Labor Productivity Table: Work Description Manhours Per Quantity LOW Average High

The document provides labor productivity rates for various earthworks, carpentry works, and concrete works activities. It lists the estimated manhours per quantity or area needed to complete each task for low, average, and high productivity scenarios. Tasks include activities like excavation, backfilling, formwork installation, stripping forms, and finishing works. The rates are to be used for planning and estimating labor requirements for construction projects.

Uploaded by

Lonel Castillo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (4 votes)
10K views8 pages

Labor Productivity Table: Work Description Manhours Per Quantity LOW Average High

The document provides labor productivity rates for various earthworks, carpentry works, and concrete works activities. It lists the estimated manhours per quantity or area needed to complete each task for low, average, and high productivity scenarios. Tasks include activities like excavation, backfilling, formwork installation, stripping forms, and finishing works. The rates are to be used for planning and estimating labor requirements for construction projects.

Uploaded by

Lonel Castillo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

LABOR PRODUCTIVITY TABLE

MANHOURS PER QUANTITY


WORK DESCRIPTION
LOW AVERAGE HIGH
I. EARTHWORKS

1.0 MACHINE EXCAVATION


1.01 Sand 1.20 MH/CM 0.60 MH/CM 0.48 MH/CM
1.02 Sand and Marl 1.60 MH/CM 0.80 MH/CM 0.64 MH/CM
1.03 Marl 2.20 MH/CM 1.10 MH/CM 0.88 MH/CM

2.0 GRANULAR BACKFILL 2.40 MH/CM 1.20 MH/CM 0.96 MH/CM

3.0 GRANULAR SOIL BACKFILL 3.00 MH/CM 1.50 MH/CM 1.20 MH/CM

4.0 MANUAL FOUNDATION EXCAVATION AND


4.01 Excavation of Sand 9.00 MH/CM 4.50 MH/CM 3.60 MH/CM
4.02 Excavation of Sand and Marl 13.00 MH/CM 6.50 MH/CM 5.20 MH/CM
4.03 Excavation of Marl 21.00 MH/CM 10.50 MH/CM 8.40 MH/CM
4.04 Backfill of Sand 11.00 MH/CM 5.50 MH/CM 4.40 MH/CM
4.05 Backfill of Sand and Marl 16.00 MH/CM 8.00 MH/CM 6.40 MH/CM
4.06 Backfill of Marl 24.00 MH/CM 12.00 MH/CM 9.60 MH/CM

5.0 FLOOR SLAB AND GRADE


5.01 Manual Grading 2.60 MH/SM 1.30 MH/SM 1.04 MH/SM
5.02 Excavation and Backfill 36.00 MH/CM 18.00 MH/CM 14.40 MH/CM

6.0 FINE GRADING AND FINISHING


6.01 Grading 0.90 MH/SM 0.45 MH/SM 0.36 MH/SM
6.02 Finishing Soil Surface 1.10 MH/SM 0.55 MH/SM 0.44 MH/SM
6.03 Dikes 2.40 MH/CM 1.20 MH/CM 0.96 MH/CM
6.04 Road Works
a. Base Coarse 0.24 MH/SM 0.12 MH/SM 0.10 MH/SM
b. Curves and Gutters 3.60 MH/CM 1.80 MH/CM 1.44 MH/CM
c. 4" thk. Road 2.60 MH/SM 1.30 MH/SM 1.04 MH/SM
d. 6" thk. Road 2.80 MH/SM 1.40 MH/SM 1.12 MH/SM
e. 8" thk. Road 3.00 MH/SM 1.50 MH/SM 1.20 MH/SM
f. Trowel Finish 0.64 MH/SM 0.32 MH/SM 0.26 MH/SM
g. Special Topping 2.40 MH/SM 1.20 MH/SM 0.96 MH/SM
h. 4" Stone or Shell Road 0.64 MH/SM 0.32 MH/SM 0.26 MH/SM
i. 6" Stone or Shell Road 0.84 MH/SM 0.42 MH/SM 0.34 MH/SM
j. 8" Stone or Shell Road 1.04 MH/SM 0.52 MH/SM 0.42 MH/SM
k. Acid Proofing 1.20 MH/CM 0.60 MH/CM 0.48 MH/CM

