Quantity Computation
Quantity Computation
CF QTY
Excav. QTY
COLUMN FOOTING
MAT'LS.
TOTAL
QUANTITY UNIT COST PER UNIT
COST
31.10 bags 250.00 / bag 7,776.00
1.73 cu-m 500.00 / cu-m 864.00
3.46 cu-m 700.00 / cu-m 2,419.20
19.20 pc(s) 350.00 / pc 6,720.00
-
2.17 kg(s) 75.00 / kg 163.02
0.86 cu.m 700.00 / cu-m 604.80
COLUMN
MAT'LS.
TOTAL
QUANTITY UNIT COST PER UNIT
COST
21.60 bags 250.00 / bag 5,400.00
1.20 cu-m 500.00 / cu-m 600.00
2.40 cu-m 700.00 / cu-m 1,680.00
11.60 pc(s) 350.00 / pc 4,060.00
28.80 pc(s) 150.00 / pc 4,320.00
2.45 kg(s) 75.00 / kg 183.40
COLUMN
TOTAL
MAT'LS. QUANTITY UNIT COST PER UNIT
COST
.5" thk Plywood 5.00 pcs 350.00 / bag 1,750.00
2x2 Lumber 60.00 bd.ft 23.00 / bd.ft 1,380.00
2x3 Lumber 350.00 bd.ft 25.00 / bd.ft 8,750.00
CWN Assorted 10.00 kg(s) 80.00 / kg 800.00
0.00
QUANTITY COMPUTATION:
FRAME
TOTAL
MAT'LS. QUANTITY UNIT COST PER UNIT
COST
3" dia. GI Pipe 15.87 length(s) 1,500.00 / lengtth 23,800.00
1.5" dia. GI Pipe 30.98 length(s) 1,000.00 / lengtth 30,983.33
.4mx.4m Base plate 24.00 pc(s) 300.00 / pc 7,200.00
16MM dia. Mbolts 24.00 pc(s) 150.00 / pc 3,600.00
12MM dia. Mbolts 24.00 pc(s) 75.00 / pc 1,800.00
Gusset plate 1.00 pc(s) 1,500.00 / kg 1,500.00
Welding Rod 5.00 boxes 3,500.00 / box 17,500.00
Welding Machine 15.00 days 1,300.00 / day 19,500.00
Bar Cutter 10.00 days 300.00 / day 3,000.00
Crane 4.00 days 5,000.00 / day 20,000.00
FRAME
TOTAL
MAT'LS. QUANTITY UNIT COST PER UNIT
COST
LATEX Paint 5.00 GAL 650.00 / GAL 3,250.00
ROOF Paint 3.00 GAL 500.00 / GAL 1,500.00
TINTING COLORS 3.00 GAL 350.00 / GAL 1,050.00
ROLLER Brush 2.00 sets 120.00 / set 240.00
PAINT BRUSH 5.00 pc(s) 65.00 / pc 325.00
Polytuff 3.00 GAL 590.00 / GAL 1,770.00
7.14 1
6.97 1
Republic of the Philippines
Autonomous Region in Muslim Mindanao
Province of Maguindanao
Office of the Provincial Engineer
Buluan, Maguindanao
60 CD
Construction of 4" CHB Perimeter Fence
(11) Implementing Procedure:
By Contract
Foreman, Mason, Steelman, Carpenter, Laborer Bagger Mixer, Bar Cutter, Concrete Vibrator
ITEM I - EARTHWORKS
a.) Structure Excavation 3.71% 12.10 cu.m 1,074.20 P 12,993.48
b.) Backfill 0.38% 4.84 cu.m 272.10 P 1,316.52
c.) Gravel Bedding 0.46% 0.86 cu.m 1,855.00 P 1,602.72
-
ITEM II - CONCRETE WORKS -
a.) Footing, Column 16.95% 5.86 cu.m 10,130.39 P 59,323.54
-
ITEM III - MASONRY WORKS -
a.) Setting of CHB 4.19% 8.20 sq.m 1,786.31 P 14,647.72
b.) Plaster Finish 2.39% 21.32 sq.m 391.98 P 8,357.04
-
ITEM IV - CARPENTRY WORKS -
a.) Forms and Scaffoldings 5.41% 435.84 bd.ft. 43.47 P 18,946.44
-
ITEM V - METAL WORKS 53.90% 1.00 lot 188,663.04 P 188,663.04
A. Direct Cost
1. Mobilization/Demobilization
2. Materials -------------------------------------------------------------------------------------------------------------------- 64.39% P 225,365.00
3. 3.1 Supply Delivery
3.2 Testing of Materials
4. Labor ------------------------------------------------------------------------------------------------------------------------- 18.09% P 63,300.00
