Delegation of Powers for Procurement
Delegation of Powers for Procurement
)
Sl. No.          Subject matter of Delegation                E.D.       C.G. M./    D.G.M.       Sr.                                            Remarks
                                                                          G.M.                Manager
  (1)                           (2)                           (3)          (4)        (5)        (6)                                                (7)
  1       Accord of technical sanction to detailed (pre- Full Powers   15 Crore    75 Lac     35 Lac     1 (a) The Delegation at S. No. 1 is for components of a project, or for sub-packages
          tender) cost estimate for works, i.e. other                                                    constituting a component, as provided for in FR/ DPR/O&M BUDGET/ Annual plan
          than supply contracts which are dealt with at                                                  and as approved by the Board/ Govt. of India.
          Sl. Nos. 4 to 7 and Service/ Consultancy                                                       (b)(i) PMSG Division will finalize the packages/Turn Key mode of contract for the works
          contracts dealt at Sl No. 26.                                                                  to be awarded at Corporate Office on the recommendations of a committee comprising
                                                                                                         of Heads of PMSG, Design & Engineering, Design (E&M), Contracts Divisions and
                                                                                                         Corporate Planning Division. PMSG will obtain approval of Chairman and Managing
                                                                                                         Director after the recommendation of concerned Director.
                                                                                                         Executive Director (PMSG)/Chief General Manager/GM (PMSG) shall act as Member-
                                                                                                         Convenor to the above committee. The PMSG Division shall forward the approval to
                                                                                                         ED of the Region for raising the Requisitions for initiation of the tendering process.
                                                                                                         (c)(i) Technical Specification (TS) and Bill of Quantities (BOQ) shall be drawn by the
                                                                                                         concerned Corporate Design Division for works to be awarded at Corporate Office and
                                                                                                         send the same to CED. The required data/inputs for preparation of estimates shall be
                                                                                                         supplied by the projects, CEP, Civil Design, HM Design and E&M design for Civil, HM
                                                                                                         and E&M works to CED.
                                                                                                         (ii) Technical Specification (TS) and Bill of Quantities (BOQ) shall be drawn by the
                                                                                                         executing division for works to be awarded at projects before the same is sent to the
                                                                                                         concerned division at project responsible for planning & cost engineering.
                                                                                                         (d) (i) Detailed (Pre tender) cost estimates for components of a Project, or for sub-
                                                                                                         packages constituting a Component, which are to be awarded at Corporate office, shall
                                                                                                         be prepared by CED duly vetted by Associate Finance and ED (CED), CO.
                                                                                                         (ii) For works to be awarded at projects/units, detailed (Pre tender) cost estimates shall
                                                                                                         be prepared by the concerned division of project/unit responsible for planning & cost
                                                                                                         engineering, vetted by Associate Finance and approved at the appropriate level of
                                                                                                         concerned project/unit as per delegation at S.No.1.
 
    Sl. No.   Subject matter of Delegation   E.D.   C.G. M./   D.G.M.              Sr.                                              Remarks
                                                     G.M.                      Manager
      (1)                 (2)                (3)      (4)          (5)             (6)                                                   (7)
 
                                                                                             (e) Excess over FR/DPR/O&M Budget / Annual plan in cost estimate shall be analysed
                                                                                             in a format as per Annex-I, which shall be attached to the cost estimate referred to at
                                                                                             (d) above.
                                                                                             (f) The variance between FR/DPR/O&M Budget/ Annual plan and the cost estimates
                                                                                             of over 10% or 15 Crores whichever is less in each package /sub- package for which
                                                                                             the cost estimate has been prepared shall be intimated by the project through the
                                                                                             regional offices to CED quarterly. CED after compilation shall submit the quarterly
                                                                                             report to functional Directors for their information with a view of apprising them of the
                                                                                             impact of such variances on the project cost/ O&M expenditure.
                                                                                             (g) While exercising these powers for technical sanction in the case of O&M Projects,
                                                                                             administrative approval for the execution of work shall be obtained from the HOP not
                                                                                             below the rank of GM subject to availability of budget. Additional Budget / Re-
                                                                                             appropriation of Budget will be as per Budget Circular issued from time to time by CO
                                                                                             Finance.
                                                                                             (h) Before according technical sanction by executives of the rank of GM and below in
                                                                                             the case of Construction Projects and Survey Investigation units, Administrative
                                                                                             approval for the execution of work shall be obtained from the HOP not below the rank
                                                                                             of GM subject to availability of budget even if such works are incorporated in the FR/
                                                                                             DPR. For works not covered in the DPR/FR etc. prior approval from the CMD shall be
                                                                                             obtained after the recommendation of concerned Director.
                                                                                             (i) Project schedule of rates (PSR) for works other than supply, services will be fixed
                                                                                             and reviewed annually before the first month of the financial year (i.e. April) by the
                                                                                             concerned division at project responsible for planning & cost engineering after vetting
                                                                                             by project finance and approval by the HOP not below the rank of GM on the basis of
                                                                                             respective State Schedule of rates. In case of certain items not being present in the
                                                                                             State Schedule of rates then for those items rates would be fixed on the basis of CPWD
                                                                                             rates/ market rates and got approved by the HOP not below the rank of GM. Copy of
                                                                                             the PSR shall be forwarded to ED of the Region & CED, CO.
                                                                                             In respect of corporate office the action on remark (i) above will be taken by concerned
                                                                                             executing division.
                                                                         Page 2 of 25                                                                                   
                                                                                                                                                                 Section‐I, DOP‐2019 
 
    Sl. No.          Subject matter of Delegation             E.D.   C.G. M./   D.G.M.              Sr.                                               Remarks
                                                                      G.M.                      Manager
      (1)                          (2)                        (3)      (4)          (5)             (6)                                                    (7)
 
                                                                                                              (j) While exercising these powers in the case of CO and RO, Administrative approval
                                                                                                              for the execution of work shall be obtained from the HOD (in case of CO)/ ED (in case
                                                                                                              of RO) subject to Budget approved by BOD for the year.
      2       Approval for calling of tenders, and/or                                                         (i) Tenders are to be invited by the Contracts and Procurement Group at Corporate
              issuing award for works i.e., other than mere                                                   Office and by P&C division at Projects as are functionally responsible thereof, only
              supply items, after approval of cost                                                            after approved Requisition is received and pre-tender cost estimate/ Technical
              estimates, vide (1) above.                                                                      sanctioned estimate is approved by competent authority vide (1) above. Irrespective
                                                                                                              of the powers delegated, tenders for supplies/services at the Projects shall be invited
                                                                                                              after clearance by HOP or head of division responsible for maintenance of Corporate
                                                                                                              office building/residential colony/other facilities in respect of the functions entrusted to
                                                                                                              them.However for Sl. No. 1(c) (i) Tender check estimate (Technical Sanction Estimate)
                                                                                                              shall be prepared by CED well before submission of price bids.
                                                                                                              (ii) Tender documents shall be approved by the authority who has the power for
                                                                                                              approval for calling of tenders and/or issuing award for works.
                                                                                                              (iii) Fees for tender documents and amount of EMD for tenders shall be regulated as
                                                                                                              per guidelines contained in circular no. CS/D/2010/4 dated 03.05.2010 and
                                                                                                              CS/D/2016/20 dated 30.03.2018 respectively or as amended from time to time.
                                                                                                              (iv) “Other than mere supply items” shall mean the works involving installation and/or
                                                                                                              other services, the estimated cost of which is not less than 15% of total estimated cost
                                                                                                              of the work package.
                                                                                                              (v) In respect of contract packages beyond the powers of Executive Director, the
                                                                                                              qualification criteria shall be formulated and approved by an empowered Committee
                                                                                                              as per annexure-II. In other cases, the authority competent for call of tender shall
                                                                                                              approve the qualification criteria. The evaluation of qualification of applicants / bidders
                                                                                                              meeting the specified qualifying criteria will be done by the Tender Evaluation
                                                                                                              Committee (TEC) to be constituted as per Annexure-II. TEC is empowered to seek
                                                                                                              clarifications from the bidders as per tender conditions.
                                                                                          Page 3 of 25                                                                                      
                                                                                                                                                                                     Section‐I, DOP‐2019 
 
