The document provides man-hour estimates for various earthworks and masonry tasks. For earthworks, it gives the low, average, and high man-hours required per unit of measurement for different types of excavation, backfilling, grading, paving and other tasks. Similarly for masonry, it provides man-hour estimates for tasks like plastering, brickwork, tile installation and other masonry construction activities. The estimates are meant to aid in planning and estimating the labor required for various earthworks and masonry construction jobs.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
2K views9 pages

Construction Labor Estimates

The document provides man-hour estimates for various earthworks and masonry tasks. For earthworks, it gives the low, average, and high man-hours required per unit of measurement for different types of excavation, backfilling, grading, paving and other tasks. Similarly for masonry, it provides man-hour estimates for tasks like plastering, brickwork, tile installation and other masonry construction activities. The estimates are meant to aid in planning and estimating the labor required for various earthworks and masonry construction jobs.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 9

EARTHWORKS

Man-hour per quantity


DESCRIPTION LOW AVERAGE HIGH
Qty Unit Qty Unit Qty Unit
1.1 Machine Excavation
Sand 1.20 MH/CM 0.60 MH/CM 0.48 MH/CM
Sand and Marl 1.6 MH/CM 0.80 MH/CM 0.64 MH/CM
Marl 2.20 MH/CM 1.10 MH/CM 0.88 MH/CM
1.2 Granural Backfill 2.40 MH/CM 1.20 MH/CM 0.96 MH/CM
1.3 Granural Soil Backfill 3.00 MH/CM 1.50 MH/CM 1.20 MH/CM
1.4 Manual Foundation Excavation and Backfill
Sand 8.00 MH/CM 4.00 MH/CM 3.20 MH/CM
Excavation of Sand and Marl 13.00 MH/CM 6.50 MH/CM 5.20 MH/CM
Excavation of Marl 21.00 MH/CM 10.50 MH/CM 8.40 MH/CM
Backfill of sand 11.00 MH/CM 5.50 MH/CM 4.40 MH/CM
Backfill of Sand and Marl 16.00 MH/CM 8.00 6.40
Backfill of Marl 24.00 MH/CM 12.00 MH/CM 9.60 MH/CM
1.5 Floor Slab and Grade
Grading, Manual 2.60 MH/SM 1.30 MH/SM 1.04 MH/SM
Excavation and Backfill 36.00 MH/CM 18.00 MH/CM 14.40 MH/CM
1.6 Fine Grading and Finishing
Grading 0.90 MH/SM 0.45 MH/SM 0.36 MH/SM
Finishing soil surface 1.10 MH/SM 0.55 MH/SM 0.44 MH/SM
Dikes 2.40 MH/CM 1.20 MH/CM 0.96 MH/CM
Road Works
Base Coarse 0.24 MH/SM 0.12 MH/SM 0.10 MH/SM
Curbes and Gutters 3.60 MH/CM 1.80 MH/CM 1.44 MH/CM
4" Thck Road 2.60 MH/SM 1.30 MH/SM 1.04 MH/SM
6" Thck Road 2.80 MH/SM 1.40 MH/SM 1.12 MH/SM
8" Thck Road 3.00 MH/SM 1.50 MH/SM 1.20 MH/SM
Trowel Topping 0.64 MH/SM 0.32 MH/SM 0.26 MH/SM
Special Topping 2.40 MH/SM 1.20 MH/SM 0.96 MH/SM
4" Stone or Shell Road 0.64 MH/SM 0.32 MH/SM 0.26 MH/SM
6" Stone or Shell Road 0.84 MH/SM 0.42 MH/SM 0.34 MH/SM
8" Stone or Shell Road 1.04 MH/SM 0.52 MH/SM 0.42 MH/SM
Acid Proofing 1.20 MH/SM 0.60 MH/SM 0.48 MH/SM
1.7 Asphalt Paving
Fine Grading 0.84 MH/SM 0.42 MH/SM 0.34 MH/SM
Place Base Course 0.40 MH/SM 0.20 MH/SM 0.16 MH/SM
Asphalt 0.40 MH/SM 0.20 MH/SM 0.16 MH/SM
1.8 Acid Block or Paving Block
Fine Grading 0.84 MH/SM 0.42 MH/SM 0.34 MH/SM
Install Brick 8.40 MH/SM 4.20 MH/SM 3.36 MH/SM
1.9 Crush Stone or Shell Surfacing
Fine Grading 0.64 MH/SM 0.32 MH/SM 0.26 MH/SM
Place, Spread and Compact Stone To 4" thk 0.84 MH/SM 0.42 MH/SM 0.34 MH/SM
Over 8" thk 1.04 MH/SM 0.52 MH/SM 0.42 MH/SM
2.0 Tank Cushions
Sand Cushions 1.40 MH/CM 0.70 MH/CM 0.56 MH/CM
Asphalt Retainer Ring 0.40 MH/SM 0.20 MH/SM 0.16 MH/SM
2.1 Non-Granular Backfill 4.00 MH/CM 2.00 MH/CM 1.60 MH/CM
2.2 Excavation - Manual
Common Earth 16.00 MH/CM 8.00 MH/CM 6.40 MH/CM
Loan of Sand 2.62 MH/CM 1.31 MH/CM 1.05 MH/CM
Clay and Heavy Soil 3.28 MH/CM 1.64 MH/CM 1.31 MH/CM
Rock 5.26 MH/CM 2.63 MH/CM 2.10 MH/CM
2.3 Mechanical Excavation
Common Earth 13.34 MH/CM 6.67 MH/CM 5.34 MH/CM
Rock w/ Jackhammer 33.34 MH/CM 16.67 MH/CM 13.34 MH/CM
2.4 Backfilling
Common Manual 1.64 MH/CM 0.82 MH/CM 0.66 MH/CM
Gravel Fill Manual 10.00 MH/CM 5.00 MH/CM 4.00 MH/CM