7.0 ASPHALT PAVING 0.84 MH/SM 0.42 MH/SM 0.34 MH/SM


7.01 Fine Grading 0.40 MH/SM 0.20 MH/SM 0.16 MH/SM
7.02 Place Base Coarse 0.40 MH/SM 0.20 MH/SM 0.16 MH/SM
7.03 Asphalt

8.0 ACID BLOCK OR PAVING BLOCK


8.01 Fine Grading 0.84 MH/SM 0.42 MH/SM 0.34 MH/SM
8.02 Install Brick 8.40 MH/SM 4.20 MH/SM 3.36 MH/SM
9.0 CRUSH STONE OR SHELL SURFACING
9.01 Fine Grading 0.64 MH/SM 0.32 MH/SM 0.26 MH/SM
9.02 Place, Spread, and Compact stone to 0.84 MH/SM 0.42 MH/SM 0.34 MH/SM
9.03 Over 8" 1.04 MH/SM 0.52 MH/SM 0.42 MH/SM

10.0 TANK CUSHIONS


10.01 Sand Cushions 1.40 MH/CM 0.70 MH/CM 0.56 MH/CM
10.02 Asphalt Retainer Ring 0.40 MH/SM 0.20 MH/SM 0.16 MH/SM

11.0 NON-GRANULAR BACKFILL 4.00 MH/CM 2.00 MH/CM 1.60 MH/CM


12.0 EXCAVATION - MANUAL
12.01 Common Earth 16.00 MH/CM 8.00 MH/CM 6.40 MH/CM
12.02 Loam of sand 2.62 MH/CM 1.31 MH/CM 1.05 MH/CM
12.03 Clay of Heavy Soil 3.28 MH/CM 1.64 MH/CM 1.31 MH/CM
12.04 Rock 5.26 MH/CM 2.63 MH/CM 2.10 MH/CM

13.0 MECHANICAL EXCAVATION


13.01 Common Earth 13.34 MH/CM 6.67 MH/CM 5.34 MH/CM
13.02 Rock with Jackhammer 33.34 MH/CM 16.67 MH/CM 13.34 MH/CM

14.0 BACKFILLING
14.01 Common Manual 1.64 MH/CM 0.82 MH/CM 0.66 MH/CM
14.02 Gravel Fill Manual 10.00 MH/CM 5.00 MH/CM 4.00 MH/CM

15.0 MANUAL TRENCHING AND BACKFILLING OF


From 0 to 2 mtrs depth 2.50 MH/LM 1.25 MH/LM 1.00 MH/LM
2 to 3 mtrs depth 3.34 MH/LM 1.67 MH/LM 1.34 MH/LM
3 to 4 mtrs depth 5.00 MH/LM 2.50 MH/LM 2.00 MH/LM
4 to 5 mtrs depth 6.66 MH/LM 3.33 MH/LM 2.66 MH/LM

16.0 PLACING BINDER - GRAVEL 0.21 MH/CM 0.11 MH/CM 0.08 MH/CM

17.0 ESCOMBRO BACKFILLING 0.42 MH/CM 0.21 MH/CM 0.17 MH/CM

18.0 SPREADING, TAMPING AND GRADING 0.96 MH/SM 0.48 MH/SM 0.38 MH/SM

19.0 MECHANICAL COMPACTION, PLATE 0.11 MH/CM 0.06 MH/CM 0.04 MH/CM

20.0 MANUAL CLEARING AND GRUBBING


20.01 Clearing Undergrowth and Trees - 12" 0.10 MH/SM 0.05 MH/SM 0.04 MH/SM
20.02 Clearing Undergrowth & Shrubs 0.06 MH/SM 0.03 MH/SM 0.02 MH/SM

21.0 DISPOSAL OF SOIL 3.38 MH/CM 1.69 MH/CM 1.35 MH/CM

22.0 HAULING OF SOIL 2.00 MH/CM 1.00 MH/CM 0.80 MH/CM

23.0 GRAVEL FILL 4.14 MH/CM 2.07 MH/CM 1.66 MH/CM

24.0 EXCAVATION - CRANE & CLAMSHELL


with 8 men and 2 carpenters 2.14 MH/CM 1.07 MH/CM 0.86 MH/CM

II. CARPENTRY WORKS

1.0 FORMWORKS INSTALLATION


1.01 Wall on Ground 4.00 MH/SM 2.00 MH/SM 1.60 MH/SM
1.02 Wall above Ground 4.70 MH/SM 2.35 MH/SM 1.88 MH/SM
1.03 Beams 6.16 MH/SM 3.08 MH/SM 2.46 MH/SM
1.04 Columns 4.70 MH/SM 2.35 MH/SM 1.88 MH/SM
1.05 Suspended Slab
a. 0 to 18" 3.34 MH/SM 1.67 MH/SM 1.34 MH/SM
b. 18" to 36" up 6.66 MH/SM 3.33 MH/SM 2.66 MH/SM
1.06 Elevated & Shored Slab Forming
a. Forming Only 17.20 MH/SM 8.60 MH/SM 6.88 MH/SM
b. Forming and Shoring 22.00 MH/SM 11.00 MH/SM 8.80 MH/SM
1.07 Wood Wall and Partitions 1.00 MH/SM 0.50 MH/SM 0.40 MH/SM