4.1 Direct Cost
4.2 Leaves
4.3 GSIS/SSS
4.4 Medicare
4.5 State Insurance
5. Equipment Expenses ----------------------------------------------------------------------------------------------------- 4.86% 17,000.00
6. Supervision
7. Miscellaneous (Fuel & Lubricant)
8. Contingencies
B. Indirect Cost
1. Profit (10% to 15% of A1 to A7) ----------------------------------------------------------------------------------------- 4.37% P 15,283.25
2. Tax (3% of A to B1) 0.97
3. VAT --------------------------------------------------------------------------------------------------------------------------- 5.66% P 19,807.09
4. OCM (7% to 12% of A1 to A7) MARK UP & VAT --------------------------------------------------------------------- 2.64% P 9,244.66
SUB-TOTAL
(15.3) III - CONTINGENCIES/RESERVES
Prepared by:
Recommending Approval:
ELMER T. BARNEDO
Drafstman II
ABDULWAHAB V. TUNGA
Provincial Engineer
Checked by:
Approved:
JAYPEE P. PIANG
Engineer IV
ESMAEL G. MANGUDADATU
Provincial Governor
DETAILED ESTIMATES
ITEM I - EARTHWORKS
Excavator = 1 unit
Output/Day = 240.0 cu.m
No. of Days = 12.10 = 0.05
1 x 240.0 Say 1 day(s)
Labor:
1 - Const. Foreman for 1 day(s) @ P 350.00 /day P 350.00
5 - Laborer(s) for 1 day(s) @ P 200.00 /day P 1,000.00
Labor Cost P 1,350.00
Equipment:
1 - Excavator for 1 day(s) @ P 10,000.00 /day P 10,000.00
Equipment Cost P 10,000.00
12,993.48
Unit Cost =
12.10
P 1,074.20
cu.m
b.) Backfill
Quantity = 4.84 cu.m
No. of Laborer = 4
Output/Day = 2.0 cu.m
No. of Days = 4.84 = 0.60
4 x 2.0 Say 1 day(s)
Labor:
1 - Const. Foreman for 1 day(s) @ P 350.00 /day P 350.00
4 - Laborer(s) for 1 day(s) @ P 200.00 /day P 800.00
Labor Cost P 1,150.00
1,316.52
Unit Cost =
4.84
P 272.10
cu.m
c.) Gravel Bedding
Quantity = 0.86 cu.m
Materials:
Labor:
1 - Const. Foreman for 1 day(s) @ P 350.00 /day P 350.00
2 - Laborer(s) for 1 day(s) @ P 200.00 /day P 400.00
Labor Cost P 750.00
1,602.72
Unit Cost =
0.86
P 1,855.00
cu.m
Materials:
Labor:
1 - Const. Foreman for 3 day(s) @ P 400.00 /day P 1,200.00
1 - Mason(s) for 3 day(s) @ P 350.00 /day P 1,050.00
1 - Steelman for 3 day(s) @ P 300.00 /day P 900.00
4 - Laborer(s) for 3 day(s) @ P 250.00 /day P 3,000.00
Labor Cost P 6,150.00
Equipment:
1 - Concrete Vibrator for 2 day(s) @ P 1,500.00 /day P 3,000.00
1 - Concrete Mixer (1-Bagger) for 2 day(s) @ P 2,000.00 /day P 4,000.00
Equipment Cost P 7,000.00
59,323.54
Unit Cost =
5.86
P 10,130.39
cu.m
Materials:
4.28 10 bags - Portland Cement @ P 250.00 /bag P 2,500.00
0.36 2 cu.m - Sand (Washed & Screened) @ P 700.00 /cu.m P 1,400.00
102.50 250 pcs - 4"x8"x16" CHB @ P 12.00 /pc P 3,000.00
5.85 12 pcs - 12mmØ x 6.0m RSB @ P 210.00 /pc P 2,520.00
1.26 5 kgs - Tie Wire @ P 75.00 /kg P 375.00
Material Cost P 9,795.00
Labor:
1 - Const. Foreman for 2 day(s) @ P 400.00 /day P 800.00
1 - Mason(s) for 2 day(s) @ P 350.00 /day P 700.00