Earthworks Pages 1 of 2
EARTHWORKS
Man-hour per quantity
DESCRIPTION LOW AVERAGE HIGH
Qty Unit Qty Unit Qty Unit
2.5 Trenching and Backfilling of Underground
2.6 piping using excavation materials manual
from 0 - 2mtrs depth 2.50 MH/LM 1.25 MH/LM 1.00 MH/LM
2 - 3mtrs depth 3.34 MH/LM 1.67 MH/LM 1.34 MH/LM
3 - 4mtrs depth 5.00 MH/LM 2.50 MH/LM 2.00 MH/LM
4 - 5mtrs depth 6.66 MH/LM 3.33 MH/LM 2.66 MH/LM
2.7 Placing Binder - Gravel 0.21 MH/CM 0.11 MH/CM 0.08 MH/CM
2.8 Escombro Backfilling 0.42 MH/CM 0.21 MH/CM 0.17 MH/CM
2.9 Spreading, Tamping, and Grading 0.96 MH/SM 0.48 MH/SM 0.38 MH/SM
3 Mechanical Compaction, Plate Compaction 0.11 MH/CM 0.06 MH/CM 0.04 MH/CM
3.1 Manual Clearing and Grubbing
Clearing undergrowth and tress 12" 0.10 MH/SM 0.05 MH/SM 0.04 MH/SM
Clearing undergrowth and scrubs 0.06 MH/SM 0.03 MH/SM 0.02 MH/SM
3.2 Disposal of Soil 3.38 MH/CM 1.69 MH/CM 1.35 MH/CM
3.3 Hauling of Soil 2.00 MH/CM 1.00 MH/CM 0.80 MH/CM
3.4 Gravel Fill 4.14 MH/CM 2.07 MH/CM 1.66 MH/CM
3.5 Excavation - crane and Clampshell
with 8-men and 2-carpenters 2.14 MH/CM 1.07 MH/CM 0.86 MH/CM

