The document summarizes the results of a mandrel test conducted on ducting for a street lighting project. It includes a table listing 14 duct runs between manholes or poles, identified by number. The table includes 14 columns to indicate the test results for up to 14 ducts in each run, with slashes indicating the ducts were tested and found clear/unclogged. The test was conducted to check for blockages or restrictions in underground ducting used for cable runs.

Uploaded by

amirul aizad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2K views5 pages

Mandrel Test

The document summarizes the results of a mandrel test conducted on ducting for a street lighting project. It includes a table listing 14 duct runs between manholes or poles, identified by number. The table includes 14 columns to indicate the test results for up to 14 ducts in each run, with slashes indicating the ducts were tested and found clear/unclogged. The test was conducted to check for blockages or restrictions in underground ducting used for cable runs.

Uploaded by

amirul aizad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 5

POWER METER TEST

BERSATU ELECTRICAL
ENGINEERING SDN BHD
Project Description :
Area / Location :
Unit No. Results (dBm) Remarks
Unit 2 15.22/15.13
Unit 2A 14.77/14.12
Unit 6 13.92/14.95
Unit 8 13.86/13.89
Block A
Unit 10 13.14/14.19
Unit 12 14.87/14.87
Unit 12A 15.16/15.23
Unit 16 14.98/14.98
Unit 18 14.93/14.93
Unit No. Results (dBm) Remarks
Unit 66 15.02/15.03
Unit 62A 13.45/13.50
Unit 62 14.64/14.12
Unit 60 14.86/15.19
Block B
Unit 58 13.92/14.12
Unit 56 14.64/14.64
Unit 52A 13.13/13.13
Unit 52 14.43/14.43
Unit 50 13.79/13.79
Unit No. Results (dBm) Remarks
Unit 20 13.2/13.24
Unit 22 13.86/13.90
Unit 22A 13.51/13.00
Block C Unit 26 13.74/13.00
Unit 28 14.03/14.03
Unit 30 14.45/14.50
Unit 32 14.19/14.30
Unit 32A 13.65/13.65
Unit No. Results (dBm) Remarks
Unit 48 13.66/14.00
Unit 46 14.89/14.89
Unit 42A 14.63/14.65
Block D Unit 42 14.64/14.64
Unit 40 13.98/14.00
Unit 38 14.37/14.37
Unit 36 14.3
Unit 32A 14.93
PREPARED BY : REVIEWED BY : ACCEPTED BY :
CONTRACTOR REPRESENTATIVE SITE COORDINATOR REGION REPRESENTATIVE
DATE
NAME

SIGNATURE
Doc Ref :
BERSATU ELECTRICAL ENGINEERING SDN BHD
Rev. No : 1
INTEGRATED STANDARD OPERATING PROCEDURES
Issue Date : 21-Mar-19
MANDREL TEST
Page No : 1 of 1

PROJECT : 149 UNIT RAWANG

CONTRACTOR : BERSATU ELECTRICAL ENGINEERING SDN BHD

BLOCK : INFRA TM MANHOLE

LOCATION :

MANHOLE TYPE :

to to

REMARKS :

Electrical Contractor Main Contractor COW / PM / SO

Name : BERSATU ELECTRICAL ENGINEERING SDN BHD Name : MTL CONSTRUCTION SDN BHD Name : MINCONSULT SDN BHD
Date : Date : Date :
MANDREL TEST RESULT
BERSATU ELECTRICAL ENGINEERING SDN BHD
Project Description : Eco Forest
Area / Location : Hazelton Main Boulevard
MAIN DUCT
NO. DUCTING FOR STREET LIGHTING DATE TESTED REMARKS
1 2 3 4 1 2 3 4 5 6 7 8

1 GI Pipe No. 1 / /

2 GI Pipe No. 2 / /

3 GI Pipe No. 3 / /

4 GI Pipe No. 4 / /

5 GI Pipe No. 5 / /

6 Pole No. 1 - Pole No. 2 / /

7 Pole No. 2 - Pole No. 3 / /

9 Pole No. 3 - Pole No. 4 / /

10 Pole No. 4 - Pole No. 5 / /

11 Pole No. 5 - Pole No. 6 / /

12 Pole No. 6 - Pole No. 7 / /

13 Pole No. 7 - Pole No. 8 / /

14 Pole No. 8 - Pole No. 9 / /

15 Pole No. 9 - Pole No. 10 / /

16 Pole No. 10 - Pole No. 11 / /

17 Pole No. 11 - Pole No. 12 / /

18 Pole No. 12 - Pole No. 13 / /

19 Pole No. 13 - Pole No. 14 / /

PREPARED BY : REVIEWED BY : ACCEPTED BY :


