The Boilers Act,1923 ,
&
Safety Aspects
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT
THE BOILER ACT ,1923
BOILER OPERATION ENGINEERS’ RULES , 2011
BOILER ATTENDANTS’ RULES, 2011
INDIAN BOILER REGULATION 1950
EASE OF DOING BUSINESS
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 2
THE BOILERS ACT,1923
WHAT IS BOILER AND BOILER COMPONENT?
STEAM PIPE ,ECONOMISER ,FEED PIPE ?
BOILER REGISTRATION REQUIREMENTS
BOILER CERTIFICATE RENEWAL REQUIREMENT
BOILER REPAIRING
BOILER TRANSFER /SELL / PURCHASE
BOILER NON USE/SCRAPPING
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 3
THE BOILERS ACT,1923
THE DUTY OF BOILER OWNERS
THE PENALTIES FOR NON-COMPLIANCE
AUTHORITY FOR MAKING REGULATIONS (CENTRAL BOILER BOARD)
THE POWERS OF CENTRAL AND STATE GOVERNMENTS TO MAKE RULES
APPEAL AGAINST INSPECTORS OR CHIEF INSPECTOR’S ORDERS.
EXEMPTIONS
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 4
DEFINITIONS
• “BOILER” MEANS A PRESSURE VESSEL IN WHICH STEAM IS GENERATED FOR USE
EXTERNAL TO ITSELF BY APPLICATION OF HEAT WHICH IS WHOLLY OR PARTLY
UNDER PRESSURE WHEN STEAM IS SHUT OFF BUT DOES NOT INCLUDE A
PRESSURE VESSEL,
I. WITH CAPACITY LESS THAN 25 LITERS. (SUCH CAPACITY BEING MEASURED
FROM THE FEED CHECK VALVE TO THE MAIN STEAM STOP VALVE);
II. WITH LESS THAN ONE KILOGRAM PER CENTIMETER SQUARE DESIGN GAUGE
PRESSURE AND WORKING GAUGE PRESSURE; OR
III. IN WHICH WATER IS HEATED BELOW ONE HUNDRED DEGREES CENTIGRADE:
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 5
DEFINITIONS
• “BOILER COMPONENTS” MEANS
• STEAM PIPING, FEED PIPING, ECONOMISER, SUPER HEATER, ANY MOUNTING OR
OTHER FITTING AND ANY OTHER EXTERNAL OR INTERNAL PART OF A BOILER WHICH
IS SUBJECT TO PRESSURE EXCEEDING ONE KILOGRAM PER CENTIMETER SQUARE
GAUGE
• “STEAM PIPE” MEANS ANY PIPE THROUGH WHICH STEAM PASSES IF,
i. THE PRESSURE AT WHICH STEAM PASSES THROUGH SUCH PIPE EXCEEDS 3.5
KILOGRAMS PER SQUARE CENTIMETER ABOVE ATMOSPHERIC PRESSURE ; OR
ii. SUCH PIPE EXCEEDS 254 MILLIMETERS IN INTERNAL DIAMETER AND THE PRESSURE
OF STEAM EXCEEDS 1 KILOGRAMS PER SQUARE CENTIMETER ABOVE THE
ATMOSPHERIC PRESSURE,
• AND INCLUDES IN EITHER CASE ANY CONNECTED FITTING OF A STEAM PIPE:
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 6
DEFINITIONS
• “ACCIDENT” MEANS
• AN EXPLOSION OF BOILER, OR BOILER COMPONENT, WHICH IS CALCULATED TO WEAKEN
THE STRENGTH OR AN UNCONTROLLED RELEASE OF WATER OR STEAM THERE FROM,
LIABLE TO CAUSE DEATH OR INJURY TO ANY PERSON OR DAMAGE TO ANY PROPERTY;
“ OWNER” INCLUDES ANY PERSON “POSSESSING OR” USING A BOILER AS A AGENT OF THE
OWNER THEREOF AND ANY PERSON USING A BOILER WHICH HE HAS HIRED OR OBTAINED
ON LOAN FROM THE OWNER THEREOF;
“ MANUFACTURE” MEANS MANUFACTURE, CONSTRUCTION AND FABRICATION OF BOILER
OR BOILER COMPONENT, OR BOTH
“MANUFACTURER” MEANS A PERSON ENGAGED IN THE MANUFACTURE;
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 7
WHY REGISTRATION OF BOILER ?
