MacCorkle Avenue Project

The memorandum summarizes the MacCorkle Avenue Reconstruction Project from 33rd Street to 40th Street in Charleston, WV. The project will begin on April 11th and involve installing new drainage, sidewalks, medians, lighting and signals. The $10 million project was awarded to Mountaineer Construction Company and will be managed by Mead & Hunt. An interactive website will provide public information and CCTV of traffic. Reconstruction will maintain two lanes in each direction and require night and weekend work.

Uploaded by

Jeff Morris
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views23 pages

MacCorkle Avenue Project

The memorandum summarizes the MacCorkle Avenue Reconstruction Project from 33rd Street to 40th Street in Charleston, WV. The project will begin on April 11th and involve installing new drainage, sidewalks, medians, lighting and signals. The $10 million project was awarded to Mountaineer Construction Company and will be managed by Mead & Hunt. An interactive website will provide public information and CCTV of traffic. Reconstruction will maintain two lanes in each direction and require night and weekend work.

Uploaded by

Jeff Morris
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 23

CITY OF CHARLESTON

OFFICE OF THE CITY MANAGER

MEMORANDUM

TO: City Council Members

FROM: Jonathan T. Storage, City Manager

DATE: April 4, 2022

SUBJECT: MacCorkle Avenue Reconstruction Project – 33rd Street to 40th Street

Please be advised that on Monday, April 11, 2022, the West Virginia Division of Highways will
begin a significant road reconstruction project in Kanawha City along WV Route 61 (MacCorkle
Avenue) from 33rd Street to 40th Street.

The project will involve installing new drainage systems, constructing gutters and sidewalks,
constructing new median islands and curbs, and installing new roadway lighting and signals.
The entire stretch of roadway will be reconstructed, meaning all pavement and road support
structures will be removed to base soil. New concrete slabs will be installed with a new
pavement overlay. The contract was awarded to Mountaineer Construction Company for
approximately $10 million, and the day-to-day project management will be handled by Mead &
Hunt.

The scope of this project significantly exceeds a regular paving job and will require the DOH to
engage in exceptional logistical coordination with stakeholders, and Mead & Hunt has
developed a robust coordination campaign.

On April 11, 2022, an interactive project website will go live, which will provide key information
to the public and interested parties, including access to CCTV feeds to show work zone traffic
queues. The website address will be kanawhacityreconstruction.com.

Additional information about the project may be found in the attached slide presentation.

City Hall | 501 Virginia Street, East | Post Office Box 2749 | Charleston, West Virginia 25330
charlestonwv.gov | 304.348.8014 | 304.348.8157 fax
33rd to 58th Street Reconstruction April 1, 2022
Welcome Stakeholders
Today’s
Purpose
• Provide a personal venue for
Stakeholders
• Provide Project Information
• WVDOH Communication Efforts
• Obtain Feedback
• Lessen Impacts
• Partner for a successful project
Welcome
Stakeholders
• WVDOH
• City of Charleston
• Kanawha County Commission
• Charleston Area Medical Center
• Kanawha County Office of
Emergency Management
• Kanawha County Schools
Transportation
33rd to 58th Street CEI

Two Construction
Contracts
33rd Street to
40th Street
40th Street
to 58th Street
33rd to 40th Street

Bid Summary for Proposal 2020000593


33rd to 40th Street

• Start Date: Monday,


April 11, 2022
• Completion Date:
Tuesday, July 26, 2024
Primary Activities – 33rd Street to 40th Street

• Traffic control w/ CCTV cameras

• Install new drainage, remove/modify existing

• Full-depth reconstruction of existing roadway

• Construct gutters, sidewalks, roadway lighting/


signals

• Construct median islands and curbs

• Pave final surface


Maintenance of Traffic

• Maintain two lanes northbound and two lanes southbound during all phases of
construction
• Night shift is expected, along with weekends
− Lane closures are not permitted between 6 am and 9 pm
− Intersection closures only permitted Friday 9 pm – Monday 6 am
MOT Construction Phases – 33rd to 40th Street

Phase 1 Work in median area

Phase 2 Work southbound lanes (hill side) Limited to Stages

Phase 3 Work northbound lanes (river side) Limited to Stages

Phase 4 Gutters, sidewalk, lights/signals

Phase 5 Construct median islands, final surface paving


33rd to 40th Street
33rd to 40th Street
Key Project Personnel

• Gary Mullins – WVDOH District One Construction Engineer


• Ryan Canfield – WVDOH District One Area Construction Engineer
− ryan.m.canfield@wv.gov
− Phone – (304) 205-6986
• Aaron Gillispie – Project Manager Mead and Hunt
• Andy Womack – Project Supervisor Mead and Hunt
40th Street to 58th Street Reconstruction

Currently in design
by WVDOH
WVDOH Communication Efforts

o Stakeholder Meeting

o Project Website
 Email page
 Traffic Phases
 Live Project Cameras

o Business Communications (leave behinds, etc.)

o Media Day Plan


kanawhacityreconstruction.com
kanawhacityreconstruction.com
Communication with Local Businesses During Construction

Phases 2 and 3

Prior to each construction Stage

Door to door

Provide Information

Nature of work and projected


timeframe
WVDOH Media Day – Kanawha City Reconstruction

• When – Thursday April 7,


2022 beginning at 10 am

• Where – CAMC Cancer


Center Parking Lot
33rd Street to 58th
Street Reconstruction
Stakeholder Meeting

Questions?

April 1, 2022