EP Wells Operations Summary Report
EP Wells Operations Summary Report
 8/8/1990    00:00 - 11:45 11.75     D17     DRR                  234.00 CONT'D DRILLING AHEAD FROM 117 m. TO 350 m.
                                                                         NO LOSSES.
             11:45 - 12:00    0.25   D17     MNR                  234.00 DAILY MAINTENANCE.
             12:00 - 14:45    2.75   D17     DRR                  300.00 DRILLED AHEAD FROM 350 m TO 416 m.
             14:45 - 15:00    0.25   D17     NOA                  300.00 H2s ALERT.
             15:00 - 20:30    5.50   D17     DRR                  382.00 CONT'D DRILLED AHEAD FROM 416 m TO 498 m.
             20:30 - 20:45    0.25   D17     NOA                  382.00 FLOW CHECK. NO LOSSES.
             20:45 - 21:30    0.75   D17     PCD                  382.00 CIRCULATED HOLE CLEAN. SPOTTED 10 m3 Hi-VISC
                                                                         ON BOTTOM.
             21:30 - 21:45    0.25   D17     DVM                  382.00 DROP TOTCO. F/CHECK, STATIC.
             21:45 - 00:00    2.25   D17     DRT                  382.00 POOH TO 31 m MAX O/PULL 30000 daN. WIPED
                                                                         TIGHT SPOTS.
 8/9/1990    00:00 - 02:45    2.75   D17     DRT                  382.00 CONT'D POOH L/D STAB, 2 x 9 1/2 DCs, S/SUB &
                                                                         BIT. RECOVERED TOTCO (1 DEGREE).
             02:45 - 03:00    0.25   D17     NOA                  382.00 HOUSEKEEPING ON RIGFLOOR.
             03:00 - 03:30    0.50   D17     MNR                  382.00 SLIPPED BLOCKLINE 8.4 m.
             03:30 - 03:45    0.25   C17     NOA                  382.00 HELD SAFETY TALK PRIOR RIH 13 3/8 CSG.
             03:45 - 04:15    0.50   C17     RUD                  382.00 R/U FOR 13 3/8 CSG.
             04:15 - 08:30    4.25   C17     CLR                  382.00 M/U 13 3/8" SHOETRACK, BACKERLOCKED. TESTED
                                                                         FLOATS EQUIPS. OK. AND RIH 13 3/8" K55, BTC,
                                                                         81.1 kg/m. TO RESISTANCE @ 455 m.
             08:30 - 11:30    3.00   C17     CLR                  382.00 W/DOWN FROM 455 m TO 497 m.
             11:30 - 12:00    0.50   C17     PCD                  382.00 CIRC. 120% CSG CONTENTS. NO LOSSES.
             12:00 - 12:30    0.50   C17     CLC                  382.00 R/U DOWELL CMT HEAD & CMT LINES.
             12:30 - 12:45    0.25   C17     PRE                  382.00 FLUSHED & P/TESTED CEMENT LINES TO 21000 kPa.OK.
             12:45 - 13:30    0.75   C17     CLC                  382.00 DOWELL PREFLUSHED 3m3, DROPPED BTM PLUG. INST.
                                                                         TOP PLUG. CEMENTED 300 SKS POZMIX 16.1 kPa/m.
                                                                         RELEASED TOP PLUG.
             13:30 - 14:00    0.50   C17     PCD                  382.00 PUMPED 1.5m3 AFTER FLUSH. DISPLACED PLUG AND
                                                                         BUMPED SAME WITH RIG-PUMPS.
8/10/1990    00:00 - 03:00    3.00   C17     RUD                  382.00 CONT'D N/U BOP's.
             03:00 - 08:15    5.25   C17     BPT                  382.00 FUNCTION TESTED KOOMEY UNIT & BOP. M/U 13.3/8
                                                                         CTT. P/TEST S/O & HYDRIL 10500 kPa. M/U PTT
                                                                         P/T BOP & RELATED EQUIPTS. TO 21000 kPa. OK.
             08:15 - 10:15    2.00   C17     BPT                  382.00 P/U KELLY. P/TEST SURFACE LINES, KK's AND
                                                                         GRAY-VALVES TO 21000 kPa. OK.
             10:15 - 13:15    3.00   D12     DRT                  382.00 M/UP BHASSY NO.2 & RIH TO 471 m. TAGGED
                                                                         TOC @ 471 m.
