Bombay HC Arbitration Case: WSGI vs. BCCI
Bombay HC Arbitration Case: WSGI vs. BCCI
docx
Digitally signed
by ANJALI
ANJALI TUSHAR
TUSHAR
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ASWALE
Date:
ASWALE 2022.03.16
18:18:39 +0530
ORDINARY ORIGINAL CIVIL JURISDICTION
IN ITS COMMERCIAL DIVISION
COMMERCIAL ARBITRATION PETITION(L) NO. 6451 OF 2020
Vs.
WITH
INTERIM APPLICATION (L)NO.6456 OF 2020
IN
COMMERCIAL ARBITRATION PETITION(L) NO. 6451 OF 2020
Vs.
Mr. Aspi Chinoy, Senior Advocate a/w Mr. Rajat Taimni, Mr. Saurajay
Nanda, Mr. Anubhav Dutta i/b Tuli & Co, for the Petitioner/Applicant.
Mr. Rafiq Dada, Senior Advocate a/w Mr. Indranil Deshmukh, Ms. Gathi
Prakash, Mr. Rishabh Malaviya i/b Cyril A. Mangaldas, for the Respondent.
CORAM :- B. P. COLABAWALLA, J.
Aswale Page 1 of 89
carbpl.6451.2020 bcci.docx
J U D G E M E N T :-
matter were concluded on 18th March 2021 and parties had also tendered
COVID-19 pandemic and also other exigencies of work, there was a delay
the matter on Board today (i.e. 16th March 2022) at 2:30 pm in chambers
JUDGEMENT”. I did this because almost a year has elapsed since the
judgment was reserved, and I wanted to inquire from the parties if they
not want to make any further submissions and I should proceed for
judgment today.
Aswale Page 2 of 89
carbpl.6451.2020 bcci.docx
Arbitration and Conciliation Act, 1996 (for short “the Arbitration Act”)
seeking to set aside the Majority Award of the Arbitral Tribunal dated 13th
July 2020. The Majority Award is passed by Mrs. Justice Sujata Manohar
(Retd.), a former Judge of the Supreme Court of India and Dr. Justice
The dissenting Award dated 20th July 2020 is given by a former Judge of
Agreement dated 25th March 2009 (for short, the “2nd BCCI-WSGI
MRLA”) was rejected. Under the 2nd BCCI-WSGI MRLA, the Petitioner
(for short the “IPL”) for the “Rest of the World” (“RoW”) territories (i.e.
all territories other than the Indian Sub-Continent), for the period 2009-
2017. In the Majority Award, the Arbitrators upheld that the said
transaction. Since the said MRLA was part of a composite fraud, the
Award.
Aswale Page 3 of 89
carbpl.6451.2020 bcci.docx
to set out the description of the parties. The Petitioner, World Sports
incorporated under the provisions of the Companies Act, 1956. It was part
under the provisions of the Tamil Nadu Registration of Societies Act, 1975
and is the governing body for the sport of cricket in India. In fact, BCCI
Respondent as “BCCI”.
Indian Premier League (for short the “IPL”) which was the first of its
differed from the then existing structure of either the 5-day TEST
Aswale Page 4 of 89
carbpl.6451.2020 bcci.docx
IPL.
to acquire a license for the IPL Media Rights for a period of 10 years
starting from 2008 to 2017. The tender contemplated IPL Media Rights
(i) for the Indian Sub-Continent (consisting of India, Pakistan, Sri Lanka,
Bangladesh, Nepal, Bhutan, and the Maldives) and (ii) for the “Rest of the
awarded the contract for the Global Media Rights Package of the IPL for
Aswale Page 5 of 89
carbpl.6451.2020 bcci.docx
MSM Satellite (Singapore) Pte. Ltd. (for short “MSM”) which had a
successful bidder for the IPL Global Media Rights Package for the entire
a direct Media Rights License Agreement (MRLA) with BCCI for the
the period 2008-2012. To facilitate this process, MSM, with the consent
January 2008 with BCCI (for short the “1st BCCI-MSM MRLA”) for the
period 2008-2012 for USD275.40 Million. This 1st BCCI-MSM MRLA was
Rights License Agreement was also executed between BCCI and WSGI
(for short the “1st BCCI-WSGI MRLA”) for (i) the India Rights for the
crores); and (ii) the RoW Media Rights (i.e. excluding India Rights) for
amount receivable by BCCI for the India Rights for the period 2008-2017
was USD 824.50 Million (USD 274.50 Million from MSM + USD 550
Aswale Page 6 of 89
carbpl.6451.2020 bcci.docx
9. Since MSM had only acquired India Rights for the period
entered into between WSGI and MSM whereunder MSM was given the
option to acquire the India Rights for the period 2013-2017 from WSGI
was in addition to the License Fee of USD 550 Million which was payable
to BCCI by WSGI under the 1st BCCI-WSGI MRLA. For the sake of
Agreements.
10. The first season of the IPL was conducted between April and
May of 2008 and was a resounding success. After the first season of the
IPL, disputes arose between BCCI and MSM which lead to BCCI
terminating the 1st BCCI-MSM MRLA (which was for the India Rights for
Arbitration Act and sought interim relief against BCCI from acting on the
Aswale Page 7 of 89
carbpl.6451.2020 bcci.docx
11. Since BCCI had terminated the 1st BCCI-MSM MRLA on 14th
March 2009, BCCI became entitled to re-auction the India Rights for the
BCCI wanted to substantially increase the License Fee receivable for the
India Rights not only for the period 2009-2012 but also for the period
dated 21st January 2008). In other words, BCCI was desirous of re-
auctioning and concluding a new Media Rights Agreement for the India
Agreement dated 21st January 2008 (the 1st BCCI-WSGI MRLA) so that
BCCI could unbundle the India Rights for the period 2013-2017 and
aggregate the same with the India Rights for the period 2009-2012 and
amount. To achieve this objective, BBCI would enter into a fresh MRLA
with WSGI or its affiliate World Sport Group (Mauritius) Limited (for
short “WSGM”), granting it the India Rights for the period 2009-2017.