Earthworks Pages 2 of 2
MASONRY WORKS
Man-hour per quantity
DESCRIPTION LOW AVERAGE HIGH
Qty Unit Qty Unit Qty Unit
1.1 Grouting and Tol Plastering 3.34 MH/SM 1.67 MH/SM 1.34 MH/SM
1.2 Pebble Finished 2.86 MH/SM 1.43 MH/SM 1.14 MH/SM
1.3 Marble Installation 4 MH/SM 2.00 MH/SM 1.60 MH/SM
1.4 1/4" x 2 x 8 Red Bricks 10.00 MH/SM 5.00 MH/SM 4.00 MH/SM
1.5 Glazed Tiles 21.06 MH/SM 10.53 MH/SM 8.42 MH/SM
1.6 Unglazed Tiles 8.70 MH/SM 4.35 MH/SM 3.48 MH/SM
1.7 Glazed Wall Tiles 6.00 MH/SM 3.00 MH/SM 2.40 MH/SM
1.8 Concrete Block Ext. Wall 9.00 MH/SM 4.50 MH/SM 3.60 MH/SM
1.9 Concrete Block Int. Wall 8.00 MH/SM 4.00 MH/SM 3.20 MH/SM
2 Brickwork 1.00 MH/SM 0.50 MH/SM 0.40 MH/SM
2.1 Plaster Wall and Ceiling 6.00 MH/SM 3.00 MH/SM 2.40 MH/SM
2.2 Hollow Tile Wall 4.00 MH/SM 2.00 MH/SM 1.60 MH/SM
2.3 Acoustic Ceiling 2.40 MH/SM 1.20 MH/SM 0.96 MH/SM
2.4 Vinyl Floor Tile 3.60 MH/SM 1.80 MH/SM 1.44 MH/SM
2.5 Unglazed or Mosaic Floor Tile 17.00 MH/SM 8.50 MH/SM 6.80 MH/SM
2.6 Laying of CHB and Adobe 2.28 MH/SM 1.14 MH/SM 0.91 MH/SM
2.7 Cement Finish 1.43 MH/SM 0.72 MH/SM 0.57 MH/SM
2.8 Concrete Hollow Blocks Laying
6" CHB 3.20 MH/SM 1.60 MH/SM 1.28 MH/SM
4" CHB 2.66 MH/SM 1.33 MH/SM 1.06 MH/SM
8" CHB 4.00 MH/SM 2.00 MH/SM 1.60 MH/SM
2.9 Vit. Tiles Floor 10.66 MH/SM 5.33 MH/SM 4.26 MH/SM
3.0 Vit. Tiles Wall 11.94 MH/SM 5.97 MH/SM 4.78 MH/SM

Masonry Works Pages 1 of 1


TINSMITHING WORKS
Man-hour per quantity
DESCRIPTION LOW AVERAGE HIGH
Qty Unit Qty Unit Qty Unit
1.1 Coorugated G.I. Sheet
Lifting 2.16 MH/SM 1.08 MH/SM 0.86 MH/SM
Installation 6.12 MH/SM 3.06 MH/SM 2.45 MH/SM
1.2 Installation of Asbestos Roofing 2.00 MH/SH 1 MH/SH 0.80 MH/SH
1.3 Installation of Aluminum or G.I. Sheet 1.60 MH/SH 0.8 MH/SH 0.64 MH/SH
1.4 Copper Cladding Roof Deck 1.01 MH/LM 0.505 MH/LM 0.40 MH/LM
1.5 Fabrication of G.I. Gutter 6.94 MH/SM 3.47 MH/SM 2.78 MH/SM
1.6 G.I. Sheet Roofing 1.64 MH/SH 0.82 MH/SH 0.66 MH/SH
1.7 Fabrication of G.I. Gutter 1.05 MH/LM 0.525 MH/LM 0.42 MH/LM
1.8 Fabrication of Downspout 1.94 MH/LM 0.97 MH/LM 0.78 MH/LM
1.9 Gutter Cut and Shape 0.32 MH/LM 0.16 MH/LM 0.13 MH/LM
2 Installation of Gutter 1.78 MH/LM 0.89 MH/LM 0.71 MH/LM
2.1 Downspout Cut and Shape 0.59 MH/LM 0.295 MH/LM 0.24 MH/LM
2.2 Downspout Installation 0.27 MH/LM 0.135 MH/LM 0.11 MH/LM
2.3 Corr. G.I. Roofing 3.60 MH/SM 1.8 MH/SM 1.44 MH/SM
2.4 Corr. Aluminum Roofing 3.60 MH/SM 1.8 MH/SM 1.44 MH/SM
2.5 Built-up Roofing 4-ply 17.00 MH/SM 8.5 MH/SM 6.80 MH/SM
2.6 Protected Metal 4.00 MH/SM 2 MH/SM 1.60 MH/SM
2.7 Corr.Asbestos Insy., lifting Hauling 3.40 MH/SM 1.7 MH/SM 1.36 MH/SM
2.8 Leaders and Gutters 1.20 MH/SM 0.6 MH/SM 0.48 MH/SM