AS PER SECTION 6, USE OF UNREGISTERED AND UNCERTIFIED BOILER IS PROHIBITED
NO OWNER OF BOILER SHALL USE OR PERMIT IT TO BE USED ,
UNLESS BOILER HAS BEEN REGISTERED AS PER ACT
IN CASE OF TRANSFERRED BOILER, SUCH TRANSFER HAS BEEN REPORTED IN PRESCRIBED
MANNER
BOILER CERTIFICATE OR PROVISIONAL ORDER AUTHORIZING TO USE A BOILER IN FORCE
AT A HIGHER PRESSURE THAN THE MAXIMUM PRESSURE RECORDED IN BOILER
CERTIFICATE/PO
WHEN BOILER IS NOT IN CHARGE OF PERSONS HOLDING PROFICIENCY OR COMPETENCY
CERTIFICATE AS REQUIRED BY RULES
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 8
REGISTRATION OF A NEW BOILER
AS PER SECTION 4C
BOILER MANUFACTURER MUST HAVE FACILITIES FOR DESIGN AND CONSTRUCTION AS
PRESCRIBED IN IBR 1950 . ( BOILER MANUFACTURER ARE RECOGNIZED BY IA)
DESIGN AND DRAWINGS OF A BOILER IS TO BE APPROVED BY IA
ALL THE MATERIALS, MOUNTINGS AND FITTINGS WHICH ARE TO BE USED IN
CONSTRUCTION OF BOILER MUST MEET THE SPECIFICATIONS AS PRESCRIBED IN
REGULATIONS
PERSONS ENGAGED FOR WELDING OF BOILER MUST HAVE WELDERS CERTIFICATE
ISSUED BY CI
THAT MEANS PURCHASE BOILER FROM AUTHORIZED MANUFACTURER. LIST OF BOILER
MANUF. FOR GUJARAT STATE IS AVAILABLE ON DEPT. WEBSITE WWW.DOB.GUJARAT.GOV.IN
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 9
WITH THE BOILER, MANUFACTURER WILL HANDOVER MAKERS PAPERS MEANS
FORM II ,FORM III, FORM IVA, RUB OFF OR FACSIMILE, AS BUILT APPROVED
DRAWINGS, NDT REPORTS, MTC OF ALL MOUNTINGS AND FITTINGS.
THIS FORMS ARE REVISED RECENTLY SO CHECK FOR THE FORMAT
LEAST PRESSURE OF BOILER COMPONENT MUST BE MENTIONED IN FORM III
APPLY ONLINE FOR REGISTRATION OF BOILER THROUGH IFP.
IN PARALLEL,
APPLY FOR ERECTION PERMISSION IF BOILER IS SITE ERECTED REPAIRER LETTER
SUBMIT STEAM, FEED & BLOW DOWN LINE DRAWING FOR APPROVAL AND
FABRICATION PERMISSION DRG.APPR
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 10
(1) ERECTION PERMISSION :
FIRMS LETTER WITH APPROPRIATE CLASS REPAIRER/ERECTOR LETTER,
REPAIRER CERT. , IBR APPD. WELDER CERT. REQUIRED (REPAIRER LIST
AVAILABLE ON DEPT. WEBSITE)
CHECK CLASS OF REPAIRER (BOILER PRESSURE IS CRITERIA ) & WELDER
(MATERIAL GRADE & POSITION) ,VALIDITY
• WATCH SAME IBR APPD WELDER IS ENGAGED DURING WELDING AND WORK IS
BEING SUPERVISED BY ENGINEER
• KEEP RECORD FOR OPEN INSPECTION , MATERIAL INSPECTION BY COMPETENT
PERSON
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 11
(2) SUBMIT STEAM, FEED , BLOW DOWN LINE DRAWING FOR APPROVAL AND FABRICATION
PERMISSION
SAME DOCUMENTS OF REPAIRER & WELDER AS ABOVE MENTIONED PLUS REQUIRED DRG
SCRUTINY AND HT FEES.
