To:               Nancy Meyers
From:             Alex Michel
          Date:             February 16, 2022
          Subject:          APLED 121-Progress Report
                                      BEDROOM RENOVATION PROGRESS REPORT
          PURPOSE OF REPORT
          The purpose of this report is to update myself on the progress we currently made in the process
          of completing my bedroom renovation. I’m doing this project for the first time with my cousin
          and one other friend. We began this project on January 28th, 2021 and wrote this progress
          report on March 7th, 2021.
          To do list and estimated dates:
                1.   Design blueprint for room (January 28-29)       6. Drywall & insulation (March 5-8)
                2.   Contact Framers (February 1)                    7. Install doors (March 14)
                3.   Tear dividing wall down (February 12-14)        8. Paint room (March 19-21)
                4.   Frame closet area (February 23)                 9. Cleanup (March 26-28)
                5.   Install new light fixture (March 1)             10. Refurnish (April 1st)
          GANTT TABLE
Task                                   Week 1-2         Week 3-4     Week 5-6       Week 7-8        Week 9-10
Design Bedroom layout
Contact framers
Tear dividing wall down
Frame closet area
Install new light fixture in closet
Drywall and insulation
Install doors
Paint room
Cleanup
Refurnish
          Work Completed                                Work Remaining
          WORK COMPLETED
WEEK 1-2
   •   Design layout was completed on the 29th of January
   •   Framers were contacted on February 1st
WEEK 3-4
  • Tearing down the dividing wall for closet was completed on February 14th
  • February 23rd the framing for the closet was completed
WEEK 5-6
  • Installing the light fixtures and bulbs for room was done on March 1st
  • Insulation is completed on the 5th of march
PROBLEMS ENCOUNTERED
   •   Period of no progress being made while waiting for material and framers to show up
       and complete their job.
   •   The installation of lights and insulation got pushed back so drywalling had to be done a
       couple days later.
WORK REMAINING
WEEK 5-6
   •   Finish drywalling, mudding, and prepping the closet
WEEK 7-8
   •   Install the closet and bedroom door
   •   Finding the colored paint and painting the room
WEEK 9-10
   •   Need to cleanup at the end of the project
   •   Refurnish the bedroom and closet once the rest is completed
CONCLUSION
Up to this current period we have completed everything up to insulation in the closet and in the
process of drywalling in week 5-6. The target date I set for the project to be done is April 8th.
We fell of track at the beginning of the project with waiting on material and framers but were
managed to catch back up on track for the upcoming estimated dates.
RECOMMENDATIONS
  •   I recommend calling the framers as soon as possible to get you scheduled the soonest
      possible date for maximum efficiency.
  •   Prepare a material list so you know exactly what is needed to do your project, this helps
      not have to go to the store mid work because something is missing.