2.0 FORMWORKS FABRICATION 2.15 MH/SM 1.08 MH/SM 0.86 MH/SM

3.0 STRIPPING OF FORMWORKS


3.01 Wall on Ground 0.50 MH/SM 0.25 MH/SM 0.20 MH/SM
3.02 Wall above 10" 2.58 MH/SM 1.29 MH/SM 1.03 MH/SM
3.03 Beams 2.06 MH/SM 1.03 MH/SM 0.82 MH/SM
3.04 Columns 1.70 MH/SM 0.85 MH/SM 0.68 MH/SM
3.05 Suspended Slab
a. 0 to 18" 1.67 MH/SM 0.84 MH/SM 0.67 MH/SM
b. 18" to 36" up 2.16 MH/SM 1.08 MH/SM 0.86 MH/SM
3.06 Elevated & Shored Slab Forming - 7.00 MH/SM 3.50 MH/SM 2.80 MH/SM
3.07 Floor Slab at Grade - Strip of Forms 5.60 MH/SM 2.80 MH/SM 2.24 MH/SM

4.0 INSTALLATION OF CARPENTRY WORKS


4.01 Plywood Partition 2.00 MH/PC 1.00 MH/PC 0.80 MH/PC
4.02 T & G Flooring and Siding 0.29 MH/BF 0.15 MH/BF 0.12 MH/BF
4.03 Ceiling Framework 0.73 MH/BF 0.37 MH/BF 0.29 MH/BF
4.04 Siding Framework 0.53 MH/BF 0.27 MH/BF 0.21 MH/BF
4.05 Flooring Framing 1.94 MH/BF 0.97 MH/BF 0.78 MH/BF
4.06 Wooden Post Erection 0.85 MH/BF 0.43 MH/BF 0.34 MH/BF
4.07 Truss Fabrication 0.70 MH/BF 0.35 MH/BF 0.28 MH/BF
4.08 Truss Installation 1.60 MH/BF 0.80 MH/BF 0.64 MH/BF
4.09 Girt Installation 0.43 MH/BF 0.22 MH/BF 0.17 MH/BF
4.10 Plates Installation 0.27 MH/BF 0.14 MH/BF 0.11 MH/BF
4.11 Purlins Installation 0.53 MH/BF 0.27 MH/BF 0.21 MH/BF
4.12 Facia Board Installation 0.91 MH/BF 0.46 MH/BF 0.36 MH/BF
4.13 1/4" or 3/4" thk plywood
a. cutting by manual 2.00 MH/PC 1.00 MH/PC 0.80 MH/PC
b. assembly 0.83 MH/SH 0.42 MH/SH 0.33 MH/SH
4.14 Ceiling
a. Frame Installation 2.66 MH/SM 1.33 MH/SM 1.06 MH/SM
b. Plywood Installation 2.00 MH/SH 1.00 MH/SH 0.80 MH/SH
4.15 Cabinet Boarding 0.26 MH/BF 0.13 MH/BF 0.10 MH/BF
4.16 Cabinet Framing 0.36 MH/BF 0.18 MH/BF 0.14 MH/BF
4.17 Wood Wall Partitions 1.00 MH/SM 0.50 MH/SM 0.40 MH/SM
4.18 Panel Wall 14.00 MH/SM 7.00 MH/SM 5.60 MH/SM
4.19 Forming Weights Anchor Bolts 9.00 MH/SM 4.50 MH/SM 3.60 MH/SM
4.20 Wet Forming 7.00 MH/SM 3.50 MH/SM 2.80 MH/SM