BUY STEAM LINE MATERIALS FROM RELIABLE SOURCES
ALWAYS ASK FOR ORIGINAL MTC WITH MATERIAL SUPPLY , CHECK ALL MATERIALS WITH MTC &
VERIFY STAMPING , ARRANGE ALL MATERIAL FOR INSPECTION ( PUT VIDEO)
IN MTC CHECK MATERIAL GRADE , DESIGN PRESSURE AND TEMP , ETC
DO PMI FOR ALLOY STEEL MATERIAL
INSIST FOR FRESH MATERIAL
FORM III A FOR PIPE (Q = 5), III B FOR TUBES (Q = 10) III C FOR MOUNTINGS & FITTINGS (Q =50)
(PUT SAMPLE)
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 12
FORM IIIA
FORM IIIB
FORM IIIC
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 13
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 14
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 15
(3) APPROVAL OF RADIOGRAPHY REPORTS & SR CHART
CHECK REPORT WITH FILMS, SOURCE MOVEMENT PERMISSION, RADIOGRAPHER
CERT. AND ITS VALIDITY
ERECTION PERMISSION FOR BOILER,
STEAM, FEED, BLOWDOWN LINE DRG AND IT’S FABRICATION PERMISSION
UP TO 17.5 KG/CM2 IS GRANTED BY DY. DIRECTOR OF REGION AND ABOVE IS GRANTED
BY DIRECTOR OF BOILERS
NDT REPORTS AND SR CHART IS APPROVED BY D.DY. OF REGION.
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 16
SECOND HAND BOILER :
FIRST OF ALL APPLY FOR OWNERSHIP TRANSFER ON DEPT. WEBSITE. BUYER AND
SELLER LETTER IS REQUIRED
ONCE TRANSFER IS EFFECTED,
APPLY FOR ERECTION PERMISSION IF REQD.
STEAM, FEED,BLOW DOWN LINE DRG APPROVAL AND FABRICATION AND ERECTION
PERMISSION
APPROVAL OF NDT REPORTS
OFFER FOR HYD.TESTING
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 17
REGISTRATION OF A BOILER
AS PER SECTION 7,
AN APPLICATION WITH SUCH DOCUMENTS AS PRESCRIBED IN REGULATIONS AND
REQUIRED FEES IS TO BE MADE TO INSPECTOR
A DATE IS FIXED FOR EXAMINATION OF BOILER
AFTER INSPECTION OF BOILER, INSPECTOR SUBMITS HIS REPORT TO CHIEF INSPECTOR
CHIEF INSPECTOR MAY REGISTER A BOILER AND ASSIGN REGISTRATION NUMBER OR
SUGGEST ANY ALTERATION, ADDITION OR RENEWAL IF NECESSARY
A CERTIFICATE/PO IS ISSUED WITH A TIME LIMIT AND PERMITTED MAX. PRESSURE
OWNER TO MARK REGISTRATION NUMBER WITHIN PRESCRIBED TIME LIMIT.
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 18
RENEWAL OF A BOILER CERTIFICATE
AS PER SECTION 8 , A CERTIFICATE OF BOILER IS CEASE ..