    Sl. No.   Subject matter of Delegation   E.D.   C.G. M./   D.G.M.              Sr.                                              Remarks
                                                     G.M.                      Manager
      (1)                 (2)                (3)      (4)          (5)             (6)                                                   (7)
 
                                                                                             (vi) Tender Evaluation Committee/Tender Opening Committee (as per Annexure – II)
                                                                                             shall be constituted with the approval of the authority competent to approve the call of
                                                                                             tender or such other authority that is authorised to approve the constitution of the
                                                                                             committee. Nomination of members for the Prequalification/Tender Evaluation
                                                                                             Committee for the cases beyond the powers of Executive Director shall be approved
                                                                                             by the concerned ED (at Regional Office for cases dealt at Projects/Power
                                                                                             Stations/RO)/ HOD, Contract Division, CO. (for cases to be dealt at C.O.) after receipt
                                                                                             of Nominations from concerned HODs.
                                                                                             (vii) Wherever two-stage/ two-envelope system of bidding are resorted to, the
                                                                                             techno-commercial evaluation report and opening of price bids shall be approved by
                                                                                             the authority competent to approve the call of tender.
                                                                                             viii) The cases for which the approval for calling of tenders and/or award of works are
                                                                                             beyond the powers of ED, the approvals required under ii) and vii) above shall be
                                                                                             accorded by CMD. However, Tender Documents containing Terms & Conditions (viz.
                                                                                             General Conditions, Special Conditions, Instruction to Bidders and Annexure thereto)
                                                                                             already approved earlier by Director/ CMD before issuance of this DOP, or
                                                                                             routine/minor changes therein may be approved by ED/ HOD of Contracts Division of
                                                                                             Corporate Office. The other parts of bid document shall be approved by the respective
                                                                                             HODs of Corporate Office, who are responsible for preparation thereof. Amendment
                                                                                             to Bid Document containing terms and conditions/data received from concerned HODs
                                                                                             of C.O. shall be approved by ED (Contracts). In case terms of commercial conditions
                                                                                             (GCC, SCC, ITB) are not already approved by CMD, then shall be approved by CMD
                                                                                             after the recommendation of concerned Director. The policy changes in the terms and
                                                                                             conditions of Contract shall be approved by CMD in the routine manner and shall be
                                                                                             updated in the contract documents by Contract Division in the normal course.
                                                                                             (ix) (a) In case of powers within the competency of ED( Region/HOD at CO) or
                                                                                             below
                                                                                             (i) The accepting officer shall be empowered to accept tender provided the variation in
                                                                                             tendered amount does not exceed more than 10% of the Technical Sanction Estimate.
                                                                         Page 4 of 25                                                                                   
                                                                                                                                                                 Section‐I, DOP‐2019 
 
    Sl. No.         Subject matter of Delegation      E.D.     C.G. M./    D.G.M.              Sr.                                                Remarks
                                                                 G.M.                      Manager
      (1)                       (2)                    (3)        (4)          (5)             (6)                                                     (7)
 
                                                                                                         (ii) The cases where finally accepted tender is more than 10% and up to 25% of
                                                                                                         ‘Technical Sanction Estimate’ shall be approved by next higher authority (instead of
                                                                                                         empowered accepting officer) to that mentioned in the Delegation of Power.
                                                                                                         (iii) The cases where finally accepted tender is more than 25% of ‘Technical Sanction
                                                                                                         Estimate’ shall be approved by authority superior to next higher authority (instead of
                                                                                                         next higher authority) to that mentioned in the Delegation of Powers restricted up to
                                                                                                         Director concerned.
                                                                                                         (ix) (b) Powers beyond competency of ED (Region/HOD at CO)
                                                                                                         The cases where finally accepted tender is more than 25% of ‘Technical Sanction
                                                                                                         Estimate’ shall be approved by CMD after the recommendation of concerned Director.
                                                                                                         (x) Delegation alongside (not Technical Sanction Estimate) shall be the basis for
                                                                                                         determining level of competency for award of works. However, for estimates consisting
                                                                                                         supply and works both, percentage of supply will also be seen at the time of award to
                                                                                                         decide approving authority.
                                                                                                         (xi) In respect of contract packages beyond the powers of Executive Director, approval
                                                                                                         for calling of tenders shall be approved by concerned ED (at Regional Office, for cases
                                                                                                         dealt at Projects/Power Stations/RO)/ HOD, Contract Division, C.O. (For cases to be
                                                                                                         dealt at C.O.).
     2.1      Open tender                          25 Crore   10 Crore    75 Lac          35 Lac         2.1. a. Open tenders are those enquiries issued-
                                                                                                         -   All    Notice       Inviting       Tenders          (NITs)   and    tender       related
                                                                                                             notices/information/addendums such as change in Qualification Requirement
                                                                                                             (QR), Amendments/Corrigendum regarding date of submission of bid etc. shall
                                                                                                             only be uploaded on the web portals of NHPC, Central Public Procurement/e-
                                                                                                             Procurement service providers and no press publication shall be issued.
                                                                                                             After start of publishing the NITs on GeM portal, all NITs and Corrigendum shall
                                                                                                             also be published on GeM portal.
                                                                                                         -   Through press advertisement in international journals / newspapers for the
                                                                                                             invitation of international contracts bids wherever required as per policy guidelines
                                                                                     Page 5 of 25                                                                                      
                                                                                                                                                                                Section‐I, DOP‐2019 
 
    Sl. No.         Subject matter of Delegation       E.D.     C.G. M./    D.G.M.              Sr.                                              Remarks
                                                                 G.M.                       Manager
      (1)                       (2)                    (3)        (4)           (5)             (6)                                                   (7)
 