Tinsmithing Work Pages 1 of 1


CONCRETE WORKS
Man-hour per quantity
DESCRIPTION LOW AVERAGE HIGH
Qty Unit Qty Unit Qty Unit
1.1 Placing Concrete
Slab on Fill 10.00 MH/CM 5.00 MH/CM 4.00 MH/CM
Slip Form 50.00 MH/CM 25.00 MH/CM 20.00 MH/CM
Floor Finish Unhardened 2.00 MH/SM 1.00 MH/SM 0.80 MH/SM
Concrete Finish Hardened 2.86 MH/SH 1.43 MH/SH 1.14 MH/SH
1.2 Rebar Works
Ground Floor Installation 0.14 MH/KG 0.07 MH/KG 0.06 MH/KG
Upper Floor Installation 0.16 MH/KG 0.08 MH/KG 0.06 MH/KG
Fabrication 0.20 MH/KG 0.10 MH/KG 0.08 MH/KG
1.3 Mixing Manual 32.00 MH/CM 16.00 MH/CM 12.80 MH/CM
1.4 Mixing Machine 3.60 MH/CM 1.80 MH/CM 1.44 MH/CM
1.5 More Than 1.80cm Pour
Chute From Truck 14.00 MH/CM 7.00 MH/CM 5.60 MH/CM
Crane and Bucket 28.00 MH/CM 14.00 MH/CM 11.20 MH/CM
Wheeling 54.00 MH/CM 27.00 MH/CM 21.60 MH/CM
Finishing 5.60 MH/SM 2.80 MH/SM 2.24 MH/SM
1.6 Concrete Pour on Elevated and Shored Slab
Forming, chute and bucket 42.00 MH/CM 21.00 MH/CM 16.80 MH/CM
1.7 Placement of Rebars on Footing 1.06 MH/KG 0.53 MH/KG 0.42 MH/KG
1.8 Field Fabrication of Rebars 0.66 MH/KG 0.33 MH/KG 0.26 MH/KG

Concrete Works Pages 1 of 1


PLUMBING WORKS
Man-hour per quantity
DESCRIPTION LOW AVERAGE HIGH
Qty Unit Qty Unit Qty Unit
1.1 Laying Asbestos Pipe
1/2" Dia 1.32 MH/LM 0.66 MH/LM 0.53 MH/LM
3/4" Dia 1.32 MH/LM 0.66 MH/LM 0.53 MH/LM
1-1/4" Dia 1.48 MH/LM 0.74 MH/LM 0.59 MH/LM
1 1/2" - 2" Dia 1.64 MH/LM 0.82 MH/LM 0.66 MH/LM
2 1/2" Dia 1.97 MH/LM 0.99 MH/LM 0.79 MH/LM
3" 2.16 MH/LM 1.08 MH/LM 0.86 MH/LM
3 1/2" Dia 2.30 MH/LM 1.15 MH/LM 0.92 MH/LM
4" 2.64 MH/LM 1.32 MH/LM 1.06 MH/LM
1.2 Cast Iron Pipe
2" 4.38 MH/LM 2.19 MH/LM 1.75 MH/LM
4" 6.58 MH/LM 3.29 MH/LM 2.63 MH/LM
6" 9.84 MH/LM 4.92 MH/LM 3.94 MH/LM
8" 13.14 MH/LM 6.57 MH/LM 5.26 MH/LM
10" 19.70 MH/LM 9.85 MH/LM 7.88 MH/LM
12" 20.62 MH/LM 10.31 MH/LM 8.25 MH/LM
14" 24.10 MH/LM 12.05 MH/LM 9.64 MH/LM
16" 27.38 MH/LM 13.69 MH/LM 10.95 MH/LM
18" 30.68 MH/LM 15.34 MH/LM 12.27 MH/LM
20" 32.86 MH/LM 16.43 MH/LM 13.14 MH/LM
24" 36.14 MH/LM 18.07 MH/LM 14.46 MH/LM
30" 41.08 MH/LM 20.54 MH/LM 16.43 MH/LM
1.3 Laying of PVC Pipe
1/2" - 3/4" Dia 0.38 MH/LM 0.19 MH/LM 0.15 MH/LM
1" - 1 1/4" Dia 1.48 MH/LM 0.74 MH/LM 0.59 MH/LM
1 1/2" - 2" Dia 1.64 MH/LM 0.82 MH/LM 0.66 MH/LM
2 1/2" Dia 1.96 MH/LM 0.98 MH/LM 0.78 MH/LM
3" 2.16 MH/LM 1.08 MH/LM 0.86 MH/LM
4" 2.62 MH/LM 1.31 MH/LM 1.05 MH/LM
5" 3.28 MH/LM 1.64 MH/LM 1.31 MH/LM
6" 4.92 MH/LM 2.46 MH/LM 1.97 MH/LM
1.4 Laying RCP 8men (1 team)
24" 8.00 MH/LM 4.00 MH/LM 3.20 MH/LM
36" 12.80 MH/LM 6.40 MH/LM 5.12 MH/LM
48" 21.34 MH/LM 10.67 MH/LM 8.54 MH/LM
6' - 18" 2.66 MH/LM 1.33 MH/LM 1.06 MH/LM
1.5 Lavatory 16.00 MH/LM 8.00 MH/LM 6.40 MH/LM
1.6 Water Closet 24.00 MH/LM 12.00 MH/LM 9.60 MH/LM
1.7 Urinal Utility Stall 48.00 MH/LM 24.00 MH/LM 19.20 MH/LM
1.8 Urinal, Pedestal Type 32.00 MH/LM 16.00 MH/LM 12.80 MH/LM
1.9 Shower and Stall 20.00 MH/LM 10.00 MH/LM 8.00 MH/LM
2 5-man Group Shower 72.00 MH/LM 36.00 MH/LM 28.80 MH/LM
2.1 Bath Tubs 48.00 MH/LM 24.00 MH/LM 19.20 MH/LM
2.2 Slope Sink 28.00 MH/LM 14.00 MH/LM 11.20 MH/LM
2.3 Hot Water Heater 28.00 MH/LM 14.00 MH/LM 11.20 MH/LM
2.4 6-person Wash Sink 52.00 MH/LM 26.00 MH/LM 20.80 MH/LM
2.5 Drinking Fountain 26.00 MH/LM 13.00 MH/LM 10.40 MH/LM
2.6 Eye Wash 16.00 MH/LM 8.00 MH/LM 6.40 MH/LM
2.7 Miscellaneous Fixtures 4.00 MH/LM 2.00 MH/LM 1.60 MH/LM
2.8 Partitions 16.00 MH/LM 8.00 MH/LM 6.40 MH/LM
2.9 Laying of 24" Dia. RCP 8.00 MH/LM 4.00 MH/LM 3.20 MH/LM
3 Laying of 36" Dia. RCP 12.80 MH/LM 6.40 MH/LM 5.12 MH/LM
3.1 Laying of 48" Dia. RCP 21.32 MH/LM 10.66 MH/LM 8.53 MH/LM

