SAUDI ARAMCO ID/PID FORM REV 1 - 010109 (Standard Cutoff - March 2013) Rev 7 31-Mar-13
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
Centrifugal Gas Compressor (Process Air or Gas Service) SATIP-K-402-01 30-Apr-13 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
1.0 DOCUMENT REVIEW
Eqpt. Storage, Handling and Preservation-
1.1 SAIC-K-2001 SAIC-K-2001 W RH
Compressors
2.0 MATERIAL RECEIVING
Equipment Verification of NMR and Visual
2.1 SAIC-K-2002 SAIC-K-2002 H W See Note 1- General Notes for SA Inspection
Inspection
Equipment Handling, Storage and
2.2 SAIC-K-2003 SAIC-K-2003 I W See Note 1- General Notes for SA Inspection
Preservation of Mech Components
2.3 Lube and Seal oil System See Remarks See Remarks Refer to SATIP-G-115-01
2.4 Controls & Instrumentation See Remarks See Remarks Refer to SATIP -J-902-03
2.5 Auxiliary Electrical Components See Remarks See Remarks Refer to SATIP -P-515-01
2.6 Electrical Motor Drivers See Remarks See Remarks Refer to P-113-02
3.0 INSTALLATION
3.1 Concrete Placement for Foundation See Remarks See Remarks See SATIP-Q-001-02
Inspect Support Structure for Release for
3.2 SAIC-M-2006 SAIC-M-2006 I W See Note 1- General Notes for SA Inspection
equipment installation
Mounting Plate ( Base plate and Use SATR-K-2001
3.3 SAIC-K-2004 SAIC-K-2004 I W
Soleplate) Installation and Leveling
3.4 Compressor/driver Pre-alignment SAIC-K-2008 SAIC-K-2008 H W Use SATR-K-2002
See SATIP-Q-010-01 or Q-011-01whichever is
3.5 Grouting of Machinery Support See Remarks See Remarks
applicable
3.6 Inspection of Auxiliary Piping Installation SAIC-K-2005 SAIC-K-2005 H W
3.7 Driver Installation inspection See Remarks See Remarks Refer to SATIP-P-113-02
3.8 Control and Instrumentation See Remarks See Remarks Refer to SATIP-J-902-03
Skid Mounted Aux. Electrical System
3.9 See Remarks See Remarks Refer to SATIP-P-515-01, P-113-01 or P-113-02
installation
Page 1 of 3
SAUDI ARAMCO ID/PID FORM REV 1 - 010109 (Standard Cutoff - March 2013) Rev 7 31-Mar-13
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
Centrifugal Gas Compressor (Process Air or Gas Service) SATIP-K-402-01 30-Apr-13 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
(Lube & seal Oil) Lubrication, Shaft
4.0 See Remarks See Remarks Refer to SATIP-G-115-01
Sealing & Control Oil System
4.1 Structural steel Installation and Access See Remarks See Remarks Refer to SATIP-M-001-01
4.2 Painting/Repair Painting of Equipment See Remarks See Remarks Refer to the ap[plicable SATIP-H Series
4.3 Insulation/ Cladding (where required) See Remarks See Remarks Refer to SATIP-N-001-02
4.4 Welding See Remarks See Remarks See SATIP-W-011-01
Compressor Suction and Discharge
4.5 Process Piping Connection & SAIC-K-2007 SAIC-K-2007 H W See Note 1- General Notes for SA Inspection
requirements
Flange Joint, gasket verification and bolt Use SATR-L-2001 - See Note 1 of General Notes for
4.6 SAIC-L-2014 SAIC-L-2014 H W
tightening SA Responsibility
4.7 Fire detection and spray system See Remarks See Remarks Refer to SATIP-L-350-05
4.0 PRE-COMMISSIONING
4.1 Final compressor/driver alignment SAIC-K-2008 SAIC-K-2008 H H Use SATR-K-2002
Instrumentation and Electrical Pre- Refer to the respective SATIPs for Electrical &
4.2 See Remarks See Remarks
Commissioning prior MCC Instrumentation noted above.
Final Inspection/Re-instatement of Use SATR-A-2011
4.3 SAIC-K-2009 SAIC-K-2009 H W
Centrifugas Gas Compressor
Mechanical Completion Punch listing
4.4 Form SA-6133 Form SA-6133 H
(PMCC or Final MCC)
Page 2 of 3
SAUDI ARAMCO ID/PID FORM REV 1 - 010109 (Standard Cutoff - March 2013) Rev 7 31-Mar-13
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
Centrifugal Gas Compressor (Process Air or Gas Service) SATIP-K-402-01 30-Apr-13 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels
1 of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative
3 is not present.
4 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection
Page 3 of 3