The document provides an overview of cost estimation for an industrial plant project. It discusses the different types of capital investments required, including fixed capital for manufacturing facilities and working capital for operations. It also outlines the various direct and indirect costs considered in developing order-of-magnitude, study, preliminary, definitive, and detailed cost estimates over the stages of a project. Specific cost calculations are provided for major equipment like a gasifier, heat exchanger, and absorber column. The total fixed capital cost, working capital, and investment required for the example project are estimated. Annual fixed and variable operating costs are also calculated.

Uploaded by

Awais Javaid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
427 views9 pages

Cost Estimation

The document provides an overview of cost estimation for an industrial plant project. It discusses the different types of capital investments required, including fixed capital for manufacturing facilities and working capital for operations. It also outlines the various direct and indirect costs considered in developing order-of-magnitude, study, preliminary, definitive, and detailed cost estimates over the stages of a project. Specific cost calculations are provided for major equipment like a gasifier, heat exchanger, and absorber column. The total fixed capital cost, working capital, and investment required for the example project are estimated. Annual fixed and variable operating costs are also calculated.

Uploaded by

Awais Javaid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 9

COST ESTIMATION

Cost Estimation Overview


A capital investment is required for any industrial process and
determination of the necessary investment is an important part of a plant
design project. Evaluation of this investment is referred to as cost
estimation.
Capital investment
Before industrial plant can put into operation, a large sum of money must be
supplied to purchase and install the necessary machinery and equipment. Land
and service facilities must be obtained and the plant must be erected complete
with all piping, controls and service. In addition, it is necessary to have money
available for theinstallation and working of a plant is called total capital
investment. Total Capital Investment = Fixed Capital + Working Capital

Fixed Capital Investment


The capital needed to supply the necessary manufacturing and plant
facilities is called fixed capital investment. The fixed capital is further
subdivided into followings.
Manufacturing fixed capital investment
Non-manufacturing fixed capital investment

The fixed capital investment classified in to two sub divisions:


1. Direct Cost
2. Indirect Cost
Direct Cost
The direct cost items arc incurred in the construction of the plant in addition
to the cost of equipment.
Purchased equipment cost
Purchased equipment installation
Insulation cost
Instrumentation and control
Piping

Electrical installation
Building including services
Yard improvement
Service facilities
Land
Indirect Cost
In Direct cost can be estimated by estimating following costs.
Engineering and supervision
Construction expenses
Contractors fee
Contingencies
Start-up expenses
Working Capital
The capital required for the operation of the plant is known as working
capital. Working Capital Includes following things to be considered
Raw materials and supplies carried in stock
Finished product in stock and semi-finished products in the process of
being manufactured
Accounts receivable
Cash kept on hand for monthly payment of operating expenses, such as
salaries, wages and raw material purchases
Accounts payable
Taxes payable
Capital cost estimates
An estimate of the capital investment for a process may vary, pre-design
estimated based on little information except the size of the proposed
project to a detailed estimate prepared from complete drawings and
specifications. Between these two extremes of capital investment estimates
there can be numerous other estimates which vary in accuracy depending
on the stage of development of the project. These estimates are called by a
variety of names, but the following five categories represent the accuracy
range and designation normally used for the design purposes.
1. Order of magnitude estimates
2. Study estimate (factorial estimate)
3. Preliminary estimates( Budget authorization estimate

4. Definitive estimate (project control estimate)


5. Detailed estimate (Contractors estimate).

Cost of Gasifier

Types = Fluidized Bed Gasifier

Material of construction = stainless steel

Pressure factor = 1.1

L=3m

D = 1m

Pressure = 30 bar

Bare cost mid 2004 = 18560 $

The purchased cost can be calculated using

Purchased cost = Bare cost from figure x Type factor x Pressure factor

Purchased cost = 18560 x 1.1 x 1

Purchased cost = 20416 $ in mid 2004

cost in 2004 cost in 2013 = cost index in 2004 cost index in 2013

Cost in 2015 = 20416 (1.025)^8 Cost in 2004 = 23149.6 $

Cost of heat exchanger

Type = Shell and tube heat exchanger

Material of construction = stainless steel

Pressure factor = 1

Type factor = Fixed head x 1.0


Heat transfer area = 83m2

Pressure = 20bar

Bare cost mid 2004 = 105000 $

The purchased cost can be calculated using

Purchased cost = Bare cost from figure x Type factor x Pressure factor

Purchased cost = 105000 x 1 x 1

Purchased cost = 105000 in mid 2004

cost in 2004*cost in 2015=cost index in 2004*cost index in 2015

Cost in 2015 = 105000 (1.025)^8

Cost in 2015 = 127932.3 $

SHIFT CONVERTOR

Density = 1213 kg/m3

Volume = 1.504 m3

Density = mass/volume

Mass = density x volume

Mass = 12016.96 Kg

= 26437.312 lb

Cost of LTS in 1990 = 1.3 x 105 dollars

Present cost by using marshall and swift index.