Aswale Page 8 of 89
carbpl.6451.2020 bcci.docx
Additionally, BCCI would also enter into a fresh MRLA with WSGI for the
RoW rights for the period 2009-2017. It is not in dispute that at that
1st BCCI-WSGI MRLA dated 21st January 2008 only in order to enable
BCCI to receive an enhanced License Fee for the India Rights for the
period 2009-2017 on the condition (i) that the India Rights for the period
Rights for the period 2013-2017; and (ii) that BCCI would reinstate
WSGI’s RoW Rights for the period 2009-2017 by entering into a fresh
MRLA with WSGI on the same terms and conditions as was recorded in
2009 (for short the “DMAT”). On the same date, i.e. 15th March 2009,
with WSGM for licensing/ sub-licensing the India Rights for the period
Aswale Page 9 of 89
carbpl.6451.2020 bcci.docx
Rights for the period 2009-2017 under the MRLAs of 2008, were licensed
India Rights for the period 2009-2017 for an additional sum of Rs.1791
crores. One of the terms of this MRLA was that WSGM was required to
Since BCCI and WSGM had entered into the BCCI-WSGM MRLA on 15th
March 2009, an affidavit was filed by Mr. Lalit Modi on behalf of BCCI in
the Section 9 Petition (filed by MSM before this Court) stating that an
MRLA was already executed between WSGM and BCCI on 15th March
2009. In this light, arguments were heard by this Court in MSM’s Section
extended first till 21st March 2009 and then till 24th March 2009. The
March 2009. By the said order, this Court refused interim reliefs to MSM
inter alia on the basis that the India Rights of the IPL for the period 2009-
2017 had already been granted to WSGM under the BCCI-WSGM MRLA
Aswale Page 10 of 89
carbpl.6451.2020 bcci.docx
Media Rights, according to WSGI, between 15th March 2009 and 19th
broadcasters who were desirous of securing the India Rights for the
period 2009-2017. For securing the India Rights for the period 2009-
2017, MSM (i) was willing to match the amount payable by WSGM to
BCCI under the BCCI-WSGM MRLA (i.e. pay Rs.4791 crores to BCCI for
the period 2009-2017); and (ii) since MSM was insistent on a direct
it was agreed between WSGM, MSM and BCCI that WSGM would allow
its rights under the BCCI-WSGM MRLA dated 15th March 2009 to lapse
and BCCI would thereafter enter into a direct MRLA with MSM for the
India Rights for the entire period of 2009-2017 on the same terms i.e. by
paying BCCI Rs.4791 crores. In addition thereto, MSM would pay WSGM
MRLA dated 15th March 2009 was allowed to lapse and a letter dated 25th
Aswale Page 11 of 89
carbpl.6451.2020 bcci.docx
March 2009 was executed by WSGM and BCCI confirming that the BCCI-
WSGM MRLA had lapsed on 25th March 2009. This gave way for MSM to
enter into a MRLA directly with BCCI for the India Rights for the period
agreement with BCCI for the India Rights for the period 2009-2017 for
MRLA”). On the same day (i.e. 25th March 2009), WSGM and MSM also
assisted MSM in finalising the 2nd BCCI-MSM MRLA and that MSM had
such Facilitation Services. It is the case of WSGI that though the BCCI-
WSGM MRLA is dated 15th March 2009, inadvertently the same was
additional amount of Rs.1791 crores for the India Rights for the period
2009-2017 i.e. Rs.4791 crores minus Rs.3000 crores [for the same period
were given to it under the 1st BCCI-WSGI MRLA, BCCI also executed a
Aswale Page 12 of 89
carbpl.6451.2020 bcci.docx
2009 for the RoW rights for the period 2009-2017 w. e. f. 15th March 2009
(for short the “2nd BCCI-WSGI MRLA”). This MRLA had the same
terms and conditions as stipulated in the 1st BCCI-WSGI MRLA dated 21st
January 2008 save and except that the 2nd BCCI-WSGI MRLA contained
Clause 27.5 which inter alia stipulated that upon BCCI receiving a notice
BCCI would either terminate the 2nd BCCI-MSM MRLA or pay the
19. It is the case of the WSGI that the arrangement set out above
and all the Agreements entered into in 2009 (to give effect to the above
(i) enabled BCCI to re-auction the India Rights for the period
2009-2017 for an increased License Fee of Rs.4791 crores in
comparison to the original License Fee of Rs.3000 crores (i.e.
an increase of Rs.1791 crores). BCCI was able to get this
increased amount by re-auctioning the India Rights for the
entire period of 2009-2017 only because WSGI agreed to the
termination of its 1st BCCI-WSGI MRLA and thereby giving up
its India Rights for the period 2013-2017 to BCCI as recorded
in the DMAT;
Aswale Page 13 of 89
carbpl.6451.2020 bcci.docx
(ii) WSGI, who was entitled to the India Rights for the period
2013-2017, relinquished the same to BCCI under the DMAT
only to enable BCCI to re-auction the same by clubbing it with
the India Rights for the period 2009-2012 which accrued to
BCCI pursuant to the termination notice issued by BCCI to
MSM on 14th March 2009. This relinquishment was subject to
BBCI entering into a fresh MRLA with WSGI or its affiliate –
WSGM, granting it the India Rights for the period 2009-2017;
and
(iii) WSGI’s RoW Media Rights for the period 2009-2017 were
restored and reinstated w.e.f. 15th March 2009 on the same
terms and conditions as the 1st BCCI-WSGI MRLA, with the
exception of insertion of Clause 27.5, which inter alia
stipulated that upon BCCI receiving a notice regarding non-
payment of the Facilitation Fee amount by MSM, BCCI will
either terminate the 2nd BCCI-MSM MRLA or pay the amount
owed by MSM.
20. According to WSGI, during the 2nd and 3rd seasons of the IPL
(i.e. the IPL held in 2009 & 2010), all parties acted on the Agreements
entered into in 2009. In other words, MSM dealt with the India Rights
and agreed to pay the enhanced License Fee of Rs.4791 crores to BCCI
while WSGI dealt with the RoW rights. According to WSGI, during the
course of the 3rd season of the IPL, there were reports of disputes between
Mr. Lalit Modi and other office bearers of the BCCI. As there were media
Aswale Page 14 of 89
carbpl.6451.2020 bcci.docx
BCCI, MSM, on 23rd April 2010, issued a press statement about the
the Facilitation Fee to WSGM. The aforesaid press release inter alia
stated:
(i) MSM’s intent to secure the India Rights from WSGM, who
had acquired said Rights under the BCCI-WSGM MRLA dated
15th March 2009;
MSM, acting contrary to the aforesaid press statement and at the instance
Facilitation Deed on the ground that WSGM had falsely represented that
WSGM had executed an Agreement dated 23rd March 2009 with BCCI
including the India Rights and that the said rights were subsisting with
Aswale Page 15 of 89
carbpl.6451.2020 bcci.docx
dated 23rd March 2009 instead of 15th March 2009. According to WSGI,
MSM’s said allegations were ex-facie contrary to and belied by its own
press statement dated 23rd April 2010 which referred only to the BCCI-
WSGM MRLA dated 15th March 2009 and made absolutely no reference
was entered into between BCCI and MSM amending the 2nd BCCI-MSM
MRLA dated 25th March 2009. This Agreement inter alia deleted Clause
10.4 of the said 2nd BCCI-MSM MRLA which stipulated that upon BCCI
alleging that the 2nd BCCI-WSGI MRLA dated 25th March 2009 (and
which related only to the RoW rights for 2009-2017) was on the face of it
Aswale Page 16 of 89
carbpl.6451.2020 bcci.docx
notice dated 28th June 2010, were responded to by WSGI vide its letter
dated 30th June 2010. Thereafter, WSGI filed a Section 9 Petition seeking
A learned Single Judge of this Court rejected the said Section 9 Petition
Appeal was filed before a Division Bench of this Court. The Division
Bench in Appeal, by order dated 23rd February 2011, allowed the Appeal
Supreme Court, by its order dated 21st April 2011, disposed of the SLP
Aswale Page 17 of 89
carbpl.6451.2020 bcci.docx
(d) The net annual income (that is the difference between the total
of amounts remitted to the Escrow Account every year less the
amount equivalent to the licence fee that is drawn by BCCI in terms
of agreement dated 25.3.2009) shall be kept in a fixed deposit for a
term of one year. Such fixed deposits shall be renewed yearly till
the final adjudication of the disputes between the respondent and
the appellant by a competent court or arbitral tribunal (if the
remedy of arbitration is available or agreed) as the case may be.
(e) BCCI shall file yearly accounts (after furnishing a copy thereof to
the respondent) in regard to the amounts received, the amount
remitted to the Escrow Account, amounts drawn by BCCI
(equivalent to the licence fee under the agreement dated
25.3.2009) and the net amount invested in fixed deposits.
WSGI filed its Statement of Claim before the Arbitral Tribunal on 7th June
2016. On 13th July 2016 BCCI filed its Statement of Defence. Thereafter,
Aswale Page 18 of 89
carbpl.6451.2020 bcci.docx
and on 22nd February 2017, BCCI filed its amended Statement of Defence
incorporating the ground that the arbitration was not maintainable in the
Thereafter, the matter went to trial and the impugned Majority Award
dated 13th July 2020 was passed and which is challenged in the present
Petition.