             13:15 - 14:30    1.25   D12     DCM                  382.00 DRILLED SHOETRACK AND POCKET. SHOE @ 496 m.
                                                                         CLEANED AND WIPED SAME.
             14:30 - 14:45    0.25   D12     NOA                  382.00 FLOW-CHECK. STATIC.
             14:45 - 23:45    9.00   D12     DRR                  614.00 DRILLED AHEAD FROM 498 m TO 730 m.
                                                                         LOSSES STARTED @ 580 m 2 m3/hr STATIC.
             23:45 - 00:00    0.25   D12     MNR                  614.00 DAILY MAINTENANCE.
8/11/1990    00:00 - 22:15 22.25     D12     DRR                  781.00 CONT'D DRILLING AHEAD FROM 730m TO 897m.
                                                                         LOSSES AT 870m:STATIC 10m3/hr.
             22:15 - 23:15    1.00   D12     PCD                  781.00 PRESSURE DROP OFF 4600Kpa AT 897m AND LOST 9 TONS
                                                                         OFF STRING WEIGTH.CIRC HOLE CLEAN AND SPOT 5m3
                                                                         VISC ABOVE TOP FISH.
             23:15 - 00:00    0.75   D12     DRT                  781.00 POOH
8/12/1990    00:00 - 02:00    2.00   D12     DRT                  781.00 POOH.LEFT IN HOLE BIT-F/S-2xDC-STAB-3xDC.
                                                                         LENGTH OF FISH 48.88m.
             05:15 - 06:00    0.75   D12     SWF                  781.00 LATCH ON FISH AND MAKE FISH FRE MAX O/P 25000dan
             06:00 - 06:30    0.50   D12     PCD                  781.00 CIRC HOLE CLEAN.
             06:30 - 10:30    4.00   D12     DRT                  781.00 POOH RELEASED O/S FROM FISH,L/D O/S DC AND BIT
                                                                         VISUALLY INSPECTED ALL DC CONECTIONS FOR CRACKS.
             10:30 - 15:00    4.50   D12     DRT                  781.00 M/U BIT # 3 AND RIH TO 890m.
             15:00 - 15:15    0.25   D12     PCD                  781.00 W/D FROM 890m TO 897m AND CIRC FOR JUNK.
             15:15 - 00:00    8.75   D12     DRR                  996.00 DRILLED FROM 897m TO 1112m.
                                                                         LOSSES: FROM 897m TO 1013m 25 TO 40m3/hr
                                                                            : FROM 1013m TOTAL LOSSES.
8/13/1990    00:00 - 00:30    0.50   D12     DRR                1,000.00 DRILLED FROM 1112m TO 1116m
             00:30 - 01:15    0.75   D12     PCD                1,000.00 PRESSUREDROP OF 4600kpa AT 1116m AND LOST 19000dan
                                                                         STRING WEIGTH.CIRC HOLE CLEAN AND SPOT 5m3 VISC
                                                                         ABOVE TOP FISH.
             01:15 - 04:00    2.75   D12     DRT                1,000.00 POOH:LEFT IN HOLE BIT-JUNK BASKET-SHOCK EZE-2xDC-
                                                                         STAB-9xDC:LENGTH OF FISH 109m.
             04:00 - 06:45    2.75   D12     DRT                1,000.00 M/U 11 3/4" O/S WIDTH 8"BASKET GRAPPLE AND RIH TO
                                                                         TOP OF FISH AT 1007m.
8/14/1990    00:00 - 01:00    1.00   D12     PCD                1,036.00 SWEEP 5m3 VISC ROUND AND SPOT 15m3 VISC ON BOTTEM.
             01:00 - 01:15    0.25   D12     ELO      LSS       1,036.00 DRILLED BIT SAMPLE.
             01:15 - 02:30    1.25   D12     NOA                1,036.00 F/S WELL FLOWING,CLOSE BOP,pdp & pann 0,SQUEEZED
                                                                         10m3 OF 13.3Kpa MUD,F/S TOTAL LOSSES,OPEN BOP,
                                                                         FILL UP ANNULUS WITH WSW.
             02:30 - 02:45    0.25   D12     DVM                1,036.00 DROP TOTCO.
             02:45 - 04:45    2.00   D12     DRT                1,036.00 POOH AT 510m WELL FLOW AGAIN,CLOSE BOP.
                                                                         pdp & pann 0Kpa.
             04:45 - 05:15    0.50   D12     NOA                1,036.00 SQUEEZED 3m3 OF 13.3Kpa MUD,F/S TOTAL LOSSES.