3 - Laborer(s) for 2 day(s) @ P 250.00 /day P 1,500.00
Labor Cost P 3,000.00
14,647.72
Unit Cost =
8.20
P 1,786.31
sq.m
Materials:
5.09 10 bags - Portland Cement @ P 250.00 /bag P 2,500.00
1.34 4 cu.m - Sand (Washed & Screened) @ P 700.00 /cu.m P 2,800.00
Material Cost P 5,300.00
Labor:
1 - Const. Foreman for 2 day(s) @ P 400.00 /day P 800.00
1 - Mason(s) for 2 day(s) @ P 350.00 /day P 700.00
1 - Laborer(s) for 2 day(s) @ P 250.00 /day P 500.00
Labor Cost P 2,000.00
8,357.04
Unit Cost =
21.32
P 391.98
sq.m
Materials:
6 pcs. - 4' x 8' x 1/2" Thk. Plywood @ P 650.00 /pc P 3,900.00
100 bd.ft - 2" x 2" Coco Lumber @ P 18.00 /bd.ft P 1,800.00
350 bd.ft - 2" x 3" Coco Lumber @ P 18.00 /bd.ft P 6,300.00
10 kgs. - CW Nails (Assorted) @ P 80.00 /kg P 800.00
Material Cost P 12,800.00
Labor:
1 - Const. Foreman for 3 day(s) @ P 400.00 /day P 1,200.00
1 - Carpenter(s) for 3 day(s) @ P 350.00 /day P 1,050.00
2 - Laborer(s) for 3 day(s) @ P 250.00 /day P 1,500.00
Labor Cost P 3,750.00
TOTAL DIRECT COST P 16,550.00
Profit (5% of TDC) P 827.50
OCM (3% of TDC) P 496.50
Materials:
20 length(s) - 3" dia. X 6.0m G.I. Pipe (SCH. 40) @ P 2,100.00 /length P 42,000.00
35 length(s) - 1.5" dia. X 6.0m G.I. Pipe (SCH. 40) @ P 1,200.00 /length P 42,000.00
6 pc(s) - 0.40mx0.40mx10mm Thk. Base plate @ P 600.00 /pc P 3,600.00
24 pc(s) - 16MM dia. Mbolts with Nuts & Washers @ P 500.00 /pc P 12,000.00
24 pc(s) - 12MM dia. Mbolts with Nuts & Washers @ P 350.00 /pc P 8,400.00
79.0815 6 pc(s) - 0.30mx0.30mx10mm Thk. Gusset plate @ P 350.00 /pc P 2,100.00
0.2 5 boxes - Welding Rod @ P 3,500.00 /box P 17,500.00
Material Cost P 127,600.00
Labor:
1 - Const. Foreman for 12 day(s) @ P 400.00 /day P 4,800.00
2 - Steelman/Welder for 12 day(s) @ P 350.00 /day P 8,400.00
8 - Laborer(s) for 12 day(s) @ P 250.00 /day P 24,000.00
Labor Cost P 37,200.00
Materials:
5 gal - Latex ( Boysen ) @ P 500.00 /gal P 2,500.00
5 gal - Roof Paint @ P 470.00 /gal P 2,350.00
3 cans - Assltd. Tinting Color @ P 60.00 /can P 180.00
5 sets - Roller Brush @ P 120.00 /set P 600.00
4 gal - Polytuff @ P 590.00 /gal P 2,360.00
8 gal - Paint Thinner @ P 320.00 /gal P 2,560.00
Material Cost P 10,550.00
Labor:
1 - Const. Foreman for 3 day(s) @ P 400.00 /day P 1,200.00
1 - Painter(s) for 3 day(s) @ P 350.00 /day P 1,050.00
2 - Laborer(s) for 3 day(s) @ P 250.00 /day P 1,500.00
Labor Cost P 3,750.00
Materials:
1 l.s. - Prefabricated Fiber Board Name Plate with Accessories @ P 20,000.00 /l.s. P 20,000.00
Material Cost P 20,000.00
Labor:
1 - Const. Foreman for 3 day(s) @ P 400.00 /day P 1,200.00
4 - Laborer(s) for 3 day(s) @ P 250.00 /day P 3,000.00
Labor Cost P 4,200.00
ITEM I - EARTHWORKS
a.) Structure Excavation 3.71% 12.10 cu.m 1,074.20 P 12,993.48
b.) Backfill 0.38% 4.84 cu.m 272.10 P 1,316.52
c.) Gravel Bedding 0.46% 0.86 cu.m 1,855.00 P 1,602.72
Prepared by :
Concurred :
1. CHB
Using 4" x 8" x 16" CHB - By Area Method
No. of CHB = (CHB Area) x (12.5) = 102.50 pcs.