WSGI’s SUBMISSIONS:
BCCI was able to receive from MSM an increased License Fee of Rs.4791
crores for the India Rights for the period from 2009-2017 by virtue of the
Agreements entered into between BCCI, WSGI, WSGM and MSM in the
year 2009. Mr. Chinoy submitted that pursuant to all the Agreements
entered into between the period 15th March 2009 to 25th March 2009
(including the DMAT), WSGI, relinquished its India Rights for the period
with the India Rights for 2009-2012 (which reverted to BCCI pursuant to
the termination of the 1st BCCI-MSM MRLA dated 21st January 2008),
Aswale Page 19 of 89
carbpl.6451.2020 bcci.docx
and then re-sell/re-auction the India Rights for the entire period of 2009-
2017 (as a single package) for a substantially higher License Fee. Mr.
Agreements entered into between 15th March 2009 and 25th March 2009
Aswale Page 20 of 89
carbpl.6451.2020 bcci.docx
pointed out that in the entire Award, there is not a single reference to the
crores and which BCCI had retained, had been specifically averred/stated
(qq) thereof. Mr. Chinoy submitted that BCCI had gained and retained
the benefit of an increase in the License Fee of Rs. 1791 crores because of
the composite transaction entered into between BCCI, MSM, WSGM and
WSGI respectively. This being the case, BCCI was precluded from
impugning / rescinding any part of the composite transaction (i.e. all the
Agreements entered into in the year 2009). Despite having urged this
has failed to consider the aforesaid argument which would go to the root
460, 463, 465, 467, 485, 486 and 536 of the paper book which relate to
post hearing submissions of WSGI. Mr. Chinoy submitted that the fact
Aswale Page 21 of 89
carbpl.6451.2020 bcci.docx
that BCCI received and retained this benefit of Rs. 1791 crores and
also noted in the Minority Award. Mr. Chinoy submitted that the only
reason he refers to the Minority Award is to show to the Court that the
aforesaid argument was specifically put in issue before the Tribunal and
the Majority Award completely overlooks this argument and has not even
are ex-facie contrary to the express terms of the DMAT. In this regard,
Mr. Chinoy submitted that while the increased License Fee of Rs. 4791
crores was undoubtedly due to the increased popularity of the IPL after
the 1st season of the IPL in 2008, BCCI would not have been able to secure
such increased License Fees for the India Rights for the period 2013-2017
without WSGI agreeing to surrender their India Rights for the aforesaid
period to BCCI under the DMAT. It is the DMAT that enabled BCCI to re-
liable to be set aside on the ground of patent illegality and perversity for
Aswale Page 22 of 89
carbpl.6451.2020 bcci.docx
totally failing to advert to and consider the facts and evidence that under
the composite transaction (and more particularly the DMAT), BCCI was
able to re-sell the India Rights for the period 2009-2017 to MSM for an
enhanced License Fee of Rs.4791 crores and which sum BCCI had
retained and enjoyed the benefit thereof. Mr. Chinoy submitted that if
this fact had been considered, it would necessarily lead to the conclusion
transaction (i.e. the Agreements entered into in 2009) or any part thereof,
30. The next argument canvassed by Mr. Chinoy was that the
policy of Indian Law. Mr. Chinoy submitted that the Majority Award
upholds the rescission of the 2nd BCCI-WSGI MRLA dated 25th March
require BCCI to restore the benefit it had received under all the
Chinoy submitted that BCCI has only purported to rescind the 2nd BCCI-
Aswale Page 23 of 89
carbpl.6451.2020 bcci.docx
WSGI MRLA dated 25th March 2009 and had not terminated/rescinded
despite the fact that it is BCCI’s own case that all the Agreements from
15th March 2009 to 25th March 2009, (including the DMAT) formed part
BCCI could not have rescinded only the 2nd BCCI-WSGI MRLA dated 25th
including the DMAT. Mr. Chinoy submitted that the reason why the other
BCCI did not terminate the other Agreements, including the DMAT, as
that would have resulted in requiring BCCI to restore the benefits it had
received thereunder i.e. it would have had to restore to WSGI (i) the India
Rights for the period 2013-2017; and (ii) the RoW rights for the period
in the License Fee of Rs.1160 crores which it had received from MSM for
the India Rights for the period 2013-2017. Mr. Chinoy submitted that the
rescission of only the 2nd BCCI-WSGI MRLA dated 25th March 2009 and
not of the DMAT and other Agreements executed in 2009 (which formed
in law. By purporting to rescind only the 2nd BCCI-WSGI MRLA and not
Aswale Page 24 of 89
carbpl.6451.2020 bcci.docx
return the benefit/advantage it had received under the DMAT i.e. the
India Rights for the period 2013-2017 and the RoW Rights for the period
2009-2017.
upholding the termination of only the 2nd BCCI-WSGI MRLA dated 25th
March 2009 (despite BCCI’s own case that it formed part of the
Indian Law. Mr. Chinoy clarified that WSGI was not seeking restoration
WSGI’s submission that the purported rescission was bad in law as BCCI
had not terminated the other Agreements, including the DMAT, and had
Aswale Page 25 of 89
carbpl.6451.2020 bcci.docx
DMAT.
submission of BCCI before the Tribunal that the termination of the 2nd
was required or warranted. The Award, however, holds that there was no
the fraud, all these Agreements were determined by the efflux of time. Mr.
Chinoy submitted that the finding in the Majority Award that there was
efflux of time by the time the Respondent discovered the fraud and,
therefore, there was no requirement for the BCCI to rescind the other
Aswale Page 26 of 89
carbpl.6451.2020 bcci.docx
MSM at a higher price of Rs.4791 crores only because WSGI had, under
the DMAT, agreed to surrender/revert its India Rights for the period
2013-2017 to BCCI. BCCI acted on the basis of that surrender and re-
licensed the India Rights for the period 2009-2017 to MSM. This being
the factual position, Mr. Chinoy submitted that there was no question of
would have statutorily been required to return to WSGI the benefit it had
received thereunder i.e. the India Rights for the period 2013-2017 as well
as the RoW Rights for the period 2009-2017. He, therefore, submitted
that the Award is also perverse and suffers from a patent illegality on this
ground as well.
DMAT and its stated purpose and object is clearly contrary to the express
not even the possible view. In this regard, Mr. Chinoy submitted that the
Majority Award holds that WSGI’s contention that the DMAT was
Aswale Page 27 of 89
carbpl.6451.2020 bcci.docx
make its subsequent aggregation with the India Rights for the period
2009-2012 possible (which would get BCCI more money), does not
also holds that there is no reference to the unbundling of the India Rights
by WSGI in the order to enhance its value when sold as an entire package
for the period 2009-2017. He submitted that the Award further goes on
to hold that by the DMAT, the WSGI agreed to give up its India Rights for
Award regarding the DMAT, are contrary to the express terms thereof.
recitals (D) and (E) of the DMAT as well as the definition of the term
“New WSG Media Rights Agreements” as well as Clauses 2.1 and 2.2
thereof. Relying upon the aforesaid clauses, Mr. Chinoy submitted that
the DMAT makes it clear: (a) that BCCI, which now held the India Rights
MSM MRLA dated 21st January 2008), had requested WSGI to agree to a
dated 21st January 2008) which encapsulated the RoW rights for the
period 2008-2017 and the India Rights for the period 2013-2017; (b) on
this Mutual Termination, WSGI’s India Rights for the period 2013-2017
Aswale Page 28 of 89
carbpl.6451.2020 bcci.docx
would revert to BCCI; (c) this arrangement would enable BCCI to re-
package and receive a higher License Fee; (d) BCCI would license the
India Rights for the period 2009-2017 to WSGM (an affiliate of WSGI)
(e) BCCI would restore to WSGI the RoW rights for the period 2009-2017
on the same terms as the 1st BCCI-WSGI MRLA dated 21st January 2008
MRLA dated 15th March 2009 between BCCI and WSGM for the India
Rights for the period 2009-2017 at the increased fee of Rs.4791 crores
was in pursuance of the DMAT and was clearly only a means for BCCI to
Rights. When one reads the terms of the DMAT, Mr. Chinoy submitted
that the Majority Award’s decision that the object of the DMAT was for
WSGI to assign its India Rights to its affiliate WSGM, is ex-facie perverse
and would mean that WSGI gave up its valuable India Rights for the
period 2013-2017 to BCCI, only in order to receive the same rights back
Aswale Page 29 of 89
carbpl.6451.2020 bcci.docx
also from the point of view that there is absolutely no explanation in the
Majority Award as to why WSGI would give up its valuable rights for the
this ground also the impugned Award cannot stand and must be set aside.
