0% found this document useful (0 votes)
482 views1 page

Tata Consulting Engineers Limited: Building Vitrified Tiling Checklist

This document is a checklist for tiling work that includes materials, application, and workmanship. It lists items to check such as tile type and color approval, mortar ingredients and thickness, substrate inspection, and application procedures. It also checks that tiles are plumb and cracks free, joints are uniform, and slopes are proper where required. The contractor, TCE representative, and client must sign off on the completed work.

Uploaded by

Sandip Paul
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
482 views1 page

Tata Consulting Engineers Limited: Building Vitrified Tiling Checklist

This document is a checklist for tiling work that includes materials, application, and workmanship. It lists items to check such as tile type and color approval, mortar ingredients and thickness, substrate inspection, and application procedures. It also checks that tiles are plumb and cracks free, joints are uniform, and slopes are proper where required. The contractor, TCE representative, and client must sign off on the completed work.

Uploaded by

Sandip Paul
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

TATA CONSULTING ENGINEERS LIMITED

TCE-M7-CV-ER-F- SH.:1 of 1
051A BUILDING VITRIFIED TILING CHECKLIST
Project : System / Bldg. :
Client / Job No. : Area / Floor :
Contractor : Ref. Documents 1)
Description : 2)

Accept
Items to Check Date
Contr’r TCE Remarks

1. Type and colour of tile, manufacturer –


Approved by customer
Materials

2. Ingredients of mortar and thickness (1:4 / 20


mm thick)
3. Approval of Kota stone by Customer/ Mock up
approval
1. Jointing pattern approved – Y / N

2. Inspection of substrate

3. Proportioning of mortar mixture (1:4)

4. Application procedure – As per Method


Application

Statement
5. Gap between tiles less than 1 mm

6. Application cement slurry @ 3.3 kg/Sqm

7. Joints filled with Epoxy grout as per


manufacture’s specification

1. Tile face plumb & right angles


Workmanship

2. Cracks, misalignment, hollowness in bedding

3. Joints are uniform

4. Proper slope / s in flooring, where applicable

5. Skirting works line matching with flooring lines


Notes:

Contractor TCE Client