                                                                                                          -   Through Notice Inviting Tender in English/Hindi and the written language of the
                                                                                                              district and pasted on notice boards of various circles of Projects/Units for works
                                                                                                              valued below 50 Lac. A copy should also be sent to Central PWD Divisions, Zonal
                                                                                                              Office, the Circle Office, Local Municipalities and DM’s/Collector’s Office/State
                                                                                                              PWD Divisions operating at the station of the work and Headquarters of the Project
                                                                                                              Office.
                                                                                                          -   Inviting tenders from bidders pre-qualified for a particular work.
                                                                                                          2.1. b. In case where not less than 3 valid offers are received, it shall be approved by
                                                                                                          the competent officer as per financial limit. However when the number of valid offers
                                                                                                          are less than 3, then the fact be brought to the notice of the competent authority i.e
                                                                                                          next higher authority before opening of bids and approval of the next higher authority
                                                                                                          is required before placing order except in case where the proposals falls within the
                                                                                                          powers of ED and above. However, the TEC shall not be reconstituted by the next
                                                                                                          higher authority competent to award.
     2.2      Limited tender                       5 Crore    1 Crore      15 lac          7 lac          Limited tender enquiries are those issued for requirements which do not fall under
                                                                                                          Open Tender category or which are required due to urgency or for specialized jobs
                                                                                                          and issued preferably to not less than five vendors whose names have been registered
                                                                                                          or maintained in a list or based on past experience or current offers or from the vendor
                                                                                                          lists maintained in the State Govt./ Central Govt./ PSUs.
                                                                                                          (i) The number and names of parties selected for issue of limited tender enquiry vide
                                                                                                          (2.2.a) above shall be approved by an authority, next higher to the authority competent
                                                                                                          to award, except in case of award proposals falling within the powers of CGM/GM and
                                                                                                          above.
                                                                                                          2.2.b (ii) Delegated powers at Sr. No. 2.2 are to be used only if minimum 3 valid
                                                                                                          quotations are received. If valid offers are less than three then the fact be brought to
                                                                                                          the notice of competent authority i.e next higher Authority before opening of bids. The
                                                                                                          approval of the next higher authority is required before placing order except in case of
                                                                                                          award proposals falling within the powers of ED and above.
                                                                                      Page 6 of 25                                                                                    
                                                                                                                                                                               Section‐I, DOP‐2019 
 
    Sl. No.          Subject matter of Delegation                 E.D.        C.G. M./        D.G.M.              Sr.                                              Remarks
                                                                                G.M.                          Manager
      (1)                          (2)                            (3)               (4)           (5)             (6)                                                   (7)
 
     2.3      Single tender without call of tenders in case   2.5 Crore     50 Lac        -                  -              2.3. a. Single tender enquiry is to be resorted to only in case of urgency /single source
              of urgency or specialized jobs.                                                                               availability and includes negotiated tender without call of tenders where resorting to
                                                                                                                            tenders is neither practical nor economical.
                                                                                                                            2.3. b. The rates at which the negotiated tenders are awarded shall be within the
                                                                                                                            applicable project schedule rates/ prevailing market rates.
                                                                                                                            In case rates are based on prevailing market rates the reasonableness of the price
                                                                                                                            shall be determined, which shall be recorded accordingly.
                                                                                                                            2.3 (c)- The urgency certificate in prescribed format is to be approved by HoP not
                                                                                                                            below the rank of GM.
     2.4      Spot Work Orders                                30 lac        7 lac         1.5 Lac            75,000         2.4 The spot work orders are to be resorted to under extreme circumstances based on
                                                                                                                            field requirement and at the PSR.
                                                                                                                            Deviations in spot work orders shall normally be avoided. However, in case of quantity
                                                                                                                            deviations in a work order, the authority competent to award the work order inclusive
                                                                                                                            of the above deviations (i.e. original value plus deviations) shall approve these
                                                                                                                            deviations.
     2.5      a) Execution of deposit works through           10 Crore      1.5 Crore     -                  -              2.5. Powers are to be exercised by the head of the project not below the rank of
              Government Agencies, Autonomous Bodies                                                                        General Manager after considering all factors like urgency, specialized jobs,
              controlled by Government, Public Sector                                                                       availability of budget, reasonableness of rates and after ascertaining that the same
              Undertakings.                                                                                                 rates are being charged from other Government departments.
              b) Approval for conducting Model Studies        1 Crore       20 Lac                                          This power shall also be applicable to Deposit work relating to Catchment Area
              and specialized tests/tests from external                     (HOP in the                                     Treatment work, Bulk power supply line works, State PWD roads/bridges, etc.
              institutions for investigations/EIA & EMP                     case of                                         Powers in column 2.5 (b) shall be exercised by respective head of deptt, in case of
              Study/ Model Study construction/ O&M/                         Projects                                        C.O.
              Geo-Tech/ R&D schemes from Government                         and HOD in
              Agencies, Autonomous Bodies controlled by                     case of CO)                                     Waiver of E-tendering can also be authorised by approving authority in such cases.
              Government, Public Sector Undertakings.
      3       Approval of Purchase Requisition for supply     Full Powers   3 Crore       75 Lac             30 Lac         3. (i) Supply items for the purpose of this delegation include all supply/work packages
              items with cost estimates thereof.                                                                            involving supply component of more than 85% of total estimated cost.
                                                                                                                            (ii) The remarks against S.No.1 apply to this item as well.
                                                                                                                            (iii) Administrative Approval of HOP not below GM is required.
                                                                                                        Page 7 of 25                                                                                   
                                                                                                                                                                                                Section‐I, DOP‐2019 
 
    Sl. No.          Subject matter of Delegation                 E.D.     C.G. M./       D.G.M.              Sr.                                              Remarks
                                                                            G.M.                          Manager
      (1)                          (2)                            (3)        (4)              (5)             (6)                                                   (7)
 
      4       Approval for calling of tenders for purchase/                                                             4. Tenders are to be invited by the Procurement & Contract Services group and other
              supply of items and Award thereof against                                                                 divisions as are functionally responsible for items against approved purchase
              approved indents.                                                                                         requisition and cost estimate vide (3.ii) above.
                                                                                                                        All remarks given against delegation at Sr. no. 2 except 2.2.b (ii) and 2.3.b. apply to
                                                                                                                        this delegation as well.
                                                                                                                        Procurement of Construction and allied machinery/tools should be as per Circular no.
                                                                                                                        CS/A/83 dated 26.08.08 or as amended from time to time.
                                                                                                                        Procurement shall be made from GeM portal wherever applicable as per extant
                                                                                                                        guidelines. Further, in such cases procedure as per GeM portal shall be followed for
                                                                                                                        procurement without requiring any approval at intermediate stage except for award of
                                                                                                                        tender.
     4.1      Procurement of Steel in case of MOU with        25 Crore   10 Crore     -                                 Delegation is subject to signing of MOU with the approval of Competent authority.
              SAIL/RINL
     4.2      Open tender                                     10 Crore   3 Crore      35 Lac             20 Lac         In case where not less than 3 valid offers are received, it shall be approved by the
              Cement /Steel                                   20 Crore   5 Crore      35 Lac             20 Lac         competent officer as per financial limit. However when the number of valid offers are
                                                                                                                        less than 3, then the fact be brought to the notice of the competent authority i.e next
                                                                                                                        higher authority before opening of bids and approval of the next higher authority is
                                                                                                                        required before placing order except in case where the proposals falls within the
                                                                                                                        powers of ED and above. However, the TEC shall not be reconstituted by the next
                                                                                                                        higher authority competent to award.
     4.3      Limited tender                                  3 Crore    50 Lac       15 Lac             7 Lac          For single tender and limited tender enquiries, reasons are to be recorded in writing
                                                                                                                        before approval of the competent authority is obtained. Parties to be identified for the
                                                                                                                        purpose is to be approved by next higher authority except in case proposals for award
                                                                                                                        falling within the powers of CGM/GM and above.
                                                                                                                        Delegated powers are to be used only if minimum 3 valid quotations are received. If
                                                                                                                        valid offers are less than three then the fact be brought to the notice of competent
                                                                                                                        authority i.e next higher Authority before opening of bids. The approval of the next
                                                                                                                        higher authority is required before placing order except in case of award proposals
                                                                                                                        falling within the powers of ED and above.
                                                                                                    Page 8 of 25                                                                                   
                                                                                                                                                                                            Section‐I, DOP‐2019 
 