36. Mr. Chinoy then submitted that the Majority Award is also
enjoying the benefit of an increase in the License Fee of Rs.1791 crores for
the India Rights for the period 2009-2017 and at the same time upholding
and/or giving up its India Rights for the period 2009-2017 was fraudulent
Award upholds BCCI’s rescission of the 2nd BCCI-WSGI MRLA dated 25th
March 2009 under which WSGI got the RoW rights for the period 2009-
2017. Mr. Chinoy submitted that this effectively means that BCCI whilst
receiving the aforesaid benefit of Rs. 1791 crores has deprived WSGI of all
the rights it had under the 1st BCCI-WSGI MRLA, and all the benefits that
37. In this regard, Mr. Chinoy submitted that initially WSGI had
Aswale Page 30 of 89
carbpl.6451.2020 bcci.docx
the India Rights for the period 2013-2017 as well as the RoW Rights for
for a higher License Fee only on the basis that it would be given
back/restored its RoW rights for the period 2009-2017 and would be
compensated for giving up its India Rights for the period 2013-2017 by
license the India Rights for the period 2009-2017 to MSM for Rs.4791
crores i.e. an increase of Rs. 1791 crores. However, whilst receiving and
compensation (termed as the Facilitation Fee) for the India Rights for the
period 2013-2017 and has also deprived WSGI of its RoW rights for the
38. Lastly, Mr. Chinoy submitted that the finding in the Majority
Aswale Page 31 of 89
carbpl.6451.2020 bcci.docx
doubt, and therefore can be a valid ground for rescinding the 2nd BCCI-
WSGI MRLA dated 25th March 2009, is vitiated by perversity and patent
view of the DMAT and by the Tribunal’s total failure to consider material
evidence/facts i.e. the MSM Press Note/statement dated 23rd April 2010.
Mr. Chinoy submitted that the Press Note issued by MSM and who
according to BCCI was not part of the alleged fraud, clearly states that the
entire India Rights transaction was done after negotiations and with
WSGM relinquishing its rights. Mr. Chinoy submitted that this would be
again relates to the India Rights whereas the subject matter of the present
arbitration was the RoW rights. He brought to my attention the fact that
BCCI objected to WSGI’s reliance on the aforesaid Press Note as not being
proved during the cross examination of RW-4 but the same was not
accepted by the Tribunal. Mr. Chinoy submitted that the finding of fraud
of the DMAT and their total failure to consider MSM’s Press Note. Mr.
Chinoy submitted that the Award totally fails to consider the Press Note
Aswale Page 32 of 89
carbpl.6451.2020 bcci.docx
issued by MSM and which in fact establishes that WSGM’s rights under
relinquished its India Rights / agreed to give up its India Rights in favour
of MSM by letting the BCCI-WSGM MRLA dated 15th March 2009 lapse.
This enabled MSM to enter into a direct contract / license with BCCI. In
was quantified at Rs. 425 crores. This Facilitation Fee was the premium
that MSM would have to otherwise pay to WSGM if it had taken a sub-
license from WSGM for the India Rights. Mr. Chinoy submitted that the
Award however only refers to the fact that WSGM’s rights came to an end
on 24th March 2009 and on that basis holds that there was a
considering the aforesaid circumstances set out by MSM in its Press Note
lapse so that on 25th March 2009 MSM could enter into a direct
Aswale Page 33 of 89
carbpl.6451.2020 bcci.docx
39. Mr. Chinoy submitted that the total perversity of the finding
(ii) WSGI gave up its valuable India Rights for the period 2013-
Deed.
ignores the commercial purpose, object and terms of the DMAT, and is
Aswale Page 34 of 89
carbpl.6451.2020 bcci.docx
Press Note. For all the aforesaid reasons, Mr. Chinoy submitted that the
BCCI’s SUBMISSIONS:
41. On the other hand, Mr. Dada, the learned senior counsel
that WSGI’s challenge to the Majority Award is nothing else but to seek
42. Mr. Dada submitted that WSGI has extensively relied upon
rejected in the Majority Award. Mr. Dada submitted that none of the
Arbitration Act (as amended in 2015). Mr. Dada submitted that it is now
Aswale Page 35 of 89
carbpl.6451.2020 bcci.docx
ground available to set aside an Arbitral Award. Mr. Dada submitted that
this Court under Section 34, unless the Arbitral Tribunal construes the
other words, Mr. Dada submitted that it is only when the Arbitrator’s view
is such that no other prudent person would have taken such a view, would
this Court interfere under Section 34 of the Arbitration Act. Mr. Dada
whilst delivering the Arbitral Award. Even if the Award is based on little
Dada submitted that it is now well settled that the scope of judicial
Aswale Page 36 of 89
carbpl.6451.2020 bcci.docx
submitted that WSGI has alleged that its actions in relinquishing its India
Rights for the period 2013-2017 (by executing the DMAT) and bundling
it with the India Rights for the period 2009-2012, enabled BCCI to an
increase in the License Fee to the tune of Rs.1791 crores. Mr. Dada
submitted that WSGI contends that this was a material fact, and the
Award is perverse as it does not consider this fact. Mr. Dada submitted
WSGI are false as it is apparent from a perusal of the DMAT that WSGI
agreed to give up its India Rights for the period 2013-2017 (acquired
facilitate the acquisition of the India Rights for the period 2009-2017 by
WSGM. Mr. Dada further submitted that the Arbitral Tribunal in its
Majority Award has also rightly held that from a perusal of the recitals of
the DMAT, it is clear that the Petitioner agreed to the termination of the
1st BCCI-WSGI MRLA to unbundle the India Rights for the period 2013-
Aswale Page 37 of 89
carbpl.6451.2020 bcci.docx
2017 in order to facilitate the acquisition of the India Rights for the period
from 2009-2017 by WSGM. Mr. Dada submitted that upon the execution
of the BCCI-WSGM MRLA, whereunder the India Rights for the period
consideration under the DMAT. At this stage, the DMAT was sublimated
[being its obligation (a) to make an upfront payment of INR 112.5 crores
on the signing of the MRLA; (b) to provide a bank guarantee of INR 335
crores within 7 days of the MRLA; and (c) to find a sub-licensing partner
within 72 hours of the signing of the MRLA], all rights under the BCCI-
consequences are spelt out in the DMAT for what would happen if the
License Fee payable to BCCI under the 2nd BCCI-MSM MRLA was not on
account of WSGI releasing any rights. Mr. Dada submitted that the
MSM MRLA on 14th March 2009 and the increased popularity of the IPL
in the year 2009. Mr. Dada submitted that the value of such enhancement
would go to the rights holder i.e. BCCI, since after the said termination it
was open for BCCI to auction the said rights in the market. Mr. Dada
Aswale Page 38 of 89
carbpl.6451.2020 bcci.docx
submitted that WSGM had agreed to pay an additional sum of Rs. 1791
crores to BCCI, but never paid the same. Ultimately, MSM agreed to pay
in value was not relatable to any acts of WSGI. In this regard, it is also
pertinent to note that under the 2nd BCCI-MSM MRLA, MSM was granted
was not available under the 1st BCCI WSGI MRLA and the 1st BCCI-MSM
MRLA. Mr. Dada submitted that the 2nd BCCI-MSM MRLA was
executed between BCCI and MSM dated 28th June 2010 (for short the
at after fresh negotiations. It was under the 3rd BCCI-MSM MRLA that
BCCI received the amount of Rs.4791 crores, post discovery of the fraud.
crores towards the India Rights for the period 2010-2017 under the 3rd
BCCI-MSM MRLA. Over and above this, MSM also agreed to pay an
amount of Rs.125 crores, if the same was recovered from the WSGM. Mr.
