PHILIPPINE PRODUCTIVITY RATIOS
DESCRIPTION                      MANHOUR/UNIT     UNIT
1.STRUCTURAL EXCAVATION
    Common excavation
    Hand                                                        6         MH/M3
    Machine                                                    0.5        MH/M3
    Rock excavation                                             8         MH/M3
    Hauling of spoils                                           1         MH/M3
2.STRUCTURAL BACKFILL
    By hand                                                     5         MH/M3
    By machine                                                  2         MH/M3
    3.TRENCHING
    By hand                                                     6         MH/M3
    By machine                                                 0.5        MH/M3
3.EXCAVATION- MANUAL
    Common earth                                                8         MH/M3
    Loam of sand                                               1.31       MH/M3
    Clay or heavy soil                                         1.64       MH/M3
    Rock                                                       2.63       MH/M3
4.EXCAVATION- MECHANICAL
    Common earth                                               6.67       MH/M3
    Rock with jack hammer                                     16.67       MH/M3
5.BACKFILLING
    Common manual                                              0.82       MH/M3
    Gravel fill manual                                          5         MH/M3
6.TRENCHING & BACFILLING OF UNDERGROUND PIPING
USING EXCAVATION MATLS MANUAL FROM:
    0 – 2m Depth                                               1.25       MH/LM
    2 – 3m Depth                                               1.67       MH/LM
    3 – 4m Depth                                               2.5        MH/LM
    4 – 5m Depth                                               3.33       MH/LM
    Placing binder gravel                                      0.11       MH/M3
    Escombro backfilling                                       0.21       MH/M3
    Spreading,tamping & grading                                0.48       MH/M2
    Mechanical compaction, plate compaction                    0.06       MH/M3
7.MANUAL CLEARING & GRUBBING
    Clearing under growth & trees – 12″                        0.05       MH/M2
    Clearing under growth & shrubs                             0.03       MH/M2
    Disposal of soil                                           1.69       MH/M3
    Hauling of soil                                             1         MH/M3
    Gravel fill                                                2.07       MH/M3
8.EXCAVATION – CRANE & CLAMPSHELL
    With 8 men & 2 carpenters                                  1.07       MH/M3
9.ROOFING AND SIDING
    Roofing
      Metallic                                                 0.97       MH/m2
      Non-Metallic                                             1.51       MH/m2
    Siding
      Metallic                                                 1.29       MH/m2
      Non-Metallic                                             1.51       MH/m2
10.CONCRETE WORKS
   Grade members
     Formworks                                               2.54         MH/M2
     Concreting                                              8.54         MH/M3
     Rebar                                                   0.07         MH/kg
     Finishing                                               0.4          MH/M2
   Suspended members
     Formworks                                               3.28         MH/M2
      Concreting                                          16.7   MH/M3
      Rebar                                               0.08   MH/kg
      Finishing                                           0.8    MH/M2
      Embeded metal                                       0.27   MH/kg
      Water proofing                                      1.82   MH/M2
      Joint filler                                        0.3    MH/lLm
11.PLACING CONCRETE
    Slab on Fill                                           5     MH/M3
    Slip Form                                              25    MH/M3
    Floor Finish Unhardened                                1     MH/M3
    Concrete finished hardened                            1.43   MH/M3
12.REBAR WORKS
    Ground floor installation                             0.07   MH/M3
    Upper floor installation                              0.08   MH/M3
    Fabrication                                           0.1    MH/M3
    Mixing manual                                          16    MH/M3
    Mixing machine                                        1.8    MH/M3
13.MORE THAN 1.8 M3 POUR
    Chute from truck                                       7     MH/M3
    Crane & bucket                                        14     MH/M3
    Wheeling                                              27     MH/M3
    Finishing                                             2.8    MH/M3
14.FORMWORKS & CARPENTRY WORKS
    FORM WORKS INSTALLATION
        Wall on ground                                     2     MH/M2
        Wall above ground                                 2.35   MH/M2
        Beams                                             3.08   MH/M2
        Columns                                           2.35   MH/M2
        Suspended slab
        Suspended slab 0 – 18″                            1.67   MH/M2
        Suspended slab 10 – 36″ up                        3.33   MH/M2
        Elevated & shored slab forming
        Forming only                                      8.6    MH/M2
        Forming & Shoring                                 11     MH/M2
        Wood wall & Partition                             0.5    MH/M2
    FORM WORKS FABRICATION
        Form works fabrication                             1     MH/M2
    STRIPPING OF FORMS
        Wall on ground                                    0.25   MH/M2
        Wall above 10″                                    1.29   MH/M2
        Beams                                             1.03   MH/M2
        Columns                                           0.85   MH/M2
    Suspended slab
        Suspended slab 0 – 18″                            0.83   MH/M2
        Suspended slab 10 – 36″ up                        1.08   MH/M2
        Elevated & shored slab forming – strip of forms   3.5    MH/M2
        Floor slab at grade – strip of forms              2.8    MH/M2
    INSTALLATION OF CARPENTRY WORKS
        Plywood partition                                  1     MH/PC
        T & G Flooring and Siding                         0.14   MH/B.F.