    Sl. No.          Subject matter of Delegation                  E.D.        C.G. M./        D.G.M.              Sr.                                                Remarks
                                                                                    G.M.                       Manager
      (1)                           (2)                            (3)               (4)           (5)             (6)                                                     (7)
 
                                                                                                         Page 9 of 25                                                                                      
                                                                                                                                                                                                    Section‐I, DOP‐2019 
 
    Sl. No.          Subject matter of Delegation               E.D.        C.G. M./     D.G.M.            Sr.                                               Remarks
                                                                              G.M.                     Manager
      (1)                           (2)                         (3)               (4)        (5)           (6)                                                    (7)
 
                                                                                                                      (f) Purchases beyond Rs. 2 Lac shall be made by a committee comprising one member
                                                                                                                      each from the indenting department, Proc. division and Finance Division. The
                                                                                                                      Committee level shall not be less than E-3.
                                                                                                                      (g)The authority to exercise these powers shall be decided on the basis of total
                                                                                                                      purchase requirement for particular occasion. Such requirements shall not be broken
                                                                                                                      and procured in instalments to bring it within the powers of the lower authority.
     8.1      Approval of Indent and cost estimate          Full Powers   Full Powers   70 Lac         15 Lac         Remarks against Sl. No. 1 and 2 to the extent as applicable shall apply to this
                                                                                                                      delegation also.
     8.2      Call of tenders and award of work, against                                                              a. Executives of the level of Sr. Manager and above will have the full powers in respect
              indent at 8.1 above for clearance, handling                                                             of transportation by rail and sea. However transportation by air, which shall be resorted
              and transportation.                                                                                     to in case of emergency or any other valid recorded reason, will require the approval
     8.2.1    Open tender                                   3 crore       70 Lac        15 lac         3 lac          of head of the project not below the level of GM.
     8.2.2    Limited Tender                                60 Lac        20 Lac        1.5 Lac        75,000         b. Open tender shall mean and be invited by advertisement in local newspapers for
     8.2.3    Single Tender                                 15 lac        4 lac         40,000                        value between Rs. 10 lac to Rs. 50 lac. Tenders beyond the value of Rs. 50 lacs shall
                                                                                                                      be invited by advertisement in local and national newspapers.
                                                                                                 Page 10 of 25                                                                                    
                                                                                                                                                                                           Section‐I, DOP‐2019 
 
    Sl. No.          Subject matter of Delegation                  E.D.        C.G. M./     D.G.M.           Sr.                                                   Remarks
                                                                                 G.M.                   Manager
      (1)                           (2)                             (3)           (4)           (5)          (6)                                                        (7)
 
                                                                                                                          d. The prices against original contract were not given to compensate for urgent/earlier
                                                                                                                          deliveries.
                                                                                                                          e. Repeat order shall not be placed more than once.
                                                                                                                          f. In case repeat order envisages different locations for delivery/works suitable
                                                                                                                          adjustment in price shall be considered to cover this aspect.
      10      Variation during post award execution of                                                                    10 (a) quarterly statement on the projected completion cost of the package shall be
              works/supply in respect of Contracts                                                                        prepared by the project (categorizing the reason for increase whether due to design,
              awarded on approval of Director /CMD /                                                                      site or unforeseen reasons) and shall submit to Cost Engineering Division (CED) with
              Committee of Directors /Board due to scope                                                                  a copy to Project Monitoring and Service Group. CED shall compile package wise
              / quantity variations/ new or extra items etc.                                                              detail and shall put up to management on quarterly basis.
                                                                                                                          The powers delegated hereunder are subject to the condition that quarterly statements
                                                                                                                          are submitted by ED of the Region to CED, CO. No further approval (technical as well
                                                                                                                          as rates) shall be done by ED of the Region unless the quarterly statement upto
                                                                                                                          preceding quarter are forwarded to CED.
                                                                                                                          (b) The design division will issue the drawing as per the design/ site requirement and
                                                                                                                          project shall go ahead for its implementation at site.
                                                                                                  Page 11 of 25                                                                                          
                                                                                                                                                                                                  Section‐I, DOP‐2019 
 
    Sl. No.   Subject matter of Delegation   E.D.   C.G. M./   D.G.M.          Sr.                                                      Remarks
                                                     G.M.                  Manager
      (1)                 (2)                (3)      (4)          (5)         (6)                                                            (7)
 
                                                                                          (c) Proposal seeking Technical Approval due to design/ site /unforeseen condition
                                                                                          should be processed by the project immediately upon issuance / issuance of drawings
                                                                                          giving rise to deviation/occurrence of event as the case may be with detailed
                                                                                          justification. ED of the region shall accord the Technical Approval (quantities of items
                                                                                          of work) up to the powers delegated to CMD.
                                                                                          Based upon the Technical Approval, the value /financial implication involved for the
                                                                                          particular item shall be worked out by the standing committee as per Annexure-III. The
                                                                                          committee       shall       deliberate   on   the    categorisation   of   the   items   as   new
                                                                                          /extra/substituted/analogous items and recommend for technical approval along with
                                                                                          admissibility and unit rate. The recommendations of committee shall be put up to
                                                                                          Regional ED through HOP for approval of rates .ED of the region shall approve the
                                                                                          quantities and rates up to the powers delegated to CMD.-
                                                                                          (d) Pending technical approval of ED, HOP is authorised to release the provisional
                                                                                          payment for the deviation in executed quantities of BOQ items not requiring rate
                                                                                          revision, the payment upto 75% of rates assessed by the project, for items i.e. new/
                                                                                          extra /substituted /BOQ item may be released by the project. Project shall ensure that
                                                                                          the proposal seeking technical approval along with recommendation of standing
                                                                                          committee be put up to CA at the earliest but not later than four months from date of
                                                                                          release of provisional payment subject of overall variation in any case should not
                                                                                          exceed the power delegated to CMD( refer annexure A Sr., No. 5 ( c ) to DOP).
                                                                                          (e) Financial implication shall mean additional value involved after considering all
                                                                                          positive and negative variations. However, where overall deviation is in negative, it is
                                                                                          to be approved by HOP not below the rank of GM. However the same variation in the
                                                                                          quantity should be brought to the notice of next higher authority not below the rank of
                                                                                          GM. In case of negative variation i.e. quantities not attaining the BOQ quantities, there
                                                                                          shall be no revision of rates except provided otherwise in the contract.
                                                                                          (f) Design Division shall take approval from Director (Technical) for issuance of
                                                                                          drawings which in its opinion are of major change in works like conceptual change in
                                                                                          layout /support system, slope stabilization etc.
                                                                     Page 12 of 25                                                                                            
                                                                                                                                                                       Section‐I, DOP‐2019 
 