Dada submitted that the License Fee for the India Rights was the specific
Aswale Page 39 of 89
carbpl.6451.2020 bcci.docx
MSM and BCCI, namely, two letters both dated 2nd June 2010, one
45. Mr. Dada submitted that the submission of WSGI that the
BCCI and MSM renegotiated the License Fee for the India Rights. Thus,
the enhanced fees were a direct result of the fresh negotiations and new
terms agreed upon with respect to the License Fee for the period 2010-
2017. Mr. Dada submitted that the 3rd BCCI-MSM MRLA also contains
submitted that when one reads the 3rd BCCI-MSM MRLA, it is quite clear
that it superseded and replaced the earlier MRLA and the earlier
understanding. When one looks at it from this angle, post discovery of the
fraud, the enhanced India Rights Fees were thus received under the 3rd
BCCI-MSM MRLA, and not under the 2nd BCCI-MSM MRLA. Mr. Dada
submitted that it is not BCCI’s case that the 3rd BCCI-MSM MRLA formed
was successfully performed and has now determined by the efflux of time.
Aswale Page 40 of 89
carbpl.6451.2020 bcci.docx
benefit from the fraud. Mr. Dada, therefore, submitted that the view
taken by the Tribunal in the Majority Award is correct or is, at the very
the Majority Award perverse, Mr. Dada submitted that the Tribunal has
Dada submitted that in any event, as stated earlier, there was no benefit
fee that BCCI received was not relatable to any acts of the WSGI. Further,
WSGM not only breached the BCCI-WSGM MRLA but also committed a
Majority Award perverse. Mr. Dada, therefore, submitted that there was
Aswale Page 41 of 89
carbpl.6451.2020 bcci.docx
increased License Fee of Rs.4791 crores for the India Rights for the period
2009-2017 because WSGI had relinquished its India Rights for the period
2013-2017 to BCCI.
47. Mr. Dada then submitted that even the argument of Mr.
any merit. Mr. Dada submitted that there is no prayer and/or pleading in
the Statement of Claim filed before the Tribunal for “restoration” of any
alleged benefit under Sections 64 and 65 of the Indian Contract Act, 1872.
Mr. Dada submitted that at no point in time, did WSGI quantify its
from WSGI) under the 2nd BCCI-WSGI MRLA. In the absence of the
same, the Tribunal could not have granted any relief under Sections 64 &
65 of the Contract Act to WSGI. Mr. Dada submitted that under Sections
64 and 65: (a) the alleged benefit is required to have been received by
BCCI under the 2nd BCCI-WSGI MRLA itself & which admittedly is not
Aswale Page 42 of 89
carbpl.6451.2020 bcci.docx
48. Mr. Dada then submitted that in any event, Sections 64 and
65 of the Contract Act will not aid WSGI since admittedly it had been
found to have committed the fraud. Mr. Dada submitted that WSGI was
was no question of WSGI being returned any rights it had lost under the
DMAT. The whole reason for the rescission was that WSGI was involved
defeat the entire purpose and effect of the rescission, was the submission.
Mr. Dada submitted that this argument has been dealt with by the
pleading or evidence led to that effect. The Tribunal has further recorded
that there was no oral argument on this issue, as well. The Tribunal,
therefore, holds that this contention cannot be raised at this stage. Mr.
Dada pointed out that the Tribunal further goes on to hold that nothing
Aswale Page 43 of 89
carbpl.6451.2020 bcci.docx
DMAT and its stated purpose and object is contrary to the express
under the 1st BCCI-WSGI MRLA dated 21st January 2008, WSGI had the
RoW rights for the period 2008-2017 along with the India Rights for the
period 2013-2017. Even after the execution of the DMAT and the 2nd
BCCI-WSGI MRLA, WSGI continued to have the RoW Rights for the
period 2009-2017. What WSGI gave up was the India Rights for the
whole, the RoW Rights were not WSGI’s consideration for anything at all
because WSGI always had those rights. The consideration was clearly the
retention of the RoW Rights was not the WSGI’s consideration for the
DMAT. The consideration for the DMAT was the diversion of WSGI’s
India Rights to WSGM. Mr. Dada submitted that this is exactly what the
Aswale Page 44 of 89
carbpl.6451.2020 bcci.docx
(a) The WSGI’s consideration for the DMAT was the diversion
of the India Rights for the period 2009-2017 to its affiliate
WSGM;
(b) WSGI did not surrender the India Rights for the period
2013-2017 to BCCI absolutely. The DMAT itself
contemplated reversion of the India Rights for the period
2013-2017 to the BCCI for the limited purpose of enabling
the BCCI to sign the BCCI-WSGM-MRLA, and it is for this
reason that WSGM was party to the DMAT;
liable for anything when the WSGI already received its consideration
under the DMAT. Mr. Dada submitted that the DMAT having been
or rescind. Mr. Dada submitted that it was in this light that the Tribunal
held that the DMAT along with all the other Agreements had come to an
end by the efflux of time, and hence, there was no need for any
Aswale Page 45 of 89
carbpl.6451.2020 bcci.docx
composite fraud was the 2nd BCCI-WSGI MRLA and that is what was
exactly done by BCCI vide its termination notice dated 28th June 2010.
with relation to the DMAT were fully justified. In any event, Mr. Dada
submitted that the view taken by the Tribunal in the Majority Award on
this Court ought not interfere with those findings under Section 34 of the
Arbitration Act.
51. Mr. Dada then submitted that WSGI contends that BCCI has
not been able to establish fraud beyond reasonable doubt because the
MSM’s Press Note. In this regard, Mr. Dada submitted that the contents
of the Press Note were never proved in the proceedings before the Arbitral
Tribunal. As such, WSGI cannot rely on the Press Note at all. The said
Press Note was denied by BCCI vide its statement of admissions and
denials dated 5th May 2017 filed in the arbitration proceedings. Thus,
WSGI is not entitled to rely upon the Press Note since the contents and
the truth thereof were never proved by WSGI in the arbitral proceedings.
Mr. Dada submitted that despite WSGI relying heavily on MSM’s Press
Note dated 23rd April 2010, it has not led evidence of any witnesses to
Aswale Page 46 of 89
carbpl.6451.2020 bcci.docx
prove the correctness of the contents thereof. Further, WSGI has also
Tribunal under which the said Tribunal held that MSM was justified in
rescinding the Facilitation Deed executed between the MSM and WSGM.
Mr. Dada submitted that therefore, the learned Arbitral Tribunal has
rightly not attached any evidentiary value to MSM’s Press Note and has
not referred to or relied upon the same in its Majority Award. For all the
aforesaid reasons, Mr. Dada submitted that there was no merit in the
52. I have heard the learned counsel for the parties and perused
the papers and proceedings in the above Petition. I have also gone
through in detail the Majority Award dated 13th July 2020. Before I deal
apposite to recapitulate the facts in brief once again. In the year 2007,
Media Rights for the IPL, BCCI floated a tender. WSGI was the successful
tenderer and was accordingly awarded the Global Media Rights for the
IPL for the period 2008-2017. Since WSGI was only a trader in Media
Aswale Page 47 of 89
carbpl.6451.2020 bcci.docx
License Agreement [MRLA] with BCCI. Further, MSM only wanted the
India Rights for the period 2008-2012. To facilitate this entire process, in
the year 2008, the following Agreements were entered into between
Aswale Page 48 of 89
carbpl.6451.2020 bcci.docx
WSGI has ever called into question the validity of these Agreements.