Plumbing Works Pages 1 of 2


PLUMBING WORKS
Man-hour per quantity
DESCRIPTION LOW AVERAGE HIGH
Qty Unit Qty Unit Qty Unit

Plumbing Works Pages 2 of 2


CARPENTRY WORKS
Man-hour per quantity
DESCRIPTION LOW AVERAGE HIGH
Qty Unit Qty Unit Qty Unit
A. FORM WORKS INSTALLATION
1.1 Wall in Ground 4.00 MH/SM 2.00 MH/SM 1.60 MH/SM
1.2 Wall above ground 4.70 MH/SM 2.35 MH/SM 1.88 MH/SM
1.3 Beams 6.16 MH/SM 3.08 MH/SM 2.46 MH/SM
1.4 Columns 4.70 MH/SM 2.35 MH/SM 1.88 MH/SM
1.5 Suspended slab
0 - 18" 3.34 MH/SM 1.67 MH/SM 1.34 MH/SM
18 - 36" 6.66 MH/SM 3.33 MH/SM 2.66 MH/SM
1.6 Elevated and shored slab forming
Forming only 17.20 MH/SM 8.60 MH/SM 6.88 MH/SM
Forming and shoring 22.00 MH/SM 11.00 MH/SM 8.80 MH/SM
1.7 Wood wall and partition 1.00 MH/SM 0.50 MH/SM 0.40 MH/SM

B. FORM WORKS FABRICATION 2.15 MH/SM 1.08 MH/SM 0.86 MH/SM

C. STRIPPING OF FORM WORKS

1.1 Wall in Ground 0.50 MH/SM 0.25 MH/SM 0.20 MH/SM


1.2 Wall above ground 2.58 MH/SM 1.29 MH/SM 1.03 MH/SM
1.3 Beams 2.06 MH/SM 1.03 MH/SM 0.82 MH/SM
1.4 Columns 1.70 MH/SM 0.85 MH/SM 0.68 MH/SM
1.5 Suspended slab
0 - 18" 1.67 MH/SM 0.83 MH/SM 0.67 MH/SM
18 - 36" 2.16 MH/SM 1.08 MH/SM 0.86 MH/SM
1.6 Elevated and shored slab forming
1.7 strip of forms 7.00 MH/SM 3.50 MH/SM 2.80 MH/SM

