Element of Structure: Construction of HCB: Submitted By: For Contractor

This inspection checklist is for the construction of HCB (hollow concrete blocks) at a residential tower project in Addis Ababa, Ethiopia. It contains 20 items to inspect regarding the quality of HCB, mortar materials and testing, rebar installation, wall alignments, corners, grouting, and scaffolding. The checklist is to be filled out and signed by representatives of the contractor and consultant to confirm inspections were completed.

Uploaded by

bedr kemeredin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
770 views1 page

Element of Structure: Construction of HCB: Submitted By: For Contractor

This inspection checklist is for the construction of HCB (hollow concrete blocks) at a residential tower project in Addis Ababa, Ethiopia. It contains 20 items to inspect regarding the quality of HCB, mortar materials and testing, rebar installation, wall alignments, corners, grouting, and scaffolding. The checklist is to be filled out and signed by representatives of the contractor and consultant to confirm inspections were completed.

Uploaded by

bedr kemeredin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Inspection Check List Form Ref:

PROJECT INFORMATION
CLIENT: AE FIRM
EAGLE HILLS ETHIOPIA REAL ESTATE P.L.C. ZIAS DESIGN INTERNATIONAL P.L.C.
PROJECT TITLE: CONTRACTOR:
LA GARE RESIDENTIAL TOWER 1 BUILDING, COMPLETION WORKS PACKAGE ELMI OLINDO CONSTRUCTION P.L.C.
PROJECT LOCATION: CONTRACT NO:
ADDIS ABABA
Submittal Information
Reference
Submission Date: Drawing No.
Issue No: Technical Specificatio
Spec Division: Bill Of Quantities
Section Catalogues
No. Pages In Submittal Others

Element of Structure:
Construction of HCB
1. HCB quality test result is submitted. Yes No
2. HCB size and geometry is inspected. Yes No
3. Mortar ingredients (raw materials, sand cement & water) and strength test result are
submitted. Yes No
4. Mortar Mix ratio /box size/ is checked. Yes No
5. Mortar joint thickness checked. Yes No
6. Program to prevent expiry of mortar during longer break Yes No

7. Re-bar diameter checked & strength test is submitted, installing at vertical 1m spacing
and placing horizontal truss type at every two coarse checked.
Yes No
8. Internal / External Corner Coordinates are given. Yes No
9. Offset Coordinates are given. Yes No

10. First course of the HCB work is checked as per the pre-set out coordinates.
Yes No
11. Horizontal Alignment of the wall is checked. Yes No
12. Vertical alignment of the wall is checked using plum bob hand tool. (At every two(2)
courses of the wall.) Yes No
13. Inside Corner (right angle) of the wall is checked using squadra hand tool.
Yes No

14. Horizontal & vertical Re-bar diameter & arrangement are checked as per the drawing.
Yes No
15. The Proper implementation of Epoxy grouting is checked. Yes No
16. Confirm the wall can meet the specified STC class. Yes No
17. Embedment of electrical & sanitary items are checked. Yes No
18. Means of transport of goods. Yes No
19. Submittal of scaffolding design. Yes No
20. Labor tools Quality. Yes No

Submitted By: For Contractor


Name Signature Date

For Consultant
Surveyor
Name Signature Date

Site Inspector
Name Signature Date

Material Inspector
Name Signature Date