Engineering Procedure
SAEP-397                                                                                20 October 2015
Vendor Performance Escalation
Document Responsibility: Project Quality Standards Committee
                                               Contents
                                           1    Scope.............................................................. 2
                                           2    Intended Users............................................... 2
                                           3    Applicable Documents.................................... 2
                                           4    Definitions....................................................... 3
                                           5    Deficiency Classification................................. 4
                                           6    Escalation Process......................................... 4
                                                6.1 Notification Stage....................................... 4
                                                6.2 Warning Stage........................................... 5
                                                6.3 On Hold Stage............................................ 6
                                           7    Responsibilities............................................... 7
                                        Appendix A - Vendor Escalation Process Flowchart.... 9
Previous Issue: New                     Next Planned Update: 20 October 2018
                                                                                                        Page 1 of 9
Contact: Al-Ghamdi, Khalid Salem (ghamks0k) on +966-13-8801775
                             Copyright©Saudi Aramco 2015. All rights reserved.
Document Responsibility: Project Quality Standards Committee                                SAEP-397
Issue Date: 20 October 2015
Next Planned Update: 20 October 2018                                     Vendor Performance Escalation
1       Scope
        This procedure provides guidelines on escalating major quality and technical
        deficiencies and unsatisfactory performance by Company-approved vendors that supply
        inspectable commodities.
        The objective of the escalation process is to communicate major quality and technical
        deficiencies, which directly impact the quality of supplied products, to vendor’s senior
        management and ensure timely completion of corrective actions and improve vendors’
        overall performance.
2       Intended Users
        This procedure is intended for use by Engineering Services Admin area technical and
        quality teams.
3       Applicable Documents
        The requirements contained in the following documents apply to the extent specified in
        this procedure.
        3.1     Saudi Aramco Documents
                Saudi Aramco Engineering Procedures
                    SAEP-301                   Instruction for Establishing and Maintaining Saudi
                                                  Aramco Engineering Requirements
                    SAEP-379                   Quality Issues Notification
                    SAEP-380                   Equipment Deficiency Report
                    SAEP-381                   Project Quality Issues Escalation Process
                    SAEP-1150                  Inspection Coverage on Projects
                Other Document
                    Vendor Review Committee (VRC) Bylaws
        3.2     Industry Code and Standard
                International Organization for Standardization
                    ISO-9001:2008              Quality Management Systems
                                                                                            Page 2 of 9
Document Responsibility: Project Quality Standards Committee                             SAEP-397
Issue Date: 20 October 2015
Next Planned Update: 20 October 2018                                  Vendor Performance Escalation
4       Definitions
        Equipment Deficiency Report (EDR): SAP notification (type Q4) listing equipment
        deficiencies with sufficient detail reflecting procurement document, specifications, the
        equipment manufacturer and investigation result in accordance with SAEP-380.
        Responsible Inspection Office Supervisor: Supervisor of Quality Assurance Unit of
        Vendor Inspection Division in SAO, Quality Management Head in AOC-The Hague &
        AAJ-Tokyo, and ASC Inspection Supervisor.
        Responsible Standards Committee Chairman: Chairman of the engineering
        standards committee for standards and commodities.
        Responsible Technical and Quality Teams: Designated Engineering Services
        individuals (In-Kingdom & out-of-Kingdom) to review and assess vendors’ approval
        and performance matters for inspectable commodities.
        Saudi Aramco Subsidiaries Appropriate Entity: Saudi Aramco Subsidiaries
        Managing Directors or their delegates.
        Responsible Assessor: Either the responsible Inspection office supervisor or the
        responsible Standards Committee chairman or their delegates.
        Responsible Standardization Agent: The RSA represents the highest level of
        engineering or technical expertise within Saudi Aramco for a specific class or subclass
        of material master items.
        Vendor Review Committee (VRC): A review committee led by Engineering Services
        Chief Engineer to oversee, review, and approve actions pertaining to vendors’ approval,
        rejection, as well as change of status for existing suppliers.
