Toc 16r-90
Toc 16r-90
90
           E
CONDUCTINGTECHNI
               CALAND
        PL
ECONOMICEVALUATI
               ONS-AS
APPLIEDFORTHEPROCESSAND
      M
UTILI
    TYINDUSTRI
             ES
  SA
                    AACE® International Recommended Practice No. 16R-90
                                                E
  AS APPLIED FOR THE PROCESS AND UTILITY INDUSTRIES
                                  TCM Framework: 3.2 – Asset Planning
                                    3.3 – Investment Decision Making
                             PL               Rev. April 1, 1991
   Note: As AACE International Recommended Practices evolve over time, please refer to www.aacei.org for the latest
                                                    revisions.
             M
SA
This recommended practice is the culmination of several years of effort by a special AACE ad hoc
committee. The document has been reviewed by all concerned technical committees in AACE
and was formally accepted by the AACE Board of Directors as a recommended practice in
September 1990.
                                                                                                            April 1, 1991
                         (*)
1. INTRODUCTION
The American Association of Cost Engineers (AACE) has had a long-standing interest in developing standards and
recommended practices. The Recommended Practice described herein is for executing techno-economic
evaluations of process oriented engineering projects. Most, if not all, cost engineers are involved in process-
oriented techno-economic studies in the course of their work. Some concentrate in estimating only plant
investment; others are involved in specific areas of cost estimating or only in financial analysis; still others, in
overall economics. Adherence to a consistent set of process evaluation guidelines would improve the quality of
these studies and would lower the cost to prepare them (improve productivity).
                                                             E
There are several ways of conducting technical and economic evaluations in the process industries and within
these ways there are many variations. This recommended practice was developed to reduce the variations to a
                                             PL
manageable level.
2. CRITERIA
The AACE Recommended Practices and Standards (RPS) Committee and other standards-making organizations
                                  M
have stated that standards should, at the minimum, meet the dual criteria of verifiability and comparability.
*The Practice was developed by an AACE ad hoc committee set up for this purpose. Members of this ad hoc
committee were as follows:
               SA
      American National Standards Institute (ANSI), who provided information necessary to achieve
      consensus and who established that there was a genuine technical community interest in the
      Practice.
The Recommended Practice described herein was developed to meet these criteria in the following manner:
April 1, 1991
       Verifiability - The technical and economic evaluation should be conducted and reported such that all aspects
        of the study may be independently verified with reasonable effort.
       Comparability - The evaluation should be conducted and reported in ways that assure that changes in
        assumptions are readily and consistently evaluated. Also maximized is the ease of comparing any or all
        aspects of the subject study with any other study conducted under the aegis of the recommended practice.
In addition to the goals of verifiability and comparability, the Practice should facilitate evaluations that are
accurate and correct. Thus another criteria for this Practice is:
       Accuracy - The evaluation should be conducted in a manner that yields technically and economically correct
        results within the levels of uncertainty corresponding to the level of detail required.
This recommended practice is not intended to replace existing procedures but rather to provide guidelines such
that the above criteria may be met. Different industries (and different companies within these industries) conduct
technical and economic studies in different ways. This recommended practice is largely oriented to the chemical
                                                                E
process industries although most of the methods outlined may be adapted to other industries.
This recommended practice was largely written for budget-type estimates defined by AACE as having a +30% to -
                                               PL
15% accuracy. It is primarily intended for those companies seeking preliminary quotations from contractors such
that all are on the same basis and may be readily compared. Others could find the practice useful to conduct their
own preliminary evaluations in a consistent manner. Still others could find the practice useful within their own
company and for publishing or other external purposes (such as for sales discussions).
AACE feels that the collaboration of individuals on this project who represent the private sector, government and
                                   M
not-for-profit institutions have made an impressive contribution to the development of this Practice.
3. SCOPE
               SA
3.1                  This practice establishes a consistent procedure for conducting budget-type technical and
                     economic evaluations for use by the process industries such that ease of comparability and
                     verification are of paramount importance.
3.2                  Mass and energy balances, composition and properties of all streams, equipment specifications,
                     and performance criteria are all developed and reported according to a recommended format.
3.3                  Direct costs of plant sections are developed and reported according to recommended procedures
                     and formats.
3.4                  Other costs, such as foundations, structures, insulation, instruments, etc. are established by
                     recommended factors for each type of process or type of equipment.