21,600.00 pcs.
Note: 1 LN.m =
Using Class "B" mixture - By Area Method
CEMENT = (CHB Area) x (.522) = 4.28 bags Quantity By Ratio:
SAND = (CHB Area) x (.0435) = 0.36 cu-m.
Using 10mm dia. (60cm Vert. spacing @ every 3 layer Hor. Spacing) - By Area Method
Vert. Bars = (CHB Area) x (2.13) = 17.47
Hor. Bars = (CHB Area) x (2.15) = 17.63
35.10 m. long
Total No. Bars = 5.85 pcs.
1,235.00 pcs.
Using 30cm Cutting of GI tie wire (53meters/kg.)
Tie Wire = (CHB Area) x (.032) = 1.26 kgs.
57.00 kgs.
2. WALL FOOTING
Dimensions:
thickness = 0.15 m. Depth to bottom = 0.6 m
width = 0.40 m.
WF length = 4.10 m.
WF Qty. = 0.25 cu.m.
WF Qty. Excav. = 0.98 cu.m.
Using 12mm dia. (60cm Cross. spacing @ 3pcs. Long. ) - By Area Method
Vert. Bars = (WF Length) x (width) = 2.73
(Spacing)
Hor. Bars = (WF Length) x (3pcs.) = 12.30
15.03 m. long
Total No. Bars = 2.51 pcs. 352
3. CHB PLASTERING
Using 16 mm thk Plaster Class "B":
No. of side = 2 side/s
4. COLUMN FOOTING
thickness = 0.25 m nL = 4 pc(s)
width = 0.8 m nW = 4 pc(s)
length = 0.8 m Spacing = 0.2 m
No. of CF = 2.00 Depth to bottom = 1 m
Say 5 pc(s) Gravel THK. = 0.1 m
CF Quantity = 0.32 cu.m
Excavation Qty. = 1.28 cu.m
Gravel = 0.13 cu.m
5. COLUMN
height = 3.3 m nTies = 17.5 pc(s)
width = 0.3 m nMBars = 4 pc(s)
length = 0.3 m Spacing = 0.2 m
No. of Col = 2
Say 5 pc(s)
Col Quantity = 0.594 cu.m
LTies RSB = [(height / Spacing) x 2(W + L) x N)] = 6.60 pc(s) 10mm dia RSB
6 Say 637 pc(s)
Say
3,449.61
14,948.30
A. Direct Cost
1. Mobilization/Demobilization
2. Materials ------------------------------------------------------------------------------------------------------------------------------ 62.29% P 10,235,254.00
3. 3.1 Supply Delivery
3.2 Testing of Materials
4. Labor ----------------------------------------------------------------------------------------------------------------------------------- 18.07% P 2,969,500.00
4.1 Direct Cost
4.2 Leaves
4.3 GSIS/SSS
4.4 Medicare
4.5 State Insurance
5. Equipment Expenses
6. Supervision
7. Miscellaneous (Fuel & Lubricant)
8. Contingencies
B. Indirect Cost
1. Profit (10% to 15% of A1 to A7) -------------------------------------------------------------------------------------------------- 6.45% P 1,059,602.82
2. Tax (3% of A to B1) 0.97 2.46% 404,171.37
3. VAT ------------------------------------------------------------------------------------------------------------------------------------ 10.73% P 1,763,602.19
4. OCM (7% to 12% of A1 to A7) MARK UP & VAT ----------------------------------------------------------------------------- 0.00% P -
SUB-TOTAL
(15.3) III - CONTINGENCIES/RESERVES
Prepared by:
Recommending Approval:
ANTHONY S. KASAN
Engineer III
ABDULRAKMAN K. ASIM , PME
OIC-Provincial Engineer
Checked by:
Approved:
JAYPEE P. PIANG
Engineer IV, DPPD
