0% found this document useful (0 votes)
62 views2 pages

Electricity Supply Timeline in Mumbai

The document discusses practice directions under the Electricity Supply Code Regulations regarding the period for giving electricity supply. It summarizes that distribution licensees are required to provide new connections and supply within 1 month under the Electricity Act. However, the Commission views that licensees should endeavor to provide supply within 15 days for all consumer categories in the Municipal Corporation of Greater Mumbai area. Considering their experience there, licensees should endeavor to extend this 15 day period to other Maharashtra areas depending on actual site conditions. This practice direction is effective from the date of issue.

Uploaded by

vaibhav_sparsh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
62 views2 pages

Electricity Supply Timeline in Mumbai

The document discusses practice directions under the Electricity Supply Code Regulations regarding the period for giving electricity supply. It summarizes that distribution licensees are required to provide new connections and supply within 1 month under the Electricity Act. However, the Commission views that licensees should endeavor to provide supply within 15 days for all consumer categories in the Municipal Corporation of Greater Mumbai area. Considering their experience there, licensees should endeavor to extend this 15 day period to other Maharashtra areas depending on actual site conditions. This practice direction is effective from the date of issue.

Uploaded by

vaibhav_sparsh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Ref. no.

MERC/CGRF CELL /REG/2015 20 April, 2015

PRACTICE DIRECTIONS UNDER ELECTRICITY SUPPLY CODE


REGULATIONS, 2005:
PERIOD FOR GIVING SUPPLY OF ELECTRICITY

Preamble

Distribution Licensees in Maharashtra are required to provide, upon application, new


connections and supply of electricity within the time period stipulated under Section 43(1) of
the Electricity Act, 2003 (subject to its provisos), read with Regulation 4.7 of the MERC
(Standards of Performance of Distribution Licensees, Period for Giving Supply and
Determination of Compensation) Regulations (‘SoP Regulations’), 2014.

Subject to certain provisos, Section 43 (1) of the Act provides as follows:

“Section 43. (Duty to supply on request): (1) Save as otherwise provided in this Act,
every distribution licensee, shall, on an application by the owner or occupier of any
premises, give supply of electricity to such premises, within one month after receipt of
the application requiring such supply:...”

Regulation 4.7 of the SoP Regulations specifies that:

“4.7 The Distribution Licensee shall, on an application by the owner or occupier of any
premises, give supply of electricity to such premises, within one (1) month after receipt
of the completed application and payment of charges for requiring such supply, if the
supply to an applicant is to be given from an existing network of the Distribution
Licensee.”

The period stipulated under the statutory provisions cited above is the maximum period
for providing supply of electricity, beyond which compensation becomes payable if claimed.
The matter of providing such supply within a shorter period has been under discussion with
the Distribution Licensees. In the background of these discussions, the Commission is of the
view that Distribution Licensees should endeavour to provide supply of electricity to all
categories of consumers, within the area of the Municipal Corporation of Greater Mumbai as
a first step, within 15 days, i.e. well before the stipulated maximum period, so as to provide
more expeditious service to consumers and improve the ease of doing business. Considering
their experience in the Municipal Corporation of Greater Mumbai area, the Distribution
Licensees could extend this dispensation to other areas of Maharashtra as per the actual site
conditions.

The following Practice Direction is issued accordingly under Regulation 22 of the


Supply Code Regulations, 2005.
Practice Direction

Subject to the statutory provisos, the Distribution Licensees shall endeavour to


release new connections and provide supply of electricity to all categories of consumers
within the area of the Municipal Corporation of Greater Mumbai within fifteen days of
the receipt of applications complete in all respects.

Considering their experience in the Municipal Corporation of Greater Mumbai


area, the Distribution Licensees shall endeavour to extend this dispensation to other
areas of Maharashtra as per the actual site conditions.

This Practice Direction shall be effective from the date of its issue.

Sd/- Sd/- Sd/-


(Deepak Lad) (Azeez M. Khan) (Chandra Iyengar)