3.5                  Field indirects, engineering, overhead and administrative costs are determined by factors herein
                     recommended.
3.6                  Operating costs are developed based on estimates of raw material, utility and operating labor
                     requirements. Other elements of operating costs such as maintenance and overhead are based on
                     factors recommended herein.
April 1, 1991
3.8                  A sensitivity study may be conducted to determine the effects of changes in key variables and
                     assumptions.
3.9                  A recommended reporting format is provided to be sure that all information required for
                     verifiability and comparability is included. Also included are listings of deviations from this
                     established practice.
4.2                  AACE Metropolitan New York Section, AACE Transactions, "The Module Estimating Technique as an
                     Aid in Developing Plant Capital Costs," 1962.
                                                                   E
4.3                  Brown, D. R. et al, An Assessment Methodology for Thermal Energy Storage Evaluation, Prepared
                     for U.S. Department of Energy by Battelle Memorial Institute, Pacific Northwest Laboratory,
                                                 PL
                     November, 1987.
                                                                    tm
4.4                  Electric Power Research Institute (EPRI), TAG - Technical Assessment Guide, Vol. 1, Electricity
                     Supply - 1989; Vol. 2, Electricity End-Use - Part 1, 1987, Parts 2 & 3, 1988; Vol. 3, Fundamentals and
                     Methods, Supply - 1987; Vol. 4, Fundamentals and End-Use - 1987, EPRI P-4463-SR, Palo Alto, CA.
                                    M
4.5                  Guthrie, K. M., Process Plant Estimating Evaluation and Control, Craftsman Book Company of
                     America, Solana Beach, CA, 1974.
4.6                  Humphreys, K. K. and P. Wellman, Basic Cost Engineering, 2nd ed., Marcel Dekker, Inc., New York,
               SA
1987.
4.7                  Peters, M. S. and K. D. Timmerhaus, Plant Design and Economics for Chemical Engineers, 3rd ed,
                     McGraw-Hill Book Co., New York 1980.
4.8                  Weinheimer, W. R., Cost Engineers' Notebook, "Percent Your Indirect Field Costs," Revision 1 dated
                     November 1984
4.9                  Wessell, H. E., "New Graph Correlates Operating Labor Data for Chemical Processes," Chemical
                     Engineering, July 1952, p. 209.
5. DEFINITIONS
5.1                  For the purpose of this document the following terms are defined, (Other terms used are defined in
                     AACE Recommended Practice No. 10S-90, "Cost Engineering Terminology”).
5.1.1                ADR (Asset Depreciation Range) Class Life. Approximate ranges of useful equipment life established
                     by the Internal Revenue Service for tax purposes.
April 1, 1991
5.1.2                Depreciable Life. The legal capital cost recovery period established by the Modified Accelerated
                     Cost Recovery System (MACRS). MACRS and its predecessor technique ACRS, Accelerated Cost
                     Recovery System, are depreciation techniques mandated by U.S. tax law.
5.1.3                Measure of Merit. An economic measurement (e.g., present value, interest rate of return) used to
                     determine the economic viability of a project. Syn. Figure of Merit
5.1.4                Inflation. A rise in the general price level, usually expressed as a percentage rate. "Inflation" is
                     usually used to describe the general change in prices for all goods and services. "Escalation" usually
                     refers to specific items.
5.1.5                Internal Rate of Return. The compound rate of interest that, when used to discount study period
                     costs and benefits of a project, will make the two equal, i.e., the discount rate that results in a net
                     present value of zero.
5.1.6 Levelized (Annualized) Production Cost. A unit cost equal to the annualized cost of production
                                                                    E
                     divided by the annual production rate. The annualized cost, recurring every year for the life of a
                     project, has a present value equivalent to the present value of all project costs. When the discount
                     rate used is the after-tax weighted cost of capital, the levelized production cost is similar to the
                                                  PL
                     revenue requirements used by the utility companies, and the cost of capital is considered part of
                     the cost of production.
5.1.7                Net Present Value. The sum of all project cash flows, both negative and positive, discounted to the
                     present time.
                                     M
5.1.8                Nominal (Current) Dollars. Dollars of purchasing power in which actual prices are stated, including
                     inflation or deflation. In the absence of inflation or deflation, current dollars equal constant dollars.