5.0 DOORS AND WINDOWS


5.01 W-Panel Installation 0.80 MH/PC 0.40 MH/PC 0.32 MH/PC
5.02 Steel Window Installation 4.00 MH/PC 2.00 MH/PC 1.60 MH/PC
5.03 Louver Window Installation
a. Fixed Asbestos 9.26 MH/SM 4.63 MH/SM 3.70 MH/SM
b. Fixed Metal Louvers 6.24 MH/SM 3.12 MH/SM 2.50 MH/SM
c. Fixed G.I. Sheet 9.26 MH/SM 4.63 MH/SM 3.70 MH/SM
d. Fixed Glass 6.24 MH/SM 3.12 MH/SM 2.50 MH/SM
e. Fixed Wood 6.76 MH/SM 3.38 MH/SM 2.70 MH/SM
5.04 Aluminum Framed Windows 20.00 MH/PC 10.00 MH/PC 8.00 MH/PC
5.05 Sliding Glass Door 24.00 MH/PC 12.00 MH/PC 9.60 MH/PC
5.06 Hollow Metal Door 20.00 MH/PC 10.00 MH/PC 8.00 MH/PC
5.07 Rolling Door 50.00 MH/PC 25.00 MH/PC 20.00 MH/PC
5.08 Fixed Window 0.63 MH/SF 0.32 MH/SF 0.25 MH/SF
5.09 Door Lockset 3.20 MH/SET 1.60 MH/SET 1.28 MH/SET
5.10 Door Jamb
a. Fabrication 0.44 MH/BF 0.22 MH/BF 0.18 MH/BF
b. Installation 0.66 MH/BF 0.33 MH/BF 0.26 MH/BF
5.11 Cyclone Wire Installation 6.24 MH/SM 3.12 MH/SM 2.50 MH/SM

III. MASONRY WORKS

1.0 GROUTING AND TDL PLASTERING 3.34 MH/SM 1.67 MH/SM 1.34 MH/SM

2.0 PEBBLE FINISH 2.86 MH/SM 1.43 MH/SM 1.14 MH/SM

3.0 MARBLE INSTALLATION 4.00 MH/SM 2.00 MH/SM 1.60 MH/SM

4.0 1/4' x 2" x 8" RED BRICKS 10.00 MH/SM 5.00 MH/SM 4.00 MH/SM

5.0 GLAZED TILES 21.06 MH/SM 10.53 MH/SM 8.42 MH/SM


6.0 UNGLAZED TILES 8.70 MH/SM 4.35 MH/SM 3.48 MH/SM

7.0 GLAZED WALL TILES 6.00 MH/SM 3.00 MH/SM 2.40 MH/SM
8.0 CONCRETE BLOCK EXT. WALL 9.00 MH/SM 4.50 MH/SM 3.60 MH/SM

9.0 CONCRETE BLOCK INT. WALL 8.00 MH/SM 4.00 MH/SM 3.20 MH/SM

10.0 BRICKWORK 1.00 MH/SM 0.50 MH/SM 0.40 MH/SM

11.0 PLASTER WALL AND CEILING 6.00 MH/SM 3.00 MH/SM 2.40 MH/SM

12.0 HOLLOW TILE WALL 4.00 MH/SM 2.00 MH/SM 1.60 MH/SM

13.0 ACCOUSTIC CEILING 2.40 MH/SM 1.20 MH/SM 0.96 MH/SM

14.0 VINYL FLOOR TILE 3.60 MH/SM 1.80 MH/SM 1.44 MH/SM

15.0 UNGLAZED OR MOSAIC TILE 17.00 MH/SM 8.50 MH/SM 6.80 MH/SM

16.0 LAYING OF CHB OR ADOBE 2.28 MH/SM 1.14 MH/SM 0.91 MH/SM

17.0 CEMENT FINISH 4.13 MH/SM 2.07 MH/SM 1.65 MH/SM

18.0 CONCRETE HOLLOW BLOCK LAYING


18.01 4" CHB 2.66 MH/SM 1.33 MH/SM 1.06 MH/SM
18.02 6" CHB 3.20 MH/SM 1.60 MH/SM 1.28 MH/SM
18.03 8" CHB 4.00 MH/SM 2.00 MH/SM 1.60 MH/SM

19.0 VIT. FLOOR TILES 10.66 MH/SM 5.33 MH/SM 4.26 MH/SM

20.0 VIT. WALL TILES 11.94 MH/SM 5.97 MH/SM 4.78 MH/SM

IV. TINSMITHING WORKS


1.0 CORRUGATED G.I. SHEET
1.01 Lifting 2.16 MH/SM 1.08 MH/SM 0.86 MH/SM
1.02 Installation 6.12 MH/SM 3.06 MH/SM 2.45 MH/SM