Floor Slab at grade strip of forms 5.60 MH/SM 2.80 MH/SM 2.24 MH/SM

D. INSTALLATION OF CARPENTRY WORKS

1.1 Plywood partition 2.00 MH/PC 1.00 MH/PC 0.80 MH/PC


1.2 T & G Flooring and Siding 0.29 MH/BF 0.14 MH/BF 0.11 MH/BF
1.3 Ceiling Framework 0.73 MH/BF 0.36 MH/BF 0.29 MH/BF
1.4 Siding Framework 0.53 MH/BF 0.27 MH/BF 0.21 MH/BF
1.5 Flooring framing 1.94 MH/BF 0.97 MH/BF 0.77 MH/BF
1.6 Wooden Post Erection 0.85 MH/BF 0.43 MH/BF 0.34 MH/BF
1.7 Truss Fabrication 0.70 MH/BF 0.35 MH/BF 0.28 MH/BF
1.8 Truss Installation 1.60 MH/BF 0.80 MH/BF 0.64 MH/BF
1.9 Girt Installation 0.43 MH/BF 0.21 MH/BF 0.17 MH/BF
2 Plates Installation 0.27 MH/BF 0.13 MH/BF 0.11 MH/BF
2.1 Purlins Installation 0.53 MH/BF 0.27 MH/BF 0.21 MH/BF
2.2 Facia Board Installation 0.91 MH/BF 0.46 MH/BF 0.36 MH/BF
2.3 1/4" or 3/4" thck plywood
cutting by manual 2.00 MH/PC 1.00 MH/PC 0.80 MH/PC
assembly 0.83 MH/SH 0.42 MH/SH 0.33 MH/SH
2.4 Ceiling Framework
Frame Installation 2.66 MH/SM 1.33 MH/SM 1.06 MH/SM
Plywood Installation 2.00 MH/SM 1.00 MH/SM 0.80 MH/SM
2.5 Cabinet Boarding 0.26 MH/BF 0.13 MH/BF 0.10 MH/BF
2.6 Cabinet Framing 0.36 MH/BF 0.18 MH/BF 0.14 MH/BF
2.7 Wood Wall Partitions 1.00 MH/SM 0.50 MH/SM 0.40 MH/SM
2.8 Panel Wall 14.00 MH/SM 7.00 MH/SM 5.60 MH/SM
2.9 Forming Weight Anchor Bolts 9.00 MH/SM 4.50 MH/SM 3.60 MH/SM
3.0 Net Forming 7.00 MH/SM 3.50 MH/SM 2.80 MH/SM

E. DOORS AND WINDOWS

Carpentry Works Pages 1 of 2


CARPENTRY WORKS
Man-hour per quantity
DESCRIPTION LOW AVERAGE HIGH
Qty Unit Qty Unit Qty Unit

1.1 W-Panel Installation 0.8 MH/PC 0.40 MH/PC 0.32 MH/PC


1.2 Steel Windows Installation 4.00 MH/PC 2.00 MH/PC 1.60 MH/PC
1.3 Louver Windows Installation
Fixed Asbestos 9.26 MH/SM 4.63 MH/SM 3.70 MH/SM
Fixed Metal Louver 6.24 MH/SM 3.12 MH/SM 2.50 MH/SM
Fixed G.I. Sheet 9.26 MH/SM 4.63 MH/SM 3.70 MH/SM
Fixed Glass 6.24 MH/SM 3.12 MH/SM 2.50 MH/SM
Fixed Wooden 6.76 MH/SM 3.38 MH/SM 2.70 MH/SM
1.4 Aluminum Framed Windows 20.00 MH/EA 10.00 MH/EA 8.00 MH/EA
1.5 Sliding Glass Door 24.00 MH/EA 12.00 MH/EA 9.60 MH/EA
1.6 Hollow Metal Door 20.00 MH/EA 10.00 MH/EA 8.00 MH/EA
1.7 Rolling Doors 50.00 MH/EA 25.00 MH/EA 20.00 MH/EA
1.8 Fixed Window 0.63 MH/SF 0.31 MH/SF 0.25 MH/SF
1.9 Door Lockset 3.20 MH/SET 1.60 MH/SET 1.28 MH/SET
2.0 Door Jamb: Fabrication 0.44 MH/BF 0.22 MH/BF 0.18 MH/BF
Installation 0.66 MH/BF 0.33 MH/BF 0.26 MH/BF
2.1 Cyclone wire Installation 6.24 MH/SM 3.12 MH/SM 2.50 MH/SM

Carpentry Works Pages 2 of 2