5.1.9                Overnight Cost. A measurement of capital investment that excludes any interest expense or
               SA
                     escalation of costs that may occur during the construction period, as if the project had literally
                     been built overnight.
5.1.10               Payoff Period, Discounted. The length of time required for the cumulative present value of after-tax
                     cash flows of a project to become positive.
5.1.11               Price Year. The reference year for a cost estimate or cash flow. For example, a capital cost estimate
                     might be based on 1990 dollars or some other year's dollars.
5.1.12               Profitability Ratio. The net present value of a project divided by the present value of the initial
                     capital investment.
5.1.13               Real (Constant) Dollars. Dollars of uniform purchasing power exclusive of general inflation or
                     deflation. Constant dollars are tied to a reference year.
April 1, 1991
7.1                  The significance of this Recommended Practice is that it provides a comprehensive yet consistent
                     procedure for taking into account all the technical information needed to develop a budget-type
                     estimate as well as all the relevant costs necessary to evaluate the economic performance of a
                     process being evaluated.
                                                                   E
7.2                  The method is intended to compare readily and in a consistent manner the economics of
                     competing processes as well as the economic viability of individual processes. The consistency of
                                                 PL
                     the method, providing verifiability and comparability, makes it particularly useful for publishing
                     results or for other external purposes such as for sales discussions. The method may also be used in
                     analyzing possible cost reductions in existing plants, for incremental studies, to design and cost
                     individual components of projects or for optimizing purposes. In short, the method has applications
                     wherever conceptual, preliminary or budget-type techno-economic studies are required. The
                     method is not intended for definitive-type estimates, although some parts of the practice may be
                                    M
                     adapted for this use (particularly the financial analysis model).
7.3                  The practice is not intended to replace existing design and cost procedures but rather to provide
                     guidelines such that the criteria of verifiability and comparability in the transmission of results to
               SA
                     others may be readily met. The words, "This study was performed using the AACE Recommended
                     Practice" should provide instant information as to exactly what was done and exactly how it was
                     done.
8.1                  Identify Objectives, Alternatives and Assumptions Necessary to Conduct the Study. The first step in
                     the procedure is to establish the specific objectives of the study, identify alternative ways of
                     accomplishing these objectives and bring out any constraints that limit the resultant analysis.
8.2                  Develop the Design. A process plant size is first established based on market considerations. Flow
                     sheets showing the major equipment required with detailed material and energy balances around
                     each equipment item are developed. Standard engineering practice as outlined in such texts as
                     Peters & Timmerhaus (ref. 4.7) are followed using a common set of recommended design premises.
8.3                  Develop Equipment Specifications. Major equipment components are sized according to the
                     requirements of the process flow sheet and material and energy balances. Major equipment items
                     are specified sufficiently to conduct budget-type costing. For example, in a budget-type estimate
                     for a heat exchanger, only the surface area, required type of exchanger and materials of
April 1, 1991
                     construction are needed to develop the cost. Such details as the tube pitch and length of tubes are
                     helpful but are not necessary for a budget estimate of the cost.
8.4                  Establish Total Capital Requirement. Plant costs are built up by first establishing the cost of each
                     equipment item delivered to the plant site. Material and labor costs to set and install equipment
                     are next estimated using recommended factors. Total plant costs are established by adding field
                     indirects, engineering costs, overhead and administration based on recommended factors. Finally,
                     total capital requirement is established by adding in such costs as pre-production or start-up costs,
                     inventory capital, initial chemicals and catalyst charges and land.
8.5                  Estimate Plant Operating Cost. Operating labor, utility and chemical requirements are first
                     estimated from the design data and from these total operating costs are established by means of
                     recommended factors.
8.6                  Conduct Financial Analysis. Detailed cash flows (year-by-year) are first established based on
                     recommended procedures. One or more of a set of measures-of-merit techniques are selected
                                                                   E
                     generally involving discounted cash flow in order to determine economic viability.
8.7                  Conduct Sensitivity Study. A set of key variables and assumptions are selected and the effects of
                                                PL
                     changes in these on the previous results are determined.
8.8                  Prepare Report. All the findings and the basis for them are documented by a set of recommended
                     tables. Discussions of the results are included in the report. All deviations from the recommended
                     practice are documented and reasons for the changes from those recommended are discussed.
                                    M
                     The above steps are described in more detail in Section 12.