ESMAEL G. MANGUDADATU
Provincial Governor
DETAILED ESTIMATES
ITEM I - EARTHWORKS
No. of Laborer = 10
Output/Day = 1.5 cu.m
No. of Days = 50.00 = 3.33 day(s)
10 x 1.5 Say 10 day(s)
Labor:
1 - Const. Foreman for 10 day(s) @ P 550.00 /day P 5,500.00
10 - Laborer(s) for 10 day(s) @ P 300.00 /day P 30,000.00
Labor Cost P 35,500.00
88,270.00
Unit Cost =
50.00
P 1,765.40
cu.m
b.) Backfill
Quantity = 37.50 cu.m
No. of Laborer = 7
Output/Day = 2.0 cu.m
No. of Days = 37.50 = 2.68 day(s)
7 x 2.0 Say 8 day(s)
Labor:
1 - Const. Foreman for 8 day(s) @ P 550.00 /day P 4,400.00
7 - Laborer(s) for 8 day(s) @ P 300.00 /day P 16,800.00
Labor Cost P 21,200.00
26,355.84
Unit Cost =
37.50
P 702.82
cu.m
c.) Earthfill
Quantity = 2,140.17 cu.m
No. of Laborer = 28
Output/Day = 2.0 cu.m
No. of Days = 2,140.17 = 38.22 day(s)
28 x 2.0 Say 38 day(s)
Materials:
550 load(s) - Filling Materials @ P 3,000.00 /load P 1,650,000.00
Material Cost P 1,650,000.00
Labor:
1 - Const. Foreman for 38 day(s) @ P 550.00 /day P 20,900.00
28 - Laborer(s) for 38 day(s) @ P 300.00 /day P 319,200.00
Labor Cost P 340,100.00
2,474,092.32
Unit Cost =
2,140.17
P 1,156.02
cu.m
ITEM II - CONCRETE WORKS
Materials:
Labor:
1 - Const. Foreman for 48 day(s) @ P 550.00 /day P 26,400.00
16 - Mason(s) for 48 day(s) @ P 400.00 /day P 307,200.00
15 - Steelman for 48 day(s) @ P 400.00 /day P 288,000.00
24 - Laborer(s) for 48 day(s) @ P 300.00 /day P 345,600.00
Labor Cost P 967,200.00
3,827,812.80
Unit Cost =
216.07
P 17,715.25
cu.m
Materials:
1,090 bags - Portland Cement @ P 260.00 /bag P 283,400.00
90 cu.m - Sand (Washed & Screened) @ P 950.00 /cu.m P 85,500.00
13,150 pcs - 4"x8"x16" CHB @ P 13.00 /pc P 170,950.00
6,600 pcs - 6"x8"x16" CHB @ P 15.00 /pc P 99,000.00
1,200 pcs - 12mmØ x 6.0m RSB @ P 223.00 /pc P 267,600.00
75 kgs - Tie Wire @ P 75.00 /kg P 5,625.00
Material Cost P 912,075.00
Labor:
1 - Const. Foreman for 42 day(s) @ P 450.00 /day P 18,900.00
15 - Mason(s) for 42 day(s) @ P 300.00 /day P 189,000.00
24 - Laborer(s) for 42 day(s) @ P 200.00 /day P 201,600.00
Labor Cost P 409,500.00
1,642,982.04
Unit Cost =
1,573.25
P 1,044.33
sq.m
Materials:
350 bags - Portland Cement @ P 260.00 /bag P 91,000.00
200 cu.m - Sand (Washed & Screened) @ P 950.00 /cu.m P 190,000.00
Material Cost P 281,000.00
Labor:
1 - Const. Foreman for 20 day(s) @ P 450.00 /day P 9,000.00
10 - Mason(s) for 20 day(s) @ P 300.00 /day P 60,000.00
15 - Laborer(s) for 20 day(s) @ P 200.00 /day P 60,000.00
Labor Cost P 129,000.00
Materials:
150 pcs. - .40mx.40m Tiles @ P 110.00 /pc P 16,500.00
250 pcs. - .25mx.25m Tiles @ P 75.00 /pc P 18,750.00
20 pcs. - Cement @ P 260.00 /bag P 5,200.00
2 pcs. - Sand @ P 950.00 /cu.m P 1,900.00
Material Cost P 35,250.00
Labor:
1 - Const. Foreman for 8 day(s) @ P 450.00 /day P 3,600.00