CONTRACTOR REPRESENTATIVE CONSULTANT
DATE
NAME

SIGNATURE
MANDREL TEST RESULT
BERSATU ELECTRICAL ENGINEERING SDN BHD
Project Description : Eco Forest
Area / Location : Hazelton Main Boulevard
NOS. OF MAIN DUCT
NO. DUCTING FOR TNB DATE TESTED REMARKS
1 2 3 4 5 6 7 8 9 10 11 12 13 14

1 FP-1 to DB-1 / /

2 Fp-1 to DB-2 / /

TNB Manhole No. 1(1.8 x 1.8 x


3 1.2) to TNB Manhole No. 2(1.8 / / / / / / / / / / / /
x 1.8 x 1.2)

TNB Manhole No. 2(1.8 x 1.8 x


4 1.2) to TNB Manhole No. 3(1.8 / /
x 1.8 x 1.2)

TNB Manhole No. 2(1.8 x 1.8 x


5 1.2) to TNB Manhole No. 4(1.8 / / / / / / / / / /
x 1.8 x 1.2)

TNB Manhole No. 3(1.8 x 1.8 x


6 1.2) to TNB Manhole No. 6(1.8 / / /
x 1.8 x 1.2)

TNB Manhole No. 4(1.8 x 1.8 x


7 1.2) to TNB Manhole No. 5(1.8 / / / / / / / / / / /
x 1.8 x 1.2)

TNB Manhole No. 6(1.8 x 1.8 x


8 1.2) to TNB Manhole No. 1(3.38 / /
x 2.18 x 2.2)

TNB Manhole No. 6(1.8 x 1.8 x


9 1.2) to TNB Manhole No. 7(1.8 / / / / /
x 1.8 x 1.2)

TNB Manhole No. 1(3.38 x 2.18


10 x 2.2) to TNB Manhole No. / / / / / / / / / /
8(1.8 x 1.8 x 1.2)

TNB Manhole No. 8(1.8 x 1.8 x


11 1.2) to TNB Manhole No. 9(1.8 / / / / / / / /
x 1.8 x 1.2)

TNB Manhole No. 7(1.8 x 1.8 x


12 1.2) to TNB Manhole No. 10(1.8 / / / /
x 1.8 x 1.2)

TNB Manhole No. 9(1.8 x 1.8 x


13 1.2) to TNB Manhole No. 11(1.8 / /
x 1.8 x 1.2)

TNB Manhole No. 10(1.8 x 1.8 x


14 1.2) to TNB Manhole No. 12(1.8 / /
x 1.8 x 1.2)

TNB Manhole No. 11(1.8 x 1.8 x


15 1.2) to TNB Manhole No. 13(1.8 /
x 1.8 x 1.2)
PREPARED BY : REVIEWED BY : ACCEPTED BY :
CONTRACTOR REPRESENTATIVE CONSULTANT
DATE
NAME

SIGNATURE
MANDREL TEST RESULT
BERSATU ELECTRICAL ENGINEERING SDN BHD
Project Description : Eco Forest
Area / Location : Hazelton Main Boulevard
MAIN DUCT
NO. DUCTING FOR TELEKOM DATE TESTED REMARKS
1 2 3 4 1 2 3 4 5 6 7 8
JC9C Manhole (1) - Future
1 / / / /
Connection (1)
JC9C Manhole (1) - JC9C
2 / / / /
Manhole (2)
JC9C Manhole (2) - JC9C
3 / / / /
Manhole (3)
JC9C Manhole (3) - JC9C
4 Manhole (4) / / / /

JC9C Manhole (4) - Future


5 Connection (3) / / / / / /

JC9C Manhole (3) - Future


6 Connection (2) / / / /

PREPARED BY : REVIEWED BY : ACCEPTED BY :


CONTRACTOR REPRESENTATIVE CONSULTANT
DATE