    Sl. No.          Subject matter of Delegation             E.D.      C.G. M./   D.G.M.          Sr.                                                Remarks
                                                                         G.M.                  Manager
      (1)                         (2)                         (3)         (4)          (5)         (6)                                                     (7)
 
     10.1     Technical approval and approval for rates   Full Powers                                         Regional ED will exercise the powers upto the powers delegated to CMD as per
              for above                                                                                       procedure given at Serial No.10 above.
                                                                                                              Director shall accord Technical approval for variations to be approved by COD/ BOD,
                                                                                                              irrespective of the Competence to award the contract.
     10.2     Approval of overall deviation statement                                                         10.2 (a) Based upon technical approval and rate approved by CA against 10.1 above,
                                                                                                              the project shall prepare the deviation statement with reasons thereof as per the
                                                                                                              approved rates and submit it along with recommendations for approval of CA. Cases
                                                                                                              requiring the approval of BOD, ED shall approve deviation upto the powers delegated
                                                                                                              and will recommend the proposal to Contract division, CO for obtaining approval of
                                                                                                              competent authority for deviation and subsequent change order in terms of delegation
                                                                                                              alongside.
                                                                                                              (b) These powers will be exercised in consultation with associate finance. The powers
                                                                                                              against 10.2.2 will be exercised for supply and installation contract and powers against
                                                                                                              10.2.3 will be exercised in the case of turnkey contract, where provision for ceiling on
                                                                                                              contingencies are already built in the contract and 10.2.4 will be exercised for all item
                                                                                                              rate / unit price contracts.
                                                                                                              (c) In respect of civil works and supply cum erection packages awarded by corporate
                                                                                                              office and executed at site, these powers will be exercised by the site authorities as
                                                                                                              per delegation alongside.
                                                                                                              (d) All variances due to variations in quantity / rate and due to extra & substituted item
                                                                                                              shall be reported in a quarterly management report by respective projects through
                                                                                                              Regional ED to Cost Engineering of corporate office. PMSG shall monitor and ensure
                                                                                                              the submission of report. Non Submission of quarterly Deviation Statement shall be
                                                                                                              reported to the management by PMSG through exception report.
                                                                                                              (e) A copy of the change order as per 10.2 issued by the project shall be sent to Cost
                                                                                                              Engineering Division with copy to contract /design and Corporate Finance
                                                                                                              (f) The Corporate Cost Engineering division shall submit to CMD and D(F) through
                                                                                                              D(T)/ D (Proj.), a quarterly report of project wise cost variations with brief reasons, with
                                                                                                              a copy to Planning Division for initiating action wherever required for seeking approval
                                                                                                              of the Competent Authority.
                                                                                         Page 13 of 25                                                                                      
                                                                                                                                                                                     Section‐I, DOP‐2019 
 
    Sl. No.            Subject matter of Delegation                 E.D.           C.G. M./   D.G.M.          Sr.                                             Remarks
                                                                                    G.M.                  Manager
      (1)                           (2)                             (3)              (4)          (5)         (6)                                                  (7)
 
    10.2.3    Turnkey contracts where overall contingency Full powers         Full powers                                The New rates wherever applicable shall be approved by ED of the region.
              limit is specified covering Quantity variation   up to          up to 50%
              without rate revision and extra & substituted    overall        of
              items.                                           contingency contingency
                                                               limit of the   limit of the
                                                               contract       contract
    10.2.4    Rural Electrification Works                      Full Powers    2% of the                                  10.2.4 These powers shall be exercised by the respective ED of the Rural
              Due to Design and/or Site requirement or         subject to     Contract                                   Electrification Works.
              any other valid reason in Supply &               remarks        sum                                        The new rates wherever applicable shall be approved by ED of the Region.
              installation RE contracts.                       column at                                                 These powers shall be subject to prior approval of Revised Cost Estimate (RCE) by
                                                               serial no.                                                the Competent Authority (by NHPC/REC/Monitoring Committee as per guidelines of
                                                               10 above.                                                 MOP for RE Works).
                                                                                                    Page 14 of 25                                                                               
                                                                                                                                                                                         Section‐I, DOP‐2019 
 
    Sl. No.          Subject matter of Delegation               E.D.        C.G. M./      D.G.M.            Sr.                                                Remarks
                                                                                G.M.                    Manager
      (1)                           (2)                         (3)             (4)             (5)            (6)                                                  (7)
 
                                                                                                  Page 15 of 25                                                                                   
                                                                                                                                                                                           Section‐I, DOP‐2019 
 
    Sl. No.          Subject matter of Delegation                  E.D.        C.G. M./        D.G.M.          Sr.                                               Remarks
                                                                                 G.M.                      Manager
      (1)                          (2)                             (3)           (4)               (5)         (6)                                                    (7)
 
      12      Extension in completion period and levying     -             -               -               -              These powers shall be exercised as per the guidelines issued in this regard
              of liquidated damages                                                                                       • The cut-off date for consideration of hindrance for evaluation of time extension shall
12.1 a) Extension in completion period for Full Powers Full Powers be upto the original contract completion/ subsequent approved time extension.
                                                                                                     Page 16 of 25                                                                                   
                                                                                                                                                                                              Section‐I, DOP‐2019 
 
    Sl. No.          Subject matter of Delegation                     E.D.         C.G. M./         D.G.M.          Sr.                                                     Remarks
                                                                                    G.M.                        Manager
      (1)                           (2)                               (3)            (4)                (5)         (6)                                                           (7)
 