From these Agreements it is clear that for the India Rights for the period
Million [ i.e. USD 274.50 Million from MSM for the period 2008-2012 +
USD 550 Million from WSGI for the period 2013-2017]. This was
India Rights from WSGI for period 2013-2017, MSM could opt to acquire
Option Deed. This was in addition to USD 550 Million that MSM would
have to pay to BCCI for the India Rights for the period 2013-2017.
The reason why fresh Agreements had to be executed in the year 2009
was because BCCI, on 14th March 2009, terminated its Media Rights
Agreement with MSM (being the 1st BCCI-MSM MRLA dated 21st January
Aswale Page 49 of 89
carbpl.6451.2020 bcci.docx
2008) for the period 2008-2012. Hence, the India Rights of the IPL for
the period 2009-2012 reverted to BCCI. Since the first season of the IPL
IPL for the entire period of 2009-2017 for a higher License Fee. To
facilitate this process, the following Agreements were entered into in the
year 2009:
Aswale Page 50 of 89
carbpl.6451.2020 bcci.docx
Aswale Page 51 of 89
carbpl.6451.2020 bcci.docx
55. BCCI alleges that all the aforesaid Agreements entered into
in the year 2009 (the MRLAs of 2009), including the DMAT, form part of
Aswale Page 52 of 89
carbpl.6451.2020 bcci.docx
terminate the 2nd BCCI-WSGI MRLA dated 25th March 2009. To put it in
a nutshell, the fraud alleged by BCCI is that the Facilitation Fee payable
by MSM to WSGM under the Facilitation Deed were monies that were
were entered into for the purposes of diverting to WSGM the sum of
Rs.425 crores which actually belonged to BCCI. Since WSGI and WSGM
are sister concerns and the fact that WSGI and WSGM were both parties
to the DMAT, WSGI was complicit in the aforesaid fraud which gave BCCI
the right to rescind the 2nd BCCI-WSGI MRLA dated 25th March 2009
even though the same pertained only to the RoW Rights (as defined in the
DMAT) and not the India Rights. It was this rescission that was
challenged before the Arbitral Tribunal, and which has been upheld in the
Majority Award.
56. The first grievance made by Mr. Chinoy is that the Majority
Agreements entered into in 2009, and which BCCI now alleges are a part
Fee of Rs. 4791 crores for the India Rights for the period 2009-2017 in
contrast to the amount of Rs.3,000 crores that BCCI would have received
under the MRLAs of 2008 for the same period. In other words, by virtue
Aswale Page 53 of 89
carbpl.6451.2020 bcci.docx
enormous benefit that inured to BCCI, and the fact that BCCI retained the
be disputed that by virtue of the Agreements entered into 2009, BCCI was
able to re-sell/re-auction the India Rights for the period 2009-2017 for a
sum totalling to Rs.4791 crores. It is also not in dispute that under the
unquestioned 2008 MRLAs, for the same period, BCCI would have
received a sum of Rs.3000 crores for the India Rights. This means that
BCCI got a benefit of Rs.1791 crores. Despite this, I find that the Majority
received by BCCI under the Agreements entered into in the year 2009. I
must mention that this was specifically put in issue before the Tribunal
Aswale Page 54 of 89
carbpl.6451.2020 bcci.docx
(emphasis supplied)
the fraud was an “all pervasive fraud” and which attached itself even to
rescinded. BCCI could not have merely rescinded the 2nd BCCI-WSGI
MRLA and that too for an alleged fraud which did not in any way attach
itself to the RoW rights but only to the India Rights. To counter the
argument of Mr. Chinoy on this aspect, Mr. Dada submitted that the
Aswale Page 55 of 89
carbpl.6451.2020 bcci.docx
“35. The next question which arises is: If the final result was to
grant RoW rights for the years 2009-2017 to WSGI why
was the first BCCI-WSGI-MRLA which did precisely this,
terminated? The Claimant’s submission is that this was
done in order to unbundle the India Rights for 2013 to
2017 so as to make its subsequent aggregation with India
Rights for 2009-2012 possible, which would get for the
Respondent more money. This does not appear to be
convincing. In the first place, apart from this submission,
there is no oral evidence before us to support such a
reason. If we look at the documentary evidence, Clause 2
of the Deed of Mutually Agreed Termination of 1st WSGI
Media Rights Agreement provides as follows:
Aswale Page 56 of 89
carbpl.6451.2020 bcci.docx
not find anything therein that would lead me to believe that the Tribunal
in the Majority Award has considered the benefit of Rs.1791 crores that
inured to BCCI and the effect it would have on BCCI’s rescission of the
2nd BCCI-WSGI MRLA dated 25th March 2009. In fact, there is absolutely
regarding the fact that by the Agreements entered into in the year 2009,
and under which WSGI gave up its India Rights for the period 2013-2017
to BCCI in order to enable it to aggregate the same with the India Rights
Aswale Page 57 of 89
carbpl.6451.2020 bcci.docx
to BCCI. In fact, all that the Majority Tribunal has done is that it sets out
the argument of WSGI in part and thereafter gives the finding that the
same “does not appear to be convincing”. From what is stated in the said
India Rights for the period 2013-2017 to get absolutely nothing in return,
WSGI were to give up its India Rights for the period 2013-2017 to MSM,
15th March 2009), it is ex-facie clear that WSGI agreed to the termination
of the 1st BCCI-WSGI MRLA so that BCCI would be able to re-license the
India Rights for the period 2009-2017 for a much higher price and which
Rights would be granted back to WSGI for the period 2009-2017. It was
to facilitate BCCI receiving a higher License Fee that WSGI agreed to the
the India Rights for the entire period (2009-2017) as a single package.
Any other interpretation just does not make any sense. The findings in
Majority Award would effectively mean that WSGI gave up its valuable
India Rights to BCCI for the period 2013-2017 just to get it back through
its affiliate – WSGM and that too by agreeing to pay an additional amount
of Rs.1791 crores. When one reads these Agreements together with the
Aswale Page 58 of 89
carbpl.6451.2020 bcci.docx
findings and reasons given in the Majority Award, I find that the issue
(in the Majority Award) upheld BCCI’s rescission on the ground of an “all
could be held to be valid when BCCI had received a benefit of Rs. 1791
crores under the very Agreements which it now alleges form the subject
BCCI the right to terminate the 2nd BCCI-WSGI MRLA. I say this because
at the same time. A party cannot be permitted to blow hot and cold, fast
and binding effect of that contract on him. Once a party takes advantage
document. This has been so held by the Hon’ble Supreme Court in the
“26. It is also not disputed that the plaintiff and Defendants 1 to 3 herein
filed suit for eviction of an occupant in which he claimed that the
property had been bequeathed to him by Hari Ram. According to the
Aswale Page 59 of 89
carbpl.6451.2020 bcci.docx
defendants, the plaintiff having accepted the will of Hariram and having
taken benefit of the same, cannot turn around and urge that the will is
not valid and that the entire property is a joint family property. The
plaintiff and Defendants 1 to 3 by accepting the bequest under the will
elected to accept the will. It is trite law that a party cannot be permitted
to approbate and reprobate at the same time. This principle is based on
the principle of doctrine of election. In respect of wills, this doctrine has
been held to mean that a person who takes benefit of a portion of the
will cannot challenge the remaining portion of the will. In Rajasthan State
Industrial Development & Investment Corpn. v. Diamond & Gem
Development Corpn. Ltd. [Rajasthan State Industrial Development &
Investment Corpn. v. Diamond & Gem Development Corpn. Ltd., (2013) 5
SCC 470 : (2013) 3 SCC (Civ) 153 : AIR 2013 SC 1241] , this Court made an
observation that a party cannot be permitted to “blow hot and cold”,
“fast and loose” or “approbate and reprobate”. Where one party
knowingly accepts the benefits of a contract or conveyance or an order,
it is estopped to deny the validity or binding effect on him of such
contract or conveyance or order.