The objective of this Technical and Economic Practice is to provide a consistent and reliable guide to performing
budget-type estimates such that communication of results to others is readily achieved with clear and unequivocal
understanding of what was and what was not included in the study. The criteria of verifiability and comparability
are the goals to be met.
The method is primarily aimed at generating budget-type estimates as defined by AACE having accuracy limits of
+30% to -15%. The method is also adaptable to order-of-magnitude estimates. The method is aimed at the process
industries and those doing business with them, but here again, other industries may find it useful.
The method does not detail rigid engineering design techniques. These are more than adequately covered in plant
design texts and other sources. Major equipment components are only specified sufficiently to conduct budget-
type estimates. Certain factors (or ranges of factors) in the costing procedure are specified for the purpose of
consistency. Recommended procedures for year-by-year cash flows and financial analyses are provided. Here
again, deviations are allowed as long as they are specified.
Finally, individual sections of the practice, such as the operating cost routine or the financial analysis procedure,
may be followed as long as it is made clear as to what is being done.
April 1, 1991
The primary assumption in using the recommended practice is that the process has been developed enough so
that sufficient detail is available to conduct the study for a budget-type estimate that will result in an accuracy
range of +30% to -15%. Reliable data for developing mass and energy balances around major equipment items
should be available. A sensitivity study, described below, is to be conducted on those items for which insufficient
data (including costs) are available or for which questionable assumptions are made. The reliability of the data, as
well as other factors, may necessitate deviating from the recommended practice. Deviations from the
recommended practice must be well documented in the report.
Some of the data needed in the specific calculations have been discussed and will also be covered in the following
sections. Briefly, these are summarized as follows:
                                                                 E
 11.1                Plant Design. Material balance, energy balance, stream compositions and quality, flow sheets
                     showing plant configuration.
 11.2
                                                PL
                     Equipment Specifications. Design of individual equipment to the extent necessary for costing;
                     materials of construction required; number of equipment items necessary; sparing philosophy
                     used; utility requirements; etc.
 11.3                Total Capital Requirements. Factors to be applied if not using recommended ones; cost curves and
                     data (including utility investment costs); construction labor rates.
                                    M
 11.4                Operating Costs. Factors required if not using recommended ones; operating labor requirements;
                     annual utility and chemical requirements; raw material and byproduct unit costs and quantity
                     requirements.
               SA
 11.5                Financial Analysis. Factors required if not using recommended practice factors; timing of cash
                     flows; cost of capital; discount factors; inflation rates for operating labor; investment capital;
                     power rates, chemical and catalyst rates.
12.1 Identify the Objectives, Alternatives and Assumptions. It is first necessary to establish the specific objectives
     for the technical economic study. For example, two or more design changes may be evaluated to determine
     which has the best economic potential in the overall scheme. Thus, a contractor could optimize the design
     to produce the desired end result and thus be competitive with other contractors when opening discussions
     with a client. The client might be evaluating two or more processes from different contractors to determine
     which, if any, are worthy of further consideration. If all the studies are done in a consistent manner as
     outlined in this practice, then comparisons are possible.
         It is also necessary to establish basic assumptions in applying the practice to the objective desired. The
         comprehensiveness of the study will depend on the degree of complexity of the problem, the intended
         purpose of the evaluation, the cost and resources available to perform the evaluation, and the impact, both
April 1, 1991
         monetary and non-monetary, contingent on the investment decision. Each of these may require different
         assumptions and different detail within the budget-type estimate.
         Assumptions made with respect to engineering design and bare equipment costs should be carefully
         considered. An error in establishing bare equipment costs can be magnified three to five times by the time
         the final results are estimated.
         Deviations from the recommended practice should be carefully documented and explained. Keep in mind
         that one of the main objectives of the practice is one of communicating to others exactly what is and what is
         not included in the study so that verification and comparability of results are readily obtained.
12.2 Develop the Design. This section includes a description of the necessary information to define properly the
     process under consideration. This section also defines the recommended design premises to be used in the
     study.
12.2.1 Process Definition -- Budget estimates require a detailed process flow diagram and stream
                                                                   E
                   summaries incorporating the following data:
                   Mass and energy balances should be conducted according to normally acceptable engineering
                   practices and using the design premises outlined below. It is not necessary to document the
                                     M
                   complete design unit but basic performance design criteria on which conclusions rest should be
                   documented. In most cases, all that would be necessary are the flow diagrams outlined above, the
                   equipment list (described below) and deviations from the design premises (described below).