              (b) Modification in the Terms of Tenders            Time extensions for bid submission etc. during the tendering process, shall be decided by the authority competent for call of tenders. For
              including extension of bid submission, date,        other modifications, before opening of Tenders, the powers shall be exercised by the authority competent for call of tenders. After opening
              payment terms, time for performance,                of tenders, in case of proprietary items/ OEMs modifications shall be approved by authority competent for call of tenders and for tenders
              specification etc. After call and before the        other than proprietary items/OEMs, the modifications shall be approved by next higher authority for call of tenders except in the cases falling
              award of Tender:                                    in the powers of ED.
                                                                  In respect of Tenders to be approved by CMD/ Board, ED (Contracts), for cases dealt at C.O. /Regional ED, for cases dealt at Projects/Power
                                                                  Stations/RO shall be competent to approve the modifications in the tender documents after receipt of same from the concerned Divisions.
      14      Modification in terms of Contract.                                                                               14. Modification of terms shall be made only as a last resort to enable the work being
                                                                                                                               carried out.
     14.1     Having no financial implication                     Full Powers   Full Powers     -               -
                                                                                                                               These powers can be exercised in the Project/Corporate office, wherever the contract
                                                                                                                               is being operated.
     14.2     Approval of Manufacturers /sub-                     Full powers   Full Powers                                    14.2       E.D       /HOP   of   the   concerned     project   shall       approve   the   proposed
              contractors/vendors as per the contract                           in respect of                                  addition/substitution for contracts awarded at Regional/ Project level respectively. In
              terms and addition or substitution in any                         contract                                       case of contracts awarded from C.O., the proposed addition/substitution shall be made
              existing list of manufacturers /                                  approved                                       by Contracts Division after technical vetting of it by the respective Design Division.
              subcontractors/ vendors.                                          by himself
                                                                                or lower                                       This clause is applicable only where there is no additional financial implication.
                                                                                authority.
      15      Acceptance of stores under deviation in             Full powers   Full Powers                     -              15 (a) These powers shall be exercised by the indenting Department.
              specifications                                                                                                   b) Cost compensation on account of such deviation in specifications, if any, shall be
                                                                                                                               worked out and/or negotiated by a Committee constituted as per Annexure-
                                                                                                                               III/Annexure-IV as the case may be Change order based on such recommendations
                                                                                                                               of the Committee shall be approved as per delegation under clause 10.2.2 or 10.2.3
                                                                                                                               and 10.2.4 in case of RE works.
      16      a)     Sanction       for      disposal        of                                                                As per the approved Disposal Policy.
              surplus/unserviceable/      obsolete      items,
              equipments and spares
              Disposal including administrative approval                           Extent of Power                             Officer Authorised to exercise powers subject to approved Disposal Policy of the
              of:                                                                                                              Corporation.
                                                                                                          Page 17 of 25                                                                                               
                                                                                                                                                                                                               Section‐I, DOP‐2019 
 
    Sl. No.          Subject matter of Delegation                    E.D.        C.G. M./        D.G.M.          Sr.                                               Remarks
                                                                                   G.M.                      Manager
      (1)                            (2)                             (3)            (4)              (5)         (6)                                                    (7)
 
              (v) New surplus spare parts(imported as well                          Full Powers                             Head of the Project/Liaison Office /Services Division/POS in C.O. not below the rank
              as indigenous) of various plants, equipments                                                                  of GM.
              and vehicles
              (vi) Approval for calling of tenders for 5 Crore                 2 crore       -               -              The power at column no. 2 shall be exercised by HOP not below the rank of GM.
              disposal / issue of letter of award including
              administrative   approval    for   disposal   of
              surplus, old unused steel.
              b) Disposal of Scrap & Misc. Items not             Full powers to Head of the Project not below the           This should be as per duties and responsibilities for disposal of machinery
              covered by Disposal Policy.                        rank of GM and Head of Division in case of C.O.            instrument/equipment/     material   etc.   as        per   Part-I       of   Office   Order    no.
                                                                                                                            PIE/CO/100/D&R/1545 dated 03.06.03 and amended from time to time.
                                                                                                                            Reserve price will be fixed by the Committee comprising the officers as indicated at
                                                                                                                            Sr. No-5 of Annexure –II.
                                                                                                                            IT&C items shall be disposed as per IT&C Policy.
                                                                                                       Page 18 of 25                                                                                             
                                                                                                                                                                                                          Section‐I, DOP‐2019 
 
    Sl. No.          Subject matter of Delegation                E.D.        C.G. M./         D.G.M.          Sr.                                                  Remarks
                                                                               G.M.                       Manager
      (1)                           (2)                           (3)           (4)               (5)            (6)                                                    (7)
 
              c) Transfer of construction plant, equipment   Full powers to Head of the CEP not below the rank Subject to fulfilment of all formalities as per following procedures:
              (as specified in Annexure – III of disposal    of GM.Within the region, full powers to ED of the 1. Procedure for transfer of Construction plant and equipment as per DOC. No.
              policy – page 15) and vehicles within NHPC     Region under intimation to CEP Division.                      QSP/CEP/75/02 with effective date of 17.06.2002 and as amended from time to time.
              Projects                                                                                                     2. General procedure for transfer of surplus equipment and spares within the units of
                                                                                                                           NHPC for departmental use (page IV of Directory of Construction Plants & Equipment
                                                                                                                           sixth edition, December, 2003) or as amended from time to time.
      17      Calling of tenders and award of work for                                                                     17(i) Subject to approval of Cost estimates and adherence to tendering procedures.
              replacement, repair & maintenance works.                                                                     Cost estimates are to be approved at the level of authority to award, delegated herein
              A. PLANT/ STRUCTURE                                                                                          for open tender.
              S & Equipment                                                                                                (ii) Justifications are to be recorded in respect of limited/single tender / work order.
              i) Open tender                                 15 Crore      2.5 Crore      40 Lac          15 Lac           (iii) Plant/Structures shall mean all Permanent equipment and appurtenant civil
              ii) Limited tender                             5 Crore       75 Lac         15 Lac          7 Lac            /fabricated structures of the Projects. Infrastructure works shall mean all facilities
              iii) Single tender including negotiated tender. 3 Crore      30 Lac                                          required for construction and operation of the Project /Corporate Office including
                                                                                                                           roads, buildings and bridges.
              iv) Spot Work Order                            30 Lac        7 Lac          75,000          40,000
                                                                                                                           (iv) Remarks against Sl. No.1 and 2 to the extent as applicable, shall apply to this
              B. INFRASTRUCTURE WORKS
                                                                                                                           delegation also.
              i) Open Tender                                 10 Crore      2 Crores       70 Lac          40 Lac
                                                                                                                           (v) Alongside DOP clause is applicable for power station/projects/RO/Corporate
              ii) Limited tender                             2 Crore       40 Lac         7 Lac           3 Lac
                                                                                                                           Office/units for the Repair & maintenance works and is not applicable for supply/
              iii) Single tender including negotiated tender. 1.5 Crore    15 lac         -               -
                                                                                                                           service contracts.
              iv) Spot Work Order                            30 Lac        7 Lac          70,000          40,000
      18      Approval for indenting of stock item by        Full powers   Full Powers    30 Lac          15 Lac           18. These powers shall be exercised by Materials Management to maintain minimum
              materials deptt.                                                                                             stocks as per norms to prevent stock out.
      19      Approval of indent for issue of materials      Full powers   Full Powers    Full            Full             19 (i). For non-stipulated items or items in excess of estimates, approval of engineer
              from stores.                                                                Powers          Powers           in charge not below the rank of GM will be obtained.
                                                                                                                           19 (ii). Issue of non – stipulated materials to the contractors is to be avoided and it may
                                                                                                                           be allowed only in case of exigencies, where the requisite material cannot be arranged
                                                                                                                           by the contractor in reasonable time and it might delay the work. In the event of issue
                                                                                                                           of non – stipulated materials, the issue rate should be the highest of the following three
                                                                                                                           rate formula-
                                                                                                    Page 19 of 25                                                                                       
                                                                                                                                                                                                 Section‐I, DOP‐2019 
 