3 - Mason(s) for 8 day(s) @ P 300.00 /day P 7,200.00
6 - Laborer(s) for 8 day(s) @ P 200.00 /day P 9,600.00
Labor Cost P 20,400.00
69,184.08
Unit Cost =
52.08
P 1,328.42
sq.m
Materials:
340 pcs. - 4' x 8' x 12mm Thk. Plywood @ P 670.00 /pc P 227,800.00
13,850 bd.ft - 2" x 2" Coco Lumber @ P 18.00 /bd.ft P 249,300.00
3,700 bd.ft - 2" x 3" Coco Lumber @ P 18.00 /bd.ft P 66,600.00
160 kgs. - CW Nails 4" @ P 75.00 /kg P 12,000.00
140 kgs. - CW Nails 3" @ P 80.00 /kg P 11,200.00
100 kgs. - CW Nails 2 1/2" @ P 80.00 /kg P 8,000.00
Material Cost P 574,900.00
Labor:
1 - Const. Foreman for 35 day(s) @ P 450.00 /day P 15,750.00
12 - Carpenter(s) for 35 day(s) @ P 300.00 /day P 126,000.00
18 - Laborer(s) for 35 day(s) @ P 200.00 /day P 126,000.00
Labor Cost P 267,750.00
1,047,582.48
Unit Cost =
961.19
P 1,089.88
sq.m
b.) Ceiling
Quantity = 511.40 sq.m
Materials:
210 pcs. - 4' x 8' x 6mm Thk. Plywood @ P 300.00 /pc P 63,000.00
3,700 bd.ft - 2" x 2" x 8' Good Lumber @ P 18.00 /bd.ft P 66,600.00
120 kgs. - CW Nails 4" @ P 75.00 /kg P 9,000.00
135 kgs. - CW Nails 3" @ P 80.00 /kg P 10,800.00
60 kgs. - CW Nails 1" @ P 80.00 /kg P 4,800.00
Material Cost P 154,200.00
Labor:
1 - Const. Foreman for 15 day(s) @ P 450.00 /day P 6,750.00
4 - Carpenter(s) for 15 day(s) @ P 300.00 /day P 18,000.00
15 - Laborer(s) for 15 day(s) @ P 200.00 /day P 45,000.00
Labor Cost P 69,750.00
Materials:
6 pcs. - 4' x 8' x 6mm Thk. Plywood @ P 300.00 /pc P 1,800.00
270 bd.ft - 10 - 3" x 6" x 18' Guijo Lumber @ P 40.00 /bd.ft P 10,800.00
3 set(s) - .80m x 2.10m Panel Door @ P 3,200.00 /set P 9,600.00
2 set(s) - .70m x 2.10m PVC Door @ P 3,000.00 /set P 6,000.00
4 set(s) - 2.10m x 2.0m Sliding Window @ P 3,500.00 /set P 14,000.00
2 set(s) - 1/4" - .50m x .50m Jalousie Window @ P 1,000.00 /set P 2,000.00
1 set - 1/4" - 2.10m x 2.0m Clear Glass Window @ P 800.00 /set P 800.00
5 kgs. - CW Nails 4" @ P 75.00 /kg P 375.00
9 kgs. - CW Nails 3" @ P 85.00 /kg P 765.00
2 kgs. - CW Nails 1" @ P 80.00 /kg P 160.00
Material Cost P 46,300.00
Labor:
1 - Const. Foreman for 12 day(s) @ P 450.00 /day P 5,400.00
2 - Carpenter(s) for 12 day(s) @ P 300.00 /day P 7,200.00
5 - Laborer(s) for 12 day(s) @ P 200.00 /day P 12,000.00
Labor Cost P 24,600.00
88,142.88
Unit Cost =
6.93
P 12,719.03
sq.m
Materials:
150 pcs. - 2"x2"x6.0mx1/4mm THK. Angle Bar @ P 1,250.00 /pc P 187,500.00
80 pcs. - 2.5"x2.5"x6.0mx1/4mm THK. Angle Bar @ P 1,450.00 /pc P 116,000.00
42 pcs. - 12mmØx6.0m Plain Round Bar @ P 285.00 /pc P 11,970.00
32 pcs. - 5/8"Øx4x16 Turned Buckles @ P 400.00 /pc P 12,800.00
20 pcs. - .50mx.50mx20mm THK. Base Plate @ P 1,400.00 /pc P 28,000.00
120 pcs. - 20mmØx.30m Bolt w/ nuts & washers @ P 600.00 /pc P 72,000.00
60 pcs. - 2.5"Øx6.0m G.I. Pipe @ P 650.00 /pc P 39,000.00