(emphasis supplied)
Aswale Page 60 of 89
carbpl.6451.2020 bcci.docx
Supreme Court has clearly held that a decision of the Tribunal which
appearing on the face of the Award. The Supreme Court has inter
illegality. This has so been held by the Supreme Court in the case of
Aswale Page 61 of 89
carbpl.6451.2020 bcci.docx
40. The change made in Section 28(3) by the Amendment Act really
follows what is stated in paras 42.3 to 45 in Associate Builders [Associate
Builders v. DDA, (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] , namely, that
the construction of the terms of a contract is primarily for an arbitrator
to decide, unless the arbitrator construes the contract in a manner that
no fair-minded or reasonable person would; in short, that the
arbitrator's view is not even a possible view to take. Also, if the arbitrator
wanders outside the contract and deals with matters not allotted to him,
he commits an error of jurisdiction. This ground of challenge will now
fall within the new ground added under Section 34(2-A).
Aswale Page 62 of 89
carbpl.6451.2020 bcci.docx
Aswale Page 63 of 89
carbpl.6451.2020 bcci.docx
ground that justice has not been done in the opinion of the Court. That
would be an entry into the merits of the dispute which, as we have seen,
is contrary to the ethos of Section 34 of the 1996 Act, as has been noted
earlier in this judgment.”
(emphasis supplied)
61. The fact that the Tribunal in the Majority Award has
(including the DMAT), and the effect it would have on BCCI’s right to
of patent illegality. I say this because this is an issue that goes to the root
crores under the Agreements of 2009, could rescind the 2nd BCCI-WSGI
MRLA (dated 25th March 2009) on the ground that all the Agreements
entered into in 2009 (including the DMAT), and under which BCCI
Aswale Page 64 of 89
carbpl.6451.2020 bcci.docx
fails to consider MSM’s Press Note dated 23rd April 2010. Mr. Dada
submitted that MSM’s Press Note has not been referred to in the
Majority Award because the same was objected to by BCCI and was
Aswale Page 65 of 89
carbpl.6451.2020 bcci.docx
(emphasis supplied)
and which was canvassed by Mr. Dada before me, was negated by
the root of the matter considering that the aforesaid Press Note sets
Aswale Page 66 of 89
carbpl.6451.2020 bcci.docx
the Press Note would have been vital before giving any finding of
fraud being established. This Press Note, and which relates to the
indicates that WSGMs rights under the BCCI-WSGM MRLA had not
to facilitate MSM entering into a direct contract with BCCI for the
Rs.425 crores. The relevant portion of the said Press Note reads
thus:-
A quick summary
1. On March 14, 2009, the BCCI unilaterally terminated the
then existing broadcasting rights agreement dated 21
January 2008 with MSM.
Aswale Page 67 of 89
carbpl.6451.2020 bcci.docx
Aswale Page 68 of 89
carbpl.6451.2020 bcci.docx
MSM has acted at all times with impeccable integrity and highest
ethical standards and corporate Governance. MSM has complied
with applicable laws. Allegations in certain sections of the media
attributing wrongful conduct to MSM are incorrect and
completely unfounded.”
(emphasis supplied)
notice that MSM was misled to believe that there was an MRLA with
WSGM dated 23rd March 2009. However, in the Press Note, MSM
Aswale Page 69 of 89
carbpl.6451.2020 bcci.docx
even in its own Press Note it has stated that the BCCI-WSGM MRLA
was dated 15th March 2009. In fact, this Press Note also goes on to
vulnerable to challenge.
Award is much to be desired. It was the case of BCCI, and which was
committed on BCCI and MSM because a sum of Rs. 425 crores was
paid and belonged to BCCI. The Tribunal holds that looking at the
Aswale Page 70 of 89
carbpl.6451.2020 bcci.docx
entered into in the year 2009 as well as the Press Note issued by
MSM dated 23rd April 2010, prima facie, it would appear that
Rs.425 crores was to be paid to WSGM for giving up its India Rights
for the period 2009-2017, and which had come to it by virtue of the
DMAT read with the BCCI-WSGM MRLA dated 15th March 2009. I
and WSGI which inter alia contemplated that if MSM wanted the
India Rights for the period 2013-2017, they would have to pay WSGI
a sum of USD 60 Million. It has never been BCCI’s case that the
Aswale Page 71 of 89
carbpl.6451.2020 bcci.docx
aforesaid Option Deed was in any way fraudulent or that the amount
of USD 60 Million which WSGI would have got under the Option
Deed was actually money which was due and payable to BCCI. I,
Majority Award) could not have come to the conclusion that fraud
beyond reasonable doubt. This being the case, even on this count,
66. There is yet another reason why I find that the Majority
“61. IPL GC meeting did take place and was held on 11th August,
2009 and there is nothing on record to suggest the second BCCI
WSGI MRLA and second BCCI MSM MRLA were discussed and
brought to the attention of the Governing Council members of the
IPL for approval in the said meeting. There is also nothing on
record to show that the contracts were available at the meeting
either and, therefore, there could not have been any ratification
and even if there be any ratification, the same was obtained
fraudulently by suppressing the most relevant clauses and by
suppressing the Facilitation Deed whereby legitimate fund of the
BCCI was sought to be diverted and misappropriated and
therefore rightly the BCCI took steps for rescission of such
Aswale Page 72 of 89
carbpl.6451.2020 bcci.docx
transaction.”
(emphasis supplied)
the 2nd BCCI-WSGI MRLA dated 25th March 2009 or the 2nd BCCI-
MSM MRLA also dated 25th March 2009, were available at the
meeting held on 11th August 2009 and therefore there could have
the Majority Award has come to this finding when there is a detailed
160) Item 6.c shown at Page 675, Vol.II of CCD gives the
provisional income and expenditure for IPL 2009 along with
the statement of all expenses by vendor. The Claimant’s
argument seems to be correct inasmuch as the media rights
fee payable by MSM and the Claimant to the Respondent is
provided and the sum payable from MSM to Respondent
increases substantially. That is reflected in the document.
161) Item 6.f shown at Page 713,Vol.II of CCD under the heading
approval of all vendor contracts for 2009 season is a
statement that “All vendor contracts are placed here in the
Aswale Page 73 of 89
carbpl.6451.2020 bcci.docx
office along with the multiple quotes that are received from
various parties.” The Respondent’s contention that Item 6.f
was left blank therefore cannot be accepted.
Aswale Page 74 of 89
carbpl.6451.2020 bcci.docx
167) The Claimant’s arguments were that the persons who were
entitled to vote and ratify the contracts were the members
of the IPL GC. RW-3 and RW-4 were office bearers who were
ex-officio members without any voting rights. The
Respondent has led no evidence to show that the usual
procedure for ratification was for considering the detailed
terms and conditions of the terms/contracts. Also, there
was clear and detailed reference to the media rights
Aswale Page 75 of 89
carbpl.6451.2020 bcci.docx
Aswale Page 76 of 89
carbpl.6451.2020 bcci.docx
member, right? A. No, the right to vote was only with the
members. We never had a right to vote. If there was voting
in the meeting, we never had a right to vote. Q. Whenever
a vote was called, you weren’t entitled to vote? A. I can only-
with regard to the deliberations, we could participate.
Aswale Page 77 of 89
carbpl.6451.2020 bcci.docx
177) The Agreement had been acted upon and the Respondent
has also received consideration in the form of media rights
fees for the IPL 2009 and 2010 season from the Claimant.
The IPL matches were in fact broadcast to various Rest of
the World territories as envisaged under the 2nd BCCI WSGI
MRLA and the Respondent was fully aware about who was
Aswale Page 78 of 89
carbpl.6451.2020 bcci.docx
(emphasis supplied)
68. I have set out the relevant paragraphs of the Minority Award
only to show that there was enough factual material before the Tribunal
in relation to the fact that the 2nd BCCI-WSGI MRLA and the 2nd BCCI-
MSM MRLA were available at the meeting held on 11th August 2009.