                                                                         FILL UP ANNULUS WITH WSW.
             05:15 - 06:45    1.50   D12     DRT                1,036.00 CONT'D POOH TO 50m.WELL FLOW AGAIN,CLOSE BOP.
             06:45 - 07:15    0.50   D12     NOA                1,036.00 SQUEEZED 3m3 OF 13.3Kpa MUD,F/S TOTAL LOSSES.
                                                                         FILL UP ANNULUS WITH WSW.
             07:15 - 08:15    1.00   D12     DRT                1,036.00 CONT'D POOH RETRIEVE TOTCO(miss fire),L/D STAB
                                                                         AND BIT.
             08:15 - 08:45    0.50   C12     RUD                1,036.00 CHANGE RAMS TO 9 5/8"
             08:45 - 09:00    0.25   C12     BPT                1,036.00 P/T BONNETS TO 10500Kpa.
             09:00 - 09:30    0.50   C12     RUD                1,036.00 R/U FOR RUNNING 9 5/8" CSG.WELL FLOW AGAIN
                                                                         CLOSE BOP.
             09:30 - 10:00    0.50   C12     NOA                1,036.00 SQUEEZED 5m3 13.3Kpa MUD.FC TOTAL LOSSES.
                                                                         FILL UP ANNULUS WITH WSW.
             10:00 - 17:30    7.50   C12     CLR                1,036.00 M/U & BACKERLOCK SHOE TRACK.TEST FLOAT EQUPMENT
                                                                         RUN CSG TO 1150m.WASH DOWN LAST 10m.F/SHOE @ 1149m
                                                                         F/COLLAR @ 1136m,BAFFLE PLATE @1124m,MSPC @ 882m
             17:30 - 18:30    1.00   C12     PCD                1,036.00 CIRC 120% CSG CONTENTS.
             18:30 - 19:15    0.75   C12     CLC                1,036.00 R/U CMT HEAD AND LINES.
             19:15 - 19:30    0.25   C12     PRE                1,036.00 FLUSH LINES AND P/T TO 21000Kpa.
             19:30 - 20:30    1.00   C12     CLC                1,036.00 DOWELL PUMP 3m3 PREFLUSH,MIX AND PUMP 878 sxs
                                                                         POZMIX CMT 16.1Kpa/m.
             20:30 - 21:00    0.50   C12     PCD                1,036.00 DROP SHUT OFF PLUG,DOWELL PUMP 1.5m3 AFTER FLUSH
                                                                         DISPLACE CMT WITH RIG PUMPS UNTIL BUMP
             21:00 - 21:15    0.25   C12     PRE                1,036.00 P/T CSG TO 17000Kpa.BLEED OFF NO BACKFLOW.
             21:15 - 21:30    0.25   C12     CLC                1,036.00 DROP BOMB,INSTALL CLOSING PLUG,LEVEL ANNULUS:TOTAL
                                                                         LOSSES.SET PACKER AND OPEN CIRC PORTS.AFTER SETING
                                                                         PACKER LOSSES 15m/hr.
             21:30 - 22:15    0.75   C12     PCD                1,036.00 CIRC ANNULUS CLEAN 4m3 CMT AT SURFACE.
             22:15 - 22:45    0.50   C12     NOA                1,036.00 AFTER CIRC OUT CMT WELL FLOW AGAIN CLOSE BOP
                                                                         SQUEEZED 4m3 OF 13.3Kpa MUD.F/C TOTAL LOSSES
             22:45 - 00:00    1.25   C12     PCD                1,036.00 WAIT TILL SURFACE SAMPLES ARE HARD,MEANWHILE CIRC
                                                                         TROUGH MSPC.
8/16/1990    00:00 - 00:45    0.75   D09     DCM                1,036.00 CONT'D DRILL SHOE TRACK (F/SHOE @1149m)MEANWHILE
                                                                         CIRC TO 12.3Kpa MUD. CLEAN POCKET.
             00:45 - 11:45 11.00     D09     DRR                1,109.00 DRILL FROM 1152m TO 1225m. O/P AT 1225m 40000dan.
             11:45 - 12:45    1.00   D09     REM                1,109.00 MAKE STRING FREE. REAM 1203m-1225m.
             12:45 - 21:15    8.50   D09     DRR                1,204.00 DRILL FROM 1225m TO 1320m.
             21:15 - 22:00    0.75   D09     PCD                1,204.00 SWEEP HOLE WITH 5m3 VISC.
