                                                                                                                                                                                       TANT                         PDC
                                                                                                                                                                                                                                                                                           Vendor
         Welding procedure Specification        Compliance with specification                                                                                                                                     Reviewed Before start
  1                                                                                        ASME Sect. IX                    Project procedure, CODE/ Standard                 WPS/PQC, Welder certificates                                         I         R            R        R          -          R
         and welder certificates                    and code/Standard                                                                                                                                            fabrication/construction
                                                     Material comply with                  ASTM, Project
  2      Material receiving                                                                                                 Project procedure, CODE/ Standard                            MRIR Report            Verified before fabrication        I         R            R        R          -          R
                                               specification and code/Standard        specification/Procedure
  3      Painting raw material                    Surface provile, thickness            Painting procedure                            Painting procedure                        Painting Inspection report                                         I         R            R        R          -          R
                                               Marking/cutting material comply
  4      Material marking and cutting                                                Comply with AFC drawing                             AFC drawing                                           -                         Every joint               I          -           -         -         -          -
                                                      with AFC drawing
                                                   Dimension, bevel angle,          Comply with WPS, and AFC
  5      Fit - up joint Inspection                                                                                                    WPS, AFC Drawing                           Fit up inspection report                Every joint               I         I          SW        SW          -          R
                                                      cleanliness joint                     drawing
                                                                                  Comply with Welding Procedure
  6      Welding joint                                Welding parameter                                                      Welding Procedure Specification                                   -                         Every joint               I          -           -         -         -          -
                                                                                          Specification
                                                   Welding profile, surface                                         Table 341.3.2 Acceptance criteria for welds- visual
  7      Visual welding Inspection                                                          ANSI B31.3                                                                      Visual Welding Inspection report             Every joint               I         W          SW        SW          -          R
                                                        appearance                                                           and radiographic examination
                                                                                                                    Table 341.3.2 Acceptance criteria for welds- visual
  8      NDT Radiography                               Welding Quality                      ANSI B31.3                                                                                Radiography report                 Every joint               R         R            R        R          -          R
                                                                                                                             and radiographic examination
                                                                                        Comply with Project                                                                                                            After complete
  9      Pneumatic test                        Leakage on weld and other area                                                 Project Specification/Procedure                        Pneumatic test report                                         I         W            W        W          -          SW
                                                                                      Specification/Procedure                                                                                                           construction
                                                        Painting visual,            Comply with AFC drawing,                                                                      AFC Drawing, Project                 After complete
 10      Final visual Inspection piping line                                                                           AFC Drawing, Project Specification/Procedure                                                                                I         W          SW        SW          -          SW
                                                      completenessvline,          project specification/Procedure                                                                Specification/Procedure                construction
         Manufacturing Data Report
 11                                                  Record of inspection        Project Specification/Procedure              Project Specification/Procedure                          MDR document                 End of construction           D          R            R        R          -          R
         (MDR)
                                               Prepared By                                                          Approved by                                                                                                                         Acknowledged by
                                               PT Trakindo Utama                                                    Consultant                                                                                  LSI - Project Management                                                 Owner /Client
         Note , for coloumn 'Inspection & Acceptance' Parties involved :
         I                                     “I” – Inspect: Visual check of a qualitative nature or a dimensional measurement being carried-out to ascertain whether or not specified requirements have been met. RFIN is issued to inform the appropriate parties of the involved items and activities, including location, timing and
         T                                     “T” – Test: Measured verification of one or more characteristics or of performance, being carried-out to ascertain whether or not specified requirements have been met. RFIN is issued to inform the appropriate parties of the involved items and activities, including location, timing and
                                                                                                                       Inspection and Test Plan Piping work Activities                                                                                             LOGO COMPANY
         Project : Pure DC - Data Center Project                                                               Location : LOGOS Metrolink Logistic Hub, Bekasi, Indonesia
         Contractors / Vendor            : PT. Trakindo Utama
         Scope                           : Piping work
         Date of Issue                   : 12/11/2021                                                                                                                                                        ITP Reference Number          :         PDC-LSI-CO-….W-XX-XX
         Revision                        : Revision 00
                                                                                                               H : Hold Points                                       T : Test                                I : Inspect                   SR: Spot Review                   D: Document Preparation
                                                                                                               W : Witness                                           R : Review                              SW : Spot Witness             A: Approval
                                                                                                                                                                                                                                                                Inspection & Acceptance
                                                                             CODE / Standard/Acceptance                                                                                                                                                                                 3rd
Item #        Activity / Description            Verification Aspect                                                           Reference Documents                               Verifying Documents                   Frequency                                    CONSUL                      OWNER/ Inspection/ Check Sheet Form No.
                                                                                       criteria                                                                                                                                                TRA       TATA                   LSI    Party ;
                                                                                                                                                                                                                                                                    TANT                        PDC
                                                                                                                                                                                                                                                                                       Vendor
         H                               “H” – Hold Point: Indicates an inspection or test that is considered vital to the quality, integrity and safe functioning of the material or services and which can be achieved only at this point. It is an inspection/test activity in the ITP that requires the presence of the CONTRACTOR and/or
         W                               “W” – Witness: Indicates inspection/test activities within the ITP that require the presence of the CONTRACTOR and RAPID PMC. The fabrication/construction process may proceed beyond this point if the inspection representative (CONTRACTOR and/or RAPID PMC) has not attended,
         SW                              “SW” Spot Witness: Indicates an inspection/test activity for ongoing fabrication/construction processes which will be witnessed on a spot check basis. RFIN is issued to inform the appropriate parties of the involved items and activities, including location, timing and duration for this type
         R                               “R” – Review: This indicates a document review by the CONTRACTOR and/or RAPID PMC. In some cases this review may be designated as a Hold point (H) indicating that the work is not to proceed until the document is approved for use.
         SR                              “SR” – Spot Review: This indicates a document review on a spot check basis.
         A                               “A” – Approval: This indicates a document approval. The CONTRACTOR is allowed to continue work related to the document only after approval of the document by RAPID PMC.
         D                               “D” – Document Preparation: This indicates preparation and submission of document from Subcontractor/CONTRACTOR that are either subject to Review (R) or Approval (A).
         Note : ITP shall cover all system function and facilities , please add. And modify as required
         and attach supporting attahment check sheet inspection as required