2.0 INSTALLATION OF ASBESTOS ROOFING 2.00 MH/SHT 1.00 MH/SHT 0.80 MH/SHT

3.0 INSTALLATION OF ALUMINUM or G.I. SHT. 1.60 MH/SHT 0.80 MH/SHT 0.64 MH/SHT

4.0 COPPER CLADDING ROOF DECK 1.01 MH/LM 0.51 MH/LM 0.40 MH/LM

5.0 FABRICATION OF G.I. GUTTER 6.94 MH/SHT 3.47 MH/SHT 2.78 MH/SHT

6.0 G.I. SHEET ROOFING 1.64 MH/SM 0.82 MH/SM 0.66 MH/SM

7.0 FABRICATION OF G.I. GUTTER 1.05 MH/LM 0.53 MH/LM 0.42 MH/LM

8.0 FABRICATION OF DOWNSPOUT 1.94 MH/LM 0.97 MH/LM 0.78 MH/LM

9.0 GUTTER- CUT AND SHAPE 0.32 MH/LM 0.16 MH/LM 0.13 MH/LM

10.0 INSTALLATION OF GUTTER 1.78 MH/LM 0.89 MH/LM 0.71 MH/LM

11.0 DOWNSPOUT - CUT AND SHAPE 0.59 MH/LM 0.30 MH/LM 0.24 MH/LM

12.0 DOWNSPOUT INSTALLATION 0.27 MH/LM 0.14 MH/LM 0.11 MH/LM

13.0 CORRUGARED G.I. ROOFING 3.60 MH/SM 1.80 MH/SM 1.44 MH/SM

14.0 CORRUGATED ALUMINUM ROOFING 3.60 MH/SM 1.80 MH/SM 1.44 MH/SM
15.0 BUILT-UP ROOFING 4-PLY 17.00 MH/SM 8.50 MH/SM 6.80 MH/SM
16.0 PROTECTED METAL 4.00 MH/SM 2.00 MH/SM 1.60 MH/SM

17.0 CORR. ASBESTOS, INSTALLATION, LIFTING , AND 3.40 MH/SM 1.70 MH/SM 1.36 MH/SM

18.0 LEADERS AAND GUTTERS 1.20 MH/SM 0.60 MH/SM 0.48 MH/SM

V. CONCRETE WORKS
1.0 PLACING CONCRETE
1.01 Slab on Fill 10.00 MH/CM 5.00 MH/CM 4.00 MH/CM
1.02 Slip Form 50.00 MH/CM 25.00 MH/CM 20.00 MH/CM
1.03 Flr. Finish Unhardened 2.00 MH/CM 1.00 MH/CM 0.80 MH/CM
1.04 Concrete Finish Hardened 2.86 MH/SM 1.43 MH/SM 1.14 MH/SM

2.0 REBAR WORKS


2.01 Ground Flr. Installation 0.14 MH/Kg 0.07 MH/Kg 0.06 MH/Kg
2.02 Upper Flr. Installation 0.16 MH/Kg 0.08 MH/Kg 0.06 MH/Kg
2.03 Fabrication 0.20 MH/Kg 0.10 MH/Kg 0.08 MH/Kg

3.0 MANUAL MIXING 32.00 MH/CM 16.00 MH/CM 12.80 MH/CM

4.0 MACHINE MIXING 3.60 MH/CM 1.80 MH/CM 1.44 MH/CM

5.0 MORE THAN 1.80 CU.M. POUR


5.01 Chute From Truck 14 MH/CM 7.00 MH/CM 5.60 MH/CM
5.02 Crane and Bucket 28 MH/CM 14.00 MH/CM 11.20 MH/CM
5.03 Wheeling 54 MH/CM 27.00 MH/CM 21.60 MH/CM
5.04 Finishing 5.6 MH/SM 2.80 MH/SM 2.24 MH/SM

6.0 CONCRETE POURMON ELEVATED AND SHORED 42.00 MH/CM 21.00 MH/CM 16.80 MH/CM

7.0 PLACEMENT OF REBARS ON FOOTING 1.06 MH/Kg 0.53 MH/Kg 0.42 MH/Kg

8.0 FIELD FABRICATION OF REBARS 0.66 MH/Kg 0.33 MH/Kg 0.26 MH/Kg

VI. UNDERGROUND PIPING AND PLUMBING WORKS


1.0 LAYING ASBESTOS PIPES
1.01 1/2"Ø 1.32 MH/LM 0.66 MH/LM 0.53 MH/LM
1.02 3/4"Ø 1.32 MH/LM 0.66 MH/LM 0.53 MH/LM
1.03 1" - 1-1/4"Ø 1.48 MH/LM 0.74 MH/LM 0.59 MH/LM
1.04 1'1/2" - 2"Ø 1.64 MH/LM 0.82 MH/LM 0.66 MH/LM
1.05 2-1/2"Ø 1.97 MH/LM 0.99 MH/LM 0.79 MH/LM
1.06 3"Ø 2.16 MH/LM 1.08 MH/LM 0.86 MH/LM
1.07 3-1/2"Ø 2.30 MH/LM 1.15 MH/LM 0.92 MH/LM
1.08 4"Ø 2.64 MH/LM 1.32 MH/LM 1.06 MH/LM