             22:00 - 23:00    1.00   D09     CWT                1,204.00 CHECKTRIP TO 9 5/8"CSG SHOE.FROM 1281m T0 SHOE O/P
                                                                         MAX 20000 dan.F/C IN SHOE:STATIC.
             23:00 - 23:45    0.75   D09     PCD                1,204.00 CIRC HOLE CLEAN.
             23:45 - 00:00    0.25   D09     DVM                1,204.00 DROP TOTCO AND DP DRIFT.FLOW CHECK:STATIC.
8/17/1990    00:00 - 04:15    4.25   D09     DRT                1,204.00 POOH FOR LOGGING L/D STAB AND RETRIEVE TOTCO
                                                                         (incl 1.5 degree).
             04:15 - 04:45    0.50   E09     ELO      RUD       1,204.00 R/U FOR SCHLUMBERGER.
             04:45 - 12:00    7.25   E09     ELO      EME       1,204.00 RUN #1:PI/MSFL/SDT/GR(in:0515 out:0745 HUD:1320m)
                                                                         RUN #2:LDT/CNT/PCD/GR(in:0815 out:1015 HUD:1320m)
                                                                         RUN #3:SHDT(in:1030 out:1200 HUD:1320m).
             12:00 - 12:30    0.50   E09     ELO      RUD       1,204.00 R/D SCHLUMBERGER R/U SSL.
             12:30 - 16:45    4.25   E09     ELO      EME       1,204.00 RUN #4:VSP(in:1230 out:1645).
             17:15 - 00:00    6.75   E09     ELO      EME       1,204.00 RUN #5:RFT(in:1800).
8/18/1990    00:00 - 01:00    1.00   E09     ELO      EME       1,204.00 CONT'D RUN # 5
             01:00 - 01:30    0.50   E09     ELO      RUD       1,204.00 PREPARED CST TOOL.
8/19/1990    00:00 - 00:45    0.75   C09     CLR                1,204.00 PULLED CUPS OUT OF LINER, BALANCED OUT 1 m3
                                                                         RETURNS. POOH TO 895 m.
             00:45 - 01:00    0.25   C09     PCD                1,204.00 CIRCULATED STRING CLEAN.
             01:00 - 03:00    2.00   C09     CLR                1,204.00 CONT'D POOH L/DOWN & SERVICED LINER SETTING
                                                                         TOOL.
             03:00 - 06:00    3.00    CU     DRT                1,204.00 M/U BHA No.6 & RIH TO 889 m.
             06:00 - 06:30    0.50    CU     NOA                1,204.00 PERFORMED BOP DRILL + HELD SAFETY MEETING.
             06:30 - 07:30    1.00    CU     NOA                1,204.00 W.O.C.
             07:30 - 07:45    0.25    CU     DRT                1,204.00 CONT'D RIH TO RESISTANCE @ 958 m.
             07:45 - 12:45    5.00    CU     DCM                1,204.00 DRILLED HARD CMT FROM 958 m TO TOL @ 1100 m.
             12:45 - 13:30    0.75    CU     PCD                1,204.00 CIRC. HOLE CLEAN WITH 5 m3 Hi-VISC PILL.
             13:30 - 13:45    0.25    CU     NOA                1,204.00 F/CHECK STATIC.
             13:45 - 17:15    3.50    CU     DRT                1,204.00 POOH, L/D HWDP & 61/4" DCs, F/S & BIT.
             17:15 - 23:00    5.75    CU     DRT                1,204.00 M/U TANDEMSRAPER ASSY #7 & RIH TO RESISTANCE
                                                                         @ 1258 m.
             23:00 - 00:00    1.00    CU     DCM                1,204.00 W/DOWN TO TOC @ 1260 m. DRILLED HARD CMT
                                                                         FROM 1260 m TO 1275 m.
8/20/1990    02:15 - 03:30    1.25    CU     PCD                1,204.00 DISPLACED HOLE TO UNFILTERED NACL BRINE OF
                                                                         11.5 kPa/m. FLUSHED ALL SURFACE LINES.
             03:30 - 04:00    0.50    CU     PRE                1,204.00 P/TESTED LINER-LAP TO 10500 kPa. OK.
             04:00 - 08:00    4.00    CU     DRT                1,204.00 POOH & L/DOWN ALL TUBULARS.
8/21/1990    00:00 - 01:00    1.00    IC     BPT                1,204.00 P/TESTED BONNETS TO 10500 kPa.