        Engineering Services Department Heads: Department Heads or their delegates to
        oversee, review, and approve actions pertaining to vendors’ approval, rejection, as well
        as change of status for existing suppliers.
        Industrial Development Department Head: Material Supply Department Head or his
        delegate responsible for strategic procurement, sourcing, supplier relation management
        and other important material supply functions.
        Mandatory Saudi Aramco Engineering Requirements (MSAER): Mandatory Saudi
        Aramco Engineering Requirements (MSAERs) are documents which include engineering
        standards (SAESs), materials system specifications (SAMSSs), engineering procedures
        (SAEPs) and standard drawings (SASDs) that are developed for uniformity and applied
        Company-wide.
                                                                                         Page 3 of 9
Document Responsibility: Project Quality Standards Committee                                 SAEP-397
Issue Date: 20 October 2015
Next Planned Update: 20 October 2018                                      Vendor Performance Escalation
5       Deficiency Classification
        Deficiencies shall be classified as major if one of the following conditions applies:
        1.    Deficiencies that put quality and integrity of the product, and project/facility
              including its workers and equipment at risk. That is, the deficiencies that prevent
              putting a facility in operation as they represent, if not corrected, an evident danger
              to Company property or personnel safety, and those that may impact the safe
              commissioning, start up, and operation of the facility.
        2.    Outsourcing core manufacturing processes without proper approval from Saudi
              Aramco Responsible Technical and Quality Teams.
6       Escalation Process
        The escalation process shall be initiated by the responsible Inspection office supervisor
        or responsible Standards Committee chairman after one or more of the following
        scenarios are experienced:
        1.    Major quality/technical concerns/deficiencies identified during manufacturing or
              plant assessment.
        2.    Major product deficiencies identified during site receiving inspection or during
              commissioning and operation.
        3.    Lack of vendor’s responsiveness to end user’s requests and after-sale services.
              Comment: Major product deficiencies identified at site and lack of vendor responsiveness
                       cases will be reported in accordance with SAEP-380. This procedure will
                       govern the escalation process of Equipment Deficiency Reports.
        Quality and/or technical concerns/deficiencies and poor performance concerns should
        be coordinated among responsible technical and quality teams and shall be brought to
        the attention of the vendor’s senior management according to the following escalation
        stages for in-Kingdom & out-of-Kingdom vendors:
        6.1     Notification Stage
                1.   Within three (3) working days of encountering one or more of the above
                     scenarios, contact the Industrial Development Department (for In-Kingdom
                     vendors) or the appropriate subsidiary entity (for out-of-Kingdom vendors)
                     to communicate the experienced Quality and/or technical deficiencies and
                     poor performance as an initiation of the escalation process.
                2.   Send Notification Letters
                     Upon receiving the concerns/deficiencies from the technical and quality
                     teams, the Industrial Development Department (for in-Kingdom vendors) or
                                                                                             Page 4 of 9
Document Responsibility: Project Quality Standards Committee                               SAEP-397
Issue Date: 20 October 2015
Next Planned Update: 20 October 2018                                    Vendor Performance Escalation
                     the appropriate subsidiary entity (for out-of-Kingdom vendors) shall send a
                     notification letter to the vendor’s senior management within two (2)
                     working days. The letter should provide details on deficiencies and shall
                     mandate the vendor to complete corrective actions within a maximum of
                     forty five (45) days of the letter date or within an agreed completion time
                     frame.
                     The letter to out-of-Kingdom vendors shall mandate the vendor to submit a
                     corrective action plan to the responsible technical and quality teams within
                     two (2) weeks of receipt of the letter.
                3.   Initiate SAP Workflow
                     Responsible Assessor shall initiate a follow up workflow in SAP using
                     transaction code ZQ0017. See Appendix A. If the case has been reported
                     in accordance with SAEP-380, a workflow is not necessary at this stage.