78 pcs. - 12mmØx6.0m RSB @ P 223.00 /pc P 17,394.00
20 gal. - Lacquer Thinner @ P 300.00 /gal. P 6,000.00
28 gal. - Redoxide @ P 450.00 /gal. P 12,600.00
8 pcs. - 4" Paint Brush @ P 70.00 /pc. P 560.00
9 doz. - Hacksaw Blade @ P 900.00 /doz. P 8,100.00
20 boxes - MT-12 Welding Rod (25 kgs/box) @ P 1,300.00 /box P 26,000.00
Material Cost P 537,924.00
Labor:
1 - Const. Foreman for 34 day(s) @ P 450.00 /day P 15,300.00
10 - Steelman/Welder for 34 day(s) @ P 300.00 /day P 102,000.00
20 - Laborer(s) for 34 day(s) @ P 200.00 /day P 136,000.00
Labor Cost P 253,300.00
983,649.68
Unit Cost =
1.00
P 983,649.68
lot
a.) Roofing
Quantity = 1.00 lot
Materials:
400 ln.m - Pre-painted Roofing @ P 600.00 /ln.m P 240,000.00
2,526 pcs. - 2.5" Tekscrew @ P 2.00 /pc P 5,052.00
350 pcs. - 2"x4"x6.0mx1.5mm THK. CEE Purlins @ P 1,100.00 /pc P 385,000.00
10 pcs. - 2"x2"x6.0mx5.5mm THK. Angle Bar @ P 1,250.00 /pc P 12,500.00
60 pcs. - 10mmØx6.0m Plain Round Bar @ P 195.00 /pc P 11,700.00
15 gal. - Lacquer Thinner @ P 300.00 /gal. P 4,500.00
10 gal. - Redoxide @ P 450.00 /gal. P 4,500.00
6 pcs. - 4" Paint Brush @ P 70.00 /pc. P 420.00
8 doz. - Hacksaw Blade @ P 900.00 /doz. P 7,200.00
4 boxes - MT-12 Welding Rod (25 kgs/box) @ P 1,300.00 /box P 5,200.00
Material Cost P 676,072.00
Labor:
1 - Const. Foreman for 40 day(s) @ P 450.00 /day P 18,000.00
10 - Tinsmen for 40 day(s) @ P 300.00 /day P 120,000.00
22 - Laborer(s) for 40 day(s) @ P 200.00 /day P 176,000.00
Labor Cost P 314,000.00
1,230,857.51
Unit Cost =
1.00
P 1,230,857.51
lot
Materials:
2 pcs. - Lavatory @ P 350.00 /pc. P 700.00
2 pcs. - Water Closet @ P 980.00 /pc. P 1,960.00
2 pcs. - 4"x4" Floor Drain @ P 80.00 /pc. P 160.00
4 pcs. - 2"Ø PVC P-Trap (S-1000) @ P 90.00 /pc. P 360.00
4 pcs. - 4"Ø x 4 Wye PVC (S-1000) @ P 140.00 /pc. P 560.00
6 pcs. - 4"Ø x 4 TEE PVC (S-1000) @ P 142.00 /pc. P 852.00
4 pcs. - 4"Ø x 2 Wye PVC (S-1000) @ P 115.00 /pc. P 460.00
4 pcs. - 4"Ø x 45 PVC Elbow (S-1000) @ P 67.00 /pc. P 268.00
6 pcs. - 2"Ø x 90 PVC Elbow (S-1000) @ P 35.00 /pc. P 210.00
4 pcs. - 4"Ø x 10' PVC (SR-1000) @ P 665.00 /pc. P 2,660.00
4 pcs. - 2"Ø x 10' PVC (SR-1000) @ P 268.00 /pc. P 1,072.00
2 qrtz. - Solvent Cement (400 Super) @ P 83.00 /qrt P 166.00
Material Cost P 9,428.00
Labor:
1 - Const. Foreman for 4 day(s) @ P 450.00 /day P 1,800.00
1 - Plumber(s) for 4 day(s) @ P 300.00 /day P 1,200.00
4 - Laborer(s) for 4 day(s) @ P 200.00 /day P 3,200.00
Labor Cost P 6,200.00
19,428.73
Unit Cost =
1.00
P 19,428.73
lot
Materials:
30 bags - Portland Cement @ P 260.00 /bag P 7,800.00
6 cu.m - Sand (Washed & Screened) @ P 950.00 /cu.m. P 5,700.00
12 cu.m - Gravel (Washed & Screened) @ P 780.00 /cu.m. P 9,360.00
200 pcs. - 4" x 8" x 16" CHB @ P 10.00 /pc P 2,000.00
30 pcs. - 10mm RSB @ P 170.00 /pc P 5,100.00