2.0 LAYING CAST IRON PIPES


2.01 2"Ø 4.38 MH/LM 2.19 MH/LM 1.75 MH/LM
2.02 4"Ø 6.50 MH/LM 3.25 MH/LM 2.60 MH/LM
2.03 6"Ø 9.84 MH/LM 4.92 MH/LM 3.94 MH/LM
2.04 8"Ø 13.14 MH/LM 6.57 MH/LM 5.26 MH/LM
2.05 10"Ø 19.70 MH/LM 9.85 MH/LM 7.88 MH/LM
2.06 12"Ø 20.62 MH/LM 10.31 MH/LM 8.25 MH/LM
2.07 14"Ø 24.10 MH/LM 12.05 MH/LM 9.64 MH/LM
2.08 16"Ø 27.38 MH/LM 13.69 MH/LM 10.95 MH/LM
2.09 18"Ø 30.68 MH/LM 15.34 MH/LM 12.27 MH/LM
2.10 20"Ø 32.86 MH/LM 16.43 MH/LM 13.14 MH/LM
2.11 24"Ø 36.14 MH/LM 18.07 MH/LM 14.46 MH/LM
2.12 30"Ø 41.08 MH/LM 20.54 MH/LM 16.43 MH/LM

3.0 LAYING PVC PIPES


3.01 1/2" - 3/4"Ø 0.38 MH/LM 0.19 MH/LM 0.15 MH/LM
3.02 1" - 1-1/4"Ø 1.48 MH/LM 0.74 MH/LM 0.59 MH/LM
3.03 1'1/2" - 2"Ø 1.64 MH/LM 0.82 MH/LM 0.66 MH/LM
3.04 2-1/2"Ø 1.96 MH/LM 0.98 MH/LM 0.78 MH/LM
3.05 3"Ø 2.16 MH/LM 1.08 MH/LM 0.86 MH/LM
3.06 4"Ø 2.62 MH/LM 1.31 MH/LM 1.05 MH/LM
3.07 5"Ø 3.20 MH/LM 1.60 MH/LM 1.28 MH/LM
3.08 6"Ø 4.92 MH/LM 2.46 MH/LM 1.97 MH/LM

4.0 LAYING RCP 8-Men (1 Team)


4.01 6" - 10"Ø 2.66 MH/LM 1.33 MH/LM 1.06 MH/LM
4.02 24"Ø 8.00 MH/LM 4.00 MH/LM 3.20 MH/LM
4.03 36"Ø 12.80 MH/LM 6.40 MH/LM 5.12 MH/LM
4.04 48"Ø 21.34 MH/LM 10.67 MH/LM 8.54 MH/LM

5.0 LAVATORY 16.00 MH/PC 8.00 MH/PC 6.40 MH/PC

6.0 WATER CLOSET 24.00 MH/PC 12.00 MH/PC 9.60 MH/PC

7.0 URINAL, UTILITY STALL 48.00 MH/PC 24.00 MH/PC 19.20 MH/PC

8.0 URINAL, PEDESTAL TYPE 32.00 MH/PC 16.00 MH/PC 12.80 MH/PC

9.0 SHOWER AND STALL 20.00 MH/PC 10.00 MH/PC 8.00 MH/PC

10.0 5-MAN GROUP SHOWER 72.00 MH/PC 36.00 MH/PC 28.80 MH/PC

11.0 BATH TUBS 48.00 MH/PC 24.00 MH/PC 19.20 MH/PC

12.0 SLOPE SINK 28.00 MH/PC 14.00 MH/PC 11.20 MH/PC

13.0 HOT WATER HEATER 28.00 MH/PC 14.00 MH/PC 11.20 MH/PC

14.0 6-PERSON WASH SINK 52.00 MH/PC 26.00 MH/PC 20.80 MH/PC

15.0 DRINKING FOUNTAIN 26.00 MH/PC 13.00 MH/PC 10.40 MH/PC

16.0 EYE WASH 16.00 MH/PC 8.00 MH/PC 6.40 MH/PC

17.0 MISCELLANEOUS FIXTURES 4.00 MH/PC 2.00 MH/PC 1.60 MH/PC

18.0 PARTITIONS 16.00 MH/PC 8.00 MH/PC 6.40 MH/PC

19.0 LAYING OF 24"Ø RCP 8.00 MH/PIPE 4.00 MH/PIPE 3.20 MH/PIPE

20.0 LAYING OF 36"Ø RCP 18.80 MH/PIPE 9.40 MH/PIPE 7.52 MH/PIPE

21.0 LAYING OF 48"Ø RCP 21.32 MH/PIPE 10.66 MH/PIPE 8.53 MH/PIPE

VII. INSULATION

1.0 VESSELS, EXCHANGES AND TANKS


1.01 Field Fabrication and Insulation 5.00 MH/SM 2.50 MH/SM 2.00 MH/SM
1.02 Field Fabrication Sht Metal Cover 24.00 MH/SM 12.00 MH/SM 9.60 MH/SM
1.03 Apply Insulation 10.00 MH/SM 5.00 MH/SM 4.00 MH/SM
1.04 Apply Sheet Metal Cover 10.00 MH/SM 5.00 MH/SM 4.00 MH/SM