                4.   Conduct Performance Counseling
                     Within two (2) weeks of issuing the notification letter to In-Kingdom
                     vendors, the responsible Inspection office supervisor or responsible SCC
                     or their delegates shall conduct a performance counseling meeting with the
                     vendor’s most senior management. The meeting minutes and attendance
                     shall be recorded in SAP using transaction code ZQ0017 workflow or using
                     SAP notification (type Q4) for Equipment Deficiency Report (EDR).
                     The objective is to produce an improvement action plan that will be
                     implemented by the vendor.
                5.   Assess Corrective Actions
                     The responsible assessor shall perform a desk review or physical assessment
                     to verify the effective implementation of the vendor’s corrective actions.
                     If the vendor’s corrective actions are effective and satisfactory, no further
                     escalation is required. The responsible assessor shall close the SAP
                     workflow as approved or close the Equipment Deficiency Report (EDR).
        6.2     Warning Stage
                In case a vendor fails to submit a satisfactory corrective action plan within the
                allocated time frame or fails to effectively complete required corrective actions
                within the given time frames the following actions shall be taken:
                1.   Send Warning Letters
                     The responsible Engineering Services Department Head or his delegate
                     shall formally request the Industrial Development Department (for in-
                                                                                           Page 5 of 9
Document Responsibility: Project Quality Standards Committee                               SAEP-397
Issue Date: 20 October 2015
Next Planned Update: 20 October 2018                                    Vendor Performance Escalation
                     Kingdom vendors) or the appropriate subsidiary entity (for out-of-Kingdom
                     vendors) to issue a warning letter to the vendor’s highest senior
                     management (CEO or equivalent) and send a copy to the Vendor Review
                     Committee. The letter shall specify all unresolved quality and/or technical
                     deficiencies and advise the vendor’s management to complete actions
                     within (14) days or risk being placed on hold.
                2.   Assess Corrective Actions
                     The responsible assessor shall perform a desk review or physical assessment
                     to verify the effective implementation of the vendor’s corrective actions.
                     If the vendor’s corrective actions are effective and satisfactory, no further
                     escalation is required. The responsible assessor shall close the SAP
                     workflow as approved or close the Equipment Deficiency Report (EDR).
        6.3     On Hold Stage
                If a vendor fails to submit and complete the corrective actions specified in the
                warning letter within the given time frame, the responsible Inspection office
                supervisor or the Standards Committee Chairman shall initiate the placement on
                hold process by the following steps:
                1.   Prepare the Vendor Review Committee Action Request forms and include
                     copies of the notification letter, the signed minutes of the performance
                     counseling meeting, and the warning letter.
                2.   Submit and present to the Vendor Review Committee the request to place
                     the vendor on hold. The presentation shall include potential impact on
                     projects, operation impacts, and alternative sourcing as a result of placing
                     the vendor on hold.
                3.   Upon obtaining VRC approval, contact the Industrial Development
                     Department to initiate SAP workflow in case a workflow is not initiated in
                     the notification stage. The responsible Inspection office supervisor and the
                     Standards Committee Chairman and their delegates shall process the
                     workflow with on hold action using SAP transaction code ZQ0017.