7 kgs. - Tie Wire @ P 75.00 /kg P 525.00
Material Cost P 30,485.00
Labor:
1 - Const. Foreman for 8 day(s) @ P 450.00 /day P 3,600.00
1 - Mason(s) for 8 day(s) @ P 300.00 /day P 2,400.00
5 - Laborer(s) for 8 day(s) @ P 200.00 /day P 8,000.00
Labor Cost P 14,000.00
Materials:
360 gal. - Paint Thinner @ P 300.00 /gal. P 108,000.00
122 gal. - Acrylic Latex Paint @ P 650.00 /gal. P 79,300.00
50 gal. - Primer Paint @ P 500.00 /gal. P 25,000.00
22 pcs. - Paint Brush (4") @ P 70.00 /pc. P 1,540.00
11 pcs. - Roller Brush @ P 180.00 /pc. P 1,980.00
Material Cost P 215,820.00
Labor:
1 - Const. Foreman for 20 day(s) @ P 450.00 /day P 9,000.00
8 - Painter(s) for 20 day(s) @ P 300.00 /day P 48,000.00
10 - Laborer(s) for 20 day(s) @ P 200.00 /day P 40,000.00
Labor Cost P 97,000.00
388,897.82
Unit Cost =
2,627.50
P 148.01
sq.m
Materials:
1 Ls Lumpsum @ P 3,000,000.00 /Ls P 3,000,000.00
Material Cost P 3,000,000.00
Labor:
1 - Const. Foreman for day(s) @ P 450.00 /day P -
4 - Electrician(s) for 0 day(s) @ P 300.00 /day P -
8 - Laborer(s) for 0 day(s) @ P 200.00 /day P -
Labor Cost P -
3,729,600.06
Unit Cost =
1.00
P 3,729,600.06
lot
Approved by:
TRESTAN V. DELA CRUZ
Civil Engineer
QUANTITY
P 10.00 / pc 4" CHB
Dimensions: P 230.00 / bag CEMENT
CHB height = 3.00 m. P 500.00 / cu.m SAND
length of span = 4.00 m. P 600.00 / cu.m GRAVEL
no. of span = 1,700.00 span(s) P 160.00 / pc 10MM DIA. RSB
Total length of span = 6,800.00 m. P 213.00 / pc 12MM DIA. RSB
CHB Area = 20,400.00 sq.m. P 75.00 / kg TIE WIRE
1. CHB
Using 4" x 8" x 16" CHB - By Area Method
No. of CHB = (CHB Area) x (12.5) = 255,000.00 pcs.
555 pcs.
Note: 1 LN.m =
Using Class "B" mixture - By Area Method
CEMENT = (CHB Area) x (.522) = 10,648.80 bags Quantity By Ratio:
SAND = (CHB Area) x (.0435) = 887.40 cu-m.
Using 10mm dia. (60cm Vert. spacing @ every 3 layer Hor. Spacing) - By Area Method
Vert. Bars = (CHB Area) x (2.13) = 43,452.00
Hor. Bars = (CHB Area) x (2.15) = 43,860.00
87,312.00 m. long 14,552.00
Total No. Bars = 14,552.00 pcs.
32.00 pcs.
Dimensions:
thickness = 0.15 m.
width = 0.40 m.
WF length = 6,800.00 m.
WF Volume = 408.00 cu.m.
Using 12mm dia. (60cm Cross. spacing @ 3pcs. Long. ) - By Area Method
Vert. Bars = (WF Length) x (width) = 4,533.33
(Spacing)
Hor. Bars = (WF Length) x (3pcs.) = 20,400.00
24,933.33 m. long
Total No. Bars = 4,155.56 pcs. 10
3. CHB PLASTERING
4. COLUMN FOOTING
thickness = 0.2 m nL = 4 pc(s)
width = 0.8 m nW = 4 pc(s)
length = 0.8 m Spacing = 0.2 m
No. of CF = 1,701.00
Say 5 pc(s)
CF Quantity = 217.73 cu.m
5. COLUMN
height = 3 m nTies = 16 pc(s)
width = 0.3 m nMBars = 4 pc(s)
length = 0.3 m Spacing = 0.2 m
No. of Col = 1,701.00
Say 5 pc(s)
Col Quantity = 459.27 cu.m
LTies RSB = [(height / Spacing) x 2(W + L) x N)] = 5,103.00 pc(s) 10mm dia RSB
6 Say 15 pc(s)