ON THE EXPIRY OF PERIOD FOR WHICH IT IS GRANTED
WHEN ANY ACCIDENT OCCURS TO THE BOILER
WHEN BOILER IS MOVED (EXCEPT PORTABLE OR VEHICULAR BOILER)
WHEN ANY STRUCTURAL ALTERATION, ADDITION OR RENEWAL IS MADE TO THE BOILER
IF CHIEF INSPECTOR OR INSPECTOR IS OF THE OPINION THAT BOILER OR BOILER
COMPONENT IS IN DANGEROUS CONDITION ( SUCH ORDER WITH THE GROUND ON WHICH
THE ORDER IS MADE IS TO BE COMMUNICATED TO THE BOILER OWNER )
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 19
1. AN APPLICATION IS TO BE MADE TO COMPETENT PERSON FOR RENEWAL
2. INSPECTION IS CARRIED OUT AS PRESCRIBED IN REGULATIONS
3. COMPETENT PERSON TO ISSUE CERTIFICATE IF SATISFIED OR REFUSE TO
ISSUE CERT. IF BOILER DOES NOT CONFORM TO THE STANDARD PRESCRIBED
BY REGULATIONS( INSPECTING AUTHORITY TO DIRECT OWNER IN WRITING TO
CARRY OUT SUCH MODIFICATIONS ,RECTIFICATIONS AS IT DEEMS
NECESSARY)
4. OWNER CAN APPLY DURING ANY TIME FOR THE RENEWAL DURING
CURRENCY OF CERTIFICATE
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 20
RENEWAL OF A BOILER CERTIFICATE
A DATE IS FIXED AS PER EXPIRY REGISTER AND INTIMATED IN ADVANCE BY “SMRUTI PATRA
“AND “KHA NOTICE”. TRY TO FOLLOW THE INSPECTION DATE SCHEDULED BY AUTHORITY
APPLY ON DEPT. WEBSITE BEFORE A WEEK OF EXPIRY DATE OF PREVIOUS CERTIFICATE
KEEP USER ID AND PASSWORD WITH YOU
IN CASE OF EARLY INSPECTION SELECT PROPER OPTION DURING ON LINE RENEWAL
APPLICATION. COMMUNICATE WITH THE AUTHORITY REGARDING CHANGE IN SCHEDULE
KEEP READY ALL APPD.DRGS., PAPERS
ARRANGE FOR LADDERS,SCAFFOLDING,TORCH AND PROPER CLEANING OF BOILER
COMPLY WITH REMARKS GIVEN IN PREVIOUS YEAR BOILER CERT.
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 21
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 22
AS PER SECTION 11 , CERTIFICATE OR PO CAN BE REVOKED ,
BY CHIEF INSPECTOR ON THE REPORT OF INSPECTOR OR OTHERWISE…
1. IF THERE IS REASON TO BELIEVE THAT CERTIFICATE / PO IS FRAUDULENTLY
OBTAINED OR GRANTED ERRONEOUSLY OR WITHOUT SUFFICIENT EXAMINATION
2. IF BOILER HAS SUSTAINED INJURY OR NOT IN GOOD CONDITION
3. IF BOILER IS NOT IN CHARGE OF A PERSON WHICH IS REQUIRED BY RULES
( UP TO 200 M2 HSA = SECOND CLASS B.A., FROM 200 - 1000 M2 HSA = FIRST CLASS B.A.,
HSA > 1000 M2 = PROFICIENCY ENGINEER IS REQUIRED)
FOR MULTIPLE BOILERS DETAILS RULES TO BE REFERRED
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 23
BOILER ATTENDANTS’ RULES,2011:
RULE : 3
THE OWNER OF A SINGLE BOILER OR TWO OR MORE BOILERS CONNECTED IN A BATTERY OR OF
MANY SEPARATE INDIVIDUAL BOILERS SHOULD HAVE A BOILER ATTENDANT WITH A CERTIFICATE
OF COMPETENCY OF REQUIRED CLASS.
RULE : 6
OWNER TO FURNISH DETAILS OF BOILER ATTENDANT WITHIN SEVEN DAYS TO DIRECTOR
OF BOILERS.(DETAILS AS NAME, SERIAL NO , DATE AND PLACE OF ISSUE OF CERTIFICATE)
RULE :24
A PERSON HAVING CERTIFICATE OBTAINED FROM OTHER STATE, ON APPLICATION TO
CHAIRMAN OF BOARD , CAN GET ENDORSED HIS CERT. BY PAYING FEE OF RS 100
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 24
RULE : 23 FIRST CLASS BOILER ATTENDANT CERTIFICATE OF COMPETENCY
CAN TAKE CHARGE OF SINGLE BOILER WITH STEAM PIPES OF ANY TYPE OR
CAPACITY OR,
TWO OR MORE BOILERS IN A BATTERY OR,
MANY SEPARATE INDIVIDUAL BOILERS
PROVIDED TOTAL HEATING SURFACE AREA DOES NOT EXCEED 1000 SQ.