2.0 PUMPS, COMPRESSORS AND TURBINES


2.01 Fabricate 34.00 MH/SM 17.00 MH/SM 13.60 MH/SM
2.02 Apply 60.00 MH/SM 30.00 MH/SM 24.00 MH/SM

3.0 PIPING AND COMPONENT INSULATION


3.01 Field Fabricate 8.00 MH/FLG 4.00 MH/FLG 3.20 MH/FLG
3.02 Field Fabricate Sht Metal Cover 1.60 MH/SM 0.80 MH/SM 0.64 MH/SM
3.03 Apply Insulation 5.40 MH/LM 2.70 MH/LM 2.16 MH/LM
3.04 Apply Sheet Metal or Paper Cover 3.00 MH/PC 1.50 MH/PC 1.20 MH/PC
3.05 Fabricate Instrument Cover 16.00 MH/PC 8.00 MH/PC 6.40 MH/PC
3.06 Install Instrument Cover 12.00 MH/PC 6.00 MH/PC 4.80 MH/PC
3.07 Insulate Pipe Hangers 8.00 MH/PC 4.00 MH/PC 3.20 MH/PC
3.08 For Steam Traced Lines 7.40 MH/LM 3.70 MH/LM 2.96 MH/LM
3.09 Removal of Old or Existing Insulation 3.00 MH/LM 1.50 MH/LM 1.20 MH/LM

VIII. FIRE PROOFING

1.0 INSTALL STUBS 1.00 MH/PC 0.50 MH/PC 0.40 MH/PC

2.0 INSTALL MESH 2.40 MH/SM 1.20 MH/SM 0.96 MH/SM

3.0 POURING
3.01 Forming 28.00 MH/SM 14.00 MH/SM 11.20 MH/SM
3.02 Strip Forms 12.00 MH/SM 6.00 MH/SM 4.80 MH/SM
3.03 Pour Concrete 140.00 MH/LM 70.00 MH/LM 56.00 MH/LM
3.04 Curing / Patching 1.20 MH/SM 0.60 MH/SM 0.48 MH/SM
3.05 Finishing 1.40 MH/SM 0.70 MH/SM 0.56 MH/SM

4.0 TROWEL, PLASTERED 5.40 MH/SM 2.70 MH/SM 2.16 MH/SM

5.0 PNEUMATIC APPLICATION


5.01 Bunite 2.40 MH/SM 1.20 MH/SM 0.96 MH/SM
6.0 APPLY FINE BRICK OR BLOCK 1.60 MH/PC 0.80 MH/PC 0.64 MH/PC

7.0 REMOVAL OF EXISTING OR OLD FIREPROOFING 5.00 MH/SM 2.50 MH/SM 2.00 MH/SM

8.0 APPLY FIREPROOFING PAINT 6.00 MH/SM 3.00 MH/SM 2.40 MH/SM

IX. FIRE PROTECTION


1.0 FIRE PROTECTION EQUIPMENT INSTALLATION
1.01 Monitor 10.00 MH/PC 5.00 MH/PC 4.00 MH/PC
1.02 Hose Reels 30.00 MH/PC 15.00 MH/PC 12.00 MH/PC
1.03 Fire Extinguishers 10.00 MH/PC 5.00 MH/PC 4.00 MH/PC

2.0 PERSONAL EQUIPMENT


2.01 Eye Wash 20.00 MH/PC 10.00 MH/PC 8.00 MH/PC
2.02 Safety Showers 20.00 MH/PC 10.00 MH/PC 8.00 MH/PC
2.03 Breathing Apparatus 10.00 MH/PC 5.00 MH/PC 4.00 MH/PC