               SA
                   Before developing the process flow diagrams, a plant size should be established based on marketing
                   conditions, expected share of market, economies of scale and other factors. In comparing
                   alternatives, plant size (output) should be kept constant except in those cases where plant size is
                   being evaluated in a sensitivity study.
12.2.2             Define Plant Sections and Sub-sections -- As the process is being developed, care should be taken to
                   establish logical plant section names and the groups of equipment to be contained within those
                   sections. Even within the same organization, slight variations in practice can complicate future
                   study-to-study comparisons (e.g., does heat exchange equipment go in its own section, in the
                   section that produces the waste heat, or in the section that benefits from the heat exchanger
                   product?). If executed with care, plant section definition will aid the ease of comparing studies, as
                   for example, the situation when the studies are executed by different entities for a single sponsor.
12.3 Develop Equipment Specifications. Major equipment items are sized according to the requirements of the
     process flow-sheets and material and energy balances. The items are specified sufficiently to conduct
     budget-type costing. Major equipment items in a process plant include heat exchangers, columns, reactors
     and other vessels, pumps, compressors, process furnaces, direct-fired heaters, miscellaneous equipment,
     specialized equipment, etc. A list of all major equipment items with design parameters specified should be
     included as part of the report. Examples of the degree of documentation that should be included are shown
April 1, 1991
         in Table 1. Appendix A provides a listing of optimum design and costing specifications for many types of
         equipment.
Table 1. Example of a Detailed Equipment List Showing Parameters Necessary for Cost Estimation
Amine contactor (4 required)                 Amine knockout drum (2 required)        Sand filters (4 required)
Size: Top, 9' ID X 29'6" high; bottom, 12'   Size: 12' ID X 16'6" high               Size: 9' ID X 15' high
ID X 35'6" high                              Operating pressure: 180 psig            Operating pressure: 50 psig
Operating pressure: 200 psig                 Operating temperature: 120°F            Operating temperature: 185°F
Operating temperature: 150°F
                                             Amine flash drum (2 required)           Carbon filters (4 required)
Amine regenerator (2 required)               Size: 10' ID X 30' high                 Size: 9' ID X 15' high
Size: 19' ID X 84' high                      Operating pressure: 60 psig             Operating pressure: 50 psig
Operating pressure: 50 psig                  Operating temperature: 150°F            Operating temperature: 185°F
Operating temperature: 260°F
                                             Regenerator reflux drum (2 req)         Lean amine pumps             (3    required,
Caustic precontactor (2 req'd)               Size: 9' ID X 11' high                  including 1 spare)
Size: 2' ID X 24' high                       Operating pressure: 50 psig             Type: centrifugal
Operating pressure: 180 psig                 Operating temperature: 100°F            Capacity: 1,475 gpm
                                                                    E
Operating temperature: 120°F                                                         Drive: motor
                                             Amine sump (2 required)                 Hp: 325
Caustic contactor (2 required)               Size: 8' ID X 8' high
                                                 PL
Size: 4'6" ID X 61' high                     Operating pressure: atmospheric         Amine filter pump (2 required)
Operating pressure: 180 psig                 Operating temperature: 160°F            Type: centrifugal
Operating temperature: 120°F                                                         Capacity: 620 gpm
                                                                                     Drive: motor
                                                                                     Hp: 25
Hp: 900
12.3.1               Design Philosophy and Equipment Sparing -- Conventional commercially available equipment
                     should be selected wherever possible. Deviations and special design equipment should be
                     documented.
                     Sparing should be done to provide 90% availability exclusive of planned maintenance unless prior
                     experience or system engineering studies have indicated that another level of sparing is
                     appropriate for the process being studied.
12.4.1               Introduction -- Total Capital Requirements are built up by first establishing the cost of purchased
                     delivered equipment items and then applying factors for: handling and setting; commodity material
                     and labor costs; field indirects; engineering; overhead and administration; contingencies.
                     Finally, factors for start-up costs, working capital, prepaid royalties, initial catalyst and chemical
                     charges, and land are applied to give the total capital requirement. The components are
                     summarized in Table B-1 in Appendix B. Details are provided in the following sections.