METERS AND SUCH BOILERS ARE WITHIN A RADIUS OF 30 METERS IN THE SAME
PREMISES AND BELONGING TO ONE OWNER. HE IS ASSISTED BY SECOND CLASS
B.A.
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 25
RULE : 23 SECOND CLASS BOILER ATTENDANT CERTIFICATE OF COMPETENCY
CAN TAKE CHARGE OF SINGLE BOILER WITH STEAM PIPES OF ANY TYPE OR
CAPACITY OR,
NOT MORE THAN THREE CONNECTED BOILERS IN A BATTERY,
PROVIDED TOTAL HEATING SURFACE AREA DOES NOT EXCEED 200 SQ.
METERS AND SUCH BOILERS ARE WITHIN A RADIUS OF 30 METERS IN THE SAME
PREMISES AND BELONGING TO ONE OWNER. HE IS ASSISTED BY FIREMAN.
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 26
RULE : 31 ELIGIBILITY CRITERIA TO APPLY IN EXAMINATION
SECOND CLASS BOILER ATTENDANT
AGE : NOT LESS THAN 18 YEARS
PASSED MATRICULATION OR EQUIVALENT EXAM AND
NOT LESS THAN TWO YEARS EXPERIENCE AS A FIREMAN OR OPERATOR OR ASST FIREMAN OR
ASST OPERATOR OR WATERMAN OR PUMP MAN ON STEAM BOILER OR
NOT LESS THAN THREE YEARS EXPERIENCE AS A FITTER WHERE BOILERS ARE MANUFACTURED
OR ERECTED , OPERATED OR REPAIRED. OUT OF THIS AT LEAST ONE YEAR EXP AS A ASST
FIREMAN. OR
NOT LESS THAN TWO YEARS SERVICE ON A SMALL INDUSTRIAL BOILER WITH A ITI CERTIFICATE.
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 27
RULE : 31 ELIGIBILITY CRITERIA TO APPLY IN EXAMINATION FIRST CLASS BOILER ATTENDANT
AGE : NOT LESS THAN 20 YEARS
NOT LESS THAN TWO YEARS EXPERIENCE AS A SECOND CLASS B A AS A SOLE IN CHARGE ON A
BOILER WITH A HEATING SURFACE OF NOT LESS THAN 50 SQUARE METERS. OR
WITH A 3 YRS. COURSE CERTIFICATE FROM TECHNICAL OR INDUSTRIAL INSTITUTION , WITH ONE
YEAR AS AN APPRENTICE IN A STEAM POWER PLANT OR AN ENGG WORKSHOP WHERE ENGINES
OR BOILERS ARE REPAIRED OR MADE AND IN ADDITION NOT LESS THAN ONE YEAR
EXPERIENCE AS A SECOND CLASS B A AS A SOLE IN CHARGE ON A BOILER WITH A NOT LESS
THAN 50 M2 H S
NOT LESS THAN TWO YEARS SERVICE AS A FIREMAN OR ASST. FIREMAN WITH A SECOND CLASS
BA CERT UNDER A FIRST CLASS BA ON A ON A BOILER WITH A HEATING SURFACE OF MORE
THAN 50 SQUARE METERS.