                                                                                           Page 6 of 9
Document Responsibility: Project Quality Standards Committee                                     SAEP-397
Issue Date: 20 October 2015
Next Planned Update: 20 October 2018                                         Vendor Performance Escalation
7       Responsibilities
         Title or Organization
                                                               Action or Task
              Accountable
             Industrial            Sends notification and warning letters to vendor’s senior
            Development             management reported by responsible technical and quality teams
         Department Head or
            his delegate           Initiate the SAP workflow to place the vendor on hold
                                   Initiate the SAP workflow for follow-up actions on vendors quality
                                    and/or technical deficiencies and poor performance concerns
              Inspection
             Department/
                                   Lead counselling meeting with in-Kingdom vendors in coordination
             Responsible
                                    with Inspection Supervisor or his delegate
           Inspection office
           supervisor or his
               delegates           Prepare Vendor Review Committee Action Request to place the
                                    vendor on hold in accordance with Engineering Services VRC
                                    bylaws
                                   Request Industrial Development Department (for in-Kingdom
        Engineering Services
                                    vendors) or the appropriate subsidiary entity (for out-of-Kingdom
        Department Heads or
                                    vendors) to issue a warning letter to the vendor’s highest senior
          their delegates
                                    management (CEO or equivalent)
            Saudi Aramco
                                   Issue official notification and warning letters to the vendor’s senior
             Subsidiaries
                                    management
          appropriate entity
                                   Initiate the escalation process in coordination with Inspection
                                    Supervisor or his delegate
        Standards Committee  Conduct counselling meeting with In-Kingdom vendors in
           Chairman or his    coordination with Inspection Supervisor or his delegate
             delegates
                             Prepare Vendor Review Committee Action Request to place the
                              vendor on hold in accordance with Engineering Services VRC
                              bylaws
                                   Oversee, review, and approve actions pertaining to vendor’s
            Vendor Review
                                    approval or rejection, as well as change status for existing
              Committee
                                    suppliers
                                                                                                 Page 7 of 9
Document Responsibility: Project Quality Standards Committee                                     SAEP-397
Issue Date: 20 October 2015
Next Planned Update: 20 October 2018                                         Vendor Performance Escalation
         Title or Organization
                                                               Action or Task
              Accountable
                                   Prepare a list of identified quality and/or technical deficiencies and
                                    vendor performance concerns
                                   Communicate to the Industrial Development Department (for in-
                                    Kingdom vendors) or the appropriate subsidiary entity (for out-of-
                                    Kingdom vendors)
             Responsible
              Assessor             Review and assess (desk review or physical) the vendor’s
                                    corrective actions plan, and corrective actions implementation
                                   Conduct counselling meeting with in-Kingdom vendors
                                   Recommend closure or escalation of vendor’s corrective action
                                    implementation
                                      Revision Summary
20 October 2015       New Saudi Aramco Engineering Procedure that defines the escalation process of major
                      quality and technical issues and unsatisfactory performance by Company-approved
                      vendors that supply inspectable commodities.
                                                                                                 Page 8 of 9
Document Responsibility: Project Quality Standards Committee                                                                                                                                                            SAEP-397
Issue Date: 20 October 2015
Next Planned Update: 20 October 2018                                                                                                                                                         Vendor Performance Escalation
                                           Appendix A                                                                      Vendor Escalation Process Flowchart
                                                                                                                                              Escalation Process Start
             Notification Stage (45 Days Max or Agreed Time Frame)
                                                                                                                                        Yes                                  No
                                                                                                                                                         IK Vendor
                                                                                                         Issue Notification Letter to                                               Issue Notification Letter to
                                                                     Shall Complete within (14 Days)
                                                                                                          Vendor Sr. Management                                                     Vendor Sr. Management
                                                                                                              within one week                                                            within one week
                                       Dyas Max)
                                                                                                                                                                                          Satisfactory
                                                                                                          Conduct Performance                                                                                      No
                                                                                                         Counselling Meeting with                                                     Corrective Action Plan
                                                                                                         Vendor Sr. Management                                                            within 14 days
                                                                                                                                                                                       Yes
                                                                                                                   Verify               Yes                                  Yes             Verify                No
                                                                                                               Corrective Action                                                        Corrective Action
                                                                                                              Implementation                                                            Implementation
                                                                                                                              No
             Warning Stage (14 Days Max)
                                                                                                          Issue warning letter to                  No further escalation.            Issue warning letter to
                                                                                                       Vendor highest management                 Document the issue in SAP         Vendor highest management
                                                                                                                  Verify                                                                     Verify
                                                                                                              Corrective Actions        Yes                                  Yes        Corrective Actions
                                                                                                              Implementation                                                            Implementation
                                                                                                                              No                                                       No
                                                                                                                                                 Inspection Supervisor or
                                                                                                                                                   SCC Recommends Hold
           On Hold Stage
                                                                                                                                                     Placement to VRC
                                                                                                                                        Yes                                  No
                                                                                                                                                      VRC Approve                                Follow VRC
                                                                                                       Place Vendor On Hold                          Recommendation                          Decision/Directives