Present cost = (1.3 x 105) x (1582.9/924)

= 22270.381 dollars
ABSORBER

Volume = area x height

= 8.6 x 13.9

Volume = 119.54 m3

Mass = volume x density

Density = 7990 Kg/m3

Mass = 959810 Kg

Diameter = 4.5 m= Diameter = 118.11 inch

Cost of one distribution plate = 1000

= 6 x 1000 = 6000

Cost of vessel = 13.9 m (height) and 4.5m dia

= 200 x 1000

= 200,000

For Distributor Plate:

Marshall and swift index for 1992 = 950

Present in 2013= O.C x (index value at present / index value at 1992)

= 9 x (6000) x (1582.9 / 950)

= 9997.26

For Column:

Present cost of vessel = 200000 x (1582.9 / 950)

= 333242.105

Cost Of Packing:
Volume of packing = 296 m3

Cost of 38mm Pall rings(plastic packing) = 340 /m3

= 340 x 296

Original cost = 100640

Present cost = 100640 x (1582.9 / 950)

= 167687.927

Total cost = for distributor + for column + for packing

Total cost = 510926.79

Total purchased cost of all equipment (PCE)


Total purchased cost of equipment = Cost of gasifier + Cost of heat exchanger
+shift converter+ Cost of H2S absorber column

PCE =23149.6 +127932+22270+510926.79

PCE = 684278 $

Fixed capital cost


Major equipment Total purchased cost factor

f1 = Equipment erection 0.4

f2 = Piping 0.70

f3 = Instrumentation 0.20

f4 = Electrical 0.10

f5 = Building process 0.15

f6 = Utilities 0.50

f7 = Storages 0.15
f8 = Site development 0.05

f9 = Ancillarybuilding 0.15 Total physical plant cost (PPC)

F10 = Design and engineering 0.30

F11 = Construction fee 0.05

F12 = Contingency 0.10

Total physical plant cost (PPC) = PCE (1 + f1 + f2 + f3 +.f9)

Total physical plant cost (PPC) = 200162 x 3.4 Total physical plant cost (PPC) =
680550.8 $ Fixed cost = PPC (1 + f10 + f11 + f12)

Fixed cost = 680550.8 x 1.45

Fixed cost = 967789.6 $

Cost of air separation unit(20% of fixed cost)= 217397.7$

Total investment required for project

Total investment required this project = Fixed capital + Working capital Suppose

working capital is 7.5 % of the fixed capital Now,

Working capital = 0.075 x Fixed capital Working capital = 0.075 x 986798.6

Working capital = 69119.8$

Total investment of the project = 986798.6+74009.8

Total investment of the project = 1170899.5 $

Fixed cost

Maintenance cost = 0.10 x Fixed capital cost

Maintenance cost = 0.10 x 986798.6

Maintenance cost = 98679.86$


Operating labor = .15x98679.86 $ = 14801.98

Laboratory cost = 0.22 x Operating labor

Laboratory cost = 0.22 x 14801.98

Laboratory cost = 3256.43 $

Supervision = 0.2 x Operating labor

Supervision = 0.2 x 14801.98

Supervision = 296.196 $

Plant overheads = 0.5 x 14801.98

Plant Overheads = 740.49 $

Capital charges = 0.1 x Fixed capital

= 0.1 x 986798.6

Capital charges = 98679.86 $

Local taxes = 0.02 x fixed capital

Local taxes = 0.02 x 986798.6

Local taxes = 19735.97 $

Royalties = 0.01 x Fixed capital Royalties = 0.01 x 986798.6

Royalties = 7868.986 $

Total fixed cost =


98679.86+14801.98+2256.43+296.196+740.49+98679.86+19735.79+96867.98 $
=293058.586$

Variable cost
Raw material cost = 100000 $
Miscellaneous cost = 0.1 x Maintenance cost

Miscellaneous cost = 0.1 x 8955.86

Miscellaneous cost = 8955.986$

Total cost for installation and running the plant


Cost for installation and running the plant = Total investment of project+ Annual
production cost

Cost for installation and running the plant = 1060808.5 + 1971704.52 Cost for
installation and running the plant = 31412820.9 $

Cost in Pakistani rupees (PKR) = 31412820.9x100 PKR = 31412820.9PKR