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 28
BOILER OPERATION ENGINEERS’
RULES,2011:
RULE : 3 THE OWNER OF A SINGLE BOILER OR TWO OR MORE BOILERS CONNECTED IN A
BATTERY OR OF MANY SEPARATE INDIVIDUAL BOILERS SITUATED WITHIN A RADIUS OF 50
METERS HAVING TOTAL HEATING SURFACE AREA EXCEEDING ONE THOUSAND SQ. METER
SHOULD USE THE SAME WHEN IT IS IN DIRECT CHARGE OF A COMPETENT PERSON HAVING
CERTIFICATE OF PROFICIENCY AS A BOILER OPERATION ENGINEER
RULE : 6
OWNER TO FURNISH DETAILS OF BOILER ATTENDANT WITHIN SEVEN DAYS TO
DIRECTOR OF BOILERS.(DETAILS AS NAME, SERIAL NO , DATE AND PLACE OF ISSUE OF
CERTIFICATE)
RULE :24
A PERSON HAVING CERTIFICATE OBTAINED FROM OTHER STATE, ON APPLICATION TO
CHAIRMAN OF BOARD , CAN GET ENDORSED HIS CERT. BY PAYING FEE OF RS 200
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 29
RULE : 31 ELIGIBILITY CRITERIA TO APPLY IN EXAMINATION
AGE : NOT LESS THAN 23 YEARS
POSSESSES DEGREE OR DIPLOMA IN MECHANICAL OR ELECTRICAL OR ELECTRICAL &
ELECTRONICS OR CHEMICAL OR POWER PLANT OR PRODUCTION OR INSTRUMENTATION OR
INSTRUMENTATION & CONTROL
NOT LESS THAN TWO YEARS EXPERIENCE FOR DEGREE HOLDER AND FIVE YEAR EXPERIENCE
FOR DIPLOMA HOLDER IN A OPERATION AND/OR MAINTENANCE OF BOILER HAVING NOT LESS
THAN 1000 SQ. METER H.S.( IN CASE OF BATTERY OF BOILERS NOT LESS THAN 1000 SQ. METER
AGGREGATE OUT OF WHICH ONE BOILER OF NOT LESS THAN 500 SQ. METER H. S.
DEGREE OR PG DIPLOMA HOLDERS OF NPTI , MIN EXP. SHALL BE ONE YEAR.
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 30
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 31
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 32
AS PER SECTION 12 AND SECTION 13 ,
CHIEF INSPECTORS PRIOR WRITTEN SANCTION IS REQUIRED ,
1. WHEN ANY STRUCTURAL ALTERATION, ADDITION OR RENEWAL IS TO BE
MADE IN ANY REGISTERED BOILER
2. WHEN ANY STRUCTURAL ALTERATION, ADDITION OR RENEWAL IS PROPOSED
IN ANY BOILER COMPONENT
SUCH REPAIR IS TO BE CARRIED OUT THROUGH A PERSON HAVING
BOILER REPAIRER CERTIFICATE AND UNDER THE SUPERVISION OF COMPETENT
PERSON
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 33
REPAIRING OF BOILER :
APPLY TO DY. DIR OR DIRECTOR WITH PROPOSAL OF REPAIRING AND
APPROVED REPAIRER LETTER,CERT.,WELDER CERT.(PUT FORMAT)
OBTAIN PERMISSION FOR REPAIR (MAJOR REPAIR DIRECTOR FOR MINOR
REPAIR DY.DIRECTOR)
OFFER MATERIAL FOR INSPECTION WITH ORIGINAL MTC
AFTER COMPLETION OF REPAIR SUBMIT NDT (RADIOGRAPHY) REPORTS FOR
APPROVAL IF APPLICABLE
OFFER HYD. TESTING.
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 34
SCRAPPING OF BOILER :
INFORM TO DIRECTOR OF BOILERS THROUGH LOCAL OFFICE
BOILER REGISTRATION NUMBER PLATE IS TO BE SUBMITTED WITH LETTER
AS A PROOF
SCRAP
NON USE OF BOILER :
IN CASE IF YOU DO NOT WANT TO OFFER BOILER / ECO. FOR ANNUAL
INSPECTION FOR LONGER PERIOD,
INTIMATE THE OFFICE IN WRITING
ISOLATE IT FROM STEAM/FEED/BLOW DOWN & FLUE GAS SIDE. NON USE
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 35
AS PER SECTION 14 ,
DUTY OF OWNER AT EXAMINATION IS AS ,
1. TO AFFORD ALL REASONABLE FACILITIES FOR THE EXAMINATION AND SUCH INFORMATION
AS REQUIRED,
2. BOILER TO BE PROPERLY PREPARED IN A MANNER AND READY FOR EXAMINATION AS
PRESCRIBED IN REGULATIONS.
3. IN CASE OF REGISTRATION DRAWINGS,SPECIFICATIONS,CERTIFICATES AND OTHER
PARTICULARS AS PRESCRIBED IN REGULATIONS.
