Reference 7
To Date…………
The Engineer
Dear Sir
Notice of Delay in the issue of Information
Further to our letter reference …………..dated…………..and to our Programme issued
on the……………….it has become apparent that the non receipt of the information
requested is now delaying our work and we therefore give notice of delay and additional
cost pursuant to Clause 6.3 of the Conditions.
It is considered that an extension of time may also be required and we therefore give
notice of our request for this pursuant to Clause 44 of the Conditions.
We shall in support of the above keep contemporary records as may reasonably be
necessary to support our claims pursuant to Clause 53.1 of the Conditions.
Yours faithfully
…………………………
Contractor Ltd