Despite all this material (as set out in the Minority Award and which is
that there is nothing on record to show that the 2nd BCCI-WSGI MRLA
and the 2nd BCCI-MSM MRLA were available at the meeting held on 11th
August 2009. This finding of the Tribunal clearly goes to show that it has
Aswale Page 79 of 89
carbpl.6451.2020 bcci.docx
the IPL Governing Council on 11th August 2009. The consideration of this
fraud in June 2010 and consequently, all the Agreements entered into in
in turn, entitled BCCI to rescind the 2nd BCCI-WSGI MRLA dated 25th
have on the issue of fraud is another factor that would render the award
unsustainable.
the Minority Award. The reason I have examined both the Awards is not
to see which view is correct. I have undertaken this exercise only because
it was the case of WSGI that a lot of important material and which would
have a bearing on the outcome of the dispute between WSGI and BCCI,
was ignored by the Arbitrators passing the Majority Award. In fact, when
I went through the Majority Award in detail, I find that one of the reasons
why the Tribunal held that a fraud was played on BCCI was because BCCI
was completely unaware of the Agreements entered into in the year 2009
and specifically the 2nd BCCI-WSGI MRLA and the 2nd BCCI-MSM
MRLA. The argument of WSGI before the Tribunal was that Mr. Lalit
Aswale Page 80 of 89
carbpl.6451.2020 bcci.docx
Modi acted throughout on behalf of BCCI and therefore BCCI had full
and who was engaged by BCCI to assist in the organization of the IPL. It
was argued by WSGI before the Tribunal that Mr. Paul Manning of IMG
drafted all the Agreements who had complete knowledge of all the
made known.
all the aforesaid Agreements, WSGI had also filed an Interim Application
IMG between the period 15th March 2009 to 30th May 2009 in relation to
Aswale Page 81 of 89
carbpl.6451.2020 bcci.docx
dated 3rd April 2017 (pages 423 to 430 of the paper book), stated that it
BCCI has not denied that IMG was appointed by BCCI and was advising
BCCI. The Tribunal also recorded that BCCI accepted that IMG was not
Mr. Lalit Modi’s personal adviser. The relevant portion of the Tribunal’s
(emphasis supplied)
72. Despite this finding of the Tribunal, and recording the fact
that IMG was appointed by BCCI, was advising them, and accepting that
Majority Award, the Tribunal records that in the present case it is the case
of BCCI that Mr. Paul Manning was taking instructions from and
to hold that looking at the facts of the present case, the knowledge of Mr.
Aswale Page 82 of 89
carbpl.6451.2020 bcci.docx
Manning cannot be attributed to BCCI and nor can it be said that BCCI
was aware of Mr. Modi's actions. It also holds that IMG acted on the
and the local legal team assisting him. There was no material before the
Tribunal to show that BCCI and its office bearers were aware of the
Aswale Page 83 of 89
carbpl.6451.2020 bcci.docx
(emphasis supplied)
has come to these findings when BCCI had conceded before the Tribunal
on 3rd April 2017 that BCCI had engaged IMG (who admittedly drafted all
the Agreements of 2009) and that IMG was not Mr. Lalit Modi’s personal
on 3rd April 2017. As can be seen from the reproduction of the order dated
3rd April 2017, the Tribunal was of the view that since BCCI accepted that
IMG was appointed by it, and the fact that it was not Lalit Modi’s personal
MRLA between 15th March 2009 and 30th May 2009. Despite this, the
Tribunal now holds that it is BCCI’s case that Mr. Manning was taking
instructions from and reporting exclusively to Mr. Lalit Modi. It was this
very fact which WSGI wanted to disprove that it sought the production of
those documents. Once the Tribunal recorded the statement of BCCI that
IMG (Mr. Paul Manning being a part thereof) was appointed by BCCI and
was advising BCCI and was not Mr. Lalit Modi’s personal adviser, how
Aswale Page 84 of 89
carbpl.6451.2020 bcci.docx
the Tribunal has come to the conclusion that Mr. Paul Manning was
thus:-
“140) The Claimant had relied upon Bradley v Riches [(1878) 9 CHD;
Pg 189 at 195-197] as well as Brahmo Dutt v Dharmi Das Ghose
[(1898) ILR 26 Cal 381; Para 8, 21-25] wherein the Court rejected
the contention that notice to the attorney is not notice to the party
and held that “the knowledge of the solicitor was the imputed
knowledge of the client.” The Courts have held that a client has
constructive notice of what is known to his Solicitor. The doctrine
laid down was:
"my solicitor is alter ego; he is myself; I stand in precisely the
same position as he does in the transaction, and therefore
his knowledge is my knowledge; and it would be a
monstrous injustice that I should have the advantage of
what he knows without the disadvantage. "
Aswale Page 85 of 89
carbpl.6451.2020 bcci.docx
141) Not only that Mr. Manning was aware, the records show that
on 11 April 2009, Mr. Modi sent an email with a copy of the 2nd
BCCI MSM MRLA dated 25 March 2009 to Ms. Akhila Kaushik, Mr.
Shashank Manohar, Mr. N. Srinivasan, Mr. Sundar Raman and Mr.
Prasanna Kannan. This email falsifies the case of fraud and
suppression raised by the Respondent. The MRLA was sent to the
President, Secretary, in house legal head and COO. Anybody could
have gone through it and asked for more information and referred
Agreements. However, in evidence, it emerges that the Secretary
had not even cared to read the Agreement. However, in evidence,
it emerges that the Secretary had not even cared to read the
Agreement.
[Shown Vol.l, page 465 (E-mail dated 11 1 11 April 2009 from Mr.
Lalit Modi &l addressed to a number of people including yourself
attaching a copy of 2nd BCCI — MSA1 A1RLA). The attachment is at
pages 466-516 produced by Respondent].
“Q, 13. Now do you agree that you had a copy of the 2nd
BCCI-MSM from 11th April 2009?
Ans. From this email, it appears that a copy of the agreement
was sent amongst others to me also. However, I did not read
it at all because prior to this in order to raise invoices I think
Lalit Modi was asked for a copy of this agreement. No
response was received from him and I may have written to
Mr. Sundar Raman expressing disappointment that there
was no response. This was followed, I remember by a mail
from Mr. Lalit Modi copied to a lot of people and then I think
Mr. Manohar intervened who was the then President and
after that this mail was sent. I vaguely remember it. By that
time, I was no more interested and therefore did not bother
to read it."
Aswale Page 86 of 89
carbpl.6451.2020 bcci.docx
The Affidavit is clear and especially given the receipt of the 11 April
2009 and the uncontroverted evidence we cannot accept the RW-
4’s version that he was not aware of the terms of the agreement. I
cannot ignore the fact that the agreement was in fact in his
possession and every person can subsequently deny knowledge of
a document received by him by saying he did not read it or only
read select parts of it. This cannot be accepted. The 2nd BCCI-WSGI
MRLA, which admittedly was known to all, contained references to
the Facilitation Deed as well.”
(emphasis supplied)
Aswale Page 87 of 89
carbpl.6451.2020 bcci.docx
correct but to only see whether material evidence, and which would go to
the root of the matter, has been missed in the Majority Award. When one
out and/or not even referred to in the Majority Award. Such an Award,
with the greatest of respect to the Arbitrators who passed the Majority
“a. The Majority Award dated 13 July 2020 be set aside under
Section 34 of the Arbitration and Conciliation Act, 1996”
76. Considering that the Majority Award has been set aside on
the ground that it fails to take into consideration material evidence which
would have a bearing on the outcome of the dispute between the parties,
I direct that in terms of Section 43(4) of the Arbitration Act, if either party
Aswale Page 88 of 89
carbpl.6451.2020 bcci.docx
disposed of, nothing survives in the above Interim Application and the
( B. P. COLABAWALLA, J. )
Aswale Page 89 of 89