    Sl. No.          Subject matter of Delegation                     E.D.         C.G. M./          D.G.M.          Sr.                                                  Remarks
                                                                                     G.M.                        Manager
      (1)                           (2)                               (3)             (4)                (5)            (6)                                                   (7)
 
                                                                                                                                  a. The element of cost of material in the rate quoted by the contractor for the finished
                                                                                                                                  item.
                                                                                                                                  b. The market rate prevailing
                                                                                                                                  c. The stock issue rate of the corporation.
      20      Authorizing payments against Bills for works/ Full powers          Full Powers     Full            Full             20 (i) Refer point no. 24 of guidelines for exercising Delegation of Powers.
              Supplies/          Services              (advance                                  Powers          Powers           (ii) Powers for release of payments shall be exercised by Engineer In Charge (EIC)
              running/ final Bills) within Contract.                                                                              only.
      21      Loan of Materials and plant and tools to and 50 lac p.a.           10 lac p.a.     -               -                21. Subject to adequate security being obtained
              from other Public Sector Undertakings/ Govt.
              departments
      22      Power to hire equipment /Machinery from             1 Crore p.a.   5 Lac p.a.      50000           25,000           22(i) Rate of hire charges should be comparable with those fixed in the project for
              contractors/ private agencies                                                      p.a.            p.a.             similar equipment when hired out to contractors/private agencies.
                                                                                                                                  (ii) The period of hiring shall not be more than 15 days at a stretch unless compelling
                                                                                                                                  circumstances demand for extension of the period.
                                                                                                                                  (iii) A clearance from Incharge of the concerned division in the Project regarding
                                                                                                                                  non-availability of the equipment should be obtained before hiring from the contractors/
                                                                                                                                  private agencies.
                                                                                                                                  (iv) Hiring of machines from the contractors/private agencies should be more
                                                                                                                                  economical than transporting a departmental machine even when the same is
                                                                                                                                  available.
    23.(a)    Approval to the encashment of Bank                  Full Powers    Full Powers     Full            Full             DGM/Sr. Mgr. will exercise powers on being designated as Engineer-in-Charge.
              Guarantee                                                                          Powers          Powers
    23 (b)    Approval for acceptance of Bank                     The Bank Guarantees submitted by the Bidders/Contractors will be accepted by the Engineer-in–Charge if already nominated. Till Engineer-
              Guarantees                                          in-charge is nominated, the Bank Guarantees will be accepted by the Officer authorised to sign the Contract.
      24      Termination/foreclosure of contract.                Full Powers    Full Powers                                      1. In terms of contract provision
                                                                  in respect     in respect of
                                                                  of contacts    contacts                                         2. Power of GM can be exercised only in case he is HOP.
                                                                  awarded by     awarded by
                                                                  him or                                                          3. Recommendations of engineer in charge is required with proper justification.
                                                                                                           Page 20 of 25                                                                                     
                                                                                                                                                                                                      Section‐I, DOP‐2019 
 
    Sl. No.            Subject matter of Delegation                  E.D.        C.G. M./    D.G.M.          Sr.                                                Remarks
                                                                                   G.M.                  Manager
      (1)                             (2)                             (3)           (4)          (5)         (6)                                                    (7)
 
              b) Identification and selection of vendors         Full Powers   Full Powers                              The enquiry selection, negotiations and placement of trial order etc. shall be in
              based on response to advertisement cited at                                                               accordance with the approved policy/ guidelines that may be issued from time to time.
              25 (a) or otherwise for reasons recorded in
              writing.
     26-A     According administrative approval, calling of                                                             i) Powers for administrative approval shall be subject to availability of provision in the
              tender and award of service contracts                                                                     approved Annual Plan / O&M Budget /Revenue Budget of the FY as applicable to the
              related to                                                                                                unit/location. Further administrative approval shall be accorded by HOP not below the
                                                                                                                        rank of GM in respect of clause 26-A.
                                                                                                                        ii) In respect of Clause 26-A: Technical sanction to the estimate shall be accorded by
                                                                                                                        the competent authority as per delegation alongside upto the level of CGM/GM. For
                                                                                                                        the cases beyond the delegated power of CGM/GM, Technical sanction to the estimate
              i) Hiring of Consultancy /Services for various 50 lac            10 lac                                   shall be accorded by concerned ED.
              purposes         including     Geological     &                                                           iii) In respect of Clause 26-B: Technical sanction to the estimate shall be accorded by
              Geotechnical works Soil/Rock/Construction                                                                 the competent to award against open tender upto the level of CGM/GM. For the cases
              Material       Testing/EIA/EMP      studies/R&D                                                           beyond the delegated power of CGM/GM, Technical sanction to the estimate shall be
              works/     conducting    Model     Studies   and                                                          accorded by concerned ED. Estimates in such cases are to be prepared on the
              specialized      tests/tests     from   external                                                          minimum wages and following other related guidelines issued by HR Department from
              institutions     for    investigations/construct                                                          time to time.
              ion/O&M/R&D schemes & for any other                                                                       iv) Proposals for hiring of services for housekeeping / security shall be accompanied
              purpose                                                                                                   by a certificate to the effect that regular manpower of the category and nature of
              ii) Hiring of services of Surveyor/ Valuer         20 Lac        5 Lac.                                   services involved in the proposal is not available in the concerned unit.
                                                                                                   Page 21 of 25                                                                                    
                                                                                                                                                                                             Section‐I, DOP‐2019 
 
    Sl. No.          Subject matter of Delegation                     E.D.     C.G. M./        D.G.M.          Sr.                                               Remarks
                                                                                 G.M.                      Manager
      (1)                           (2)                               (3)         (4)              (5)         (6)                                                    (7)
 