             01:00 - 01:45    0.75    IC     TUR                1,204.00 M/U 2 3/8" COMPLETION TAIL & RIH TO 17 m.
             01:45 - 02:00    0.25    IC     RUD                1,204.00 R/U WIRE LINE.
             02:00 - 02:15    0.25    IC     SLO                1,204.00 W/LINE SET 2 3/8" XN PLUG @ XN NIPPLE.
             02:15 - 02:45    0.50    IC     PRE                1,204.00 P/TESTED COMPLETION TAIL TO 21000 kPa. OK.
             02:45 - 03:00    0.25    IC     SLO                1,204.00 W/LINE RETRIEVED XN PLUG.
             03:00 - 03:15    0.25    IC     RUD                1,204.00 R/DOWN W/LINE.
             03:15 - 03:30    0.25    IC     RUD                1,204.00 R/U SCHLUMBERGER.
             03:30 - 04:45    1.25    IC     SLO                1,204.00 SCHLUMBERGER RIH COMPLETION TAIL ON WIRELINE
                                                                         AND SET MODEL 'D' PACKER @ 1193 m.
             04:45 - 05:00    0.25    IC     RUD                1,204.00 R/DOWN SCHLUMBERGER.
             05:00 - 06:15    1.25    IC     TUR                1,204.00 M/U 2 7/8" COMPLETION ASSY & RIH TO 71 m.
             06:15 - 06:30    0.25    IC     RUD                1,204.00 R/U WIRELINE LUBRICATOR & P/TESTED TO 21000 kPa.
             06:30 - 07:00    0.50    IC     SLO                1,204.00 W/LINE RIH & SET XN PLUG @ XN NIPPLE.
             07:00 - 07:30    0.50    IC     PRE                1,204.00 P/TESTED COMPLETION ASSY TO 21000 kPa.
             07:30 - 07:45    0.25    IC     SLO                1,204.00 W/LINE RETRIEVED XN PLUG.
             07:45 - 08:00    0.25    IC     RUD                1,204.00 R/DOWN W/LINE LUBRICATOR.
             08:00 - 13:45    5.75    IC     TUR                1,204.00 CONT'D RIH 2 7/8" COMPLETION TO 1210 m.
             13:45 - 15:15    1.50    IC     PCD                1,204.00 CIRCULATED CSG CONTENT ABOVE MODEL 'D' PACKER.
             15:15 - 16:30    1.25    IC     TUR                1,204.00 SPACED OUT. INSTALLED TBG HANGER AND
                                                                         LANDED STRING WITH 14000 daN.(INJECTED 16 STICKS).
             16:30 - 16:45    0.25    IC     PRE                1,204.00 P/TESTED HANGER FROM ABOVE TO 3500 kPa. OK.
             16:45 - 17:30    0.75    IC     RUD                1,204.00 R/U W/LINE LUBRICATOR.
             17:30 - 17:45    0.25    IC     PRE                1,204.00 P/TESTED LUBRICATOR TO 21000 kPa.
             17:45 - 19:00    1.25    IC     SLO                1,204.00 W/L RIH & SET TEST TOOL IN 2 3/8" XN NIPPLE.
                                                                         HUD @ 1209 m.
             19:00 - 19:45    0.75    IC     PRE                1,204.00 P/TESTED STRING AND G-22 SEALS TO 14000 kPa.
             19:45 - 20:45    1.00    IC     SLO                1,204.00 W/LINE RETRIEVED PRONG & PLUG.
             20:45 - 21:45    1.00    IC     SLO                1,204.00 W/LINE RIH 2 7/8" PXN PLUG & PRONG AND
                                                                         SET IN 2 7/8" XN NIPPLE.
             21:45 - 22:30    0.75    IC     PRE                1,204.00 P/TESTED TUBING STRING TO 21000 kPa FOR
                                                                         30 MINS. OK.
8/22/1990    00:00 - 00:30    0.50    IC     PRE                1,204.00 CONFIRMED PACKER SET BY PRESSURING ANNULUS
                                                                         SLOWLY TO 6000 kPa.
             01:00 - 05:30    4.50    IC     TUR                1,204.00 INSTALLED BPV & N/DOWN BOP. INSTALLED
                                                                         X-MAS TREE.
             05:30 - 06:00    0.50    IC     PRE                1,204.00 INSTALLED TWCV. P/T X-MAS TREE TO 21000 kPa.
                                                                         INSTALLED BPV.