3.0 SPRINKLER SYSTEM


3.01 Spray Nozzles 2.00 MH/PC 1.00 MH/PC 0.80 MH/PC
3.02 Water Cannons 10.00 MH/PC 5.00 MH/PC 4.00 MH/PC

X. HEATING VENTILLATION AND AIR CONDITIONING

1.0 HACV PIPING 7.00 MH/LM 3.50 MH/LM 2.80 MH/LM

2.0 INSTALL DUCK WORK 12.00 MH/SM 6.00 MH/SM 4.80 MH/SM

3.0 DUCK WORK FABRICATION 36.00 MH/SM 18.00 MH/SM 14.40 MH/SM

4.0 PACKAGE UNIT AIR CONDITIONER 18.00 MH/PC 9.00 MH/PC 7.20 MH/PC

5.0 UNIT HEATER 24.00 MH/PC 12.00 MH/PC 9.60 MH/PC

6.0 FINNED CONVERTER 10.00 MH/PC 5.00 MH/PC 4.00 MH/PC

7.0 EXHAUST FAN, PROPELLER 16.00 MH/PC 8.00 MH/PC 6.40 MH/PC

8.0 GRAVITY ROOF VENT 14.60 MH/LM 7.30 MH/LM 5.84 MH/LM

9.0 POWER ROOF VENT 48.00 MH/PC 24.00 MH/PC 19.20 MH/PC

10.0 ROUND ROOF VENT 16.00 MH/PC 8.00 MH/PC 6.40 MH/PC
11.0 PLUMBING PIPING 7.00 MH/LM 3.50 MH/LM 2.80 MH/LM

XI. PERMANENT FENCING


1.0 INSTALL FENCE 2.40 MH/LM 1.20 MH/LM 0.96 MH/LM

2.0 INSTALL GATES 6.00 MH/LM 3.00 MH/LM 2.40 MH/LM

3.0 TO RAIL 0.60 MH/LM 0.30 MH/LM 0.24 MH/LM

4.0 BARBWIRE, 3-STRANDS 0.60 MH/LM 0.30 MH/LM 0.24 MH/LM

XII. PAINTING WORKS

1.0 NEW STRUCTURAL STEEL 20.00 MH/TON 10.00 MH/TON 8.00 MH/TON

2.0 OLD STRUCTURAL STEEL 1.10 MH/SM 0.55 MH/SM 0.44 MH/SM

3.0 NEW FLAT PLATES 0.64 MH/SM 0.32 MH/SM 0.26 MH/SM

4.0 SURFACE PREPARATION


4.01 In terms of weight 16.00 MH/TON 8.00 MH/TON 6.40 MH/TON
4.02 In terms of area 0.86 MH/SM 0.43 MH/SM 0.34 MH/SM

5.0 SAND PREPARATION 60.00 MH/TON 30.00 MH/TON 24.00 MH/TON

XIII. MISCELLANEOUS WORKS


1.0 WATER STOP INSTALLATION 1.34 MH/LM 0.67 MH/LM 0.54 MH/LM

2.0 CAULING-SLAB JOINT 0.40 MH/LM 0.20 MH/LM 0.16 MH/LM

3.0 ASPHALTING 1.60 MH/SM 0.80 MH/SM 0.64 MH/SM

4.0 GROUTING AND TOOL PLASTERING 3.34 MH/SM 1.67 MH/SM 1.34 MH/SM

5.0 WATER PROOFING RUBBERIZED 1.10 MH/SM 0.55 MH/SM 0.44 MH/SM

6.0 COPPER CLADDING ROOF DECK 1.00 MH/LM 0.50 MH/LM 0.40 MH/LM

7.0 WATER PROOFING FLINKOTE 0.54 MH/SM 0.27 MH/SM 0.22 MH/SM

8.0 DEMOLITION OF ADOBE WALL 3.20 MH/CM 1.60 MH/CM 1.28 MH/CM

9.0 PAINTING 0.68 MH/SM 0.34 MH/SM 0.27 MH/SM

10.0 COPPER WATER STOP-CUT AND SHAPE 0.11 MH/LM 0.06 MH/LM 0.04 MH/LM

11.0 COPPER WATER STOP-CUT INSTALLATION 0.22 MH/LM 0.11 MH/LM 0.09 MH/LM

12.0 SETTING ANCHOR BOLTS 0.97 MH/Kg 0.49 MH/Kg 0.39 MH/Kg

13.0 SETTING ANCHOR BOXES 3.64 MH/CM 1.82 MH/CM 1.46 MH/CM

LEGEND:
MH/CM = Manhour per Cubic Meter
MH/SM = Manhour per Square Meter
MH/LM = Manhour per Linear Meter
MH/SF = Manhour per Square Foot
MH/BF = Manhour per Board-foot
MH/SHT = Manhour per Sheet
MH/Kg = Manhour per Cubic Kilogram
MH/TON = Manhour per Ton
MH/PIPE = Manhour per Pipe
MH/PC = Manhour per piece