        Ceiling & frame work                              0.36   MH/B.F.
        Siding frame work                                 0.27   MH/B.F.
        Flooring framing                                  0.97   MH/B.F.
        Wooden post errection                             0.43   MH/B.F.
        Truss Fabrication                                 0.35   MH/B.F.
        Truss Installation                                0.8    MH/B.F.
        Girt Installation                                 0.21   MH/B.F.
        Plates Installation                               0.13   MH/B.F.
        Purlins Installation                              0.27   MH/B.F.
        Fascia board Installation                   0.46      MH/B.F.
        1/4″ or 3/4″ thk. plywood
          Cutting by manual                          1        MH/PC
          Assembly                                  0.42      MH/M2
15.ARCHITECTURAL SPECIALTIES
    DOORS
        Wooden                                      2.37      MH/M2
        Steel                                       7.64      MH/M2
        Aluminum                                    8.07      MH/M2
        Cyclone wire                                7.64      MH/M2
        WINDOWS
        Glass                                      3.23       MH/M2
        Louver                                     4.63       MH/M2
        Steel                                      32.29      MH/M2
    PARTITIONS
        single wall                                 2.48      MH/M2
        Wooden wall                                 3.44      MH/M2
        Wooden Louver                               3.44      MH/M2
        cyclone Louver                              5.38      MH/M2
    PAINTING ( 3 coats )
        Equipment                                   0.24      MH/f2
        Pipes                                       0.3       MH/f2
        Miscellaneous                               0.24      MH/f2
16.STRUCTURAL STEEL WORKS
    STRUCTURAL STEEL
        Fabrication
        Light                                     110-130     MH/MT
        Heavy                                      60-90      MH/MT
        Errection
        Light                                      70-100     MH/MT
        Heavy                                      40-60      MH/MT
    WELDING ( one pass only )
        1- Welder and 1- Helper ( 16 total mh )    40-50      Lf/day
    G.1 STRUCTURAL STEEL
        Fabrication
        Heavy weight                               50-90      MH/MT
        Light weight                              100-125     MH/MT
        Grating 1 1/4″ x 3/16″                    3.0 – 3.5   MH/SF
        Star threat grating                       4.0 – 5.0   MH/SF
        Errection
        Heavy Structural teel                      30 – 60    MH/MT
        Light Structural steel                     60- 90     MH/MT
        Stacks ( Inc. full welding )              250 – 300   MH/MT
        Tanks ( Inc. full welding )               200 – 275   MH/MT
17.FINISHING AND MASONRY WORKS
    H. CHB
      4” CHB
      Laying                                      8.0 – 10    m2/day
      Tooling                                     11 – 14     m2/day
      Plastering                                  8.0 – 10    m2/day
    6” CHB
      Laying                                      7.0 – 9.0   m2/day
      Tooling                                     11 – 14     m2/day
      Plastering                                  8.0 – 10    m2/day
    8” CHB
      Laying                                      6.0 – 8.0   m2/day
      Tooling                                     11 – 14     m2/day
      Plastering                                  8.0 – 10    m2/day