IF OWNER FAILS TO PROVIDE ABOVE , BOILER EXAMINATION IS REFUSED AND CHIEF
INSPECTOR SHALL DIRECT AN OWNER TO FILE FRESH APPLICATION FOR REGISTRATION OR
RENEWAL.
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 36
AS PER SECTION 17 ,
AN INSPECTOR FOR THE PURPOSE OF INSPECTING OR EXAMINING A BOILER
OR STEAM PIPE , CAN ENTER ANY PLACE OR BUILDING AT ALL REASONABLE TIMES
WITHIN HIS JURISDICTION WHEN HE HAS REASON TO BELIEVE THAT BOILER IS IN USE.
AS PER SECTION 18 ,
OWNER OR PERSON IN CHARGE TO REPORT IN WRITING OF ANY ACCIDENT TO BOILER
OR BOILER COMPONENT WITHIN 24 HOURS TO INSPECTOR WITH DESCRIPTION OF
ACCIDENT ,DETAIL OF INJURY ETC.
EVERY PERSON IS BOUND TO ANSWER QUESTIONS OF INSPECTOR IN WRITING TO
INVESTIGATE THE ACCIDENT.
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 37
EASE OF DOING BUSINESS
• THIRD PARTY (COMPETENT PERSON) INSPECTION SCHEME
• THIRD PARTY INSPECTING AUTHORITY LIST
• THIRD PARTY CERTIFICATION (BOILER PROFICIENCY ENGG. ) FOR
BOILER/ECONOMISER DURING USE.
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 38
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 39
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 40
THIRD PARTY CERTIFICATION (BOILER PROFICIENCY ENGG. ) FOR
BOILER/ECONOMISER DURING USE
• DEGREE OF ENGINEERING IN MECHANICAL / PRODUCTION / METALLURGY WITH BOILER
OPERATION ENGINEER CERTIFICATION.
• NDT QUALIFICATION AS PER ASNT FROM ANY OTHERS PROFESSIONAL BODY RECOGNIZED
BY ASNT CERTIFIED IN LEVEL-II FOR ULTRA –SONIC TESTING & RADIOGRAPHY TESTING.
• 5 YEARS’ EXPERIENCE IN OPERATION / MAINTENANCE OF BOILERS AS A BOILER OPERATION
ENGINEER WITH SINGLE EMPLOYER
• PERMANENT EMPLOYEE OF FIRM
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 41
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 42
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 43
AS PER REGULATIONS 376 , (PREPARATION FOR EXAMINATION )
1. BOILER SHALL BE EMPTY AND THOROUGHLY CLEAN. ALL SMOKE TUBES ,EXTERIOR OF
WATER TUBES ,SMOKE BOXES, AND EXTERNAL FLUES SHALL BE SWEPT CLEAN.
2. PROVISION FOR REMOVAL OF LAGGING, BRICK WORK, FOR VERIFYING PRESSURE
GAUGE AND SAFETY VALVE DIMENSIONS AND WEIGHT.
3. EFFECTIVE ISOLATION FROM STEAM AND HOT WATER WITH OTHER BOILER.
4. WHEN ELECTRIC LIGHT IS USED IN BOILER SHELL , DRUM OR ANY CONFINED SPACE
,THE VOLTAGE SHALL NOT EXCEED 24.OWNER TO PROVIDE HAND LAMP WITH GUARD,
KEYLESS SOCKET, INSULATED HANDLE AND EXTENSION CORD OF APPROVED TYPE.
5. EFFECTIVE EARTHING IS ALSO TO BE ENSURED.
DIRECTOR OF BOILERS , GOVERNMENT OF GUJARAT P A VYAS 38
SAFETY ASPECTS
• CCTV MONITORING
• USE OF MOBILE
• BOILER INTERLOCK
• LOG SHEET & LOG BOOK
• WATER CHEMISTRY REPORT
• SELECTION OF BOILER (FUEL/AUTO-MANUAL FIRING/PRESSURE )
• MODIFICATION IN BOILER DESIGN
• SAFETY INTERLOCK