              iii) Hiring of services of Professionals/ 2 Crore              30 Lakh       -               -              v) Division entrusted with the Contract & Procurement functions at the unit/location
              Consultants/ Service Engineers/ Specialised                                                                 shall be responsible for the tendering and award formalities of cases falling in the
              Testing   Equipment     etc.   from   Original                                                              competency of HOP and below. However, for cases falling beyond the competency of
              Equipment Manufacturers (OEMs) for –                                                                        HOP, the tender is to be processed at unit/location but the approval of tender
              Installation/ Testing/ Replacement/ Repair &                                                                documents including the Qualification Requirement (QR) and constitution of Tender
              Maintenance & any other such works related                                                                  Evaluation Committee(TEC) shall be accorded by concerned Executive Director.
              to the Plants & Equipment                                                                                   vi) In respect of cases at Corporate Office, beyond the power of ED, approval of QR
                                                                                                                          shall be accorded by ED of indenting department. However, the tendering process
26 B Hiring of services for various purposes including approval of tender document is to be carried out by the Contract Division.
including Security, Housekeeping Operation Concerned division shall forward the case (along with administrative approval,
& Maintenance etc. technical sanction and special terms and conditions of contract) to Contract Division.
              a) Administrative Approval                       Full Power    1.5 Crores                                   vii) Tenders shall be awarded as per financial limit given alongside. However,
                                                                                                                          procedure for tendering shall be followed as per remarks given in serial no-2 of
              b) Calling of Tender & Award
                                                                                                                          section-I within policy guidelines as applicable.
i) Open Tender 10 Cr 1.5 Cr viii) Award of Contract on single tender/work order basis shall be subject to compliance
              ii) Limited Tender                               4 Cr          50 Lacs                                      of Guidelines for award of contract on nomination basis.
                                                                                                                          ix) Extension of time for contracts under 26-A (i) & (ii) shall be granted as per
              iii) Single Tender including negotiated tender 2 Cr            25 Lacs                                      delegation under Serial No. 12 of this section.
     26 C     Approval of Variations during execution of       Full Powers   Up to 20%                                    i) Variation on account of extension of contract period due to non-finalization of tenders
              contracts due to scope / quantity variations                   of contract                                  shall normally be avoided. Advance action shall be taken before expiry of extant
              /Extra substituted items/ due to extension of                  value                                        contract        allowing   adequate     lead          time       for       tender    processing.
              contract period                                                                                             However, if necessitated by otherwise required due to unavoidable circumstances,
                                                                                                                          such extension shall not be allowed for more than once and limited to 20% of the
                                                                                                                          original contract period with the approval of HOP not below the rank of GM. In
                                                                                                                          exceptional cases, having valid justifications, subsequent extensions can be granted
                                                                                                                          by Executive Director.
                                                                                                                          ii) Approval of variations due to extension of contract period shall deem to include
                                                                                                                          approval for time extension of the contract also.
                                                                                                     Page 22 of 25                                                                                            
                                                                                                                                                                                                       Section‐I, DOP‐2019 
 
    Sl. No.          Subject matter of Delegation               E.D.         C.G. M./     D.G.M.          Sr.                                                Remarks
                                                                                 G.M.                 Manager
      (1)                          (2)                           (3)             (4)          (5)         (6)                                                     (7)
 
                                                                                                                     iii) Rate Analysis of extra / deviated /substituted items if necessary shall be carried out
                                                                                                                     through a committee as per Ann-IV and shall be approved by HOP. Thereafter, the
                                                                                                                     variation statement on the basis of approved rates shall be processed for approval of
                                                                                                                     competent authority as per sub- delegation given alongside.
      27      Waival for witnessing pre dispatch            Head of the Department of Quality Assurance &            Reasons should be recorded for waival in consultation with respective Design Division.
              inspection/testing of Plants/ Equipments at   Inspection Division not below the rank of Chief
              Manufacturer’s Works (on shore/off shore)     General Manager/General Manager
              as incorporated in the contract/detailed
              quality assurance plan.
      28      Authorization for signing of Contract         Full powers    Full powers                               In case of contracts awarded at Corporate Office level, HOD of Contracts (Civil/E&M
                                                            to authorize   to authorize                              Division) shall have full powers to authorize an Officer not below the level of General
                                                            an Officer     an Officer                                Manager for signing Contract Agreement on behalf of the Corporation
                                                            not below      not below
                                                            the level of   the level of
                                                            GM/ DGM        Sr.
                                                            for signing    Manager for
                                                            of Contract    signing of
                                                            Agreement      Contract
                                                            on behalf of   Agreement
                                                            Corporation    on behalf of
                                                            for the        Corporation
                                                            Contracts      for the
                                                            awarded by     Contracts
                                                            him or         awarded by
                                                            lower          him or lower
                                                            authority      authority.
      29      Release of Advance Payment for purposes       20 lac                                                   1) 2 lac for HOP not below the rank of GM
              like advances to Government Department                                                                 2) Subject to CVC Guidelines, if any.
              covered under Annexure- VI, Purchases of                                                               3) The advance is to be released in terms of contract or LOA after recording the proper
                                                                                                                     reasons and time line for adjustment by the approving authority.
                                                                                                Page 23 of 25                                                                                     
                                                                                                                                                                                           Section‐I, DOP‐2019 
 
    Sl. No.          Subject matter of Delegation                E.D.        C.G. M./     D.G.M.          Sr.                                              Remarks
                                                                               G.M.                   Manager
      (1)                          (2)                           (3)            (4)           (5)         (6)                                                   (7)
 
              Vehicles, Purchases of Books, Advocates,                                                               4) Efforts should be made to get the advance secured.
              Chartered Accountant etc.                                                                              5) Proper utilization of advances be ensured (deliverables/ reports/ expenditure
                                                                                                                     statement and work completion certificate by the concerned).
                                                                                                                     6) Approving authority shall review all such cases on quarterly basis.
      30      Release of interest free advance/ down         Upto Rs.3.0
              payment with or without bank guarantee for     crores
              procurement of equipments/ spares/
              services of experts, from Original Equipment
              Manufacturers (OEM)
      31      Waiver of EMD in case of tenders for           Full Powers   Full powers
              supply/Repairs/Services (i.e. for                            in cases
              replacement and maintenance of original                      where
              /existing equipment and spares) by Original                  award of
              Equipment Manufacturers (OEMs) and                           tender falls
              award of single tender on nomination basis                   in their
              to Government agencies , Autonomous                          competency
              bodies controlled by Government , Public                     or that of
              Sector Undertakings and institutes referred                  lower
              in Annexure-VI of DOP                                        authorities
      32      Local/Spot procurements of services on         1.50 Crore    15 lac                                    a) Spot procurement of services should not form a part of a regular procurement of
              grounds of urgency for conducting various                                                              services and services so procured should be for specific purpose/ occasion.
              camps/events/functions etc.                                                                            b) The list of services to be procured, with estimated price shall be approved by the
                                                                                                                     competent authority, as per delegation alongside.
                                                                                                                     c) Indenting Deptt. should procure the services after a market survey and after
                                                                                                                     determining the reasonableness of the price, which shall be recorded accordingly.
                                                                                                                     d) Procurement of services beyond Rs. 2.0 lac shall be made by a committee
                                                                                                                     comprising one member each from the indenting Department, Proc. Division & Finance
                                                                                                                     Division. The Committee shall not have executives below the level of E-3
                                                                                                Page 24 of 25                                                                                  
                                                                                                                                                                                        Section‐I, DOP‐2019 
 
    Sl. No.   Subject matter of Delegation   E.D.   C.G. M./   D.G.M.          Sr.                                               Remarks
                                                     G.M.                  Manager
      (1)                 (2)                (3)      (4)          (5)         (6)                                                    (7)
 
                                                                                          e) The authority for exercising these powers shall be decided on the basis of total
                                                                                          procurement requirement of services for particular occasion. Such requirements shall
                                                                                          not be broken or done in instalments to bring the value within the powers of the lower
                                                                                          authority.
                                                                                          f) After procurement of services, a statement of particulars of procurement shall be
                                                                                          submitted to the approving authority by the indenting Deptt. A copy of this report shall
                                                                                          be sent to Finance Cell for clearing the advance.
                                                                                          g) Administrative Approval of HOP not below the rank of GM is required.
                                                                     Page 25 of 25                                                                                   
                                                                                                                                                              Section‐I, DOP‐2019